FUJ00079316 - Agreement between POST OFFICE COUNTERS LTD and ICL PATHWAY LIMITED (Second Supplemental Agreement CCN)

Evidence on official site

FUJ00079316
FUJ00079316

THIS SECOND SUPPLEMENTAL AGREEMENT, being Change Control Note (CCN)

No. 560 is made the 24th day of September, 1999

BETWEEN:

(1)

(2)

POST OFFICE COUNTERS LTD., whose registered office is at Gavrelle House, 2-14
Bunhill Row, London EC1Y 8HQ; and

ICL PATHWAY LIMITED, whose registered office is at 26 Finsbury Square, London
EC2A 1DS (the “Contractor”).

WHEREAS:

(A)

(B)

(©)

(D)

(E)

This Second Supplemental Agreement is supplemental to the Codified Agreement
between the parties dated 28th July, 1999 (the “Codified Agreement”) and constitutes
CCN No. 560 of that Codified Agreement.

The Contractor and POCL have been carrying out the Operational Trial and the other
Acceptance Procedures in accordance with the Codified Agreement.

By a Supplemental Agreement dated 20th August, 1999 (the “First Supplemental
Agreement”) the parties agreed that CSR Acceptance had not been achieved at the end
of the CSR Operational Trial Review Period.

By the First Supplemental Agreement the parties agreed, inter alia, a programme of
work with a view to achieving Acceptance and Release Authorisation by

24th September, 1999, and also agreed that only certain elements of the Core System
Release were required to be re-submitted for testing in the Second CSR Acceptance Test
and that only certain faults could be raised as Acceptance Incidents in relation to the
Second CSR Acceptance Test.

As at the date of this Second Supplemental Agreement the following Acceptance
Incidents (in addition to those categorised as category (c) faults) remain outstanding:-

(i) Category (b) Faults which are Substantive New Faults reported to the Contractor
after 3rd September, 1999 in respect of which no timetable for resolution has

been agreed

Those Acceptance Incidents described in Part A of Schedule 1; and

(ii) Faults not falling within recital (E)(i) above

Those Acceptance Incidents described in Part B of Schedule 1.
It is Agreed as follows

1.

11

1.2

13

14

Interpretation

Words and expressions defined in the Codified Agreement or the First Supplemental
Agreement shall bear the same meanings when used in this Agreement.

In this Agreement the expression “POCL” shall bear the meaning ascribed thereto in the
Codified Agreement.

Unless the context otherwise requires references in this Agreement to clauses, Recitals
and Schedules are to clauses of, and Recitals and Schedules to, this Agreement.

In this Agreement, unless the context otherwise requires:-

“Accounting Integrity Control Release” means the software release to implement
the functionality described in the TIP Control CCD .

“Accounting Integrity Control Release Date” means the date on which the
Accounting Integrity Control Release shall have been:-

(i) developed in accordance with the TIP Control CCD;

(ii) demonstrated by appropriate testing to have met the specification set out in the
TIP Control CCD;

(iii) observed in operation, / during a live observation period comprising two cash
account weeks, in all Outlets to which Rollout shall have taken place as at the
beginning of such observation period; and

(iv) fully deployed in all Outlets to which Rollout shall have taken place at such date.

“Cash Account Discrepancies” has the meaning ascribed thereto in Clause 7.1.

“Liabilities” means losses, costs, claims, charges, demands, expenses and liabilities.

“Rectification Plan” has the meaning ascribed to it in Clause 3.1.

“Rectification Timetable” means the document so described and initialled by the
parties or their legal advisers for the purposes of identification.

“TIP Control CCD” means the CCD entitled “Logical Design for EPOSS/TIP
Reconciliation Controls”.

“TIP Integrity Checking Period” means the period from the date of this Agreement
until the expiry of a period of four consecutive weeks after the Accounting Integrity
Control Release Date in which the TIP Integrity Checking Process shall have identified

FUJ00079316
FUJ00079316
2.1

2.2

3.1

3.2

3.3

3.4

3.5

no Cash Account Discrepancies not also identified by the Accounting Integrity Control
Release.

“TIP Integrity Checking Process” means the process to be performed by POCL
pursuant to clause 7.1.

“TIP Interface” means the systems interface described in paragraph 3.4.1 of Schedule
G01 to the Codified Agreement and defined in the CCD entitled “Pathway to TIP
Application Interface Specification”.

CSR Acceptance

The parties agree that CSR Acceptance shall be deemed to have been achieved as at
the date of this Agreement.

POCL acknowledges that the Release Authorisation Board has, in reliance on the terms
of this Agreement, authorised national rollout of the Core System with effect from
execution of this Agreement by both parties hereto.

