POA Operations Major Incident Procedure
Procedure Definition
HNG-X
This document describes the POA Operations Major Incident
Management Procedure.
APPROVED
Mike Woolgar — POA Operations
As listed on pages 4 and 5 for
Mandatory Review
Optional Review
Issued for information
For information
Dave Hulbert (POL), Mark Weaver (POL), Gary Blackburn (POL)
Richard Barber POL) Antonio Jamasb(POL)
Security Risk YES
Assessment Confirmed
Approval Authorities:
Signature
Tony Atkinson POA Head of Service See Dimensions for record of approval
Management
©Copyright Fujitsu Services Ltd 2012
FUJITSU RESTRICTED (COMMERCIALIN Ref: SVMI/SDM/PRO/0001
CONFIDENCE) Version: 7.0
Date: 16-January-2012
PageNo: tof 1
FUJ00080222
FUJ00080222
(oe) POA Operations Major Incident Procedure .
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN
CONFIDENCE)
0 Document Control
0.1 Table of Contents
0 DOCUMENT CONTROL.........cscscsssssessnssssescesssssssesssessseeseasaestecseenenseeesensneseeeesaeaee 2
0.1 Table of Contents. 2
0.2 Document History. 4
0.3 Review Details.. 5
0.4 Acceptance by Document Review. 6
0.5 Associated Documents (Internal & External 6
0.6 Abbreviations. 7
0.7 Glossary... 8
0.8 Changes Expecte 8
0.9 Accuracy... 8
0.10 Security Risk Assessmen' 8
1 INTRODUCTION.. od
141 9
1.2 9
2 10
3 DEFINITION OF A MAJOR INCIDENT.........esssssssessssessssessesseeessesscectesecessenssnensents 11
3.1 Incident Classification................ easensee
3.2. Influencing Factors in calling a Major Inciden'
3.3. Major Incident Trigger:
3.3.1 Network Triggers...
3.3.2 Infrastructure Components Trigger:
3.3.3 Data Centre Triggers..
3.3.4 Online Service Trigge:
3.3.5 Security Triggers...
4 CALLING THE MAJOR INCIDENT.
5 PROCESS FLOW.
5.1. Process Description (Any reference below made to T,
T+3 = Time Incident Occurred plus 3 minutes)..............
6 CONFERENCE CALLG........ccsccscsssssssesesssnssssesesssseseacesseeesensenssescesensnseseseseseeseneeeees 22
6.1. Technical Bridg
6.2 Service Bridge..
7 FORMAL INCIDENT CLOSURE & MAJOR INCIDENT REVIEW..........scsscseeee 25
7.1 Calculating potential LD liability for Major Incidents............:0008 11 26
8 FUJITSU ROLES AND RESPONSIBILITIES DURING A MAJOR INCIDENT.....27
©Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIALIN Ref: SVMISDM/PRO/0001
CONFIDENCE) Version: 7.0
Date: 16-January-2012
PageNo: of 1
FUJ00080222
FUJ00080222
POA Operations Major Incident Procedure
Fe)
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN
CONFIDENCE)
8.1 Role of the HSD IMT.
8.2 Role of the Major Incident Manager.
8.3 Role of the Problem Manager...
8.4 Role of the Technical Recovery Manage
8.5 Role of the SDUs: Technical Teams / Third Parti
8.6 Role of the Service Delivery Manager owning the affected se
9 POST OFFICE / FUJITSU INTERFACES.
10 APPENDICES
10.1 List of Templates....
10.2 Major Incident Manager Contact Details.
10.3 Out of Hours Duty Manager Contact Detail
10.4 POA Service Delivery Manager Contact Details.
10.5 Escalation Communication Protoco 34
10.6 Security Major Incident: 34
10.7 Roles. 34
10.8 Communication Process Flo
10.9 Special Situations...
10.9.1 Personnel Absenc
10.9.2 OOH.
10.9.3 Duty
©Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVM/SDM/PRO/0001
CONFIDENCE) Version: 7.0
Date: 16-January-2012
PageNo: 3 of 1
FUJ00080222
FUJ00080222
(oe) POA Operations Major Incident Procedure
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN
CONFIDENCE)
0.2 Document History
Version No. Date Summary of Changes and Reason for Issue Associated Change -
CP/PEAK/PPRR
Reference
ot 03-Oct-06 First draft — to detail the Major Incident Escalation process. Draft
taken from Horizon Document CS/PRD/122, V1.0.
1.0 11-Oct-06 Revision following comments from Reviewers
2.0 02-Sep-08 Changes for Acceptance by Document Review: insertion of
Section (0.4) containing table of cross references for Acceptance
by Document Review and addition of note to front page. No other
content changes.
24 24-Feb-2009 I Changes made for Acceptance by Document Review by Fiona
‘Woolfenden including the removal of references to CS/PRD/O74
which has been Withdrawn and replaced by SVM/SD/PRO/0018
and other tidying up changes.
Other changes to update Contact details
22 14-Apr-2009 Some Personnel Name changes and POA to POA +
Abbreviations. Security Updates to sections 5.1, 6.3, 8.2.1, 9.0,
23 3-June-2009 Some Personnel Changes and minor changes following review in
May 2009
3.0 T-duuly-2009 Following security audit 2 minor changes. Alan Simpson now on
distribution and 6.3, an extra bullet entry added at end of list
3.0 7-duly-2009 Following security audit 2 minor changes. Alan Simpson now on
distribution and 6.3, an extra bullet entry added at end of list.
34 14-Jan-2010 Changes following director failing to sign off v3.0, plus minor
contact changes.
40 26-Mar-2010 I Approval version
44 18-May-2010 I Following team restructure, the process has been significantly
reviewed
42 03-Jun-2010 Updated following minor comments provided during review cycle
of version 4.1. This version will be presented for approval at v5.0
5.0 07-Jun-2010 _I Approval version
60 14-Sep-2010 I Approved version following updates to personnel and table in
10.4 and section 10.8
61 15 July-2011 Updates to personnel and changes from ‘Process’ to Procedure’
62 05-Sept-2011 I Updates following changes requested by Bill Membery from 6.1,
plus clarification of TRM role
63 14-Oct-2011 I Cosmetic changes mainly changing RMGA with POA and also
updating abbreviations
64 21-Dec-2011 I Updating of details for a Service Bridge.
Also some POL requests
Despite this being an internal POA document, all external
comments that can improve the document are considered.
