FUJ00094359 - Post Office Ltd Horizon Next Generation Joint Progress Meeting 147 Minutes of 04/03/2010

Evidence on official site

FUJ00094359
FUJ00094359

Horizon Next Generation Joint Progress Meeting

Meeting 147

Notes of Horizon Next Generation Joint Progress/Release Board Meeting
Meeting of Thursday 4" March 2010

Attendees:

Name Initials_I Role Comments
Mark Burley MB Programme Manager (POL) Apologies
Debbie Richardson DR Test Manager (Fujitsu)

John Wheeler JW. PMO OManager (POL)

Kevin Tallboy KT Planning Manager (POL)

Ravi Chambers RC PMO Manager (Fujitsu)

Geoff Butts GB Programme Manager — HNG (Fujitsu)

Will Russell WR Migration Manager (POL) Chair
Vince Cochrane Wiel Network Specialist (Fujitsu)

Alan D’Alvarez AD Programme Director — HNG (Fujitsu) Apologies
Lee Farman LF Test Manager (POL)

Phil Norton PN Acceptance Manager (POL)

lan Trundell IT HNG Design Authority (POL) Apologies
Adam Martin AM Service Delivery (POL) Apologies
Dave Hulbert DH Service Delivery (POL)

Graham Welsh GW. Customer Services (Fujitsu)

Graham Allen GA Development Manager (Fujitsu)

Mike Wood MW. Director of Programmes (Fujitsu) Apologies
Gaetan van Achte GvA Service Director (Fujitsu) Apologies
Chris Dodington CD Implementation Manager (Fujitsu)

Barry Evans BE Migration Team (POL)

Peter Stanley PS Design Authority (POL)

Andy Jacques AJ Service Delivery (POL) Apologies
Distribution: As above, plus David Smith, and the Fujitsu & POL lead teams

Ref: Joint Progress Meeting Minutes 1000304.doc Page 1 of8

FUJ00094359
FUJ00094359

Horizon Next Generation Joint Progress Meeting
Meeting 147

1 Minutes from Previous Meeting

The previous minutes were accepted.

2 Actions and Points to Note from Previous Meeting/Current meeting

No.

Owner

Action or point to note

Status/Progress

Date
required

New Actions and Points from meeting of 14” January

140.08

AD GB
(GW)

Provide a process for how
releases will be implemented
beyond the current maintenance
release (01.08). Process will
need to be discussed and agreed
with POL Service Delivery.

04/03 update. (transferred from
145.11): the current pause in
rollout means that re-opening of
the migration package should be
considered — or that a future
package rolls up all changes — so

Previous actions archived.
18/02 C/fwd. Meeting to be
arranged for next week to agree a
joint strategy for the targeting of
referrals beyond RO1.08.

25/02 C/ifwd. No paper received to
date. Fujitsu internal meeting
arranged for 2" March.

04/03 C/fwd. Internal meeting
cancelled. Meeting to be
rescheduled; LF and PS to be
included in the invites.

that there is no lag between

R108.

branch migrating at R107, and
getting the fixes contained in

a

11/03

140.12 To confirm that there will
be additional migration
support available from
Fujitsu (to bring back the

rollout completion date)

BEB

21/01 C/fwd. Currently unconfirmed.

28/01 C/fwd. AD to discuss with MB on 29"
January.

04/02 C/fwd. GB has received a training
proposal from 4G and this is now under
review. GB to provide an update to MB by
5" February.

11/02 Cifwd. To be discussed after Joint
Steering Board.

18/02 C/fwd. Work in progress. Still
reviewing options proposed by 4G. See
also action 145.01

25/02 C/fwd. Revised proposal expected
next Monday,

04/03 C/fwd. Revised proposal has been
received from 4G and is being reviewed by
Fujitsu. However; given current position this
will probably need revisiting.

