Branch Support Programme - TOR v.2 In confidence Gayle Peacock July 19 2013

Branch Support Programme — Terms of Reference

Background

To address the concerns about the Horizon system that have been raised by some subpostmasters over
recent years, the Post Office commissioned an independent review of their cases. The company that
conducted the review issued an interim report on Monday 8" July 2013. The review made it clear that the
Horizon computer system and its supporting processes function effectively across our network. It did
however raise questions about the training and support we have offered some subpostmasters. It has been
acknowledged that this needs to be investigated further and improvements need to be made.

The purpose of this Programme is to understand the current business processes, operational procedures and
ways of working which are in place to support branches, identify the gaps and produce recommendations to
rectify the issues.

Scope

The interim report identified the following areas of concern which will be included within the scope

of the Programme.

© Post Office’s attitude to subpostmasters which is often defensive and unsympathetic, with a
focus to recover assets rather than to identify the root cause of the problem. There is a lack
of a subpostmaster “voice” or opportunities for them to raise their concerns.

« Inadequate Helpdesk support with responses that are script based, coupled with a decrease
in overall branch support

* Lack of timely, accurate and complete information provided to subpostmasters to support
them in resolving issues

e  Inexperienced trainers and gaps in training coverage

¢ Lack of centralised data or files specific to each branch which hinders a quality investigation
from taking place.

Whilst the review has concentrated on the cases raised by subpostmasters, each branch segment
within the network will be considered within the programme.

Approach

The approach will be to operate the Programme following normal project management principles. A
governance structure will be established, key stakeholders identified and a project plan with key milestones
and deliverables will be developed. The initial activity will be to engage with the key people to ensure they
are committed to delivering the specific activity required within their respective work areas. The progress
with the Programme will be tracked against the successful delivery against the plan.
POL00193031
POL00193031

Branch Support Programme - TOR v.2 In confidence Gayle Peacock July 19 2013

Governance and key stakeholders

Alice Perkins and Paula Vennells have requested the establishment of the Programme which will be led by
Angela Van-Den-Bogerd. Gayle Peacock and Amanda Stevens will be accountable for running the
Programme on an operational level.

The following table outlines the different key stakeholders, their areas of responsibility and suggested
people who would input at the working group level. The Programme Board will agree how the Programme
should be managed to ensure the objectives are delivered.

Business Area Programme Working Group level I Reason for inclusion within the group
Board

Network —Contact I Amanda Stevens I Kendra Dickinson Responsible for managing NBSC who are

Centres the first point of help for subpostmasters.
Programme could also have an impact on
POEX.

Network — Gayle Peacock TBC Responsible for outbound interventions

Performance to drive performance for non-sales area.

Data team sit within this area. Multiple
partner non-sales relationship.

Network — Craig Tuthill Responsible for agent contractual policy
Network Services and deployment, including the recovery
of agent debt
Network — Field Drew McBride Sue Richardson Responsible for training, support and
Support audits to all branch network
Network — Sales Karl Oliver/Andy Responsible for engaging subpostmasters
Kingham/Pam on sales.
Heap
Network — Crown Julie Thomas Tom Pegler Responsible for supporting Crown
& WHSmith branches both in training and

performance management

Network — Agent Nick Beal Responsible for agent pay and

Development relationship with NFSP

Finance Rod Ismay Andy Winn/Alison Responsible for branch accounting and
Bolsover/Paul client settlement. Also responsible for
Lebeter resolving specific branch accounting

issues
Security John Scott/Sally Joanne Responsible for detecting, investigating
Smith Hancock/Dave and preventing branch fraud

Posnett

POL00193031

POL00193031

Branch Support Programme ~ TOR v.2 In confidence Gayle Peacock July 19 2013

Network — Cash Doug Brown Graham Tilley/Clive Responsible for managing cash provision

Services Holmes/Rebecca to branches

Portch

IT Dave Hulbert TBC Responsible for branch systems (and
management of HSD?

IT RoadMap TBC TBC Potential development of IT
infrastructure to support activity may be
required

Communications Alana Renner Richard Weaver Responsible for internal and branch
communication

HR Ann Miller/Fay TBC Responsible for colleague induction and

Healey training and development

Other people will be brought into the Programme if and when required as part of the individual work
streams.

Key Deliverables
The Programme will be responsible for delivering the following:
¢ Mapping the “as-is” process for providing branch support and the various touch points for branches

Undertaking a gap-analysis for each of the respective areas regarding the concerns raised in the
interim report

* Producing recommendations for how the relevant gaps will be closed, supported by a deployment
and resource plan

The Programme will establish key work streams which will be responsible for delivering an agreed set of
lower level deliverables.

(Need to agree timescales with Angela)
Key Performance Indicators and Measures

The measure of success for the Programme will be to have consistent and effective training and support
mechanisms in place for all types of branches, resulting in an engaged network of subpostmasters and
colleagues, whilst protecting the assets and brand of Post Office. Measures for the Programme will include:

Key Performance Indicator Measures
Agent and colleague Branch survey — which focuses on value driven by each interaction,
engagement/satisfaction advisor knowledge, behaviour, follow up

High profile complaints/flag cases

POL00193031
POL00193031

Branch Support Programme - TOR v.2 In confidence Gayle Peacock July 19 2013

Contact centre measures
Reducing effort for branches to receive the right support

First time resolution

Quality of training and support Improve branch performance against conformance standards,
provided including volume of transaction corrections

Kendata (?) feedback on support provided at training
Consistency of contract case management — (measure to be defined)
Number and type of training/support interventions

FTIR

QA/follow up check with branch that intervention/contact met needs

Branch losses and debt Number and value of current agent debt — amounts not to increase
Number and value of former agent debt — amounts not to increase
Suspense account entries —-measure to be confirmed

FTIR

QA/follow up check with branch that intervention/contact met needs

Costs Cost of resource to deliver required improvement changes

Structure How is POL organised to deliver high quality levels of branch support
and engagement consistently?

System Robustness of the system
Calls into HSD

Number and type of issues not to be increased

Risks and Issues

Each area will define their respective risks and issues. The known Programme risks and issues at this stage
are:

e Lack of resource/funds to develop a technical solution to support consistent working across business
functions.

e Inability to change people’s mind-sets and ways of working
POL00193031
POL00193031

Branch Support Programme ~ TOR v.2 In confidence Gayle Peacock July 19 2013
Technical infrastructure and product transaction flow too complex to make things easier for
branches and our customers.

Dependencies

There are a number of other business activities which the Programme will be either a dependency for or
have a dependency on which include:

Royal Mail Group Separation for the Network Business Support Centre.

« Network Agency Sales Engagement activity and revised organisation structure.
e Digital Channel Strategy

e@ Network Transformation Programme.

* Fraud Software Programme pilot to help improve the detection of fraud.

Version control

Date Version I Reason for change Name of sign
off

12.7.2013 I v.1 Initial terms of reference draft

19.7.2013 I v.2 Revised following input from

Amanda