65 16-Jan-2012 Updated, following review and cosmetic changes in relation to
version 6.4
7.0 18-Jan-2012 I Approval version
©Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVM/SDM/PRO/0001
CONFIDENCE) Version: 7.0
Date: 16-January-2012
PageNo: 4of 1
Fe)
FUJITSU
POA Operations Major Incident Procedure
FUJITSU RESTRICTED (COMMERCIAL IN
CONFIDENCE)
FUJ00080222
FUJ00080222
0.3 Review Details
Review Comments by
Review Comments to Mike Woolgar
Mandatory Review
Role
Name
POA Head of Service Management
Tony Atkinson
POA Acceptance Manager David Cooke
Optional Review
Role Name
POA Business Continuity Manager
Adam Parker
POA SAP and Credence SDM.
Gaby Reynolds
POA Lead SDM, Problem and Major Incident
Steve Bansal
POA Lead SDM End User Services
Leighton Machin
POA Lead SDM Online Services
Elizabeth Bailey
POA Head Of Service Operations
Pete Thompson
Fujitsu HSD Operations Manager
Mike Clive (acting)
POA SMC Manager
Saha Saptarshi
POA Security Manager
Donna Munro
POA SDM HSD.
Sandie Bothick
POA Quality Compliance and Risk Manager
Bill Membery
POA SDM Networks
Issued for Information
distribution list to a minimum.
Position/Role
Please restrict this
‘Andy Hemingway
Name
POA CISO
Howard Pritchard
Fujitsu Unix Team Leader
Andy Gibson
Fujitsu NT Team Leader
Adrienne Thompson
Fujitsu DC Operations Manager
John Hill
POA Infrastructure Manager
Alex Kemp
(*) = Reviewers that returned comments
0.4 Acceptance by Document Review
The sections in this document that have been identified to POL as comprising evidence to support
Acceptance by Document review (DR) are listed below for the relevant Requirements:
POL NFR DR Internal FS P% Document
Acceptance Ref NFR Reference Section Number
SER-2200 SER-2178 Whole Document
SER-2202 SER-2179 Whole Document
©Copyright Fujitsu Services Ltd 2012
FUJITSU RESTRICTED (COMMERCIAL IN
CONFIDENCE)
Ref
Version:
Date:
Page No:
SVMI/SDM/PRO/0001
7.0
16-January-2012
5 of 1
FUJ00080222
FUJ00080222
(oe) POA Operations Major Incident Procedure
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN
CONFIDENCE)
SEC-3095 SEC-3266 335 Security Triggers
SEC-3095 SEC-3266 10.5 Security Major incidents
0.5 Associated Documents (Internal & External)
Reference Versiot Date Title Source
PGM/DCM/TEM/0001 Fujitsu Services Royal Mail Group Account I Dimensions
(00 NOT REMOVE) HNG-X Document Template
CS/IFS/008 POA/POL Interface Agreement for the Dimensions
Problem Management Interface
SVM/SDM/SD/0025 POA Problem Management Procedure Dimensions
PA/PRO/001 Change Control Process Dimensions
CS/QMS/001 Customer Service Policy Manual Dimensions
SVM/SDM/SD/0001 Service Desk — Service Description Dimensions
266/FRM/HSD/001 HSD Business Continuity Activities Plan Dimensions
SVM/SDM/PLA/0001 HNG-X Support Services Business Dimensions
Continuity Plan
SVM/SDM/PLA/0002 HNG-X Services Business Continuity Plan Dimensions
SVM/SDM/PLA/0030 HNG-X Engineering Service Business Dimensions
Continuity Plan
SVM/SDM/PLA/0031 HNG-X Security Business Continuity Plan Dimensions
SVM/SDM/SD/0011 Branch Network Services Service Dimensions
Description
SVM/SDM/PRO/0018 CS Incident Management Procedure Dimensions
C-MSv1.3 Manage Incidents Process BMS
C-MSv_roles Service Management Process Roles and BMS
Responsibilities
SVMISEC/STD/1823 LINK information security standard issued I Dimensions
January 2001 (subject to such dispensations
from that standard as LINK may grant from
time to time).
Unless a specific version is referred to above, reference should be made to the current approved
versions of the documents.
0.6 Abbreviations
Abbreviation Definition
AtG Advice & Guidance
BCP Business Continuity Plan
BMS Business Management System
©Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVM/SDM/PRO/0001
CONFIDENCE) Version: 7.0
Date: 16-January-2012
PageNo: 6 of 1
FUJ00080222
FUJ00080222
POA Operations Major Incident Procedure
fee)
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN
CONFIDENCE)
HSD Horizon Service Desk
IMT Incident Management Team
iso International Standards Organisation
ITIL Information Technology Infrastructure Library
KEDB Known Error Database
KEL Known Error Log
MBCI Major Business Continuity Incident
MIM Major Incident Manager
MIR Major Incident Report
msc Managed Service Change
MSU Management Support Unit
ocp Operational Change Proposal
PCI Payment Card Industry (as per Security Standards Council)
PO Post Office
POA Fujitsu Post Office Account
POA Fujitsu Post Office Account Business Unit
POL Post Office Limited
RFC Request For Change
SCT Service Continuity Team
SDM(s) Service Delivery Manager(s)
(NB: Throughout this document SDM refers to a person responsible for the Service,
and the SDM could work in, but not limited to, the Service Delivery, Service
Support, Release Management or Security teams).
SDU Service Delivery Unit
SLT Service Level Targets
SMC. Systems Management Centre
SMS Short Message Service (as known globally within Mobile Telephone Networks)
SRRC Service Resilience & Recovery Catalogue
ssc ‘System Support Centre
TB Technical Bridge
TRM Technical Recovery Manager
VIP VIP Post Office, High Profile Outlet
0.7 Glossary
Term Definition
T Time of incident occurring
T+3 Time Incident Occurred plus 3 minutes
©Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVM/SDM/PRO/0001
CONFIDENCE) Version: 7.0
Date: 16-January-2012
PageNo: of 1
FUJ00080222
FUJ00080222
POA Operations Major Incident Procedure
Fe)
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN
CONFIDENCE)
0.8 Changes Expected
ee
0.9 Accuracy
Fujitsu Services endeavours to ensure that the information contained in this document is correct but, whilst every
effort is made to ensure the accuracy of such information, it accepts no liability for any loss (however caused)
sustained as a result of any error or omission in the same.
0.10 Security Risk Assessment
Security risks have been assessed and it is considered that there are no security risks relating specifically to this
document.
©Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVM/SDM/PRO/0001
CONFIDENCE) Version: 7.0
Date: 16-January-2012
PageNo: 8 of 1
FUJ00080222
FUJ00080222
POA Operations Major Incident Procedure
Fe)
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN
CONFIDENCE)
1 Introduction
1.1 Owner
The owner of the Major Incident Management process at the local POA level is the Fujitsu POA Lead
SDM, Problem and Major Incident.
Objective
The key objective of the procedure is to ensure effective and efficient management of Major Incidents,
through:
e Improvement of communication channels
e Clarification of the need to communicate awareness of potential incidents
« Improved accuracy of reporting of incident status
e Allowing technical teams the right amount of time to diagnose and impact an incident
e Avoiding unnecessary alerting of the customer
e Demonstrating a professional approach to the Post Office
e Provision of clearly defined roles and responsibilities
e Defined reporting and updating timelines throughout a major incident.
e Improved governance
« Assessing which incidents are major and which are ‘Business as Usual’
1.2 Rationale
This document outlines the communication and management procedure and guidelines to be used for
Major Incidents impacting the live estate.
The methodology defined within this document augments the existing SMS framework procedure
presently deployed within the live estate.
The aim of the document is to provide a pre-defined procedure for future major incident communication
and management.
©Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVMI/SDM/PRO/0001
CONFIDENCE) Version: 7.0
Date: 16-January-2012
PageNo: of 1
FUJ00080222
FUJ00080222
POA Operations Major Incident Procedure
Fe)
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN
CONFIDENCE)
2
Mandatory Guidelines
It is important to maintain a balance between:
a) Allowing the technical teams the right amount of time to diagnose and impact an incident
b) Avoiding unnecessary alerting of the customer
c) Assessing which incidents are major
The following guidelines should be adhered to.
During the HSD IMT Core Hours (Monday — Friday 08:00 — 18:00 and Saturday 08:00 — 14:00)
the HSD IMT should be the first point of operational contact between Fujitsu and the end user.
Outside these hours the SMC acts as the first point of contact.
Any activity detailed in this document which is assigned to the HSD IMT is handed over to the
SMC outside the HSD IMT Core Hours.
The relevant technical teams who are aware of and monitoring a potential major incident must
page / call the appropriate Major Incident Manager (Duty Manager out of hours) as soon as
possible. This is not limited to major incidents alone, but applies wherever a state other than
Business as Usual has been detected. The Major Incident Manager must in turn communicate
the potential incident, to the POL Service Desk for awareness and monitoring in POL. This is
usually done via the HSD IMT in core hours.
The Major Incident Manager (or Duty Manager out of hours) is responsible for communicating
both up the Fujitsu organisation and across (see appendix 10.3) to their counterpart in POL.
Where this is impractical (e.g. leave, out of hours, unavailable), the initiative should be taken to
jump up the organisation. Of prime importance is that the customer is informed in a timely
manner and at the correct touch point. This communication should be by voice or direct SMS.
The communication should include the date, time, name, nature of problem, severity, if service
affecting, likely impact, and the Fujitsu owner to contact.
The Major Incident Manager (Duty Manager OOH) should also initiate communication using
SMS via the HSD IMT (08.00 to 18.00 Monday to Friday, and Saturday 08.00 to 14.00). Outside
of these hours, the SMS should be via the SMC. The SMS distribution list used is titled ‘SMS
Internal’ and amongst others includes the appropriate members of the POA Operations
Management Team.
©Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVM/SDM/PRO/0001
CONFIDENCE) Version: 7.0
Date: 16-January-2012
PageNo: 10 of 1
FUJ00080222
FUJ00080222
POA Operations Major Incident Procedure
Fe)
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN
CONFIDENCE)
3 Definition of a Major Incident
3.1 Incident Classification
As a general rule a Major Incident will be an incident rated as severity level A (critical) in the POA
Operations Incident Management Procedure document (SVM/SDM/PRO/0018), or a series of connected
lower severity incidents which combine to have a significant business impact. However not all incidents
rated at severity level A qualify as a Major Incident as the severity levels do not always reflect the
overall business impact to POL. For example a single counter post office which is unable to trade,
regardless of its business volumes, is rated as a severity A incident.
For simplicity, incidents are classified into three impact levels: High, Medium and Low.
High — An Incident that has occurred with a significant and potentially prolonged adverse impact on POL
business. Typically these incidents will initially require a significant amount of reactive management
before they can be controlled and resolved.
Medium — An incident that has the potential to cause significant impact to POL business but can be
controlled and contained through effective management.
Low — An Incident that requires business attention but if managed effectively will not have significant
impact on POL business.
3.2. Influencing Factors in calling a Major Incident
It is important that a major incident is defined as such because of its business impact on the day when it
occurs, rather than simply being defined as a major incident because it appears on a list. However the
following parameters will also feed into the consideration of whether a major incident should be called:
e Duration, i.e. how long has the vulnerability to service already existed?
e Impact across the estate, including consideration of whether a service is merely degraded or
actually stopped
e Time at which the event occurs in relation to the 24 hour business day
e Time of year - e.g. Christmas / Easter / End of month / quarter
e Anticipated time before service can be resumed
« Impact to POL branches, customers, clients or brand image
e Business initiatives e.g. product launches
3.3 Major Incident Triggers
The criteria below could trigger a major incident, however as detailed in 3.2, the influencing factors must
also be considered. As such the list below is not exhaustive, whilst if an incident occurs which is not
detailed below it should not necessarily be precluded from being declared a major incident.
©Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVMI/SDM/PRO/0001
CONFIDENCE) Version: 7.0
Date: 16-January-2012
PageNo: 11 0f 1
FUJ00080222
FUJ00080222
POA Operations Major Incident Procedure
Fe)
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN
CONFIDENCE)
3.3.1. Network Triggers
Network Major Incident triggers are as follows:
e Complete or significant outage of the Central network
« Complete or significant outage of the Talk Talk network
« Complete or significant outage of VSAT sites
e Complete or significant outage of the ISDN network (whether C&W, BT or Kingston Comms)
3.3.2. Infrastructure Components Triggers
Infrastructure component Major Incident Triggers are as follows:
e Total loss of environments providing individual online service capability
« Breach of access to data centres
e Breach of security
e Virus outbreak
3.3.3. Data Centre Triggers
Data Centre Major Incident triggers are as follows:
e Network / LAN outage
e Loss of Data Centre, or significant loss of Data Centre Components
e Breach of security
3.3.4 Online Service Triggers
Online services Major Incident Triggers are as follows:
e Online service unavailable within the Data Centre (not counter level)
e Number of Branches not able to provide online services — as defined by POL
«Third party provided service failure — e.g.DVLA, Link, Fujitsu Group
N.B Once the third party service provider has been deemed to be the source of the Major Incident, it
will be managed by either POA or POSD in accordance with whichever organisation manages that
supplier relationship.
©Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVMI/SDM/PRO/0001
CONFIDENCE) Version: 7.0
Date: 16-January-2012
PageNo: 120f 1
FUJ00080222
FUJ00080222
POA Operations Major Incident Procedure
Fe)
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN
CONFIDENCE)
3.1.5 Security Triggers
Security major incident triggers are as follows:
e Actual or suspected attacks on the Fujitsu Services Buildings and its resources, POA Network
or Information Systems
e Theft of IT equipment / property, and in particular PIN Pads
¢ Theft of software
e Any PIN Pad Issues that are in breach of FIPS 140-1 level 3 and ISO 9564 1st Edition 1991
section 6.3.1 as specified in the LINK information security standard issued January 2001 (subject
to such dispensations from that standard as LINK may grant from time to time). The main criteria
being as follows:
The purpose of this Standard is to protect the LINK Network, its Members and their
cardholders and ATM owners from attacks designed to compromise sensitive data or
defraud financial institutions and their cardholders. This protection takes into account not
just the direct financial losses that may be incurred but also the potential reputational
damage to the LINK ATM Scheme and its Members and its impact on customer
confidence in LINK and ATMs in general. It is intended to protect the Link Brand:
+ the interests of the Members
+ the interests of the Members' customers
+ the reputation and integrity of the UK cash handling infrastructure
In the event of a Security Major Incident (which may also include PCI Incidents), the POA Security
Manager MUST be alerted who will then follow the Security Incident Management processes, as detailed
in both:
SVM/SDM/PRO/0018 Appendix A
SVM/SDM/PLA/0031 HNG-X Security Business Continuity Plan (defines the actions to be taken
if security violations are identified).
In the event of a Major Incident Security trigger for Fujitsu Services Buildings and its resources, the POA
Security Manager MUST inform the Group Property Security Team who will be alerted either by
telephone on a 24/7 basis or the next working day via our Incident Reporting process and the actual or
potential impact of the incident dictates which route is followed.
The Group Property Security Team then take responsibility for interfacing into the corporate process by
entering reports on to the corporate system
©Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVMI/SDM/PRO/0001
CONFIDENCE) Version: 7.0
Date: 16-January-2012
PageNo: 130f 1
FUJ00080222
FUJ00080222
POA Operations Major Incident Procedure
fee)
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN
CONFIDENCE)
4 Calling the Major Incident
During business hours the Major Incident Manager declares and manages the Major Incident (with
handovers to the OOH Duty Manager where applicable.)
Where the impact of the incident is not immediately obvious, and it is not clear if a Major Incident should
be called, escalation and discussion with the POA Operations management team should occur, and a
collective decision made. If a Major Incident is not called, the incident should be monitored until closure,
to ensure that the impact does not increase to that of a Major Incident.
In the event that multiple services are impacted, multiple Major Incident Managers may be appointed by
the POA Lead SDM, Problem and Major Incident Management, the POA Head of Service Operations or
the POA Head of Service Management, who will remain in this role until incident closure.
Out of hours the OOH Duty Manager is responsible for declaring a Major Incident.
©Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVMI/SDM/PRO/0001
CONFIDENCE) Version: 7.0
Date: 16-January-2012
PageNo: 140f 1
FUJ00080222
FUJ00080222
oe POA Operations Major Incident Procedure ~
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN
CONFIDENCE)
5 Process Flow
MAJOR INCIDENT-~ Process, I n
x
5
x
y
x
“©Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIALIN Ref: ‘SVMISDM/PROI0001
CONFIDENCE) Version: 7.0
Date: 16-January-2012
PageNo: 15 of 1
Fe)
FUJITSU
POA Operations Major Incident Procedure
FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)
FUJ00080222
FUJ00080222
5.1 Process Description (Any reference below made to T, = Time of incident occurring. Hence T+3 = Time Incident Occurred plus 3 minutes).
I Box Title
‘Description —
: Key timescales Acti
[ i
owner
Major incident identi ed?
Incident identified, the definition of an incident is “Any event which is not part of the standard operation of a service and
which causes, or may cause, an interruption to, or a reduction in, the quality of that service.” (SVM/SDM/PRO/0018). An
incident may be reported from within POL domain, a supplier domain or other route
Major Incident Triggers Met?
An initial impact assessment of the incident is undertaken by
members of the POA Service Team taking into account impact
on:
Live Service, Financial Integrity, Business Image
The incident is profiled as a Major Incident as outlined within
this document, including consideration of influencing factors,
e.g. time, geographical coverage, business impact, security,
public perception, duration and relevant business initiatives
coinciding at POL, and decision taken to call a Major Incident.
The Major Incident Manager will consult with the Business
Continuity Plans (see section 0 of this document) to identify if
potential MBCI or MBCI triggers have been met, and inform
the POA Business Continuity Manager if appropriate.
The POL Service Desk will be informed by the Major Incident
Manager of the incident, and the incident will also be escalated
to Service Management / Service Operations team managers,
if this has not already occurred.
With agreement from the POA SDM for the affected service,
or the Duty Manager out of hours, an SMS will be sent to POA
and POL Management alerting to the potential existence of a
Major Incident.
T+3
All timescales
quoted —_ within
this document
should be
viewed as a
maximum, i.e.
to be improved
on where
possible
T+5,
Major Incident Manager
Major Incident Manager
HSD IMT (in hours)
SMC (out of hours)
3@Copyright Fujitsu Services Ltd 2012
FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)
Ref: ‘SVM/SDM/PRO/0001
Version: 65
Date: 16-January 2012
Page No’ 16 of 21
Fe)
FUJITSU
POA Operations Major Incident Procedure
FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)
FUJ00080222
FUJ00080222
BAU Incident Procedure
If a Major Incident is not declared then the BAU Incident procedure is followed — the POL Service Desk will be informed
that there is no Major Incident and a closure SMS sent. The POA SDM for the service should ensure that the Incident is re-
impacted during its lifecycle to ensure that the impact has not increased. If, subsequently the incident is declared a Major
Incident, move to box “Incident Investigation and Diagnosis started”.
Incident Investigation & Diagnosis Relevant internal SDUs / Third Parties contacted to initiate I T+ 5 Major Incident Manager
investigation & diagnosis.
