FUJ00058337 - Report re Phase 1c (North East) Weekly Progress, Issue 2 (Version 1.0).

Evidence on official site

FUJ00058337

FUJ00058337

ICL Pathway Phase 1C (North East) Ref: IM/REP/016

Version: 1.0

Weekly Progress Report Date: 02/12/97

Document Title: Phase 1C (North East) Weekly Progress Report
Document Type: Report
Issue: 2
Abstract: This weekly report summarises the progress of the

upgrade of the North East release 1b sites to release 1c.
(The data in this report is based upon the 1B - 1C
Migration schedule - version 24, dated 11/11/97)

Status: Issued

Distribution: Liz Moran - POCL Mick Ledger - POCL
Bob McDermott Mark Fisk
Bob McKain Barry Hancill
Billy Herd Greg Couper
Library

Author: David Howells

Comments to: David Howells

Comments by:

© 1997 ICL Pathway Ltd

COMMERCIAL IN CONFIDENCE Page 0 of 12
FUJ00058337

FUJ00058337
ICL Pathway Phase 1C (North East) Ref: IM/REP/016
Version: 1.0
Weekly Progress Report Date: 02/12/97
0 Document control
0.1 Document history
Version Date Reason
0.1 12/11/97 First issue
0.2 21/11/97 Second and final issue
1.0 02/12/97 Issued
0.2 Approval authorities
Name Position Signature Date
0.3 Associated documents
Reference Vers Date Title Sourc
e

0.4 Abbreviations
SPMR Subpostmaster

COMMERCIAL IN CONFIDENCE Page 1 of 12
FUJ00058337

FUJ00058337
ICL Pathway Phase 1C (North East) v Ref: MIREP IONS
‘ersion:
Weekly Progress Report Date: 02/12/97

0.5 Changes in this version

Updates from the second week of the migration programme. Also issues
collated from Exel and HFSOs have been included here.

0.6 Table of content

1 INTRODUCTION...

2 SCOPE.

3 Progress for Friday 7" November to Thursday 21% Novembet.................:+ 4
4 OUTSTANDING SUNDRIES... cece eeee es eeeeeee cece ee eeeeeeeeeeeseneeeeeeeeetee 4
5 MISCELLANEOUS. ...0......eceececcceeesesesesceseseseseseeseeesescseeecacseseeescscseaeeeeeseaeee 10
6 SCHEDULE SUMMARY....0.........ccceccsecscesseeeeceseseececeseseseeceeseeseseeeeeeeseeeseees 11

COMMERCIAL IN CONFIDENCE Page 2 of 12
FUJ00058337

FUJ00058337
ICL Pathway Phase 1C (North East) Ref: IM/REP/016
Version: 1.0
Weekly Progress Report Date: 02/12/97
1 INTRODUCTION

41

This weekly report summarises the progress of the migration of release 1b
Horizon post offices in the North East to release 1c. The purpose of this
report is to provide the POCL region with a summary of the progress to
date against the planned activity in this region, a summary of the planned

activities in the following week and outstanding sundry activities.

SCOPE

This report only covers the implementation activities for this phase within
the region and is not intended to include any reporting requirements for
outlets in steady state within the region.

Progress for Friday 7° November to Thursday 21°

November
ACTIVITY PLANNED I ACTUAL
1c Migrations 85 85
OUTSTANDING SUNDRIES

CURRENT ISSUES/OUTLETS ON HOLD

None.

COMMERCIAL IN CONFIDENCE

Page 3 of 12
FUJ00058337

FUJ00058337
ICL Pathway Phase 1C (North East) v Ref: MIREP IONS
‘ersion:
Weekly Progress Report Date: 02/12/97

4.2 Exel Issues

The following table details the issues noted by Exel during the migrations in

the offices.
FAD Office Comments
Code
163329 I Bates OM did not have supply of benefit slips. Installers}
Cottages used their contingency supply but HFSO believedI
that all the 1b installations she was at had not been
left supply of slips, till rolls etc. which should have}
been the procedure.
163329 I Bates A4 printer was moved from underneath counter toI
Cottages top. OM not happy as this interferes with coin rack.
(cont) It was agreed to leave A4 printer off the counter]
(not used at moment) but office will need to beI
revisited.
200328 I Beadnell HFSO one hour late (not aware of 8am start)
201328 I Belford No PMMC cards in base unit, DOA Ithica

174329 I Benton Rd Monitor screen 'wavy' - Swapped out
158329 IBlaydon _on/Blue screen before Riposte. SCZ swapped.
Tyne
153328 I Cambo No PMMC card

404329 I Chapel House] Keyboard swapped (sticking keys)
204329 I Clayton Rd Blue screen on SCZ. Base unit swapped.

205329 I Coatsworth Prior to installers arrival, the kit had beenI
Rd repositioned with the Ithicas disconnected and
placed under the counter. SPMR was insistent kit
could not be positioned correctly. Greg Couper
visited office and compromise reached. SCZ
swapped.

