ACTION Points
Attendees:
Expert: Peter Copping
POCL: Keith Baines, John Meagher, Ruth Holleran, Min Burdett (minutes), Graeme Seedall (376, 378), Calum Craig (376, 378), Adele Henderson (408)
Pathway: Tony Oppenheim, John Dicks, John Pope (376, 378), Dave Hollingsworth (298), Dave Cook (412), Steve Muchow (408, 412, 298)
218 Training
Work Action Workshop
shop Date Date
7 12 Pathway proposed that severity is reduced from High to Medium. POCL to review for 2"! Sept why this should not happen. 2™ Sept
Workshop 3 Update: POCL presented drafi success criteria. POCL to update draft with timescales to enable assessment before I Early 3 9 Sept
9" Sept. Also to include “no show stoppers” where the success criteria involve POCL reviews. Reconsider link with AI 408. Sept

Workshop 5 Update: Agreed that the severity is now an agreed Medium. - delete next time

Page I of 17. [ DATE \@ "dd/MM/yy" ]
FUJ00119869
FUJ00119869

Acceptance Workshop (5) Horizon Programme

Work Action Workshop
shop Date Date

8. 3 The working group will meet to progress: 8" Sept 9" Sept
formal feedback on Pre-Training Event paper

© feedback on Monitoring Training Delivery paper

* progress rectification plan (see action 218/10 below)

¢ — formalisation of process to deal with the 5% of trainees who do not reach the appropriate competence level
Feed back progress and issues to this group.

During the on-going work by POCL to review Pathway’s proposals/deliverables, POCL will raise immediately with
Pathway (Tony Oppenheim or Liam Foley) serious issues which would impact the success criteria, and not wait for the
working group meeting.

Workshop 4 Update: No show-stoppers identified. POCL comments to Pathway planned for 6/9, for formal review on 8/9 by
the working group.

Activities incorporated in rectification plan_- delete next time.

9. [3 POCL (Bruce McNiven) is writing to Pathway (Liam Foley) 2" Sept covering: 6" Sept I 6" Sept
e — endorsement of Pathway to start development of the Pre-Training event

¢ — the cost implications of the CCN for RNM training

Liam Foley to reply to POCL (Bruce McNiven and cc to Ruth Holleran). Any issues to be raised at this meeting.

Workshop 4 Update: POCL (Ruth Holleran) and Pathway (Tony Oppenheim) to determine any outstanding commercial issues 9% Sept
and bring to this group.

Workshop 5 Update: No outstanding cost/commercial issues. Delete next time.

10. I 3 POCL (Steve Grayston) and Pathway (Liam Foley) to progress and agree the rectification plan. 6" Sept
Workshop 4 Update: Plan being discussed at working group on 8 Sept. Outcome to be brought to this group. 9 Sept

Workshop 5 Update: Rectification plan now subject to some detailed changes. Confirm agreement to this group. 17" Sept

ll. I 5 Pathway to provide final AI analysis form and POCL to confirm agreement. 17" Sept

Page 2 of 17. [ DATE \@ "dd/MM/yy" I
FUJ00119869

FUJ00119869
Acceptance Workshop (5) Horizon Programme
298 System Stability
Work Action Workshop
shop Date Date
1 }2 A joint POCL/Pathway working group has been established to review deficiencies. This group is agreeing: 2"! Sept,
metrics (current and retrospective monitoring) 6" Sept
© underlying cause 13" Sept
¢ what fixes when (both introduced and in progress) and correlate these to the deficiencies
¢ results of the fixes.
The working group to report back to this group progress, outcome and issues.
Workshop 3 Update: progress satisfactory. See below for new actions arising
Delete next time
2. 2 POCL (John Meagher/Ruth Holleran) and Pathway (Terry Austin) to agree achievement levels for each deficiency. This will 6" Sept 6" Sept
establish the target levels for reducing this Acceptance Incident from High to Medium.
Workshop 4 Update: POCL presented their view of the target levels for closure. Pathway to review and feed back to this 9" Sept
meeting: the achievability of the closure target; the associated timescales; and their view of the target for moving from High to
Medium.
Workshop 5 Update: POCL to review Pathway’s proposal for reducing the severity (section 5.4 of Resolution Plan for AI 298). 13" Sept
Pathway reconsidering their “complexity of technology” argument for justifying the acceptability of higher incident rates. 13" Sept
3. 12 Pathway will develop a policy document describing how they will minimise the risk of destablising the system in subsequent 9 Sept 13" Sept
releases. Policy document to be issued and discussed with POCL (Jeremy Folkes to arrange POCL participants) in advance of
discussions at this group.