Major Incident Report opened Major Incident Manager
Tech Bridge scheduled & agenda distributed.
Tech Bridge The Tech Bridge is chaired by the Major Incident Manager with I T + 15 Major Incident Manager
assistance from the Technical Recovery Manager (TRM). The
Tech Bridge is technically focussed.
The Tech Bridge aims :
e To discuss and agree the recovery, investigation and
resolution of the Major Incident
e To provide a forum for up-to-date progress reports
e To aid communication, and if necessary, support the TRM
in producing a short term technical recovery plan and if
appropriate longer term corrective actions. These will be
included in the Major Incident report. This is to ensure that
Major Incident progress is known by all, whilst also,
ensuring that all actions whether short term or long term
are clearly stated.
* To collate information for inclusion on the Service Portal.
Attendees at the Tech Bridge may include POA Service
3@Copyright Fujitsu Services Ltd 2012
FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)
Ref: ‘SVM/SDM/PRO/0001
Version: 65
Date: 16-January 2012
Page No’ 17 of 21
Fe)
FUJITSU
POA Operations Major Incident Procedure
FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)
FUJ00080222
FUJ00080222
Management, Fujitsu SDUs, Third Parties, POL, POA
Operations Security, POL Security Managers and others
The Tech Bridge follows a set agenda which covers:
Roll call, Summary of Incident, Incident Overview,
Current Impact, Current Investigation / Recovery Action,
Remedial Actions, Actions to carry forward to Major
Incident Review
The agenda template is stored on
Following the Tech Bridge, a further SMS will be sent,
providing an update on the Incident
If the outcome of the Tech Bridge is that the incident is
determined Business As Usual (low) then an SMS
communication will be sent stating that the incident is not a
Major Incident.
From this point forward SMS communication, timing and
delivery requests becomes the responsibility of the Major
Incident Manager. 30 minute updates should be the norm
The Major Incident Manager will also distribute actions
(provided by the TRM), following the conference call.
At the time agreed at the first Tech Bridge, subsequent Tech
Bridges are held as required. The same agenda is followed,
and progress on actions / recovery is provided.
If no clear recovery path is identified, the decision is then
taken on whether to escalate for Service Bridge direction
Tech Bridge +
15
3@Copyright Fujitsu Services Ltd 2012
FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)
Ref.
Version:
Date:
Page No:
SVMISDM/PRO/0001
65
16-January 2012
18 of 21
Fe)
FUJITSU
POA Operations Major Incident Procedure
FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)
FUJ00080222
FUJ00080222
Clear recovery path identified
If during the conference call a clear recovery path is identified, this should be discussed and agreed on the call. Following
agreement the recovery should be implemented.
If there is no clear recovery path, further investigation will be undertaken.
Recovery / Investigation The Technical Recovery Manager will liaise with the SDUs and I T + x Technical Recovery Manager
/or third parties during the investigation / recovery.
Where appropriate a Technical Bridge will be called for a
technical discussion of the Major Incident.
Tech Bridge 1+ T+x Major Incident Manager
Service Bridge The nature of the incident determines which POA Service I Timescale Major Incident Manager
Team members and POL Managers are involved in the I dependant on POL Service M:
Service Bridge but it would include all or some of the I impact and ervice Manager
following: nature of
incident.
POL (personnel as instructed by POL Live Systems
Service Mgr)
POA Head of Service Management (Chair Person)
POA Head of Service Operations
POA Lead SDM, Problem and Major Incident
POA Business Continuity Manager
POA Security Manager
POA SDM owning the affected service
POA Technical Recovery Manager (if appropriate)
Third Party Executives (if appropriate)
Appointed working group representatives as appropriate
3@Copyright Fujitsu Services Ltd 2012
FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)
Ref: ‘SVM/SDM/PRO/0001
Version: 65
Date: 16-January 2012
Page No’ 19 of 21
Fe)
FUJITSU
POA Operations Major Incident Procedure
FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)
FUJ00080222
FUJ00080222
e HSD IMT Representative
The purpose of the Service Bridge is to:
e Provide appropriate direction on incident resolution
e Provide added impetus to restoration of service as quickly
as possible
e Define communication intervals to key stakeholders
e Provide focused incident management in line with the
impact and severity of the incident
Incident Resolution
Once the incident is deemed to be resolved, a final Tech
Bridge is held to agree and confirm resolution of the incident.
A Major Incident Review date is set at the final Tech Bridge.
An SMS communication is sent confirming resolution of the
incident.
A Draft Major Incident Report is distributed within 24 hours of
resolution of the Major Incident.
Major Incident Manager
Major Incident Review & formal Incident
Closure
Formal closure and a review of the Major Incident including
consideration of:
« Lessons learnt
¢ — Incident definition
« What went well
«Timeline
e Changes required to the infrastructure
e A review of the Major Incident communications
POA Lead SDM, Service Operations
3@Copyright Fujitsu Services Ltd 2012
FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)
Ref: ‘SVM/SDM/PRO/0001
Version: 65
Date: 16-January 2012
Page No: 20 of 21
FUJ00080222
FUJ00080222
co POA Operations Major Incident Procedure
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)
e Root Cause Analysis (if known at this point)
e Business impact
e Action plan, including any changes requiring MSCs
e Service Improvement Plan update
e Review any service risk(s) and update the Risk Register as
appropriate
3@Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE) Ref: SVMISDM/PRO/0001
Version: 6.5
Date 16-January 2012
Page No: 21 of 21
FUJ00080222
FUJ00080222
POA Operations Major Incident Procedure
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)
6 Conference Calls
6.1 Technical Bridge
Dial in details:i_.
Chair Code: 60233935#
This is a technical conference for experts to discuss and analyse the incident and to formulate an action
plan to restore the service to POL without delay. It should enable the Technical Recovery Manager to
baseline the anticipated response, covering resolution, time and resources required.
The Technical Bridge will be set up as required by the Major Incident Manager.
Invitations to the Technical Bridge will be via SMS, email or voice. The SMS will be sent to the
distribution list titled ‘SMS Technical Bridge’. The SMS text will be sent to all technical experts on the
POA and will include outline details of the Major Incident. Also dial in details and the start time will be
provided as part of the meeting invitation.
The Technical Bridge will be started at T + 15, and reconvened at regular intervals during the Major
Incident; the exact scheduling will be discussed and agreed at each preceding Major Incident Call.
