ICL PATHWAY CHANGE CCN NO: 633b
CONTROL NOTE (CCN) -
SHEET 1
CCN TITLE: Introduce Satellite CHANGE ADMINISTRATION USE ONLY.
Communications Access Method CR NO: N/A
CP NO: 2517
IMPLEMENTATION DATE EXPIRY DATE: 24" July 2000
OR RELEASE: During CSR+
CCN RAISED BY: J CC Dicks DATE: 3" July 2000
EMERGENCY IMPLEMENTATION DATE: N/A
SUBMISSION DATE: 3 July 2000
APPROVALS REQUIRED:
PATHWAY APPROVAL DATE POCL APPROVAL DATE
EXECUTIVE SUMMARY OF IMPACT ASSESSMENTS:
This CCN is to introduce ISBN (Integrated Satellite Business Network) communications access
method, known generally as VSAT, as the preferred method of connection when an ISDN service
cannot be installed.
OVERALL IMPACT ASSESSMENT: __ HIGH--MEDIUM~+ LOW,
REASON FOR CHANGE:
Tn certain locations an ISDN service is not available. At the date of this CCN it is anticipated that up to
350 outlets will require an alternative form of communications access. Hitherto the intention has been
to use Frame Relay connection for such outlets. However, some of these non-ISDN outlets may also
not be capable of Frame Relay connection, The VSAT method is introduced to provide an alternative
approach to handle non-ISDN cases, providing a comparable service with respect to reliability,
resilience, security and performance.
DETAILS OF CHANGE:
This CCN introduces the VSAT communications access method to the Codified Agreement. This is
achieved by introducing a summary change to para. 3.2.1 of Schedule GO1 and detailed changes to
Schedule A16, Equivalent changes are necessary in G01, para 5.3.5.1, G06, para 4.5 and minor
changes are required to various CCDs (SFS, Counter Hardware Design, SADD, Counter Installation
and Survey Requirements), for which proposed revisions are attached.
PROPOSED REVISION TO WORDING OF CODIFIED AGREEMENT:
Schedule G01, para 3.2.1, insert after first sentence:
“This interworking shall use one of the following communications access methods:
Integrated Services Digital Network (ISDN)
Integrated Satellite Business Network (ISBN), generally referred to as VSAT (Very Small Aperture
Terminal)
Frame Relay”
Ditto para 5.3.5.1
Schedule G06, Section 4.5, replace:
“BT ISDN or Frame Relay lines installation may be carried out separately and with prior notification to
Regional Liaison Manager and/or Outlet Manager (approval not required for ISDN or Frame Relay
installation provided that it is carried out during the normal working hours of the relevant outlet).
With:
ISDN, VSAT or Frame Relay lines installation may be carried out separately and with prior notification
to Regional Liaison Manager and/or Outlet Manager (approval not required for ISDN, VSAT or Frame
Relay installation provided that it is carried out during the normal working hours of the relevant outlet).
CCN No: 633 Page:
1
FUJ00000561
FUJ00000561
‘Application of changes to Schedule A16:
Reference No 467
Replace:
“Each post office configuration is linked to TMS using an ISDN or Frame Relay Wide Area
Network connection.”
With:
“Each post office configuration is linked to TMS using an ISDN, VSAT or Frame Relay Wide Area
Network connection.”
Reference No 478
Replace:
“The Pathway solution for TMS will link into each instance of OPS that is to be used for production
work using an ISDN or Frame Relay Wide Area Network connection.”
With:
“The Pathway solution for TMS will link into each instance of OPS that is to be used for production
work using an ISDN, VSAT or Frame Relay Wide Area Network connection.”
Reference No 479
Replace:
“The Pathway solution for TMS is based on a network of servers which connect to the Pathway OPS
equipment in each post office using an ISDN or Frame Relay Wide Area Network connection.”
With:
“The Pathway solution for TMS is based on a network of servers which connect to the Pathway OPS
equipment in each post office using an ISDN, VSAT or Frame Relay Wide Area Network connection.”
Replace:
“The Pathway solution for linking TMS to OPS uses ISDN or Frame Relay Wide Area connection.”
With:
The Pathway solution for linking TMS to OPS uses ISDN, VSAT or Frame Relay Wide Area Network
connection.
