FUJ00000684 - ICL Pathway Change Control Note No. 777b: Introduction of Single Point of Contact (SPoC) for postmasters to contact Support Centres

Evidence on official site

ICL PATHWAY CHANGE CCN NO: 777b
CONTROL NOTE (CCN) -

SHEET 1

CCN TITLE: CHANGE ADMINISTRATION USE ONLY.
Introduction of Single Point of Contact CR NO: RO106

(SPoC) for postmasters to contact CP NO: 2968

Support Centre's

IMPLEMENTATION DATE EXPIRY DATE: 14" August 2001
OR RELEASE: to be agreed

CCN RAISED BY: Paul Westfield DATE: 19 July 2001

EMERGENCY IMPLEMENTATION DATE:
SUBMISSION DATE: 24" July 2001
APPROVALS REQUIRED:

PATHWAY APPROVAL DATE POCL APPROVAL DATE

EXECUTIVE SUMMARY OF IMPACT ASSESSMENTS:
ICL Pathway agrees that the proposal as documented in the Single Point of Contact
Specification Document, version 1.5, dated 12 July 2001 is a technically viable
working option. It should be noted that this document is still being developed for full
agreement between ICL Pathway and POCL. Thus there are a few points to note:
1. The described 'tromboning ' effect could have serious implications on the
availability of telephone lines into the helpdesk to accept postmaster service
calls. ICL Pathway has sized the requirement for additional outbound trunk lines
to alleviate the ttomboning problem that would be seen on a typical day. ICL
Pathway agrees to the following statement proposed by POCL in response to
CCN777a.
“POCL will not be entitled to any right or remedy under the Codified Agreement in
respect of failure by ICL Pathway to achieve any Service Level to the extent that
failure was caused by the provision and/or use of the SPoC tromboning effect and,
to that extent, all Service Level measurements giving rise to such failures shall be
disregarded for the purposes of calculating or assessing such rights or remedies.

In the event of any such failure, ICL Pathway will use reasonable endeavours to
demonstrate to POCL that that failure (and the extent to which that failure) was
caused by such provision or use.”

2. ICL Pathway notes that the solution for redirected calls between the two
helpdesks is still being evaluated, as described in Section 13 of the Specification
Document.

3. Change is required to the ICL Pathway business continuity plans due to the
introduction of SPoC. These changes include updating the business continuity
tests, documents and schedules to specifically include the SPoC.

4. We confirm that ICL Pathway will not pick-up any additional costs or charges
above that of its current solution. There are two scenarios whereby ICL Pathway
will recover additional telephone call costs from POCL.

i. The postmaster has contacted the HSH in error and the HSH redirects the
call
ii. The postmaster has contacted the HSH who have partly dealt with the

CCN No: 777 Page: 1

FUJ00000684
FUJ00000684
call but then need to pass it on to the NBSC.

In each case once the call is redirected to the NBSC via the speed dial number
at the HSH, the line costs coming into the HSH and the line costs going to the
NBSC (as the line coming in will be in use whilst the NBSC resolves the query),
will be recovered from POCL. It is proposed that these costs be reported monthly
and invoiced quarterly.

5. ICL Pathway notes that the specification document will be updated with a jointly
agreed implementation plan.

The proposed change impacts the CSR+ HSH PPD (CS/PRO/0092) V3.0. This
document will need amending in Sections 3 and 4, including a diagram, to describe
the new SPoC.

HSH staff will need to be trained and their handsets updated with the speed dial for
the NBSC referrals.

ISD have already made extensive use of one of their Telecomms Specialists who
has reviewed and commented on the PON Specification Documents and attended a
joint meeting with PON.

OVERALL IMPACT ASSESSMENT: HIGH MEDIUM LOW

REASON FOR CHANGE:

The CR is to move towards the PON vision of one number for outlets to gain help,
advice and support in their day to day business transactions.

DETAILS OF CHANGE:

PON wish to move from two helpdesk telephone numbers to one utilising their NBSC
as a SPoC utilising a BT Intelligent Call Router (ICR) system to route the callers to
either the HSH or NBSC depending on the type of enquiry, to enable a seamless
operation.

PROPOSED REVISION TO WORDING OF CODIFIED AGREEMENT:

G10, 4.3 additional paragraph

Telephone answering SLAs will be measured from the point the redirected
telephone call enters the HSH telephone switch.

G01, 6.12.1 The Horizon System Helpdesk contact point for the Single Point of
Contact (SPoC) shall be a local rate telephone number.

A01, Definition of SPoC and what it means in terms of the contract to be proposed
by POCL and agreed by ICL Pathway.