Each Technical Bridge follows a set agenda which will be distributed with the meeting invitation where
possible. The conference call is chaired by the Major Incident Manager with the recovery managed by
the Technical Recovery Manager.
A request for a Technical Recovery Manager (TRM) will be made to the POA Head of Service
Operations, who will appoint one of his team to be the TRM.
Following each Technical Bridge, actions will be published by the Technical Recovery Manager to cater
for any of the following
-Recovery / restoration actions (which should normally include associated MSC numbers),
-Service Improvement Plan recommendations
-Risk Register recommendations
-Recommendations for any improvements to KELS / Alerting / Configuration changes
The above should be documented in the Major Incident Report and stored on:
under Service Support
> Major Incident Reports.
6.2 Service Bridge
~}Participant code: 48461705#
Chair Code: 37289974#
This is a service focussed call for Service Management (including the Technical Recovery Manager if
appropriate) and POL to discuss the service impact of the Major Incident and to receive updates on the
progress towards resolution.
The purpose of the Service Bridge is to provide a focussed area from which strategic decisions can be
made regarding a Major Incident.
Attendance is made up of the following or their designated representative:
©Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVMI/SDM/PRO/0001
CONFIDENCE) Version: 6.5
Date: 16-January-2012
Page No: 22 of 35
FUJ00080222
FUJ00080222
POA Operations Major Incident Procedure
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)
« POL ( personnel as instructed by POL Live Systems Service Mgr)
e POA Head of Service Management (Chairperson)
e POA Head of Service Operations
« POALead SDM, Problem and Incident Management
e POA Business Continuity Manager
e POA Security Manager
e POA SDM owning the affected service
e POA Technical Recovery Manager (if appropriate)
e Third party representation (if appropriate)
e Appointed working group representatives as appropriate
e HSD IMT representative
©Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVMISDMIPRO/O001
CONFIDENCE) Version: 6.5
Date 16-January-2012
Page No: 23 of 35
FUJ00080222
FUJ00080222
POA Operations Major Incident Procedure
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)
Service Bridge responsibilities include:
e Agreement of a containment plan
e Documentation of all agreed actions and timescales with owners
« Consistent management of the Major Incident across all the locations involved
« Management of potential / MBCIs within POL and the POA
« Co-ordinate meeting times and locations
In the event of a Major Incident requiring a Service Bridge, it is envisaged that this will be in place at
T+60. Participants required in the Service Bridge will be contacted via SMS as appropriate.
The Major Incident Manager will send out a text to organise a Service Bridge.
Invitations to the Technical Bridge will be via SMS, email or voice. The SMS will be sent to the
distribution list titled ‘SMS HNGX External’
The SMS text should state such details as
an outline of the ongoing incident,
dial in details
and also the start time.
e.g. ‘Your attendance is requiredat a Service Bridge to discuss the current Major Incident in relation to
online Services. Please calf GRO; ort Participant code: 48461705# at 11.00 hrs.’
The chairperson’s code is held by the POA Head of Service Management, POA Head of Service
Operations, POA Lead SDM, Problem and Major Incident. The chairperson, normally the POA Head of
Service Management, will initiate the call.
The TRM will attend meetings as required and provide appropriate root cause analysis and corrective
action detail.
©Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVMI/SDM/PRO/0001
CONFIDENCE) Version: 6.5
Date: 16-January-2012
Page No: 24 of 35
FUJ00080222
FUJ00080222
POA Operations Major Incident Procedure
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)
7
Formal Incident Closure & Major Incident Review
The Major Incident Review is chaired by the Major Incident Manager and follows a set agenda which
should normally be distributed with the Major Incident Review meeting invitation, along with the draft
copy of the Major Incident Report.
The purpose of a Major Incident Review is:
1.
2.
3.
6.
To understand the incident that prevented a Service or Services from being delivered.
To confirm the impact to the business during and after the Incident and agree the number of
branches impacted and duration of Major Incident.
To confirm the end-to-end recovery process and timeline, and identify that all documented
processes were followed.
To analyse the management of the incident and the effectiveness of the governance process.
To identify corrective actions to:
i. prevent recurrence of the incident
ii. minimise future business impact
iii. improve the procedure for the management of incidents
To formally close the Major Incident
Output: To confirm details provided in the draft MIR provided to POL, update with corrective actions and
redistribute. To also include
- any activities fora Service Improvement Plan
- any Changes and associated MSC numbers
- any Risks
- any Configuration changes
- any improvements to KELS, alerting and /or event management
The agreed impact of the Major Incident must be sent to the POA Infrastructure Manager for inclusion in
the Counter Availability SLT Figures.
If this review highlights areas where improvements can be made, an agreed Service Improvement Plan
will be produced with appropriate actions, owners and timescales. It will also identify any ongoing risks to
the service, together with any changes. Service Management will track all actions to resolution. Third
party actions will be reviewed at Service Review meetings.
The Agenda for the Major Incident Review i: is stored on:
under Service Support
> Major Incident Management Templates
It is important that the number of branches impacted and the duration of the Major Incident is agreed at
the Major Incident Review. This information is required to calculate the impact on Branch and Counter
Availability and any associated Liquidated Damages (LD) liabilities
©Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVMI/SDM/PRO/0001
CONFIDENCE) Version: 6.5
Date: 16-January-2012
Page No: 25 of 35
FUJ00080222
FUJ00080222
POA Operations Major Incident Procedure
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)
7.1 Calculating potential LD liability for Major Incidents
Major Incidents which qualify as Failure Events are detailed in the Branch Network Service Description
(SVM/SDM/SD0011). A Failure Event is defined in this document as an event or series of connected
events which causes one or more Counter Positions to be deemed to be Unavailable due to a Network
Wide Failure or a Local Failure. Ongoing failures will be deemed to be part of such a Failure Event until
the Failure Event is closed in accordance with the Incident closure and Major Incident Review process as
detailed in section 7.0.
For a Failure Event the Incident Closure & Major Incident Review Process will require Post Office and
Fujitsu to agree the number of branches and counter positions affected and the duration of the outage
(rounded to the nearest 30 minutes as detailed in the Network Wide Rounding Table below):
Network Wide Rounding Table
Duration of Incident Deemed duration for the
purposes of LD
calculations
30 minutes or less 30 minutes
More than 30 minutes I 1 hour
but less than 1 hour
1 hour or more but less I 1 hour
than 1 hour 30 minutes
1 hour 30 minutes or I 2 hours
more but less than 2
hours
N hours or more but I N hours
less than N hours 30
minutes
N hours 30 minutes or I (N+1) hours
more but less than
(N+1) hours
©Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVMI/SDM/PRO/0001
CONFIDENCE) Version: 6.5.
