© Fujitsu Services Ltd 2010 Commercial In Confidence
Post Office Red Alert — Independent Technical Review
James Stinchcombe, Principal Solution Architect
27 April 2010
Executive Summary
There have been a number of problems with the Post Office service over the last few
weeks, with the most severe being complete loss of the HNG-X Service on 26" and
27" March, with Horizon Banking being severely impacted on 1°‘ April (with 80% of
transactions failing). This has resulted in the account being placed on Red Alert.
As a result, an independent technical review has been requested to look at the specific
problems and also take a wider perspective. This is short assignment to provide feed
back to both the account and the Public Sector business unit.
This report is split down into the different areas considered and provides
recommendations on how things can be improved. Given this is a short assignment it
has not been possible to do a comprehensive review of all areas of the solution and
where further investigation by the account would be desirable this is included.
The problems that are causing the Red Alert are not a single issue and there is no
“magic bullet” to solve them. The teams need to continue to resolve the known issues
while continuing to investigate the problems. It is likely that additional issues will
emerge as the solution continues to be investigated.
Based on the observations in this report, the table below summarises the risk of
significant business disruption for Horizon and HNG-X that the current solution
represents. It also details which recommendations that help resolve or make progress
on these issues
These recommendations should be considered as system improvements; not all will be
necessary for re-starting HNG-X deployment. Completion of some of the activities is
likely to take some time and needs to be planned accordingly.
Introduction
The HNG-X project for Royal Mail is providing a new, centralised service for the
branches of the UK Post Office. It is currently part way through rollout, with
approximately 5% of the 11,700 branches having been migrated from Horizon (the
existing system provided by Fujitsu) to the new HNG-X solution.
To minimise running costs, HNG-X is a centralised, online only architecture. This
means that failures in the data centres are likely to cause widespread outage to the
service with knock-on business impact.
There have been a number of problems with the service over the last few weeks, with
the most severe being complete loss of the HNG-X Service for periods of the branch
trading day on 26" and 27" March, with Horizon Banking being severely impacted on
1 April (with 80% of transactions failing). This has resulted in the account being
placed on Red Alert.
Page 1
FUJ00096450
FUJ00096450
FUJ00096450
FUJ00096450
© Fujitsu Services Ltd 2010 Commercial In Confidence
As a result, an independent technical review has been requested to look at the specific
problems and also take a wider perspective. This is a short (2 day) assignment to
provide feedback to both the account and the Public Sector business unit.
This report is split down into the different areas considered and provides
recommendations on how things can be improved (marked as “Rx:”). Given this is a
short assignment it has not been possible to do a comprehensive review of all areas of
the solution and where further investigation by the account would be desirable this is
included.
The following areas have been considered:
e Capacity - can it support the volumes expected and has this been proven in the
live estate?
e Stability — how stable is the solution and what is causing the problems?
e Recoverability - how well does the system recovers from failures and the
business impact of this?
e Supportability — can the solution be supported, including appropriate
monitoring?
It is clear from the engagement that the account is working very hard to resolve the
problems and even in the 2 days of the assignment several issues have been
addressed. It is possible therefore that some information in this report may already be
out of date.
Capacity
This section looks at the capacity of the solution in live and whether the volume
testing is sufficiently representative.
Capacity — Live System
The live system has good capacity monitoring, with performance data being available
in near real time. This has allowed a comprehensive look at the capacity of the key
components of the system.
The following table shows the assessment of the capacity of the key components of
the solution from a processor, memory disk and network traffic perspective:
Key component Processor I Memory I Disk I Network
Branch Database Servers (BRDB)
(holds data for HNG-X Branches)
Branch Access Layer (BAL)
(access servers for Horzion Banking/debit
card and all HNG-X)
Network Banking Persistent Store (NPS)
Database (holds data for banking
transactions — including reversals)
Branch Support Database (BRS)
(holds historic records for
Page 2
© Fujitsu Services Ltd 2010 Commercial In Confidence
The evidence from the capacity monitoring shows that the problems with HNG-X are
being caused by stability issues rather than capacity. It is the instability of the service
(as highlighted in the next section) that is perceived by the end users as “timeouts”.
The network banking NPS is showing signs of memory stress (1). Response times for
banking shows that the system response times show large variations unpredictably at
different times of the day. -This is consistent with memory stress. (NOTE for FJ only
— instability implies that the system is not working, which is not true).
The root cause of this were changes to the NPS software, including upgrade of Oracle
from 9.2 Horizon to 10.2 HNG-X and the hosting of APOP database on the NPS.
NPS1 (which supports banking and APOP) is showing worse performance. NPS2
(which supports banking only) is showing less stress, but seems to have got slightly
worse since the Oracle patchset has been applied.