11/03

New Actions and

Points from meeting of 4° February 2010

143.04

GW.
IT

Obtain statistics regarding the
number of ‘Screen Pauses’ and
reversals experienced at the HNG
branches since migrating. And
investigate and report back on the
root cause of why this is happening.

11/02 Cifwd. Statistics provided
and monitoring continues.
Action switched to IT to lead on
working with Fujitsu to determine
how we get back to the volumes
forecast.

Closed

Ref: Joint Progress Meeting Minutes 1000304.doc

Page 20f8

FUJ00094359
FUJ00094359

Horizon Next Generation Joint Progress Meeting

Meeting 147

The number of ‘Screen Pauses’
and related Recoveries are
significantly higher than expected.

18/02 C/fwd. IT has had initial
discussions with Dave Johns,
investigations continue.

25/02 Cifwd. GW to provide
daily statistics (issue to WR, IT
and PS) on the number of
recoveries being performed and
any information on screen
freezes.

See also follow on Actions:
146.01, 146.02, 146.03 and
146.04

04/03 Closed. See 146.02

143.06 DR_ I HNG SV&I Rig -
Propose a way
forward for
managing the
contention for the

for Release 1
issues and
Release 2
development.

use of the SV&l rig

Previous actions archived.

18/02 C/fwd. Current view is that an additional
SV4&l rig will be required. DR currently working up
the details.

25/02 C/fwd. DR continuing to assess the short
term requirements and how best the Test team can
meet these. It was re-iterated that the long term
proposal would be to introduce a new rig to retain
the SV&l functionality...

LF and PS to review and assure any short term
proposals

Note: Migration issues can only be tested on the
LST rig.
04/03 C/fwd. Fujitsu are currently looking at 3
options, the first 2 are tactical:

« Provide a CIT equivalent in BRAO1

¢ Create an SV&l clone in IRE19
The third option is more strategic and involves
providing a new SV&I environment either by
enhancing the SV&I clone created for the tactical
solution of using the Vol rig once it has been
released.

A meeting has been scheduled for 10'" March to
discuss, but it is essential to understand the current
issues before a decision can be made. Additionally
an agreement on how future releases will be
implemented is a significant contributing factor to
any decision.

NOTE ; It was confirmed that the HNG SV& rig has
now been handed over to Release 2, leaving only
the LST rig to test defect fixes on HNG.

11/03

143.10 GW

To provide advice to POL as
to the correct action that

11/02 C/fwd. KELs being generated.
GW to provide update on latest position

11/03

Ref: Joint Progress Meeting Minutes 1000304.doc

Page 3 of8

FUJ00094359
FUJ00094359

Horizon Next Generation Joint Progress Meeting

Meeting 147
should be taken by Branches _ I at next Joint Steering Board.
receiving the; 18/02 C/fwd. KELs have been
‘Unable to contact Data generated, GW will generate the
Centre’ message. required documentation and forward to
Barry Evans.
25/02 C/fwd. Not received. GW to
check and re-send if required.
04/03 C/fwd.
New Actions and Points from meeting of 11 February 2010
144.08 PAL Error message seen at Branches, 18/02 C/fwd. The message Closed
GW I but not flagged up by FS needs to be revised. IT and GW
IT monitoring systems: The following I to meet to review and agree the
message; best way forward.
¢ “Do not attempt any further 25/02 Cifwd. Revised wording
transactions of this type until has been agreed. IT will work
you have confirmation they with Andy Corbett (POL
have been fixed” Reference Data Team) to
PN/GW to investigate. PN to forward I resolve.
information to GW 04/03 Complete. Message
changed in live.
New Actions and Points from meeting of 18" February 2010
145.03 PN Trial Report / Final 25/02 C/fwd. POL have requested that this 05/03
Balance issue: PN to I be a Hot Fix as it is required before we
check if the proposed migrate any further branches.
workaround is
acceptable to the Fujitsu to ensure deliverables listed in PN
business. email (dated 24" Feb) for current live
Permanent fix targeted I branches are included.
for RO1.08. However; 04/03 C/fwd. GB has received feedback
this is dependent on the I from FS legal. Info will be forwarded to PN.
acceptability of the
workaround, it may need
to be a Hot Fix.
145.07 GA Pre-Migration checks 25/02 C/fwd. Investigations continue. Fujitsu I 11/03
BE taking a long time at to provide a response by close of business
large branches: 26" Feb
Crawley took 50+ 04/03 C/fwd. Presentation sent by GA. It
minutes to run the pre- _I includes a high level summary recommending
migration checks. GA to I the preferred approach to migrating large
investigate if this will be I branches. BE to review and respond to CD.
a problem for the Crown
Offices targeted for
migration on 19" Feb.
Fujitsu need to provide
assurance that there will
not be a problem at
these branches.
145.08 GW _I Forward supporting 25/02 Completed. On going. Closed
information for the 6
dials reports to MB and