Date: 16-January-2012
Page No: 26 of 35
FUJ00080222
FUJ00080222
POA Operations Major Incident Procedure
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)
8 Fujitsu Roles and Responsibilities during a Major
Incident
This section defines the roles and responsibilities individuals and teams have as part of the Major
Incident Escalation Procedure.
8.1. Role of the HSD IMT
The role of the Horizon Service Desk Incident Management Team (HSD IMT) in the event of a Major
Incident is two-fold:
e Receive and log calls from Post Masters, and communicate the progress of investigations to any
Post Masters who call into the desk.
e Send service impact details (to include calls offered, abandoned, queuing) to the Major Incident
Manager. This template should be completed every 15 minutes from the point of declaring a
Major Incident, until the Major Incident Manager asks for this to cease.
8.2 Role of the Major Incident Manager
The primary role of the Major Incident Manager in a Major Incident is to facilitate the management of the
Incident through investigation and diagnosis to resolution, with the aim of making the process as efficient
and effective as possible. Upon determining that a Major Incident has been called, a request for a
Technical Recovery Manager (TRM) will be made to the POA Head of Service Operations, who will
appoint one of his team to be the TRM. The Major Incident Manager acts as the central point for
communication and non-technical information flow, allowing the TRM to focus on the technical situation
and the resolution of the Incident. The Major Incident Manager is also responsible for creating and
maintaining all the associated documentation.
The Major Incident Manager:
e Has responsibility for creating the Major Incident Report
« Manages the communication internally within the POA
« Communicates with the POL Service Desk on the progression of the incident
« Identifies Business and Service impact though discussions with the users, the POL Service Desk
and the HSD IMT — providing this input into the Tech Bridge.
e Calls and chairs the Technical Bridge
e Distributes the Technical Bridge actions provided by the TRM (if appropriate).
e — Liaises with the SSC to update the Service Portal
e Along with the POA Problem Manager, ensures that the TRM provides regular updates on any
longer term corrective actions.
Following the resolution of the Incident, the Major Incident Manager schedules and chairs the Major
Incident Review and creates the Major Incident Report document.
©Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVMI/SDM/PRO/0001
CONFIDENCE) Version: 6.5
Date: 16-January-2012
Page No: 27 of 35
FUJ00080222
FUJ00080222
POA Operations Major Incident Procedure
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)
8.3 Role of the Problem Manager
The Problem Manager ensures that corrective actions / investigations are tracked and completed
following the major incident.
Any corrective actions arising from the Major Incident Review will be added to the corrective actions log
and tracked through to completion. The updates will be distributed to POL as required, and in the case of
a Security Major Incident associated with PCI failures the POL Security team will also receive a copy of
the report.
8.4 Role of the Technical Recovery Manager
The primary functions of the Technical Recovery Manager are to co-ordinate and manage the restoration
of service, manage the technical teams, and act as the communication point for the technical teams and
third parties. The function will also include managing all longer term technical corrective actions, e.g.
recommendations for improvements to KELs, eventing and configuration.
The Technical Recovery Manager:
* Manages the technical recovery of the Incident — liaising with SDUs and third parties.
« Provides updates on the recovery, when technicians / representatives of technical teams are
unable to attend the Technical Bridge.
«Is the only person to liaise directly with the technical teams, including technical third parties.
e Provides summarised actions from Technical Bridge to the Major Incident Manager, including:
o Current status including impact and risk
o Planned recovery activities including timelines
o Root Cause Analysis, corrective actions, and their corresponding action owners and
timelines (where known)
The TRM will be responsible for attending any meetings and providing appropriate root cause analysis
and corrective action detail. This will also include managing any longer term technical corrective actions
that are documented in the Major Incident Report and will include where appropriate
- any activities for a Service Improvement Plan
- any Changes and MSC numbers
- any Risks
- any Configuration changes
- any improvements to KELS, alerting and /or events
©Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVMI/SDM/PRO/0001
CONFIDENCE) Version: 6.5
Date: 16-January-2012
Page No: 28 of 35
FUJ00080222
FUJ00080222
POA Operations Major Incident Procedure
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)
8.5 Role of the SDUs: Technical Teams / Third Parties
The role is to investigate the Incident, and in the event of no pre-determined recovery options, suggest
and evaluation of potential recovery options to resolve the Incident.
The technical teams should not be contacted by any party other than the Technical Recovery Manager.
The Technical Teams / Third Parties should send an attendee to the Tech Bridge and the associated
Major Incident Review meeting. Where attendance on the Tech Bridge is not possible, a suitable
alternative resource should attend. If neither is possible then a full update MUST be provided to the TRM
to ensure that the Bridge can be updated.
8.6 Role of the Service Delivery Manager owning the
affected service
e Attends Post Major Incident review
e Responsible for any further action proposed by the Problem Manager that falls outside the Major
Incident closure criteria.
©Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVMI/SDM/PRO/0001
CONFIDENCE) Version: 6.5
Date: 16-January-2012
Page No: 29 of 35
FUJ00080222
FUJ00080222
POA Operations Major Incident Procedure
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)
9 Post Office / Fujitsu Interfaces
The Post Office / Fujitsu interfaces are detailed in the Procedure Description, section 5.1. However for
ease the interfaces have been extracted into the table below.
POL Service Desk and POL management stakeholders updated — updated within 15 minutes of the
Major Incident being called and after this according to the agreed timeline.
Draft MIR (timelines) provided — provided by the Major Incident Manager within one working day
MIR (timelines, root cause analysis, corrective actions) provided - provided by the Major Incident
Manager within one working week
Service Bridge invitation — when the Major Incident has been unresolved for an hour or when it is
deemed appropriate.
As detailed under Appendix 10.3, escalation of the Major Incident will also occur; this activity running
concurrently to the interfaces detailed above.
©Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVMI/SDM/PRO/0001
CONFIDENCE) Version: 6.5
Date: 16-January-2012
Page No: 30 of 35
FUJ00080222
FUJ00080222
POA Operations Major Incident Procedure
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)
10 Appendices
10.1 List of Templates
iunder Service Support
NAME OF DISTRIBUTION
TEMPLATE i
Major Incident I The Major Incident Report contains all the information about I POL.
Report Template I a Major Incident. This document is distributed to POL.
