To: Andrew Wilson
Yvonne Walsh
Dave Cooke
cc: Stewart Putt (regarding 474/n and 475/n)
Tony Houghton
Date: 2 June 1999
From: Bob Booth
Subject: POCL Infrastructure Acceptance Meeting - Segment 4: 2 June 1999
Points of note from the POCL Infrastructure Acceptance Meeting - Segment 4 held
2 June 1999 at 10:00 in Feltham.
Attendees: Andrew Wilson [AW]
Yvonne Walsh tw]
Dave Cooke [DC]
Bob Booth [BB]
It was agreed that whilst the BA position did affect things, there was no material
difference to the body of this Acceptance Test Specification.
Criterion Comment Action
465 I2 Once confirmation of the following two bullets is received the
criterion can be accepted:
¢ no spurious input is generated when turning off the monitor
Ref. 26 8.2
¢ no magnetic card slot cleaning card is used.
474 In__ I The criteria 1-19 not explicitly mentioned below are covered by
this comment.
The ‘Technical Construction File’ VI/RES/004 version 1 was
viewed at the meeting but is in need of revision by Roger
Pullen for ICL Pathway. When it is updated DC will issue to
POCL and their expert Roger Spenceley with a covering letter
addressing or highlighting explicit points made in the Segment
4 comments dated 25 May 1999. 4/DC1
YW to supply address and details of Roger Spenceley toDC. I 4/YW2
YW will talk to Min Burdett to ensure Policy & Standards are
addressing issues in a consistent fashion. 4IYW3
474 I5 Accept.
474 I9 Accept.
474 I 11 I Accept.
474 I 12 I Noted that this has been targeted at segment 5.
474 I 18 I Accept as a Statement of Fact or Obligation.
90] ~1I >] on] A] 00
475 I 1 The Style Guide needs to be re-drafted to acknowledge
POLO, it would then be acceptable as appertaining to cover
the services covered by the OPS..
475 12 Accept. Noting the focus is Outlet facing and not concerned
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or
creating new contractual obligations between ICL Pathway, the DSS and / or POCL.
Armoutpt.doc 1 of 3
FUJ00079086
FUJ00079086
with HCI issues relating to ICL operators.
10. I 475 I3 Greame Seedall is involved via the Policy & Standards
Acceptance Test Specification and looking at the measures
that could be performed in Live Trial.
YW to discuss with Graeme Seedall. 4IYW4
DC to include the “Menu Hierarchy” and “Reports and Receipts
Functional Specification” in their current form and update as
and when the versions cognisant of the BA position are
available. 4/DC5
11. I 475 I4 See 475/3
12. I 536 I1 Accept.
13. I 537 [1 Accept.
14. I921 I4 Accept. Noting that the meeting was informed that the Outlet
Manager can assign another user to the stock unit to carry out
any required functions.
Previous me ig actions
2/AW6 POCL require no further information on consumable regarding this criterion.
466/2 is now Accepted.
Closed.
2/DC9 The Register of Connected Systems has been re-scheduled for Segment 5
and will reflect the BA position. This will be covered in the segment 5 forum.
Closed.
3/BB1 Supply of type of asset questions that would be asked at the HSH site visit.
Complete.
3/DC2 Clarify the ICL Pathway policy on time zones.
Ongoing.
3/DC3 A paper is being written (due 14-June-1999) to address the specific
legislative issues raised.
Ongoing.
3/DC4 DC informed the meeting that the measurements were compliant with the
standards and performed at 1 metre and that the Epson had 45dBa emission
and OKI 48 dBa emission. These will be incorporated into the next Counter
Hardware Design Specification (latest version is 6.0).
Complete.
3/DC5 Clarity was sought by DC on what “how data integrity is maintained in failure“
referred to. This was clarified to need to include marker based accounting
and the application imposed rules regarding what functions were available
and the overall design guidelines.
Ongoing.
3/DC6 The Planned Evaluation Matrix (Ref. 94) is contained in the Horizon
Satisfaction Forum which Phil Turnock from POCL attends.
Closed.
3/BB/DC7 To agree the status of the criteria within the POCL Infrastructure
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or
creating new contractual obligations between ICL Pathway, the DSS and / or POCL.
Armoutpt.doc 20f 3
Acceptance Specification and document variances from version 2.0.
Meeting set up for 7th. June 1999 at 14:00 in B1.
Ongoing.
Segment 5
DC had issued Segment 5 but due to failure of BB’s laptop it had not been further
disseminated. DC to mail to AW (Andrew.C.Wilson ‘and YW
(Yvonne.Walshé “idirect, and pass “adiskette copy to BB. 4/DC6
Meeting for Segment 5 was confirmed as 15th. June 1999 in Feltham at 13:00.
Segment 1
DC confirmed the site visit as Tuesday 8" June 1999 in Stevenage (STE09). DC to
provide an agenda and try to make the relevant agenda items consecutive. 4/DC7
DC highlighted some changes that were proposed in Segment 1 and an e-mail
proposing further amendment to the way the criteria are proposed to be satisfied.
AOB
TED - Due to BB's lack of e-mail DC agreed to flag back to ICL Pathway that DSS
and lan Stevenson should be removed from the NDA, the version of TED will be
checked and NDA issued. 4IDC8
Criteria Accepted this meeting
466/2 - from Segment 2.
474/5 474/9 474/11 474/18
475/2
536/1
537/1
921/4
Post Meeting Note
4IYW2 Roger Spenceley details are: Post Office Services Group
Post Office Consulting
Technical Team Leader
Technology Centre
Wheatstone Road
Dorcan
Swindon
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or
creating new contractual obligations between ICL Pathway, the DSS and / or POCL.
Armoutpt.doc 3 of 3