Ref: Joint Progress Meeting Minutes 1000304.doc

Page 4 of8

FUJ00094359

FUJ00094359
Horizon Next Generation Joint Progress Meeting
Meeting 147
WR
145.09 VG Talk to Tom Lillywhite 25/02 C/fwd. VC has discussed with TL. Closed
IT regarding the IT to confirm with Dave King if this remains
Penetration testing an issue and update VC accordingly.
performed on POL FS. 04/03 Closed.
145.10 DR Review the new High 25/02 Cifwd. Being tracked at Test Closed
Priority defects and Governance. DR to provide supporting
report back, by evidence that the recorded increase in
exception, to the board. I defects is not an issue..
DR to produce a high level summary asap.
04/03 Closed. High level summary provided
by DR on 26" February. Re-raise by
exception.
145.11 GA Release 01.08 will be 25/02 C/fwd. The proposal to implement Closed
GW I deployed post Branch RO01.08 after migration (i.e. there would be at
(PN) I Migration (the Branch least one day of trading before the branch is
will initially migrate onto I upgraded) is unacceptable to POL.
01.07). The upgrade will
be targeted for the Fujitsu to propose how the essential fixes can
following day, but could I be included into or with the Migration
take 2 or even 3 days to _I Package in order that no new branch can
be deployed. open without them.
GA/GW to provide a
level of confidence for 04/03 Closed. Investigations have shown
the rate of rollout. that to include all the “must have” fixes into
the migration package would incur an
GA/GW to coordinate additional 3 weeks minimum of testing and
with PN. puts the programme in a worse position than
the proposed approach of migrating the
branches to 01.08 the day after initial
migration.
However; the current pause in rollout means
that this should be re-opened with the view
that a one-off migration package could be
introduced at some time during full rollout.
This should be reported under 140.08 above
145.14 PN Ensure M C-J is actively I 25/02 C/fwd. There are now 3 High Severity I 11/03
GB__ I pursuing the rectification I Security incidents. Fujitsu internal meeting
(M-G-J) I of the 2 high severity later today to discuss.
GB Security incidents. Output from this meeting to be forwarded to
PN
04/03 C/fwd. Security teams have met, but
PN reported that insufficient progress has
been made. GB to provide a proposal as to
how these high severity incidents will be
resolved.
New Actions and Points from meeting of 25” February 2010
146.01 GW Excessive number of Recoveries/ 04/03 C/fwd. Data is now being I 11/03
PS Screen Freezes: provided, but this still needs to
Fujitsu to provide a formal response be referred back to the contract
on how the system is performing. Assumptions and Constraints