Reference No 517
Replace:
“BT ISDN or Frame Relay lines installation may be carried out separately and with prior notification to
the Horizon Implementation Manager and / or Outlet Manager (approval not required for ISDN or
Frame Relay installation provided that it is carried out during the normal working hours of the relevant
office).”
With:
“ISDN, VSAT or Frame Relay lines installation may be carried out separately and with prior
notification to the Horizon Implementation Manager and / or Outlet Manager (approval not required for
ISDN, VSAT or Frame Relay installation provided that it is carried out during the normal working
hours of the relevant office).”
ACCEPTANCE / IMPLEMENTATION TIMETABLE: Hardware acceptance takes place on outlet
installation. Implementation will be during the period October 2000 to February 2001.
FUJ00000561
FUJ00000561
PA/TEM/007, Version 3.0, Sheet I
CCN No: 633 Page:
2
ICL PATHWAY CHANGE CCN NO: 633b
CONTROL NOTE (CCN)
SHEET 2
CCN TITLE: Introduce Satellite Communications Access Method
COSTS TO POCL: (Including non-recurring charges and new or amended charges)
Task Man-days £
Design & Development Activities:
Testing Activities:
Sub-total
20% Contingency
TOTAL: None
IMPACT SUMMARY Impacts on Related Agreements and Services
Payment Plan/Terms of Payment: N/A
Documentation:
Codified Agreement Schedules Affected:
BP/CON/226 — Schedule G01 — POCL Infra Service Definition
BP/CON/231 — Schedule G06 — POCL Infrastructure Roll-out & Implementation
BP/CON/195 — Schedule A16 - Solutions Catalogue
New Contract Controlled & Referenced Documents: N/A
Documents Quality Reviewed: YES/NO.
Reference Title Version & Date
N/A N/A N/A
Reason for Document Update: N/A
Affected Contract Controlled/Referenced Documents:
Reference Title Version & Date
BP/DES/003 Counter Hardware Design Specification V7.0 (12/7/99)
CR/FSP/004 Service Architecture Design Document V4.0 (30/9/97)
IM/STR/026 Installation Strategy V1.0 (2/12/98)
RS/FSP/001 Security Functional Specification V4.2_(11/1/00)
IM/REQ/005 Survey Requirements Specification V4.0 (3/12/98)
Other Affected Documents (for information only):
Reference Title Version & Date
BP/REQ/006 Horizon System User Guide V1.0 (1/5/98)
CS/PRO/090 CSR+ Access Control & User Administration I V1.0 (11/2/00)
PPD
CS/PRO/097 CSR+ Operating Environment PPD V1.0 (17/2/00)
TM/REQ/030 Site Preparation Requirements V1.0 (3/12/98)
IM/REQ/038 Site Resurvey & Modification Requirements V1.0 3/12/98)
Deliverables: Counter configurations using VSAT require the use of an Ethernet connection,
with the gateway PC connecting via a separate Ethernet card to a Personal Earth Station
(PES), which comprises an Outdoor Unit (ODU) 0.98 metre antenna and a Digital Indoor Unit
(DIU) baseband signal converter. Software modifications to address the revised hardware are
as per Frame Relay solution.
CCN No: 633 Page:
3
FUJ00000561
FUJ00000561
Personnel: The installation operates without outlet staff intervention.
Existing Timetable: Installations of satellite communications will be undertaken from October
2000 to February 2001.
Implementation Plans: Minor. Planning permission to erect the antenna is not normally
required. Surveys and site preparation will take account of accommodating the PES and
connection to the gateway PC.
Security: The method uses VSAT standard secure transmission and encrypted VPN tunnels.
Risk: Low. This is a standard product line service. The software development is the same as
that already completed for the Frame Relay access method.
System Support: Failure of the PES or associated outlet equipment requires a site visit. A
switch from primary to backup satellite usage, should one occur, may require a site visit,
depending on the method used to access the backup satellite (see below).
System Management: Failure of the ground station is handled by switchover to a backup.
Failure of the transponder is handled by using spare routes. Failure of the whole satellite is
handled by switchover to a backup satellite initiated by the service provider. Reconnection of
outlets to the backup satellite will be provided by the service provider. Two methods of
reconnection will be provided. Either or both of the following alternative methods of
reconnection will be provided. ICL Pathway, its network provider and the VSAT service
provider will select the method in the light of circumstances prevailing at the time of any
failure.