220329 I Dinnington Hung at 3%,rebooted OK
228329 IEastbourne Installers were not aware they had to calibrate}

Gdns screens before beginning Autoconfig.
208328 I Embleton ISDN line failed, no light. Seemed to selfI
correct??

245329 I Grange Park INo PMMC in overshipper.

249329 I Hazelrigg No bar code label. Entered manually.
252329 I Killingworth I Scanner exchanged

211328 I Lesbury Bar code label missing.

FAD - Office ee Comment — SS
COMMERCIAL IN CONFIDENCE Page 4 of 12

FUJ00058337

FUJ00058337
ICL Pathway Phase 1C (North East) Ref: IM/REP/016
Version: 1.0
Weekly Progress Report Date: 02/12/97
Code vee : oo .
285329 I Low Dead On arrival GMI, no power - no disk error onI
Simonside replacement - SCZ error at least one server orI
driver failed - 2 GMI and 1 SCZ swapped.
228328 I Lowick No grommet hole for scanner. Completed w/c}
24/11/97
288329 I Matfen No light on ISDN box. Line reset at BT exchange.
294329 I Nelson Could not read PMMC card during POLO process -
Village Printer cable replaced.

470329 I Newsham Error message - at least one service or driver]
Farm failed. System rebooted.

214328 I North DOA Ithica
Sunderland

310329 IPalmersville IInstallers had to wait to gain entry. Issue with
positioning of Ithica printers. (B. Herd informed)

469329 I Riding Mill Dead On Arrival keyboard

303329 ISt Nicholas IPMMC not attached to Gateway

354329 I Station Rd System calibrated but would not scan label

190328 I Thropton Issue with placement of base unit blocking accessI
to safe. Repositioned on B. Herd instructions

378329 I West Boldon I Gateway retrying at 3% - CLI test fail - Ithica would
not print POLO pin number - 1 keyboard and 1
Ithica swapped.

401329 I Whitley Bar codes missing on 2 machines - need to haveI

Lodge new set printed.

402329 I Wilton Drive ISwipe readers cannot be used without moving}
keyboards out each time from underneath monitor]
stand. Suggest Office should be revisted. SPMR
and husband remained until 07:15pm to allow
installation to complete.

394329 I Winlaton No Riposte screen on last counter. SCZ swapped.
Ithica DOA also swapped.

COMMERCIAL IN CONFIDENCE Page 5 of 12
FUJ00058337

FUJ00058337
ICL Pathway Phase 1C (North East) Ref: IM/REP/016
Version: 1.0
Weekly Progress Report Date: 02/12/97
4.3 HFSO Reports

The following are usability comments collected from the HFSOs during their
visits to offices. These offices were selected as being potential problem

Offices.
FAD Office Usability Comments
Code
198328 IAlnmouth I Only complaint - length of bar code scanner.
154329 IAnnitsford I Keyboard under monitor stand needs to be reversed
or pulled out for use. No spare space available.
163329 I Bates Equipment slightly out of reach but should not cause
Cottages any problems.
200328 I Beadnell No problems.
201328 I Belford No problems.
158329 IBlaydon on/No problems in operating the system based on the
Tyne current positioning of the equipment and the space
available.
204329 I Clayton The Post Office counter is a little narrow. Using the
Road keyboard may present problems when BES cards are
in full use.
157328 I Ellington Monitor and printer on 2nd terminal are on a high
shelf to the right. Unable to see lights on printer.
Office is for sale and is expected to be relocated in
the near future.

N/A IEmbleton Position of kit in usable position, although there are
two serving positions only one kit is installed. There
are 2 part-time staff and 1 SPMR.

245329 I Grange OM has smashed 2 glass shelves on the counter to
Park enable monitor and keyboard to fit and still use
swipe facility. Pos. 3 has monitor on a stand and to
use the swipe facility you have to pull out the
keyboard 6 inches. Gateway printer overhangs 2-3
inches.
248329 I Hartford A very small Post Office with limited space. The
Colliery only way the system will operate is to pull the
keyboard out from under the monitor stand to access
the swipe facility.
163328 I High Market] The Ithica printer for position 2 is stored sideways,

but enough cable has been left to enable easy
movement to a correct serving position when in full
service.

COMMERCIAL IN CONFIDENCE Page 6 of 12
ICL Pathway

FUJ00058337

FUJ00058337

Phase 1C (North East) Ref: IM/REP/016

Version: 1.0

Weekly Progress Report Date: 02/12/97

_ FAD
_ Code

_ Office

- Comments

330329

458329

272329

252329

275329

211328

167328

212328

228328
294329

176328

306329

Hillhead

Humshaugh

Kenton
Road

Killingworth

Kirkwhelp-
ington

Lesbury

LongframI-
ington

Longhough-
ton

Lowick

Nelson
Village

North
Broomhill

Otterburn

The system is set-up on the left-hand side of the
serving hatch. The SPMR and staff are right-
handed so the system is not as easy to use as they
would like.

Keyboard has to be pulled forward or reversed in
order to use it.