Ref: Joint Progress Meeting Minutes 1000304.doc

Page 5 of8

FUJ00094359
FUJ00094359

Horizon Next Generation Joint Progress Meeting

Meeting 147
This should be measured against an I document.
Horizon Baseline and refer back to PS to confirm that the Daily
the levels agreed in the Assumptions I report is giving POL the required
and Constraints documentation. level of information.
146.02 ae Excessive number of Recoveries/ 04/03 C/fwd. Screen Pauses do I 11/03
Ad Screen Freezes: Wider MI. not create a system event,
IT to discuss with AJ, POL’s therefore the focus has switched
GB requirements for MI that Fujitsu need I to monitoring and recording
to provide regarding the on-going counter re-boots.
monitoring of Recoveries/Screen
Pauses. Additionally POL have provided
IT to then forward these requirements I a list of additional MI
to GW. requirements via email to GW.
GB to confirm back that this MI —
or an adequate variant — can be
provided

146.03 I Info I Excessive number of Recoveries/ _I For information

Screen Freezes:
This is to be treated as a Major
Incident and managed accordingly.
146.04 GW_ I Excessive number of Recoveries/ 04/03 C/fwd. 11/03
GA, Screen Freezes:
WR Daily update to be provided by GA on
progress towards resolution. (Email
to IT/WR and PS).

146.05 WR POL to re-enforce the message to 04/03 Completed. Message Closed
Branches that they must inform the has been sent to every branch.
appropriate helpdesk when problems
arise.

146.06 Info Meeting to be scheduled for next For information
Wednesday 3 March to review all
actions pertaining to the Excessive
number of Recoveries/ Screen
Freezes.

146.07 I Info I The Key Branch-impacting Issues For information
required for action before continuing wl)
rollout have been capture in a
spreadsheet and were reviewed at Key Issues required
the Board. Attached is the updated —_I Defore continuing rolk
version.

ALL please note that this
spreadsheet contains a number of
actions that need to be addressed in
addition to those captured above.
The proposal is to merge this
spreadsheet into the current
Migration RAG report and hence will
be reviewed at that forum

146.08 AD Fujitsu to provide assurance that the I 04/03 Closed. GB gave an Closed
required resources (e.g. Testers) will I assurance that all the required

Ref: Joint Progress Meeting Minutes 1000304.doc

Page 6 of8

FUJ00094359
FUJ00094359

Horizon Next Generation Joi

int Progress Meeting

Meeting 147

remain in place to ensure that testing
of the required fixes can be
performed without un-necessary
delay.

Testing resources were in place.

146.09

ALL

Please ensure that KT/JW are copied
in on all action updates or
deliverables required to close actions.

For Information

New Actions and Points from meeting of 4 March 201

0

147.01

info

The Joint Steering Board agreed that
until a clearer understanding of the
root cause of the current live issues
was understood the rollout of any
new branches will be suspended.

For Information

147.02

GB

As per Action 147.01 It was agreed
that rollout would not be
recommenced until a period of
stability had been achieved. GB/WR
to agree what is meant by ‘Stability’
and what would be an adequate
period.

New Item

11/03

147.03

GW

Set up a ‘Tech Bridge’ to manage the
latest Live Issue (as at morning of 4"
March). Invitees to include DH, JW ,

PS and the Duty Manager.

New Item

04/03

147.04

info

It was noted that RO1.08 will improve
the current position regarding screen
freezes and oter stability items, but it
will not be a complete fix.

For information

147.05

GW

Ensure that all necessary parties in
Fujitsu and their counterparts in POL
are aware that there will be an OCP
raised late on Friday to enable the
RO1.08 Data Centre and Counter

New Item

upgrades to take place.

05/03

Remote attendance numbers (when provided) are as follows:

Points to note
Incorporated into actions/points to note above

AOB

incorporated into actions/points to note above

Next meetings:

Next Interim Joint Steering Board: Thursday 11" March, 14:00 — 15:30,
Teleconference.

Next Full Joint Steering Board: Thursday 18" March, 10:00 — 13:00, London

Ref: Joint Progress Meeting Minutes 1000304.doc

Page 7 of8

FUJ00094359
FUJ00094359

Horizon Next Generation Joint Progress Meeting
Meeting 147

Number to dial: (GRO
Participant Password:

Ref: Joint Progress Meeting Minutes 1000304.doc

Page 6 of8