ACCEPTANCE / IMPLEMENTATION TIMETABLE: TBA

FUJ00000684
FUJ00000684

PA/TEM/007, Version 3.0, Sheet 1

CCN No: 777 Page: 2
ICL PATHWAY CHANGE CCN NO: 7776
CONTROL NOTE (CCN)
SHEET 2

CCN TITLE: Introduction of Single Point of Contact (SPoC) for postmasters
to contact Support Centre’s

COSTS TO POCL: (including non-recurring charges and new or amended charges)

Task Man-days £

Design & Development Activities:
Testing Activities:
Documentation (PPD)

HSH Training/Updating

ISD Telecomms Consultancy
Business Continuity Plans

@ £543 / day = 1,670.00

@ £835 / day = 5,010.00
@ £1,337 / day = 6,685.00
@ £1,337 / day = 4,011.00

Sub-total 17,376.00

oe}
SI ale aan

20% Contingency 3,475.00

TOTAL: £20,851.00

IMPACT SUMMARY /mpacts on Related Agreements and Services

Payment Plan/Terms of Payment: 100% on completion. Should PON decide not
to proceed with this change, ICL Pathway will levy any charges that have been
incurred to date.

Documentation:

Codified Agreement Schedules Affected: G10, G01 6.12.1, A01

New Contract Controlled & Referenced Documents: No

Documents Quality Reviewed: YES/NO

Reference Title Version & Date

Reason for Document Update:
The document will need amending in Sections 3 and 4, including a diagram, to
describe the new SPoC.

Affected Contract Controlled/Referenced Documents:

Reference Title Version & Date

CS/PRO/0092 I CSR+HSHPPD-CSR+ Horizon System V3.0 12.12.00
Helpdesk Processes and Procedures

Description
Other Affected Documents (for information only):
Reference Title Version & Date

Deliverables: N/A

Personnel: Helen Pharoah

Existing Timetable: N/A

Implementation Plans: N/A

Security: N/A

Risk: N/A

System Support: N/A

System Management: N/A

Standards: N/A

CCN No: 777 Page: 3

FUJ00000684
FUJ00000684
Accommodation/Location: N/A

Charging Mechanism:

Where cost estimates are included, these are quoted as a mid-point estimate of the
work to be carried out by ICL Pathway. The eventual charge will be made on an
‘actuals’ Time and Materials basis using the same man-rates. A 20% contingency
has been included in the CCN to allow for reasonable variation around the mid-point
estimate. The estimate is set so that the ICL eventual charge is as likely to be lower
as higher than the estimate excluding contingency. The contingency is included to
provide allowable headroom for invoicing purposes against a purchase order. Above
this level, ICL Pathway would have to apply for additional approval via a new CCN.

Service Delivery Criteria: N/A

Service Levels: N/A

POCL Responsibilities: N/A

Contractual Issues: N/A

Other: N/A

FUJ00000684
FUJ00000684

PA/TEM/007, Version 3.0, Sheet 2

CCN No: 777 Page: 4
CHANGE CONTROL NOTE

ID: PWY_CCN_777_  CCN:0777b Create Date: 30-MAR-2001 13:48:26
Status: APPROVED Originator: Lisa Morcom (Change Management)

Intro Of Single Point Of Contact (Spoc) For Postmasters To Contact Support Centre's

Main Description:

Related Parts

0 PWY:CCN.A:1 Lisa Morcom (Change Management)
(CHANGE MANAGEMENT)
Change Control Notes

1 PWY:CS-PRO.A;1 Lisa Morcom (Change Management)
(LIBRARY)
Procedure

1 PWY:CD_ATTACH.A:1 Ken. Westfield

(CHANGE_MANAGEMENT)
Change Document Attachments

6 PWY:CA_SCHEDULE_G.A;1 Ken, Westfield
(LIBRARY)
CODIFIED AGREEMENT Schedule G Documents

6 PWY:CA_SCHEDULE_A.A;1 Ken, Westfield
(LIBRARY)

CODIFIED AGREEMENT Schedule A Documents

Related Items
Affected
1 PWY:CS/PRO/092.A-INTDOC:3.0 (Affected) — Lisa Morcom (Change Management)
(CSPRO092.doc)
CSR+ HORIZON SYSTEM HELPDESK PPD
Affected
6 PWY:BP/CON/235.A-CONTREXT:2.0 (Affected) Ken.Westfield
(BPCON235.doc)
CODIFIED AGREEMENT SCHEDULE G10 - POCL INFRA SERVICE LEVELS & REMEDIES
Affected
6 PWY:BP/CON/226.A-CONTREXT;2.0 (Affected) Ken. Westfield
(BPCON226.doc)
CODIFIED AGREEMENT SCHEDULE G01 - POCL INFRA SERVICE DEFINITION
Affected
6 PWY:BP/CON/180.A-CONTREXT:2.0 (Affected) Ken.Westfield
(BPCONI80.doc)
CODIFIED AGREEMENT SCHEDULE A01 - INTERPRETATIONS