Page 3 of 17.

@ "dd/MMyy" I
FUJ00119869

FUJ00119869
Acceptance Workshop (5) Horizon Programme
Work Action Workshop
shop Date Date
4. 3 POCL (John Meagher) to produce mapping of Pathway to POCL classifications of the incidents. Agree this mapping with 6" Sept 6" Sept
Pathway. As part of 298/1 above, report back any issues.
Workshop 4 Update: Mapping has been done by POCL. POCL to send to Pathway for review.
Workshop 5 Update: The new report (see action 298/6 below) to be reviewed to ensure that the mapping overlaps and 13" Sept
omissions are properly accounted for and reported.
5. 3 Additional stability issues have been noted by POCL (e.g. hour glass appearing at unexpected times). POCL (John Meagher) to As they
ensure that Pathway is kept up to date with new types of incidents as seen by POCL. occur
6. I 3 To inform the 10" Sept meeting (deciding whether to roll out to the next 158/178 outlets) we need the best view we can get of the 6 Sept
data and trends. The working group should provide an initial draft of a management summary report on 6" Sept and a further 9 Sept
report for 9",
Workshop 5 Update: Pathway to produce an updated report including categories around disputed calls. This report to be 13" Sept
reviewed by POCL.
Pathway (Steve Muchow) to consider how to report the data and trends to minimise the effect of new offices’ learning curve calls. 13 Sept
7/4 Pathway issued a draft Rectification Plan. POCL (John Meagher) to review and feedback to Pathway (Terry Austin cc: Dave 9% Sept I 9 Sept
Hollingsworth). Update this meeting.
8 14 Pathway to clarify whether in the Long Term Stability Policy document there is just going to be testing, or whether other elements 9" Sept
of the development life-cycle will be part of the approach.
Page 4 of 17. [ DATE \@ "“dd/MMiyy" I

FUJ00119869

FUJ00119869
Acceptance Workshop (5) Horizon Programme
AI 314 - Provision of Technical Documentation
Work ‘Action Workshop
shop Date Date
2 43 Peter Copping to review version 0.2 of CS/SPE/007 “Development of Manual Describing Use of OPS, TMS and EPOSS APIS 6" Sept
within ICL Pathway” to decide whether it is sufficient basis for judging the fitness for purpose of the document when made
available.
Workshop 4 Update: Review identified an issue: how would procurement be structured where a new agent was required across 13" Sept
the interface. This is primarily an issue for TMS. Pathway do not want other suppliers to be developing new agents and so this
would have to be a Pathway developed new agent, or a Pathway enhancement of an existing one. POCL (Graham White) to
consider POCL’s response and to feed back to this group.
Workshop 5 Update: POCL understand Pathway’s position, and although not ideal, agree their involvement as described above.
Delete next time.
3. [3 Pathway will produce a revised version of CS/SPE/007 including: 13% Sept
(i) the document will contain Pathway specific APIs as will be required for the development process;
(ii) an undertaking to provide a list of ‘excluded’ Riposte APIs which are in conflict with the Pathway implementation;
(ii) addition of an appendix containing technical details of Systems Management and Key Management that
would be subject to an NDA;
(iv) Pathway to add a new section on standards.
Pathway to report progress to this group having discussed the revised draft with POCL.
Workshop 4 Update: Note the change in date for review by this group.
Workshop 5 Update: Document agreed. Pathway to raise final AT analysis form and POCL to confirm agreement. 17" Sept

Page Sof 17, [DATE \@ “dd/MMiyy" I
Acceptance Workshop (5) Horizon Programme

FUJ00119869
FUJ00119869

AI 369 - Scanner Reliability

Work
shop

Action
Date

Workshop
Date

1

The following were agreed:

e Pathway would write up the results of the last 100-cover laboratory tests and submit a report to POCL.

e Pathway and POCL would conduct data analysis to validate the DSS proposition that there has been a higher level of impound
rates on OBCS compared with ESNS yet, as they were all valid books, there must therefore be a higher rate of false rejection
(impounds) on OBCS than on ESNS. Pathway will conduct the data analysis and validation work for OBCS; POCL will
conduct the work for ESNS.