(a) by repositioning a backup satellite to occupy an equivalent position to that of the failed
satellite, within three days starting on the day following failure, or
(b) by re-aligning and re-re-tuning the PES equipment to the backup satellite, at the rate of 100
outlets/day, starting on the day following failure, and with priority given to busiest offices.
Standards: N/A.
Accommodation/Location: N/A
Charging Mechanism:
Where cost estimates are included, these are quoted as a mid-point estimate of the work to be
carried out by ICL Pathway. The eventual charge will be made on an ‘actuals’ Time and
Materials basis using the same man-rates. A 20% contingency has been included in the CCN
to allow for reasonable variation around the mid-point estimate. The estimate is set so that
the ICL eventual charge is as likely to be lower as higher than the estimate excluding
contingency. The contingency is included to provide allowable headroom for invoicing
purposes against a purchase order. Above this level, ICL Pathway would have to apply for
additional approval via a new CCN.
Service Delivery Criteria: N/A
Service Levels: Satellite service availability is estimated at not less than 99.85%. Mean time for
outlet reconnection in the event of a complete satellite failure depends upon the final number
of VSAT connections but is anticipated to be less than four days regardless of method.
POCL Responsibilities: N/A
Contractual Issues: N/A.
Other: This CCN replaces that already submitted CCN633a.
FUJ00000561
FUJ00000561
PA/TEM/007, Version 3.0, Sheet 2
CCN No: 633 Page: 4
CHANGE CONTROL NOTE
Create Date: 10-APR-2000 11:54:50
Originator: Lisa Morcom (Change Management)
CCN:0633b
ID: PWY_CCN_6
Status: APPROVED
Title:
Introduce Satellite Communications Access Method
Main Description:
Related Parts
0
i
i
v
PWY:CCN.A;1
(CHANGE_MANAGEMENT)
Change Control Notes
PWY:BP-DES.A:1
(LIBRARY)
Design specification
PWY:CS-PRO.A:1
(LIBRARY)
Procedure
PWY:CC_IMPLEMENTATION_DOCS.A:;1
(MANAGEMENT)
Implementation and Training Documents
PWY:CC_ARCHITECTURE_DOCS.A:1
(MANAGEMENT)
Architecture Documents
PWY:IM-REQ.A:1
(LIBRARY)
Requirement
PWY:BP-REQ.A:1
(LIBRARY)
Requirement
Related Items
Affected
PWY:BP/DES/003.A-CONTRINT:7.0 (Affected)
2
2
4
4
(BPDES003.doc)
Lisa Morcom (Change Management)
Lisa Morcom (Change Management)
Lisa Morcom (Change Management)
Lisa Morcom (Change Management)
Lisa Morcom (Change Management)
Lisa Morcom (Change Management)
Lisa Morcom (Change Management)
Lisa Morcom (Change Management)
COUNTER HARDWARE DESIGN SPECIFICATION (NB-CCD)
Affected
PWY:CR/FSP/004.A-CONTRINT:4.0 (Affected)
(CRFSP004.zip)
Lisa Morcom (Change Management)
SERVICE ARCHITECTURE DESIGN DOCUMENT (NB-CCD)
Affected
PWY:IM/REQ/005.A-INTDOC:4.0 (Affected)
(IMREQ005.doc)
Lisa Morcom (Change Management)
HORIZON COUNTER INFRA STRUCTURE ROLLOUT SURVEY REQUIREMENT
SPECIFICATION
Affected
PWY:BP/REQ/006.A-EXTDOC;1.0 (Affected)
(BPREQ006.doc)
Lisa Morcom (Change Management)
HORIZON SYSTEM USER GUIDE FOR NEW RELEASE 2
CCN No: 633
Page:
FUJ00000561
FUJ00000561
FUJ00000561
FUJ00000561
Affected
4 PWY:CS/PRO/090.A-INTDOC;1.0 (Affected) Lisa Morcom (Change Management)
(CSPRO090.doc)
CSR+ ACCESS CONTROL AND USER ADMINISTRATION PPD
Affected
4 PWY:CS/PRO/097.A-INTDOC:1.0 (Affected) Lisa Morcom (Change Management)
(CSPROO97.zip)
CSR+ OPERATING ENVIRONMENT PPD.
Affected
4 PWY:IM/REQ/030.A-INTDOC;1.0 (Affected) Lisa Morcom (Change Management)
(IMREQ030.doc)
SITE PREPARATION REQUIREMENT
Affected
4 PWY-IM/REQ/038.A-INTDOC:1.0 (Affected) Lisa Morcom (Change Management)
(IMREQ038.doc)
SITE RESURVEY AND MODIFICATION REQUIREMENTS.