It is worth noting that APOP is expected to grow and there is a change to improve
APOP resilience by it to NPS2 as well.
The quickest and simplest solution to the problem is to replace the current server
blades used to run NPS with server blades with more memory. By contrast, reducing
memory usage by the application is likely to be difficult and time consuming,
requiring both volume and resilience testing to be completed before it could be safely
applied to live.
Upgrading the hardware can be achieved with low risk (e.g. by replacing one of the
two NPS nodes, allowing this to run for a few days before replacing the other node).
Options for this replacement are already under review. The Capacity Management
Team has some suggestions on how this could be achieved.
R1: Urgently review the implementation of a hardware upgrade for the servers for
NPS. This will be the most effective solution to the problem.
R2: Consider in the very short term, whether simple measures could be made to
reduce memory usage on the NPS (e.g. by reducing the Oracle cache size or turning
‘some services) to improve stability.
The Branch Support database (BRS) is used to hold historic data from the HNG-X
branches. It is used by the support community to investigate problems, so avoiding
their workload from impacting counter performance.
Performance and other issues (for example switching off the replication during the
data to remove possible causes of instability in the branch database; some outages and
weekend upgrades) have resulted in the BRS being over 300 hours behind the branch
data (it should be only a few minutes). This makes it unusable for support. As a result
support have to use the Branch database itself for their work, making it more likely
that there will be capacity issues with the service as it rolls out.
In addition, the capacity to allow the service to fall this far behind will be reduced as
HNG-X rolls out. Given that the BRS is part of the solution to retain branch data for
audit and archive, exhausting this capacity would be a significant issue.
Page 3
FUJ00096450
FUJ00096450
© Fujitsu Services Ltd 2010 Commercial In Confidence
One of the reasons for slow performance is the high Horizon workload. This has to be
processed in large batches from the overnight processing, which is less efficient than
when those branches are migrated to HNG-X. However unless the system is keeping
up over a day (i.e. 24 hours behind) this could mean that it can never catch-up
(particularly given the need for maintenance periods etc).
R3: Do not allow further rollout of HNG-X until the BRS is stable and keeping up
(maximum of 1 day behind).
It is unclear from the performance data available why BRS is not keeping up — it
appears to have sufficient headroom in processor, disk, memory and network
resources to process the data significantly faster (although some disks are busy for
short periods of time). There are a number of performance fixes in the pipeline and in
addition Oracle has made some recommendations which are being reviewed (CAN
WE CHECK THIS IS STILL VALID ~ haven’t a number of fixes been implemented
into live already? Have the Oracle recommendations been implemented?).
R4: Engage an expert in Oracle performance to review the performance of BRS to
understand the existing performance and how to improve it.
Capacity — Volume Testing
Given the problems with the live service, questions have been asked as to how
representative is the Volume Testing environment (VOL). The following is a short
summary:
e The hardware for Volume testing is representative with some minor
differences that are not material and in general mean that VOL has slightly
less capacity than the live solution. (A spot check by the VOL team has shown
no significant differences in layout).
e The number of BAL (branch access layer) servers is fewer to simulate running
under a failure condition.
e Banking is run without standby agents
e VPN has fewer servers as it only needs to show how one cluster scales.
e There are fewer instances of the support systems than would be found in live
(including VPN, ACD, BMX, DEA, DWS).
e The large databases (e.g. BRS) are sized at 10% of live — as is normal practice
for this type of testing.
¢ VOL does not have POLFS or POLSAP.
The differences above do not invalidate the volume testing and testing on this
environment should be very similar to those expected to be seen on the live service.
However given the problems with NPS on live, it is recommended again to look at the
agents and BAL to ensure their memory usage on the database servers is
representative
RS5: Review Volume Testing with regards to memory usage for agents / BAL to
ensure that memory footprint on servers is accurate.
Page 4
FUJ00096450
FUJ00096450
© Fujitsu Services Ltd 2010 Commercial In Confidence
In general volume testing has progressed well - it has found a number of problems
with the solution and largely proved that the solution should be capable of supporting
the full volumes.
It should be noted however that volume testing is only as good as the data profiles
used to generate the test data. Given that HNG-X is so different to Horizon, it would
be worth checking experience from live to date to ensure the data profiles
(particularly reports) are accurate.
R6: Consider information from those HNG-X Branches already live to see whether
data being generated is representative.
In addition, the volume test cycle 3 has not yet completed. The main remaining
planned tests to be run are those associated with stressing the system beyond the
expected volumes. However there are also some limitations of the tests already run in
cycles 1 and 2 that need to be addressed.