Remedy of Outstanding Faults

The Contractor undertakes to use its reasonable endeavours to resolve each of the
outstanding Acceptance Incidents referred to in Part B of Schedule 1 in accordance with
the rectification plans listed Schedule 2 (“Rectification Plans”) and the Rectification
Timetable. POCL shall use its reasonable endeavours to comply with the obligations
imposed on it in the Rectification Plans. In the event of any conflict between Schedule
2 and the Rectification Timetable the provisions of Schedule 2 shall prevail.

For the avoidance of doubt, notwithstanding that the express provisions of Schedule 2
may purport to impose absolute obligations on the parties, the parties’ obligations in
respect thereof shall be limited to using their respective reasonable endeavours to
perform them.

If any of the outstanding Acceptance Incidents referred to in Part B of Schedule 1 shall
not have been remedied by the use of such reasonable endeavours by the due date
contained within the Rectification Timetable the Contractor shall continue to use
reasonable endeavours to resolve such Incident at its own expense as soon as
practicable thereafter and, where applicable, POCL shall continue to use its reasonable
endeavours to co-operate in such resolution in a manner consistent with the
co-operation required of it under the Rectification Plans.

The provisions of clause 3.4 of the First Supplemental Agreement shall apply in relation
to Acceptance Incidents referred to in Part A of Schedule 1.

All work carried out by the Contractor, its agents and its sub-contractors in remedying
any of the Acceptance Incidents referred to in Part A of Schedule 1 shall be at the sole
risk and expense of the Contractor.

FUJ00079316
FUJ00079316
3.6 The Contractor shall co-operate and join with POCL in providing such information and
explanation to the Post Office’s auditors as such auditors may reasonably require in
order to satisfy themselves that the audit reports of the Post Office and POCL should
not be qualified or contain a fundamental uncertainty paragraph as a result of the
circumstances giving rise to Acceptance Incident 376.

4. First Supplemental Agreement

4.1 Clauses 5, 6 and 7 of the First Supplemental Agreement shall be superseded by this
Agreement and shall cease to apply with effect from the date hereof. The remaining
provisions thereof shall continue in effect insofar as they remain applicable.

4.2 For the avoidance of doubt, clause 4.6 of the First Supplemental Agreement shall
continue to apply.

5. Variation of Roll Out Programme

The Roll Out Programme in Annex 1 to Schedule A12 to the Codified Agreement shall be
replaced in its entirety by the Roll Out Programme set out in Schedule 3 to this Agreement.

6. Suspension of Rollout

6.1 Tf

6.1.1 any of the criteria in parts A to C of Schedule 4 shall not have been met by 24
November, 1999; or

6.1.2 the Accounting Integrity Control Release Date shall not have occurred by 14 January,
2000; or

6.1.3 any of the criteria set out in part D of Schedule 4 shall not have been met by 14
January, 2000

POCL shall be entitled by notice to the Contractor to postpone the resumption of Rollout
from 24 January, 2000 until such later date as shall be agreed pursuant to clause 6.2
below.

6.2 If POCL gives notice pursuant to clause 6.1 above the parties shall meet as soon as
reasonably practicable thereafter with a view to agreeing and documenting:-

6.2.1 a plan and timetable for re-testing and demonstrating the satisfaction of each of the
criteria set out in Parts A to D (inclusive) of Schedule 4 not then satisfied; and

6.2.2 a revised Roll Out Programme to take effect once the satisfaction of all such criteria
shall have been demonstrated and the Accounting Integrity Control Release Date shall
have occurred.

FUJ00079316
FUJ00079316
7A

7.2

73

74

75

8.1

8.2

8.3

FUJ00079316
FUJ00079316

TIP Integrity Checking Process

POCL agrees that during the TIP Integrity Checking Period it shall, on a weekly basis,
carry out a process of creating a cash account from individual transaction data received
by it across the TIP Interface, comparing such cash account with the electronic cash
account received by it from the Contractor across the TIP Interface, reporting to the
Contractor any discrepancies between such accounts (“Cash Account Discrepancies”)
and providing to the Contractor such co-operation as shall be necessary in order to
enable the Contractor to investigate such Cash Account Discrepancies.

In consideration for POCL performing the TIP Integrity Checking Process the Contractor
shall pay to POCL a charge calculated as follows:-

(i) a fixed charge of £228,000; plus
(ii) a charge of £229 for each discrepancy reported to the Contractor.

The charge referred to in Clause 7.2(i) shall be due on the date of this Agreement and
shall be paid, together with VAT thereon, within 23 days of receipt by the Contractor of
an invoice therefor.

The charge referred to in clause 7.2(ii) shall be invoiced and paid, together with VAT
thereon, on a monthly basis, each invoice to be paid within 30 days of receipt thereof by
the Contractor.

POCL shall be entitled to set off any amount owing to it under this clause 7 against any
charges payable by it to the Contractor under the Codified Agreement.

Indemnity

The Contractor shall indemnify and keep indemnified POCL on demand (on an after tax
basis) against all Liabilities (other than any costs and expenses incurred in applying the
TIP Integrity Checking Process) which POCL may suffer or incur as a result of any
matter or circumstance arising prior to the Accounting Integrity Control Release Date
which it would not have suffered or incurred had the Accounting Integrity Control
Release Date occurred on the date hereof.