Related Child Change Documents:

Related Parent Change Documents:

CCN No: 777 Page: 5

FUJ00000684
FUJ00000684
FUJ00000684

FUJ00000684

Dependent PWY_CP_2968 CLOSED PCMS - CM Dept. (PCMS)

Introduction O} gle Point Of Contact (Spoc) For Postmasters To Contact Support Centres
Info PWY_PDACR_475 APPROVED Ken. Westfield (WESTFIELDK)

Introduction of Single Point of Contact (SPOC)

Action Messages

Action Number: 1 Date Apr 12 2001 10:29:43 By: Lisa Morcom (Change Management)
CHANGE CONTROL:Extension to 24/4/01 for CR RO106 agreed at JCCB 11/4/01.

Action Number: 1 Date Apr 25 2001 13:47:22 By: Ken Westfield

Change Control:Mecting between POCL and P Westfield, resulted in POCL to re-issue report by 4th May
2001. P Westfiel would then comment in following week. Extension requested on 23rd April 2001 to 11th May
2001 (on assumption report received by 4th).

Action Number: 3 Date Jun 6 2001 08:59:23 By: Alison Clarke (Change Management)

CCB DECISION (MTG No. 166) - DECISION: SUBMIT CCN 05/06/01 CCN 777, raised in response to
CRO106, had initially been rejected by POCL, but had been updated (CCN 777a) and was presented to CCB by
P Westfield. CCB were informed that the technical documentation had now been received from POCL and the
CCN reissued and that it was believed to be viable to proceed. P Westfield cited a neutral impact on Pathway
with no cost increase. It was stated that POCL's preferred carrier was BT but that Pathway might want to
retain the ability to move this to another carrier as required.Concern was also raised about POCL changing the
TVR at will and redirecting calls from NBSC to HSH to cover excessive calls. S Muchow suggested that this
should be covered by change control. S Muchow suggested that the wording of points 1 & 2 oft he Summary of
Impact Assessments in the CCN should be altered. P Jeram questioned whether the costs shown in the
Business Case were accurate. CCB approve for submission with the following actions: 1.P Westfield to refine
the CCN on advisement from S Muchow. 2. P Westfield/Change Management to address/revise costs shown.

3. Commercial to advise on appropriate change control e.g. CCD or not.

Action Number: 4 Date Jul 20 2001 14:36:42 By: Ken Westfield (Change Management)
Change Management:New CCN 777b loaded into PVCS as supplied from P. Westfield for presentation to
CCB.

Action Number: 6 Date Aug 15 2001 10:04:06 By: Ken Westfield (Change Management)
Change Management:CCN approved subject to hand amendments. These have been incorporated within the
PVCS copy and were agreed by the F & C Director.

Action History

1 30-MAR-2001 13:48:26 Lisa Morcom (Change Management)
M

MORCOML Cc
Document created .

2 05-JUN-2001 18:02:08 Ken. Westfield ;
WESTFIELDK “Chg Memt
Actioned document from RAISED to COMMERCIAL REVIEW

3. 05-JUN-2001 18:02:22 Ken. Westfield t.
WESTFIELDK Chg Mgmt

Actioned document from COMMERCIAL REVIEW to SUBMITTED
4 16-JUL-2001 09:20:24

WESTFIELDK Chg Mgmt

Actioned document from SUBMITTED to REJECTED

CCN No: 777 Page: 6
5 20-JUL-2001 14:36:52 Ken. Westfield:
WESTFIELDK
Actioned document from REJECTED to READY.

6 = 24-JUL-2001 08:12:10 Ken. Westfield
WESTFIELDK Chg Mgmt
Actioned document from READY_TO_SUBMIT to

7 15-AUG-2001 10:04:10 Ken. Westfield”
WESTFIELDK Chg Mgmt
Actioned document from SUBMITTED to APPROVED

Update History

0 30-MAR-2001 13:48:26 Lisa Morcom (Change Management)
MORCOML CM
Related Design Part PWY:CCN.A:1

1 30-MAR-2001 13:49:35 Lisa Morcom (Change Management)
MORCOML CM
Related Design Part PWY:CS-PRO.A;1