The following types of testing need to be run before it can be considered safe to
rollout HNG-X to the full estate:
e Testing with representative data for report volumes (current testing was
limited in this area).
e Stress testing — running the system at higher than contracted volumes. This is
needed to ensure the system is stable (this is planned as part of cycle 3).
e Resilience Testing under volume — while running at full workload, fail key
components (e.g. Branch database node; Branch access layer node, NPS node
etc) to prove the system will recover correctly from such failures. Without this
there can be no confidence the live system will recover from such failures
(testing to date in this area has only be done with very small, manually
generated data).
e Some testing was done without the BRS due to rig problems — this needs to be
resolved. Full details of which tests were impacted is available from the VOL
team.
R7: Complete performance & stress testing before rolling out HNG-X to full
volumes.
Page 5
FUJ00096450
FUJ00096450
© Fujitsu Services Ltd 2010 Commercial In Confidence
Stability
As covered in the previous section, many problems in the current solution seem to be
being caused by “stability” issues (i.e. things don’t work correctly) as opposed to
capacity (i.e. there is insufficient resource to do the work).
Due to the operational immaturity of HNG-X, it is to be expected that there will be
some problems, however many of those already identified have not yet had fixes
applied. This makes diagnosing the remaining problems difficult.
More importantly, during the recent period of instability there have been more low
level failures than would be expected. This in turn has resulted in more recovery
actions. Since the recovery itself has a number of problems (see “Recoverability”) this
in turn causes significant business problems.
There are a number of these problems that have been identified by the account that
fall into the area of “stability” including:
¢ Lots of stale network connections resulting in a firewall running out of
resources — causing failure of banking on 1° April (fixed by OCP on 6" April
— CONFIRM this is correct).
e Old network drivers for many servers (the “PV driver” issue) which result in
network connections and packets being dropped. This results in more failures
than would otherwise be the case in both banking and HNG-X.
e Problems with Oracle “hanging” on the Branch Database servers. There have
been no reported incidents since the LCK patch was implemented on 22/04/10
~ NEED TO CONFIRM THIS IS CORRECT.
e The network being configured to present more traffic than needed to the
BladeFrame server chassis (rather than just presenting traffic for those servers
within the BladeFrame, it was also presenting data for other servers, which the
BladeFrame then has to discard). This seems to resulting in the chassis itself
being overloaded and unable to process all the traffic — this has been
reproduced in VOL and looks likely as the root cause for the problems with
Horizon on 6" April (Mark Jarosz has the details for this). It is understood that
an OCP has been applied to resolve this issue.
© Servers generating significant broadcast traffic — when little or none is
expected (understood some have now been fixed by OCP on 8" and 9" April).
e Memory issue on the NPS (see previous section) causing connections to be
dropped.
e The ACE Blades (that handle load balancing to the BAL) have a known issue
that will cause HNG-X counters to fail when transaction rates in the system
grow (exact volume unclear — but is assessed to be greater 50% volumes). An
update on any planned fix would be useful here.
R8: Apply all known fixes to live that will resolve stability issues as quickly as
possible. This is needed to reduce both the likelihood of failures and also allow the
remaining problems to be diagnosed.
Recoverability
Page 6
FUJ00096450
FUJ00096450
© Fujitsu Services Ltd 2010 Commercial In Confidence
There is clear evidence from the solution that both Horizon (as a result of the PCI
changes) and HNG-X are not able to recover correctly from failures.
The most worrying are reconciliation BIMS exceptions — these are failures that
require manual intervention by both Fujitsu and Royal Mail. Many of these failures
result in end customers of the Post Office not being paid money (the exception shows
that a bank believes it has paid out the money, whereas the Horizon/HNG-X system
knows it did not pay out in reality).
The trend for these types of failure is clear:
e Before PCI/HNG-X change —7 to 8 exceptions per month
e March 2010 - 263 BIMS exceptions
e April 2010 — forecast over 500 BIMS exceptions
In March, this excess volume was a combination of higher than expected days plus
some high volumes associated with the major outages. However April’s data is
showing 30 or more problems per day and does not seem to be associated with major
issues (it is this that the forecast is based on). Joanne Ball has detailed breakdown of
the data if required.
These volumes are assuming current HNG-X branches. As HNG-X rolls out this is
likely to grow unless the problems are fixed and identified. It is worth noting that
these volumes are those that require manual intervention. Other reconciliation errors
are frequently exceeding the report threshold of 30,000 per day.
This exception workload is causing significant (and unsustainable) workload on both
Fujitsu and Royal Mail including:
e Investigation of each BIMS to ensure it really is a failure (Fujitsu Support)
e Handling of the problem with the banks etc (Royal Mail)
e Additional call volume from end customers asking why they haven’t been
allowed to take out their money (Royal Mail and other banks).