Info
7 PWY:CCN_0633_2.A-CDATTACH:1 (Info) Lisa Morcom (Change Management)
(CCN_00633_2.doc)
CCN 00633 ATTACHMENT 2
Info
9 PWY:CCN_0633_1.A-CDATTACH:1 (Info) Lisa Morcom (Change Management)
(CCN_00633_1.doc)
CCN 00633 ATTACHMENT I
Info
9 PWY:CCN_0633A_1.A-CDATTACH:1 (Info) Lisa Morcom (Change Management)
(CCN_00633a_1.doc)
CCN 00633a ATTACHMENT 1
Info
12. PWY:CCN_0633B_1.A-CDATTACH:I (Info) Lisa Morcom (Change Management)
(CCN_00633b_1.doc)
CCN 006336 ATTACHMENT 1
Related Child Change Documents:
Related Parent Change Documents:
Dependent PWY_CP_2517 CLOSED Alison.Clarke (CLARKEA)
Introduction Of Satellite Connected Post Office Outlets
Action Messages
Action Number: 1 Date Apr 11 2000 14:36:58 By: Lisa Morcom (Change Management)
CCB DECISION (MTG NO 109): CCN ISSUESThis CCN was presented for discussion only. J Dicks stated
that the associated CP2517 was to be discussed at PCCB 13/4/00. T Oppenheim/J Flynn confirmed that some
outlets cannot be serviced by Frame Relay and that K Baines had been advised of this. T Oppenheim stated
that there is no contractual obligation to connect non ISDN single counter position offices and his belief that if
offered it, POCL would accept the Satellite option for these offices. J Dicks stated that there were currently
470 single counter position non ISDN offices and J Flynn was actioned to confirm this. T Oppenheim stated
that the CCN should reconfirm satellite offer for single counter position offices. Discussion surrounding the
Business Continuity clement of this change took place and that this should be included as a caveat within the
CCN. T Oppenheim requested that the full service, implementation and technical implications of this change
should be reviewed & a standalone outline plan produced by G Chatten for both satellite & mobile CCNs. T
CCN No: 633 Page: 6
FUJ00000561
FUJ00000561
Austin identified that this change could be included in Sept/Oct B&TC regression testing. L Burchell
highlighted that a revised B&TC impact based on these dates was in progress. It was agreed that after CP
presentation to PCCB 13/4, both CP/CCN be represented to CCB 17/4 for further update.Actions:1. J Flynn to
confirm no, of single counter position, non ISDN offices.2. J Dicks to update CCN to reflect disaster
recovery/business continuity element.3. G Chatten to produce standalone outline plan for both satellite and
mobile configurations.4, CM to obtain revised B&TC impact and represent CP/CCN to CCB 17/4/00. 10.4.0
Action Number: 2 Date Apr 17 2000 09:53:43 By: Lisa Morcom (Change Management)
CHANGE CONTROL:Email received from John Dicks 14/4/00 as follows:psa revised CCN plus add-on
document for satellite for CCBThe open issues are the handling of loss of satellite, SLAs, Training,
Action Number: 2 Date Apr 25 2000 09:42:40 By: Lisa Morcom (Change Management)
CHANGE CONTROL:Revised CCN633 received from J Dicks 20/4/00. Areas where impacts are not
complete are shaded, with the exception of second sentence under "Implementation Plans" which is a new
statement,
Action Number: 5 Date May 9 2000 10:56:42 By: Lisa Morcom (Change Management)
CHANGE CONTROL:Emiail received from Horizon 9/5/00 as follows:Lisa, I have spoken to our Horizon
Business owner regarding CCN listed below.Bob Booth has requestedevidence of the comparable nature of
ISBN versus ISDN, Is there a document tosupport this request? Can you pass this onto the relevant person
within Pathway.* CCN 633: Introduce Satellite Communications Access Method await your response. (CM
this has been forwarded to J Dicks for a response).
Action Number: 6 Date May 24 2000 15:39:06 By: Lisa Morcom (Change Management)
CHANGE CONTROL:CCN633 withdrawn at the request of John Dicks 24/5/00 and email sent to Horizon as
follows:For your information, ICL Pathway are formally withdrawing CCN633 - Introduce Satellite
Communications Access Method. This is for the following reason:"ICL Pathway's supplier, Energis, has notified
us that its operator has sought to very the terms of their agreement and that it is in the course of selecting an
alternative operator.ICL Pathway will provide a revised version of the CCN when the new operator is selected".