¢ Pathway will set up field validation of actual rejects occurring in outlets. The validation tests will determine the cause of the
rejects as between scanner, user, paper, ink, damage, condition etc. This activity is expected to require a mobile laboratory
facility.

¢ POCL will seek observation of the field validation tests by DSS observers.

© POCL will request the DSS to provide the covers off books rejected during field validation &/or historically rejected books to
Pathway for laboratory testing.

© POCL will check training course material for the adequacy of scanner user training and/or instructions.

¢ POCL will obtain the DSS’s buy-in to the above approach to the resolution of this AI.

It was expected that Karen Rogers would co-ordinate this activity for POCL and that John Dicks would initially do so for
Pathway.

Actions subsumed below - delete next time.

2™' Sept
(Progress
check)

v

POCL (Karen Rogers) to issue plan to Pathway.

Workshop 4 Update: Plan issued. Initial review indicates plan OK except some difficulty with Pathway doing historical
analysis of read failures back to 25/7. Pathway and POCL to meet to review. This meeting to include: the detail of the metrics to
be used to report the failure rates; any modifications to the activities to be undertaken in the “roving lab” in the NE on 9" Sept
(see 3 below): and formal confirmation by Pathway of plan. Report back to this meeting.

Workshop 5 Update: Plan discussed and modifications agreed. Delete next time

3" Sept

7 Sept

9 Sept

Page 6 of 17. [DATE \@ “dd/MMiyy" I
FUJ00119869

FUJ00119869
Acceptance Workshop (5) Horizon Programme
Work Action Workshop
shop Date Date

3. 3 Pathway (Steve Muchow) and POCL (Karen Rogers) to develop an action plan for the “roving lab” to pick up reject books as they I 3"! Sept 13" Sept
occur. Target is for the lab to be in operation on 7" and/or 9" Sept. Pathway will attempt to provide bar-code evaluation
equipment as part of the lab.
Workshop 5 Update: Roving Lab in NE 9" Sept. Feed back outcome to this meeting.

4. 73 POCL to escalate with DSS the need to be involved in the activities (a) providing impounded books for further testing and (by 3% Sept I 6" Sept
observe the “roving lab” tests. Update this group with progress.
Workshop 4 Update: DSS (Steph Fowler) has noted that their concern with the proposal to provide impounded books is (a) 9M Sept 9 Sept
getting agreement from DSS Security and (b) concerns around the delay in returning books. POCL (Bruce MeNiven via John
Meagher) to escalate this with DSS (Ken Davenport and Vince Gaskell) to try to get their agreement.
Workshop 5 Update: Vince Gaskell no longer involved in this area. John Meagher to speak to Ken Davenport to determine 13" Sept
appropriate operational contacts in DSS to be involved with on-going issues around the service.

5. 3 Pathway reported that about 90% of books not scanned were from 4 or 5 offices. Pathway will undertake root cause analysis of 6" Sept
these offices.
Workshop 4 Update: Analysis of single office with 50% of failures indicates incorrect procedure being used in outlet. POCL 9 Sept
(Dave McLaughlin via John Meagher) to telephone to determine reason for high failure rates in the other cluster offices.
Workshop 5 Update: Ring around cluster offices has identified a number of causes of user problems with system. There is 13" Sept
some justifiable confusion with the procedures (having to do different processes in similar, but different circumstances). A
reference data change will help with one misleading icon, John Meagher to action change.

6. 15 POCL (John Meagher) and Pathway (John Dicks) to develop a joint rectification plan for presentation to DSS. This rectification I 15" Sept 17" Sept
plan to include the targeting of cluster offices (Pathway providing the MIS/POCL to determine and manage the process for
dealing with problem offices).