The Contractor shall not be liable under clause 8.1 above in respect of any Liability
suffered or incurred by POCL to the extent that such Liability would not have been
suffered or incurred but for a failure by POCL to apply the TIP Integrity Checking
Process in accordance with POCL's procedures therefor.

In the event of any matter or circumstance arising in respect of which the Contractor
may be liable under clause 8.1 above, POCL shall promptly notify the Contractor of such
matter and shall permit the Contractor, at the Contractor’s expense, for a period of four
weeks from notification of such matter to investigate and seek to resolve the matter
and/or mitigate the Liability in question. POCL shall provide to the Contractor, at the
Contractor’s expense, such co-operation as the Contractor shall reasonably request to
enable the Contractor to take such action.

8.4 The provisions of clause 810 of the Codified Agreement shall apply to any liability of the
Contractor under this Agreement. For the avoidance of doubt any liability incurred by
the Contractor under this Agreement shall be included within the aggregate liability of
the Contractor under the Codified Agreement for the purposes of Clause 810.2.3 of the
Codified Agreement.

9. First Roll Payment

If by 13 November, 1999 Roll Out shall have occurred to a number of Outlets being less than
1,800 but not less than 1,600 then the First Progress Payment of £90 million under paragraph 1
of Schedule A12 to the Codified Agreement shall be reduced to £80 million (before any
deduction pursuant to paragraph 7.2 of the said Schedule A12) and shall become due on the
later of Ist November, 1999 and the date upon which Roll Out shall have occurred in 1,600
Outlets. If so, the second Progress Payment shall be payable as currently scheduled in
paragraph 1 of Schedule A12 but shall be increased to £100 million (before any deduction
pursuant to paragraph 7.2 of Schedule A12). The figures of £80 million and £100 million
referred to in this clause equate to gross figures of £106.67 million and £133.33 million before
retention of 25 per cent. from each figure in accordance with the said paragraph 1 of Schedule
A12.

10. Further Delays

For the purposes of Clause 606.2.1 of the Codified Agreement any delay in Rollout of the Core
System caused by the default of POCL shall be disregarded to the extent that the aggregate
duration of all such delays does not exceed 42 days.

11. Further Obligation:

The Codified Agreement (including as appropriate its schedules) shall be amended so as to
impose upon the Contractor those additional ongoing obligations described in Schedule 5 and
such other obligations (if any) required by the Rectification Plans and any documents referred to

therein which the Parties agree should be treated as ongoing obligations (such agreement not
to be unreasonably withheld).

12. Miscellaneous

12.1 The provisions of clause 603 of the Codified Agreement shall apply, mutatis mutandis,
to any notice to be given by POCL under this Agreement.

12.2. No delay or omission by POCL in exercising any right, power or remedy under this
Agreement shall:-

(i) affect that right, power or remedy; or

(ii) operate as a waiver of it.

FUJ00079316
FUJ00079316
12.3

12.4

12.5

12.6

12.7

FUJ00079316
FUJ00079316

The single or partial exercise of any right, power or remedy under this Agreement shall
not preclude any other or further exercise of it or the exercise of any other right, power
or remedy.

The rights, powers and remedies provided in this Agreement are cumulative and not
exclusive of any rights, powers and remedies provided by law.

Any payment to be made by the Contractor under clause 8.1 of this Agreement shall be
made without deduction or set off on any account whatsoever.

The provisions of this Agreement shall be deemed to be incorporated as appropriate as
amendments to the Codified Agreement.

Except to the extent expressly amended by this Agreement the provisions of the

Codified Agreement and its schedules shall continue unamended and in full force and
effect.

IN WITNESS WHEREOF this Second Supplemental Agreement has been executed on

behalf of the parties as follows:-
FUJ00079316
FUJ00079316

SCHEDULE 1

Outstanding Category (a) and (b) Faults

Part A
intive New Faults Re r 34 mber, 1!

[None]
FUJ00079316
FUJ00079316

PartB
Acceptance Incidents with Rectification Plans
Acceptance Incidents 211, 218, 298, 314, 342, 369,
372, 376, 378, 390, 391, 408 and 412

each as described in the corresponding Acceptance Incident Forms contained in the Annex to
this Agreement
13.

FUJ00079316
FUJ00079316

10

SCHEDULE 2
Rectification Plans

For Remedy of Outstanding Acceptance Incidents

Documents referred to in the text of this Schedule and the timetable are annexed to this
Agreement. That Annex has been initialed for the purposes of identification.

AIN 211

The Contractor shall apply each of the fixes detailed in the Acceptance Incident Analysis Form
for AIN 211 (“Form 211”) by the date specified for such fix in Form 211.

Where no date is specified in Form 211 for the application of a fix, the Contractor confirms
that that fix has been successfully applied for all Outlets to which Rollout has occurred as of
the date of this Agreement.