Action Number: 6 Date Jun 1 2000 13:17:44 By: Lisa Morcom (Change Management)
CCB MTG NO 115:CCN633 - There was some discussion surrounding the withdrawal of this CCN. CM
undertook to confirm when this CCN had been withdrawn. It was agreed that a revised CCN must be submitted
as a matter of urgency and J Pope took an action to review situation, review technical issues with D Tanner and
highlight to M Coombs if contact with POCL was required prior to resubmission. It was also agreed that a
letter should be issued to Horizon clarifying assumptions made in latest version of IPP and that until approval of
this CCN received, these assumptions were liable to movement. J Flynn undertook this action. 30/5/00
Action Number: 8 Date Jun 1 2000 14:23:47 By: Lisa Morcom (Change Management)
CHANGE CONTROL:See attachment 2 in pves for comments on CCN received from Horizon 24/5/00. These
have been forwarded to John Dicks and John Pope for action.
Action Number: 9 Date Jun 13 2000 1 34 By: Lisa Morcom (Change Management)
CHANGE CONTROL:Revised CCN633a received from Dave Hollingsworth 9/6/00 with note as follows:Please
find attached the revised version of CCN 633, now identified as 633a. This takes account of the POCL
comments received on 633 (from Bob Booth) and includes the changes resulting from decisions at the 8th June
review with BT / Energis. The only additional information requirement I can think of is (possibly) for technical
details of the PES to be included in the appropriate implementation document as some stage. Bob McD et al
may need to check through any implications in this area. Since planning application is not normally required
there should be very little change to existing survey requirements documentation.! have lefi formal issue till we
have final confirmation from BT / Energis of the fallback arrangements after any switch to backup satellite since
this is applicable to the stated rate of service restoration in the CCN. This is expected (I understand) at the start
of next weekI am not clear if associated CP 2517 will be revised or a new CP raised (hopefully the former); I
CCN No: 633 Page: 7
FUJ00000561
FUJ00000561
have left existing reference to 2517 on this document. shall be out of office till Thursday 15th, but JCCD will
be back on Monday and can act as contact (sorry John, thought it might be done by now!).Rgds, Dave H
Action History
1 10-APR-2000 11:54:50 Lisa Morcom (Change Management)
MORCOML CM
Document created
12-APR-2000 15:17:30 Lisa Morcom (Change Management)
MORCOML CM
Actioned document from RAISED to CCN_ISSUES
3 04-MAY-2000 13:09:44 Lisa Morcom (Change Management)
MORCOML CM
Actioned document from CCN_ISSUES to COMMERCIAL_REVIEW
4 04-MAY-2000 13:09:49 Lisa Morcom (Change Management)
MORCOML CM
Actioned document from COMMERCIAL_REVIEW to READY_TO_SUBMIT
5 04-MAY-2000 13:26:14 Lisa Morcom (Change Management)
MORCOML CM
Actioned document from READY_TO_SUBMIT to SUBMITTED
6 24-MAY-2000 15:38:24 Lisa Morcom (Change Management)
MORCOML CM
Actioned document from SUBMITTED to WITHDRAWN
7 01-JUN-2000 14:22:54 Lisa Morcom (Change Management)
MORCOML CM
Actioned document from WITHDRAWN to RAISED
8 01-JUN-2000 14:23:10 Lisa Morcom (Change Management)
MORCOML CM