R9: Urgently Review causes of failures causing BIMS exceptions for both Horizon
and HNG-X. Ensure these are fixed before further rollout of the HNG-X solution.
There are also other areas in HNG-X where the system does not recover well from
failures. For example on 25" March an overnight job on the BRDB failed to run and
this resulted in none of the HNG-X counters being able to login the next morning (a
change has been applied to make the solution more defensive). There are undoubtedly
others of a similar nature that have not been found in testing and may only be found in
live operation.
Supportability
This section looks at how supportable is the solution - monitoring, and diagnosing
problems.
One of the problems with the live system at the moment is the ability to monitor the
solution. There are two broad areas that need to be monitored:
Page 7
FUJ00096450
FUJ00096450
© Fujitsu Services Ltd 2010 Commercial In Confidence
e Failures in the solution — technical faults that may or may not result in loss of
service.
e “Wellness” — is the system behaving as expected at a business level?
The second is particularly important as it makes up for any shortfalls in the
monitoring solution. It is also needed to ensure it known that the system has recovered
from any failures.
There are a number of known problems with the current monitoring solution and as a
result often the first thing operations know there is a problem is when Post Masters
phone up to say there is a problem. Working out what is the root cause of the incident
is then difficult as many problems end up with similar behaviour as far as the Post
Master is concerned (e.g. timeouts).
R10: Review current issues with monitoring solution to make sure they are given
appropriate priority. Ideally, these should be fixed before HNG-X is rolled out
further to ensure that incidents can be responded to in a timely way (this is
understood is being considered as part of the second work stream in the Red Alert).
R11: Review approach to monitoring of live based on lessons learnt with the
current problems to see if the solution provided is sufficient — particularly with the
need to monitor “wellness” in business terms that are understood by Post Office.
There are also a number of issues with the ability of the SSC to efficiently and
effectively diagnose problems or to provide evidence to the offshore teams. These
include:
e The diagnostic logs for the branch access layer are spread over 40 files (10
servers, two instances per server, two logs per instance) with each interaction
from the branch randomly using a particular instance. This means that tracing
a problem that a branch has is very time consuming since there is no tooling
support for this.
e All evidence for offshore has to be sanitised before it can be sent to remove
financial transaction information (in order to comply with the Data Protection
Act). The tools to do this sanitising aren’t trusted, so the SSC have to
manually inspect each file before shipping.
e Some of the requirements in the diagnostic area have not been met, in
generally making support less efficient than was budgeted for.
As a result of this, the stability and the recoverability issues the SSC are significantly
overloaded. This in turn makes it slower to diagnose the root cause of problems and
increases the risk that things are missed.
R12: Review how problems are diagnosed on HNG-X in the light of recent
experience to understand the gaps and their business impact.
Within the design area, it is clear that each area (e.g. Database, Networks, Platforms,
Applications etc) is working well and making good progress on their issues. However
there was no evidence of a senior architect ensuring that these different strands are
brought together effectively and being communicated (for example there is no single
list of technical issues that need to be resolved). This doesn’t mean that the teams
Page 8
FUJ00096450
FUJ00096450
© Fujitsu Services Ltd 2010 Commercial In Confidence
weren’t working together — but rather that there is a lack of technical leadership. As a
result things are likely to be taken longer to resolve than necessary, agreeing priorities
can become difficult and things are likely to be missed. This should be resolved once
the new CTO joins the account.
R13 Until the CTO joins, consider nominating one of the senior architects to
provide technical leadership across the design teams and provide a single point of
contact.
Page 9
FUJ00096450
FUJ00096450
© Fujitsu Services Ltd 2010 Commercial In Confidence
Conclusion
The problems that are causing the Red Alert are not a single issue and there is no
“magic bullet” to solve them. The teams need to continue to resolve the known issues
while continuing to investigate the problems. It is likely that additional issues will
emerge as the solution continues to be investigated.
Based on the observations in this report, the table below summarises the risk of
significant business disruption for Horizon and HNG-X that the current solution
represents. It also details which recommendations that help resolve or make progress
on these issues:
Consideration. Horizon HNG-X
Recommendations I Recommendations
Capacity RI, R2 R3, R4, RS, R6,
(ability of solution to support volumes) R7
Stability R1,R2 R8
(is the solution stable)
Recoverability RI RO
(Can the solution correctly recover from
failures)
Supportability n/a R10, R11, R12,
(ability to support and monitor the solution) R13
These recommendations should be considered as system improvements; not all will be
necessary for re-starting HNG-X deployment. Completion of some of the activities is
likely to take some time and needs to be planned accordingly.
Page 10
FUJ00096450