The Contractor shall monitor the effectiveness of the action taken by it to resolve the incident.

When the monitoring referred to in paragraph 1.3 demonstrates over a period of four
consecutive weeks that resolution of AIN 211 has been achieved, then POCL will close AIN
211.

AIN 218

Each of the Contractor and POCL shall complete the steps and achieve the objectives
applicable to it (the “218 Obligations”) detailed in section 3 and the Contractor shall meet the
critical success factors (the “Criteria”) detailed in the table headed “Critical Success Factors” in
Document CR/ACD/218 (Version 0.5) (dated 23rd September, 1999).

Each of the Contractor and POCL shall fulfil each of the 218 Obligations applicable to it and
the Contractor shall ensure that all the Criteria are met by 31st December, 1999.

When the 218 Obligations and all the Criteria shall have been satisfied, then POCL will close
AIN 218.

AIN 298

Each of the Contractor and POCL shall complete the steps and achieve the objectives
applicable to it (the “298 Obligations”) detailed in section 5 of Document CR/ACD/298
(Version 0.8) (dated 23rd September, 1999) ("CR/ACD/298”) and where that section identifies
one party as fulfilling an action, the other party shall assist the aforementioned party to reach
a successful conclusion.

Each of the Contractor and POCL shall complete each of the 298 Obligations applicable to it
by the dates and to the standards set out in section 5 of CR/ACD/298.
15.6

17.

FUJ00079316

FUJ00079316

11

Without prejudice to the generality of the above paragraphs 3.1 and 3.2, the criteria to be
met in respect of AIN 298 by 24" November, 1999 are as set out in Part A of Schedule 4 of
this Agreement.

The Contractor shall, until closure of AIN 298, record and report to POCL such data as shall be
necessary to enable POCL to calculate the number of Units being recorded as defined in
paragraph 3 of Part A of Schedule 4 to this Agreement.

For the avoidance of doubt, it is agreed that the Contractor shall be permitted to continue the
good business practice of carrying out planned reboots outside working hours, such planned
reboots not to exceed an average of one per Counter Position per month.

Without prejudice to the generality of the above paragraphs 3.1 and 3.2, as described in
paragraph 5.5.2 of CR/ACD/298, the Contractor shall produce and deliver to POCL by 30"
October, 1999 the document referred to in that paragraph for review and agreement by 24"
November, 1999 and the Contractor shall implement the provisions of that revised document
by 24% November, 1999.

When the criteria in paragraph 3.3 and the obligations in paragraph 3.6 shall have been
satisfied, POCL will close AIN 298.

AIN 314

The Contractor shall produce and deliver to POCL a document entitled “ICL Pathway
Generalised API for OPS/TMS” (the “API Document”).

The Contractor shall produce the API Document in accordance with sections 2 (“Scope”), 3
(“Document Standards”) and 4 (“Content of ICL Pathway Generalised API for OPS/TMS”) of
Document CR/SPE/007 (Version 0.3) (dated 7th September, 1999) (“CR/SPE/007”).

The Contractor and POCL shall review the version of the API Document referred to in
sub-paragraph 4.4(A) as described in section 3 of CR/SPE/007.

The Contractor shall produce and deliver the API Document to POCL:

(A) as a version for review without the “Appendix” (as defined in paragraph 5(A) of
CR/SPE/007) before ist December, 1999;

(B) as a revised version without the Appendix incorporating the changes arising from the
review referred to in the above sub-paragraph 4.4(A) and paragraph 4.3 as a CCN
before 28th December, 1999; and

(C) with the Appendix before 1st February, 2000 as a CCN.

POCL will close AIN 314 on approval of the CCN referred to in sub-paragraph 4.4(C).

AIN 342
19.

FUJ00079316

FUJ00079316

12

Until 1st October, 1999 the Contractor shall monitor the operation of the procedures detailed
in the Acceptance Incident Analysis Form for AIN 342 (“Form 342”) under the heading “New
Procedures”.

The Contractor shall ensure that the daily automatic and email reports described in Form 342
under the headings “Program Changes Required” and “New Procedures” (under sub-heading
“b. Central Processing Delays”, paragraph 2) are produced.

When the monitoring detailed in paragraph 5.1, or such other monitoring as the parties may
agree, demonstrates that AIN 342 has been resolved and the requirements of paragraph 5.2
are being fulfilled, POCL will close AIN 342.

AIN 369

Each of the Contractor and POCL shall complete the steps and achieve the objectives
applicable to it (the “369 Obligations”) detailed in the table (in two parts) extracted from
Document BA/ACC/020 (version 0.4) (dated 20th September) (“BA/ACC/020”) and where that
table identifies one party as fulfilling an action, the other party shall assist the aforementioned
party to reach a successful conclusion.

Each of the Contractor and POCL shall complete each of the 369 Obligations applicable to it
by 31st December, 1999.