POA Service Management & Service
Operations
POA Head of Service Operations
POA Head of Service Management
Fujitsu Support Teams
©Copyright Fujitsu Services Ltd 2012
FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVMI/SDM/PRO/0001
CONFIDENCE)
Version: 6.5
Date: 16-January-2012
Page No: 31 of 35
FUJ00080222
FUJ00080222
POA Operations Major Incident Procedure
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)
10.2 Major Incident Manager Contact Details
« Steve Gardiner
e Mike Woolgar
.
10.3 Out of Hours Duty Manager Contact Details
OOH Duty Manager Pager’ ) between the hours:
17.30 - 09.00 Monday PM to Thursday AM
17.00 - 09.00 Friday PM to Monday AM
Outside these times, please contact the Major Incident Manager
10.4 POA Service Delivery Manager Contact Details
NTS [ESCALATION TO: SDM
AREA OF RESPONSIBILITY IEXAMPLE INCIDENTSI"~~ service owner CONTACT DETAILS BACK UP
Infrastructure issues. Data centre issues Alex Kemp Pete Thompson
Storage Incidents a }
NT / UNIX / Data Centres NT /JUNIX incidents
All Network Issues Network Incidents /IP I Andy Hemingway Alex Kemp
Stream / VSAT / ISDN
Failures
POLSAP Issues All POLSAP issues Gaby Reynolds
including File Delivery
issues
Banking and Online Services I Online Service outages I_Elizabeth Bailey
(Inc: DVLA, Debit Card, EPAY) .
Reference Data New product not Steve Parker Kevin McKeown
functioning oe enn
ben GRO.
Business Continuity MBCls or Potential ‘Adam Parker Pete Thompson
MBCls -
©Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIAL IN Ref. SVMISDM/PRO/0001
CONFIDENCE) Version: 6.5
Date: 16-January-2012
Page No: 32 of 35
FUJ00080222
FUJ00080222
POA Operations Major Incident Procedure
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)
Major issue with Leighton Machin Tony Atkinson
engineering service powenennn
Engineering I
OBC Escalations ‘OBC job going wrong/ Chris Bourne Leighton Machin
press involved /unhappyI
postmaster
Major software problem —_I Major software problem Steve Parker
HSD/ PostShops Major TFS call logging Sandie Bothick Leighton Machin
issues. Major PostShop
outage
Security Security Issues Donna Munro Pete Thompson
Virus Alerts
Release Management / Service I _ Issues caused by Graham Welsh
Introduction Releases
smc Monitoring/ eventing of I Saheed Salawu
data centre environment}
©Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVMI/SDM/PRO/0001
CONFIDENCE) Version: 6.5
Date: 16-January-2012
Page No: 33 of 35
FUJ00080222
FUJ00080222
POA Operations Major Incident Procedure
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)
10.5 Escalation Communication Protocol
The primary principle:
Up”
and
“Across
Example:
The Major Incident Manager would escalate up to POA Lead SDM, Problem and Major Incident
Management, and across to the Post Office Service Desk.
Major Business Continuity Incidents (MBC1)
For HNG-X the MBCI triggers are listed in:
« HNG-X Support Services Business Continuity Plan (SVM/SDM/PLA/0001)
e HNG-X Services Business Continuity Plan (SVM/SDM/PLA/0002)
e HNG-X Security Business Continuity Plan (SVM/SDM/PLA/0031)
e HNG-X Engineering Service Business Continuity Plan (SVM/SDM/PLA/0030).
These documents should be referred to as appropriate in the event of Major Incident to determine if
Business Continuity needs to be invoked.
10.6 Security Major Incidents
In the event of a security major incident, the incident procedure as detailed in the POA Customer
Services Incident Management Procedure (SVM/SDM/PRO/0018 Appendix A) must also be followed.
SVM/SDM/PLA/0031 HNG-X Security Business Continuity Plan defines the actions to be taken if security
violations are identified.
10.7 Roles
e Major Incident Manager (MIM). This will by default be either the day time or OOH Duty
Manager. A separate member of the Service Management team may be appointed as the
MIM depending on the situation. The MIM will handle all communications to the HSD IMT
and keep track of time lines. The MIM is also responsible for sending SMS messages but
this can be delegated. The MIM will be assisted by a Technical Recovery Manager (TRM)
for all technical aspects, (including actions for both recovery and longer term changes / risks
and Service Improvement Plans) and also a Problem Manager who will be responsible for
managing any resultant problems to resolution. For the process to be effective, all updates
and information regarding the incident must be fed to the MIM to update the timelines and
report.
e Head of Service Management - is solely responsible for verbal and written communications
with POA senior managers and POL management.
©Copyright Fujitsu Services Ltd 2012 FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVMI/SDM/PRO/0001
CONFIDENCE) Version: 6.5
Date: 16-January-2012
Page No: 34 of 35
FUJ00080222
FUJ00080222
POA Operations Major Incident Procedure
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)
10.8 Communication Process Flow
e On suspicion or confirmation of a Major Incident, the MIM will escalate to the Lead SDM,
Problem and Major Incident Management, and to the Head of Service Operations
« The MIM will inform the POL Service Desk, via the HSD IMT, within 5 minutes of the start of the
service incident
e All updates to the POL Service Desk are via the HSD IMT within agreed timescales controlled by
the MIM
e The MIM will issue an SMS text to the POA alerting of potential issues — including date, time,
nature of problems, severity, impact and name
e The POA Head of Service Management will inform the following within 10 minutes of start of the
service incident
o POA Operations Director
o POL Senior Service Delivery Managers — currently Dave Hulbert and Tony Jamasb
and will coordinate and ensure consistency of response to POL and POA Senior Management
« Periodic (interval to be determined depending on the nature of the issue but not more than 30
minutes for Major Incidents) SMS updates to be sent to the original SMS Dist list
e On final service restoration, an SMS text message must be sent to the original SMS Dist list
e The Head of Service Management will confirm understanding of Major Incident closure with POL
management and POA senior management, and agree next steps
e The MIM will continue liaising with the HSD IMT
10.9 Special Situations
10.9.1 Personnel Absence
e Inthe absence of the POA Head of Service Management, the POA Head of Service Operations
to deputise
« In the absence of both, a nominated individual would have been chosen before hand
10.9.2 OOH
e The OOH Duty Manager will act as the Major Incident Manager
10.9.3 Duty Manager Change Over
«The Duty Manager at the beginning of the incident will be by default responsible for all MIM
communications responsibilities unless a different arrangement is made between the outgoing
and incoming Duty Managers
e The POA Head of Service Management will be informed, via text if out-of-hours, of who the
active MIM is.