The Gateway is rarely used but the Ithica printer is
resting on a slope because part of it is on the foot
holding the screen in place. Holes drilled in the
counter partially obstruct the serving positions and
looks untidy.

All using monitor stands - swipe facility hidden so
keyboards will either have to be reversed or pulled
from under stands for use. Keyboards overlap
counter by approx. 1/3rd when pulled out from under
the stands.

At the moment the keyboard is in the middle of the
serving position. The OM has asked if she can have
a shelf put on the right-hand side of the serving
position for the printer to be put on. Then the
keyboard can go underneatb the shelf.

SPMR happy with days events. Space although
very limited houses Horizon kit okay.

Unable to access swipe card facility without pulling
out keyboard. Use of A4 printer very difficult when it
will be required. A shelf would be very useful in this
respect.

No problems encountered with usability.

No problems.

If both positions are in use counter space is minimal
and the keyboards may have to be turned around.
At present there is only one person working behind
the counter so the keyboard can be used correctly.

SPMR has at times difficulty reading the screen as
she wears bi-focals.

The printer for the Gateway terminal needs to be put
on the right-hand side of the monitor or put on a
shelf above the monitor. For the slave terminal the
printer was moved to the right-hand side of the
monitor.

COMMERCIAL IN CONFIDENCE Page 7 of 12
FUJ00058337

FUJ00058337
ICL Pathway Phase 1C (North East) Ref: IM/REP/016
Version: 1.0
Weekly Progress Report Date: 02/12/97

FAD I Office Comments —

_ Code oe . a i

469329 I Riding Mill I The extra work was not carried out and the installers
had no knowlegde of the problem. The counter
serving space would be reduced if the printer was
moved to the left. A stand for the monitor would be
a great improvement for both space and ease of
use.

320329 IRochester INo problems.

217328 IShilbottle I Sub-Postmaster has built a shelf onto the side of the
counter to allow movability of the counter equipment.

461329 ISlaley The swipe can only be used when it is back to front
and pushed under the monitor stand.

357329 ISunniside I Gateway - keyboard and Ithica moved to sit on
counter top shelf instead of lower shelf. A4 printer
moved up a shelf to a better site after improvement
work.

190328 IThropton _I Alarm switch was moved and situated on the side of
the counter. The OM could not open the safe door
as the base unit was in the way. The base unit was
turned at an angle so the safe could be opened.

371329 IWalbottle I The desktop printer is pushed behind and to the left
of the monitor which when needed for general use
will be difficult to operate. It is also wobbling on the
shelf it stands on.

371329 IWalbottle I The keyboard is on a drawer which opens up from

(cont) under the monitor - in full use it will be difficult to
operate the BES cards. There is limited space in the
outlet - more space could be made if the letter scales
were located away from the PO secure area.

378329 I West Adequate space for use.

Bolden

383329 IWest Moor I Adequate space for use.

391329IWideopen IThe slave station is close to the parcel hatch on the
right hand side, but the OM is left handed so there
isn't much of a problem. OM was asked if there was
any major problems with usability and there wasn't.

392329 I Willington INo problems that would affect the use of the

Quay equipment at this office.

402329 I Wilton SPMR is unable to access the swipe reader as the

Drive keyboard lies partly under the monitor stand. The
height of the monitor cannot be raised as the SPMR
wears bi-focals.

FAD I Office” Comment

COMMERCIAL IN CONFIDENCE Page 8 of 12
ICL Pathway

Phase 1C (North East)
Weekly Progress Report

Ref:
Version:
Date:

FUJ00058337
FUJ00058337

IM/REP/016
1.0
02/12/97

5.1

5.2

Code

395329

467329

Winlaton No problems. Monitor was moved from counter to
Mill shelf 2 weeks ago - much better.

Woodlands I No problems with the use of the equipment at this

Office.

MISCELLANEOUS

Site Preparations

Four sites have been identified in the North East that require additional site
preparation works prior to the migration to 1c, Thropton (190328), Kenton
Road (272329), Winlaton Mill (395329) and Sunniside (357329). These works
where completed as planned and the sites were migrated to 1c within the
normal schedule.

Scheduling

A further change to the order of the Exel vans was made in the second week
to make better use of the spare van. This van was allocated offices at the
start of each day. This reduced the number of drops per van down to two or
three outlets a day.

COMMERCIAL IN CONFIDENCE

Page 9 of 12
FUJ00058337

FUJ00058337
ICL Pathway Phase 1C (North East) Ref: IM/REP/O16
Version: 1.0
Weekly Progress Report Date: 02/12/97
6 SCHEDULE SUMMARY
Refer 1B-1C Migration Schedule, version 31, dated 20/11/97
6.1 Week 1
Fa

COMMERCIAL IN CONFIDENCE Page 10 of 12
FUJ00058337

FUJ00058337
ICL Pathway Phase 1C (North East) Ref: IM/REP/O16
Version: 1.0
Weekly Progress Report Date: 02/12/97

6.2 Week 2

COMMERCIAL IN CONFIDENCE Page 11 of 12