When the 369 Obligations shall have been satisfied by the Contractor and POCL, POCL will
close AIN 369.

On the completion of the Contractor's 369 Obligations where the Contractor has taken the
lead on actions to be fulfilled (as referred to in BA/ACC/020), POCL shall confirm to the
Contractor in writing that such obligations have been completed. However, this confirmation
shall not affect any other of the Contractor's obligations to ensure that AIN 369 is ultimately
resolved, in accordance with BA/ACC/020.

AIN 372

The Contractor shall complete the steps detailed in Document CR/ACD/372 (Version 0.4)
(dated 16th September, 1999) (“CR/ACD/372”) in paragraph 5.2:

(A) at sub-paragraph 6 (headed “.dll checking”) by the time at which the step detailed in
paragraph 7.4 below is completed; and

(B) _ at sub-paragraph 3 by the later of the completion of the steps detailed in
sub-paragraphs 7.2(A) and 7.2(B) below plus one week.

The Contractor shall complete the steps detailed in CR/ACD/372 in paragraph 5.2 at
sub-paragraph 7, in the case of:
19.4

20.

20.3

21.

211

FUJ00079316

FUJ00079316

13

(A) running the software distribution of the “Riposte Peripheral Server (Update Number
20)” by 16th December, 1999, although the Contractor shall aim to ensure distribution
by 30th September, 1999; and

(B) running the software distribution of the “Consolidated EPOSS/Counter Applications
Upgrade” by 16th December, 1999, although the Contractor shall aim to ensure
distribution by 15th October, 1999.

The Contractor shall supply the appropriate supporting documentation as described in
paragraph 5.2 of CR/ACD/372 by ist November, 1999.

The Contractor shall review the software distribution undertaken in pursuance of the above
sub-paragraphs 7.2(A) and (B) in accordance with paragraph 5.2.1 of CR/ACD/372 by 16th
March, 2000, or if earlier, three months from the date on which the steps detailed in
paragraph 7.2 above are both completed.

When the obligations referred to in sub-paragraphs 5.2(3) and 5.2(6) of CR/ACD/372, the
software distributions referred to in the above paragraph 7.2, the supply of the supporting
documentation referred to in paragraph 7.3 above; and the review of the software distribution
referred to in paragraph 7.4 above shall have been completed, POCL will close AIN 372.

AIN 376

Each of the Contractor and POCL shall complete the steps and achieve the objectives
applicable to it (the “376 Obligations”) set out in Document CR/ACD/376 (Version 0.9) (dated
23rd September, 1999) (“CR/ACD/376”) and where that document identifies one party as
fulfilling an action, the other party shall assist the aforementioned party to reach a successful

conclusion.

Each of the Contractor and POCL shall complete each of the 376 Obligations applicable to it
by the dates and to the standards set out in CR/ACD/376.

When the TIP Integrity Checking Period ends, POCL will close AIN 376.

AIN 378

In accordance with the details set out in the Acceptance Incident Analysis Form for AIN 378
(“Form 378”) and in Document CR/ACD/378 (Version 0.3) (dated 16th September, 1999), the

Contractor confirms that it has analysed the incidents in Form 378.

The Contractor shall apply a “Diagnostic”, which shall be effective by 1st October, 1999, which
shall:

(A) detect and prevent null Cash Account IDs, if necessary by forcing the Outlet to re-run
the cash account process; and

(B) log diagnostic messages to facilitate further analysis.
23.3

24.

FUJ00079316
FUJ00079316

14

After a sufficient level of data has been acquired from the Diagnostic, the Contractor shall
promptly determine the cause of TIP 916 and shall promptly apply an appropriate fix and
monitor its application until the fix is successful for a continuous period of two weeks.

When the fix referred to in paragraph 9.3 shall have been successful for a continuous period
of two weeks, POCL will close AIN 378.

AIN 390

As described in the Acceptance Incident Analysis Form for AIN 390 the Contractor shall
introduce a facility whereby, subject to paragraph 10.2 below, following a crash of the APS at
a counter and when undertaking session recovery or disaster recovery (for those transactions
where a system receipt has been produced), the user shall still have the option of reserving a
gap of transactions and delaying recovery to a more convenient time.

The facility detailed in the above paragraph 10.1 is subject to the qualification that in the
event of a second crash occurring before the initial recovery is completed, the procedure shall
be that the clerk shall undertake recovery of all those deferred transactions and then any
other transactions that may have occurred as a result of the second crash.

The facility detailed in the above paragraph 10.1 shall be applied by the Contractor to all
Outlets to which Roll-Out has occurred as at that date of application by 30th November, 1999
and the Contractor shall then monitor the facility.

When the monitoring referred to in paragraph 10.3 shall have demonstrated over a
continuous period of two weeks that resolution of AIN 390 has been achieved, then POCL will
close AIN 390.