Actioned document from RAISED to WITHDRAWN
9 13-JUN-2000 14:24:33 Lisa Morcom (Change Management)
MORCOML. CM
Actioned document from WITHDRAWN to RAISED
10 19-JUN-2000 15:47:34 Lisa Morcom (Change Management)
MORCOML CM
Actioned document from RAISED to COMMERCIAL_REVIEW
11 27-JUN-2000 10:23:19 Sue Rutherford (Change Management)
RUTHERFS CM
Actioned document from COMMERCIAL_REVIEW to READY_TO_SUBMIT
12 27-JUN-2000 10:23:22 Sue Rutherford (Change Management)
RUTHERFS CM
Actioned document from READY_TO_SUBMIT to SUBMITTED
13 27-JUL-2000 18:59:54 Lisa Morcom (Change Management)
MORCOML CM
Actioned document from SUBMITTED to APPROVED
i
Update History
0 10-APR-2000 11:54:50 Lisa Morcom (Change Management)
MORCOML CM
Related Design Part PWY:CCN.A;1
1 11-APR-2000 14:36:58 Lisa Morcom (Change Management)
MORCOML CM
Added action description
17-APR-2000 09:53:01 Lisa Morcom (Change Management)
MORCOML CM
Detailed description edited
17-APR-2000 09:53:43 Lisa Morcom (Change Management)
MORCOML CM
i
i
CCN No: 633 Page: 8
v
i
i
i
i
i
i
i
i
v
i
i
Added action description
17-APR-2000 09:55:56 Lisa Morcom (Change Management)
MORCOML
Related Item PWY:CCN_0633_1.A-CDATTACH; I (Information)
17-APR-2000 09:58:06 Lisa Morcom (Change Management)
MORCOML
Related Item PWY:BP/DES/003.A-CONTRINT;7.0 (Affected)
17-APR-2000 09:58:06 Lisa Morcom (Change Management)
MORCOML
Related Design Part PWY:BP-DES.A:1
17-APR-2000 09:58:34 Lisa Morcom (Change Management)
MORCOML
Related Item PWY:CS/PRO/090.A-INTDOC;1.0 (Affected)
17-APR-2000 09:58:34 Lisa Morcom (Change Management)
MORCOML
Related Design Part PWY:CS-PRO.A:1
17-APR-2000 09:58:56 Lisa Morcom (Change Management)
MORCOML
Related Item PWY:BP/TRN/001.A-CONTRINT: 11.0 (Affected)
17-APR-2000 09:58:56 Lisa Morcom (Change Management)
MORCOML
Related Design Part PWY:CC_IMPLEMENTATION_DOCS.A:1
17-APR-2000 09:59:56 Lisa Morcom (Change Management)
MORCOML
Related Design Part PWY:CC_ARCHITECTURE_DOCS.A:1
17-APR-2000 09:59:56 Lisa Morcom (Change Management)
MORCOML
Related Item PWY:CR/FSP/004.A-CONTRINT:4.0 (Affected)
25-APR-2000 09:41:31 Lisa Morcom (Change Management)
MORCOML
Detailed description edited
25-APR-2000 09:42:40 Lisa Morcom (Change Management)
MORCOML.
Added action description
28-APR-2000 16:08:33 Lisa Morcom (Change Management)
MORCOML
Detailed description edited
04-MAY-2000 13:09:31 Lisa Morcom (Change Management)
MORCOML
Detailed description edited
04-MAY-2000 13:11:56 Lisa Morcom (Change Management)
MORCOML
Related Design Part PWY:IM-REQ.A:1
04-MAY-2000 13:11:56 Lisa Morcom (Change Management)
MORCOML
Related Item PWY:IM/REQ/005.A-INTDOC:4.0 (Affected)
04-MAY-2000 13:12:18 Lisa Morcom (Change Management)
MORCOML
Unrelated Item PWY:BP/TRN/001.A-CONTRINT:11.0
04-MAY-2000 13:12:45 Lisa Morcom (Change Management)
MORCOML
Unrelated Item PWY:CS/PRO/090.A-INTDOC;1.0
04-MAY-2000 13:13:25 Lisa Morcom (Change Management)
MORCOML
Related Item PWY:BP/REQ/006.A-EXTDOC;1.0 (Information)
04-MAY-2000 13:14:01 Lisa Morcom (Change Management)
MORCOML
Related Item PWY:CS/PRO/090.A-INTDOC:1.0 (Information)
04-MAY-2000 13:15:13 Lisa Morcom (Change Management)
MORCOML
CCN No: 633
CM
CM
CM
CM
CM
CM
CM
CM
CM
CM
CM
CM
CM
CM
CM
CM
CM
CM
CM
FUJ00000561
FUJ00000561
ww
Unrelated Item PWY:BP/REQ/006.A-EXTDOC;1.0