1 30-MAR-2001 13:49:35 Lisa Morcom (Change Management)
MORCOML CM
Related Item PWY:CS/PRO/092.A-INTDOC:3.0 (Affected)

1 12-APR-2001 10:29:43 Lisa Morcom (Change Management)
CM

MORCOML
Added action description
1 25-APR-2001 13:47:22
WESTFIELDK
Added action description
1 O1-JUN-2001 12:03:52
WESTFIELDK
Detailed description edited
1 O1-JUN-2001 12:05:29
WESTFIELDK
Request attribute(s) updated
1 O1-JUN-2001 12:06:33
WESTFIELDK

Chg Mgmt

Ken. Westfield {7

Chg Mgmt

Ken, Westfield
Chg Mgmt

Ken. Westfield: _
Chg Memit

Related Design Part PWY:CD_ATTACH.A:1

1 O1-JUN-2001 12:06:
WESTFIELDK

Related Item PWY:CP_02968_2.A-CDATTAC!

1 O1-JUN-2001 12:07:14
WESTFIELDK

Related Item PWY:CP_02968_3.A-CDATTACH;,

1 O1-JUN-2001 17:41:12
WESTFIELDK
Detailed description edited
1 05-JUN-2001 11:15:29
WESTFIELDK
Detailed description edited
1 05-JUN-2001 11:16:23
WESTFIELDK
Request attribute(s) updated
1 05-JUN-2001 11:19:07
WESTFIELDK

Unrelated Item PWY:CP_02968_2.A-CDATTAC

1 05-JUN-2001 11:19:
WESTFIELDK

Unrelated Item PWY:CP_02968_3.A-CDATTAC!

1 05-JUN-2001 17:20:55
WESTFIELDK
Detailed description edited
1 05-JUN-2001 18:01:38

CCN No: 777

Ken. Westfield {
Chg Mgmt
0 (In Response To)

Ken. Westfield!

Chg Mgmt
(In Response To)

Ken.Westfield) GRO!

Ken. Westfield I

Ken. Westfield.

Ken. Westfield

Ken. Westfield {7

Ken. Westfield I

Page:

FUJ00000684
FUJ00000684
6

6

6

6

6

Archived Attribute Information

WESTFIELDK

Detailed description edited
06-JUN-2001 08:59:23

CLARKEA

Added action description
06-JUN-2001 09:06:37

CLARKEA

Action descriptions edited
16-JUL-2001 09:20:12

WESTFIELDK

Request attribute(s) updated
20-JUL-2001 14:35:20

WESTFIELDK

Detailed description edited
20-JUL-2001 14:36:42

WESTFIELDK

Added action description
24-JUL-2001 08:11:49

WESTFIELDK

Detailed description edited
24-JUL-2001 08:14:12

WESTFIELDK

Request attribute(s) updated
07-AUG-2001 13:35:23

WESTFIELDK

Chg Mgmt

Chg Mgmt

Chg Mgmt

Ken, Westfield:

Chg Mgmt

Ken. Westfield {7
Chg Memt

Ken. Westfield {

Chg Mgmt

Ken. Westfield{~
Chg Mgmt

Ken.Westfiel

Cig Mgmt

Related Design Part PWY:CA_SCHEDULE_G.A:

07-AUG-2001 13:35:23
WESTFIELDK

Related Item PWY:BP/CON/235.A-CONTREX’

07-AUG-2001 13:35:24
WESTFIELDK

Ken. Westfield

Chg Mgmt

Ken. Westfield :
Chg Mgmt

Related Item PWY:BP/CON/226.A-CONTREXT:2.0 (Affected)

07-AUG-2001 13:35:24
WESTFIELDK

Related Design Part PWY:CA_SCHEDULE_A.A:

07-AUG-2001 13:35:24
WESTFIELDK

Related Item PWY:BP/CON/180.A-CONTREXT;

15-AUG-2001 10:03:28
WESTFIELDK

Detailed description edited
15-AUG-2001 10:04:06
WESTFIELDK

Added action description
15-AUG-2001 10:10:02
WESTFIELDK

Request attribute(s) updated
17-SEP-2001 17:25:07
WESTFIELDK

Request attribute(s) updated
19-AUG-2003 15:10:16
ARAINT

Request attribute(s) updated

CCN No: 777

Ken.Westfieldi.. zx
Chg Mgmt
0 (Affected)

Ken. Westfield { +
Chg Mgmt

Ken. Westfiel

Chg Mgmt

Ken. Westfield),

Che Mgmt

Ken. Westfield! 71
Chg Mgmt

Tariq Arain
SCM

------ END OF CHANGE CONTROL NOTE PWY_CCN_777 ----