AIN 391

The Contractor shall complete the steps (the “391 Obligations”) detailed in paragraphs 5.1.2
and 5.2 of Document CR/ACD/391 (Version 1.0) (dated 13th September, 1999)
(“CR/ACD/391”) and POCL shall comply with its obligations under paragraph 5.2 of
CR/ACD/391.

The Contractor shall complete the 391 Obligations in accordance with the timetable and
standards set out in paragraphs 5.1.2 and 5.2 of CR/ACD/391.

When the obligations (with the exception of the obligations relating to timetable) detailed in
paragraphs 11.1 and 11.2 shall have been completed, POCL will close the incident.

AIN 408
Each of the Contractor and POCL shall complete the outstanding steps applicable to it (the

“408 Obligations”) set out in the table in paragraph 5.4 of Document CR/ACD/408 (Version
1.5) (dated 23rd September, 1999) (“CR/ACD/408”).
24.3

25.

FUJ00079316

FUJ00079316

15

Each of the Contractor and POCL shall complete to a satisfactory standard the 408 Obligations
applicable to it in accordance with the timetable set out in the table in paragraph 5.4 of
CR/ACD/408.

When the obligations (with the exception of the obligations relating to timetable) detailed in
paragraphs 12.1 and 12.2 shall have been completed, POCL will close the AIN 408.

AIN 412

Each of the Contractor and POCL shall complete the steps and objectives applicable to it (the
“412 Obligations”), and all intermediate actions required to achieve those steps, set out in the
table at Section 6 of Document CR/ACD/412 (Version 0.2) (dated 10th September, 1999)
(“CR/ACD/412”) and (with the exception of item 1 in that table) as described in more detail in
section 5 of CR/ACD/412.

Each of the Contractor and POCL shall complete to a satisfactory standard the 412 Obligations
applicable to it (and all intermediate steps and objectives) in accordance with the timetable
set out at Section 6 of CR/ACD/412.

When the obligations (with the exception of the Obligations relating to timetable) detailed in
paragraphs 13.1 and 13.2 shall have been completed, POCL will close incident 412.
16

SCHEDULE 3

Revised Roll Out Programme

Roll Out Programme

PartA
Week Commencing Number of Outlets (inc.

live trial)
Already rolled out 299
23/08/99 24
30/08/99 1
06/09/99 47
13/09/99 80
20/09/99 158
27/09/99 178
04/10/99 203
11/10/99 203
18/10/99 203
25/10/99 203
01/11/99 203
08/11/99 0
15/11/99 0
22/11/99 0
29/11/99 0
06/12/99 0
13/12/99 0
20/12/99 0
27/12/99 0
03/01/00 0
10/01/00 0
17/01/00 0
24/01/00 120
31/01/00 180
07/02/00 250
14/02/00 306
21/02/00 306
28/02/00 306
06/03/00 306
13/03/00 306
20/03/00 306
27/03/00 306
03/04/00 306
10/04/00 306
17/04/00 244
24/04/00 244
01/05/00 244
08/05/00 306
15/05/00 306
22/05/00 306
29/05/00 244
05/06/00 306

FUJ00079316
FUJ00079316
17

Week Commencing

Number of Outlets (inc.
live trial)

12/06/00 306
19/06/00 306
26/06/00 306
03/07/00 306
10/07/00 306
17/07/00 306
24/07/00 306
31/07/00 306
07/08/00 306
14/08/00 306
21/08/00 306
28/08/00 244
04/09/00 306
22/09/00 306
18/09/00 306
25/09/00 306
02/10/00 306
09/10/00 306
16/10/00 306
23/10/00 306
30/10/00 306
06/11/00 306
13/11/00 306
20/11/00 306
27/11/00 306
04/12/00 306
11/12/00 0
18/12/00 0
25/12/00 0
01/01/01 0
08/01/01 306
15/01/01 306
22/01/01 306
29/01/01 306
05/02/01 306
12/02/01 290
19/02/01 275
26/02/01 265
05/03/01 237
Sub total 17,797

FUJ00079316
FUJ00079316
18

Part B

Qutlets to be Rolled Out under
Operational Business Change

Week Commencing

Number of Outlets (inc.
live trial)

12/03/01 165
19/03/01 120
26/03/01 100
02/04/01 85
09/04/01 63
16/04/01 50
23/04/01 30
30/04/01 22
07/05/01 20
14/05/01 18
21/05/01 16
28/05/01 15
04/06/01 14
11/06/01 12
Sub total 730
National Roll Out Total 18,527

FUJ00079316
FUJ00079316
26.

27.

28.

FUJ00079316

FUJ00079316

19

SCHEDULE 4

Acceptance Incident Rectification Criteria

PartA
System Stability (A.I. 298'

The criterion shall be measured in relation to the Counter Positions in those Outlets to which
Rollout shall have occurred by 1st October, 1999, provided that that is not less than 750
Outlets. If that shall be less than 750 Outlets then the criterion shall be measured in relation
to the Counter Positions in those Outlets in respect of which Rollout shall have occurred at the
end of the week in which Rollout shall have occurred in relation to 750 Outlets. For this
purpose a “week” is a week commencing on a date specified in the first column of the Rollout
Programme and the number of Outlets shall include the live trial Outlets.