04-MAY-2000 13:15:13 Lisa Morcom (Change Management)
MORCOML
Unrelated Item PWY:CS/PRO/090.A-INTDOC:1.0
04-MAY-2000 13:15:36 Lisa Morcom (Change Management)
MORCOML
Related Item PWY:BP/REQ/006.A-EXTDOC:1.0 (Affected)
04-MAY-2000 13:15:36 Lisa Morcom (Change Management)
MORCOML
Related Design Part PWY:BP-REQ.A:1
04-MAY-2000 13:16:00 Lisa Morcom (Change Management)
MORCOML
Related Item PWY:CS/PRO/090.A-INTDOC;1.0 (Affected)
04-MAY-2000 13:16:24 Lisa Morcom (Change Management)
MORCOML
Related Item PWY:CS/PRO/097.A-INTDOC;1.0 (Affected)
04-MAY-2000 13:16:47 Lisa Morcom (Change Management)
MORCOML
Related Item PWY:IM/REQ/030.A-INTDOC; 1.0 (Affected)
04-MAY-2000 13:17:10 Lisa Morcom (Change Management)
MORCOML
Related Item PWY:IM/REQ/038.A-INTDOC:1.0 (Affected)
04-MAY-2000 13:23:09 Lisa Morcom (Change Management)
MORCOML
Item PWY:CCN_0633_1.A-CDATTACH;1 has been deleted
04-MAY-2000 13:26:11 Lisa Morcom (Change Management)
MORCOML
Request attribute(s) updated
09-MAY-2000 10:56:42 Lisa Morcom (Change Management)
MORCOML
Added action description
24-MAY-2000 15:39:06 Lisa Morcom (Change Management)
MORCOML.
Added action description
01-JUN-2000 13:17:44 Lisa Morcom (Change Management)
MORCOML
Added action description
01-JUN-2000 14:23:00 Lisa Morcom (Change Management)
MORCOML
Related Item PWY:CCN_06: A-CDATTACH: I (Information)
01-JUN-2000 14:23:47 Lisa Morcom (Change Management)
MORCOML
Added action description
13-JUN-2000 14:24:49 Lisa Morcom (Change Management)
MORCOML
Detailed description edited
13-JUN-2000 14:25:34 Lisa Morcom (Change Management)
MORCOML
Added action description
19-JUN-2000 15:37:38 Lisa Morcom (Change Management)
MORCOML
Related Item PWY:CCN_0633_1.A-CDATTACH;1 (Information)
19-JUN-2000 15:44:07 Lisa Morcom (Change Management)
MORCOML
Detailed description edited
19-JUN-2000 15:45:54 Lisa Morcom (Change Management)
MORCOML
Request attribute(s) updated
19-JUN-2000 15:47:24 Lisa Morcom (Change Management)
MORCOML
CCN No: 633
CM
CM
CM
CM
CM
CM
CM
CM
CM
CM
CM
CM
CM
CM
CM
CM
CM
CM
CM
CM
FUJ00000561
FUJ00000561
Related Item PWY:CCN_0633A_1.A-CDATTACH;1 (Information)
27-JUN-2000 10:02:03 Sue Rutherford (Change Management)
RUTHERFS CM
Detailed description edited
27-JUN-2000 11:45:07 Sue Rutherford (Change Management)
RUTHERFS CM
Detailed description edited
03-JUL-2000 16:47:58 Sue Rutherford (Change Management)
RUTHERFS CM
Detailed description edited
27-JUL-2000 16:23:20 Lisa Morcom (Change Management)
MORCOML CM
Related Item PWY:CCN_0633B_1.A-CDATTACH: I (Information)
27-JUL-2000 16:46:10 Lisa Morcom (Change Management)
MORCOML CM
Item PWY:CCN_0633B_1.A-CDATTACH:1 has been deleted
27-JUL-2000 16:47:26 Lisa Morcom (Change Management)
MORCOML CM
Related Item PWY:CCN_0633B_1.A-CDATTACH:1 (Information)
27-JUL-2000 19:01:15 Lisa Morcom (Change Management)
MORCOML CM
Request attribute(s) updated
02-OCT-2000 15:47:19 PCMS - CM Dept.
PCMS SCM
Request attribute(s) updated
04-OCT-2000 11:40:53 PCMS - CM Dept.
PCMS SCM
Request attribute(s) updated
04-OCT-2000 12:19:55 PCMS - CM Dept.
PCMS SCM
Request attribute(s) updated
04-OCT-2000 12:55:33 PCMS - CM Dept.
PCMS SCM
Request attribute(s) updated
Archived Attribute Information
~~ END OF CHANGE CONTROL NOTE PWY_CCN_633