The criterion to be met by 24th November, 1999 shall be that during the period from 18th
October, 1999 until 14th November, 1999 the total number of Units reported to the Help Desk
in relation to the relevant Outlets shall not exceed the aggregate number of Counter Positions
in those Outlets multiplied by the fraction 4/13.

For this purpose a Unit shall be measured as follows:-
(i) each Help Desk authorised reboot shall count as one Unit;
(ii) each Help Desk authorised office snapshot print preview shall count as one Unit;

(iii) each work-around authorised by the Help Desk to remove a “no entry” sign which
denies a legitimate function shall count as half a Unit;

(iv) each work-around authorised by the Help Desk to remove the necessity to carry out a
reboot or office snapshot print preview where the time taken to carry out such
work-around (as demonstrated by the Contractor in the test environment normally
used to validate test scripts) is less than 4 minutes shall count as half a Unit.

(v) each work-around authorised by the Help Desk to remove the necessity to carry out a
reboot or office snapshot print preview where the time taken to carry out such

work-around (as demonstrated by the Contractor in the test environment normally
used to validate test scripts) is 4 minutes or longer shall count as one Unit; and

Part B

TIP Interface Accounting Integrity (A.I. 376)

FUJ00079316

FUJ00079316

20

The criteria to be met by 24th November, 1999 shall be as follows:-

(i)

(ii)

(iii)

(iv)

wv)

during the period from 3rd October, 1999 until 14th November, 1999 the percentage
of Cash Accounts received by POCL across the TIP Interface containing Cash Account
Discrepancies shall not exceed 0.6 per cent of all such Cash Accounts;

during the period from 3rd October, 1999 until 14th November, 1999, no Cash Account
Discrepancy shall arise as a result of a cause previously reported to POCL as having
been remedied;

all new causes of Cash Account Discrepancies identified after the date of this
Agreement shall have been properly analysed by the Contractor and suitable
rectification plans therefor submitted to POCL in reasonable detail within ten days of
the Contractor becoming aware of such Cash Account Discrepancy;

The Contractor shall have satisfied POCL (POCL acting reasonably) that the
Accounting Integrity Control Release would, had it been deployed at the relevant
time, have identified all Cash Account Discrepancies reported prior to 24th November,
1999 which shall have arisen as a result of any new cause identified after the date of
this Agreement; and

those elements of the Rectification Plan for Acceptance Incident 376 required to have
been carried out by 24th November, 1999 shall have been duly carried out.
FUJ00079316
FUJ00079316

21

Part C

Helpdesk Performance (A.I. 408)

The criteria to be met by 24th November, 1999 are as follows:-

(a) Service Targets
That each of the following service targets, measured on a weekly basis, shall be met in at
least four of the six weeks which fall between 4th October, 1999 and 14th November, 1999 (but so
that not all such service targets have to be met in the same four weeks):-
(i) that part of the service target referred to in paragraph 4.3.2.1 of Schedule G10 to the
Codified Agreement as refers to the answering of at least 80% of all calls to the Help
Desk within 20 seconds;
(ii) the service target contained in paragraph 4.3.2.3 of the said Schedule G10;
(iii) the service target contained in paragraph 4.3.2.4 of the said Schedule G10;
(iv) __ the service targets contained in paragraph 4.3.2.5 of the said Schedule G10; and

(v) the service targets contained in paragraph 4 of Schedule 5.
(i)

(ii)

(iii)

FUJ00079316
FUJ00079316

22

Accou
The criteria to be met by 14th January, 2000 are as follows:-

during the period from 3rd October, 1999 until 14th January, 2000 the percentage of Cash
Accounts received by POCL across the TIP Interface containing Cash Account Discrepancies
shall not exceed 0.6 per cent. of all such Cash Accounts;

during the period from 3rd October, 1999 until 14th January, 2000 no Cash Account
Discrepancy shall arise as a result of a cause previously reported to POCL as having been
remedied; and

all new causes of Cash Account Discrepancies identified after the date of this Agreement shall
have been properly analysed by the Contractor and suitable rectification plans therefor
submitted to POCL in reasonable detail within ten days of the Contractor becoming aware of
such Cash Account Discrepancy.
FUJ00079316
FUJ00079316

23

SCHEDULE 5

Additional Obligations

System Stability

A new paragraph 4.6 shall be added to Schedule G10 to the Codified Agreement as follows:-

“4.6

4.6.1

Reboot Incidents

The Contractor shall use all reasonable endeavours to ensure that the number of
Reboot Incidents reported to the Help Desk does not exceed the equivalent of one
Reboot Incident per automated Counter Position in any period of four months.

4.6.2 For the purposes of paragraph 4.6.1 above “Reboot Incident” shall mean Help Desk

4.6.3

authorised reboots, Help Desk authorised office snapshot print previews and any
work-arounds authorised by the Help Desk to remove the necessity to carry out a
reboot or office snapshot print preview where the time taken to carry out such
work-around (as demonstrated by the Contractor in the test environment normally
used to validate test scripts) is four minutes or longer.”

For the avoidance of doubt, it is agreed that the Contractor shall be permitted to
continue the good business practice of carrying out planned reboots outside working
hours, such planned reboots not to exceed one per count position per month.

Training

A new obligation shall be imposed upon the Contractor as follows:-

“The

Contractor shall:-

(i) in relation to those Outlets to which Rollout is scheduled to take place in or
after January, 2000 run 370 half day training events for 4,400 office managers
(or such lesser number as POCL may require) in accordance with the
specification contained in the document IM/PRO/172, version 0.2 -
specification of pre-entry event;

(ii) with effect from the date of this Agreement deploy the processes and procedures set
out in the document IM/PRD/066, version 0.2 - Monitoring of Trainer Quality;

(iii) with effect from 27th October, 1999, implement the new P.S.A. process
defined in the document entitled Pathway Performance Standard Assessment
Proposal, Low Level Plan.
FUJ00079316
FUJ00079316

24

3. Monitoring of Non-Polled Outlets

A new obligation shall be imposed on the Contractor to operate, with effect from the date of
closure of Acceptance Incident 342, the new reporting process described in CP2078, which will
produce an automatic report of Outlets in respect of which there is no End of Day marker in the
central journal file and shall ensure that such report is e-mailed daily to the Business Support Unit and
logged with the Help Desk for immediate investigation.

4. Help Desk Service Targets

New paragraphs 4.3.2.7, 4.3.2.8 and 4.3.2.9 shall be added to Schedule G10 to the Codified
Agreement as follows:-

“4.3.2.7 100% of calls made to the Help Desk seeking advice and/or guidance relating to cash
accounts shall be answered and satisfactorily dealt with, as and when first
received, by personnel skilled in providing such advice and/or guidance.

4.3.2.8 No call will be made to the Help Desk from any Outlet seeking the same
advice or guidance in relation to a cash account as another call from the same
Outlet in the same accounting period.

4.3.2.9 Approved call scripts shall be correctly followed by Help Desk staff in 95% of
all calls, as measured by reviews of call records carried out from time to time
by POCL.”
25

Signed by

for and on behalf of
POST OFFICE COUNTERS
LTD. in the presence of:-

Signed by

for and on behalf of
ICL PATHWAY LIMITED
in the presence of:-

€A992450029

FUJ00079316
FUJ00079316
FUJ00079316
FUJ00079316

26

CHANGE CONTROL NOTE

TD: PWY_CCN_560. CCN:0560 Create Date: 15-OCT-1999 19:09:10
Status: APPROVED Originator: Lisa Burchell (CHG/DOC MGMT)

Title:

Second Supplemental Agreement

Main Description:

Related Parts

0 PWY:CCN.A;1 Lisa Burchell (CHG/DOC MGMT)
(CHANGE_MANAGEMENT)
Change Control Notes

Related Items
Info
3. PWY:CCN_00560_1.A-CDATTACH:1 (Info) Lisa Burchell (CHG/DOC MGMT)
(CCN_00560_1 zip)
CCN 00560 ATTACHMENT 1

Related Child Change Documents:

Related Parent Change Documents:

Action Messages

1 15-OCT-1999 19:09:10 — Lisa Burchell (CHG/DOC MGMT)
BURCHELL cc /DC
Document created
15-OCT-1999 19:09:20 Lisa Burchell (CHG/DOC MGMT)
BURCHELL cc/DC
Actioned document from RAISED to APPROVED
3 15-OCT-1999 19:16:42 Lisa Burchell (CHG/DOC MGMT)
BURCHELL CC /DC
Actioned document from APPROVED to RAISED

vv
4

Update History

27

15-OCT-1999 19:16:51 Lisa Burchell (CHG/DOC MGMT)
BURCHELL cc /DC
Actioned document from RAISED to APPROVED

15-OCT-1999 19:09:10 Lisa Burchell (CHG/DOC MGMT)

BURCHELL cc /DC
Related Design Part PWY:CCN.A;1

15-OCT-1999 19:16:46 — Lisa Burchell (CHG/DOC MGMT)

BURCHELL cc /DC
Related Item PWY:CCN_00560_1.A-CDATTACH;]1 (Information)
09-OCT-2000 13:02:07 PCMS - CM Dept.

PCMS

Request attribute(s) updated
01-JUL-2003 18:55:17
TUFFSN

Request attribute(s) updated

Archived Attribute Information

AUTH_APPR_RQD=NO

ao END OF CHANGE CONTROL NOTE PWY_CCN_560 ----