Page 7 of 17. @ "dd/MMiyy" I

FUJ00119869

FUJ00119869
Acceptance Workshop (5) Horizon Programme
AI 372 - Systems Management
Work Action Workshop
shop Date Date
3. 3 Pathway to document the resolution proposal as an AT Analysis form,
Workshop 4 Update: Note change in date for next review at this meeting. 13" Sept.
a /4 POCL to review whether re-down-loading of Riposte file is an acceptable part of the test 9 Sept I 9" Sept
Workshop 5 Update: It is not acceptable to POCL that re-down loading Riposte as part of the Systems Management test. 13" Sept
Pathway to produce provisional release note for the test drop and discuss this with POCL (Bob Booth in Jeremy Folke’s absence.)
376 Data Integrity
Work Action Workshop
shop Date Date
2. 42 Pathway needs to make clear the OBC procedures and practice that will be in place, both up to CSR+ and after CSR+, for: 2™ Sept 9" or 13%
¢ changing the status of core products to non-core Sept
¢ decreasing the availability of non-core products.
This to be documented by Pathway (referring to existing documents where appropriate) and reviewed by Working Group (see 1).
There will be a test of the agreed (interim) procedures by releasing currently suppressed changes through a managed programme.
This test to be planned by 2"! Sept and progressed sufficiently to assure the procedures by 9" or 13" Workshop. Flag up on 2"!
Sept Workshop if problems with progress.
Workshop 3 Update: See new action 376/10 below.
Workshop 5 Update: Because of the nature of the process to release the embargoed reference data changes, it will not be 13" Sept
possible to manage the release, test the fix and report back in the remaining time for Acceptance. Determine the implications of
this at next meeting - each party to determine appropriate representation for the discussion.

Page 8 of 17. [DATE \@ “dd/MMiyy" I
FUJ00119869

FUJ00119869
Acceptance Workshop (5) Horizon Programme
Work Action Workshop
shop Date Date
3. 12 Pathway propose to introduce a fix to ensure that the Cash Account does not lose transactions (PinICL 27748 refers). As part of I I 26" 2"! Sept
above, review fix and confirm acceptability of fix to this group, August to
1* Sept
Workshop 3 Update: New analysis emerging. Carry forward to 6" Sept. 6" Sept
Workshop 4 Update: The working group will review the explanation of the fix that is being applied on 9" Sept and will 9" Sept
consider whether to release the retained Reference Data changes. Feedback outcome to this group.
Subsumed within 376/2 and 376/10 below - delete next time
5. ]2 Pathway are proposing a 3-level data integrity check to be implemented in December. This needs to be documented as a high 3" Sept 6" Sept.
level design including failure state analysis. POCL (Calum Craig, Graeme Seedall, Martin Box and Jeremy Folkes) to be
involved in interactive walkthroughs during the development of the design. Report progress and issues to this group.
Workshop 4 Update: POCL consider high level design generally good. Further joint work needs to be undertaken on: 9 Sept I 13 Sept
¢ failure scenarios. POCL will undertaken an internal review of the design (including TIP and TP) to determine failure
scenarios. These will be documented and fed back to John Pope by close of play 9". John Pope (calling on others if required)
will identify how these scenarios will be dealt with. Update at this meeting
© operating procedures. The development of the operating procedures, including reporting failures to TIP, will be included in
the rectification plan. (see 8 below)
Workshop 5 Update: POCL review identified failure scenarios and some issues with the high level design which needed 10"Sept I 13" Sept
clarification. (It was reconfirmed that the high level design was acceptable, but the resolution of detailed aspects of the design
may impact the high level design.). POCL and Pathway will meet to discuss the POCL paper “EPOSS/TIP Reconciliation
Controls” which summarises the failure scenarios and design issues.
Page 9 of 17. @ "dd/MMiyy" I

Acceptance Workshop (5) Horizon Programme

FUJ00119869
FUJ00119869

Work
shop

Action
Date

Workshop
Date

POCL’s position is that roll-out should not commence until data integrity can be assured. Ruth Holleran to consider with the
Auditors, and report back to this group, whether the current Pathway checks plus, possibly, continuing POCL checks, would be
adequate until Pathw: full data integrity checks are in place.

Workshop 3 Update: Due to possible dependency of this action on 376/5 above, and 376/7. below, this action may have to be
revisited on 9" Sept.

Workshop 4 Update: POCL and Pathway need to develop a contingent approach possibly including indemnities. Keith Baines
and Tony Oppenheim to meet with lawyers to initiate.

Workshop 5 Update: POCL’s position remains that this Incident should remain High until the data integrity fix is in place.
POCL have further internal meetings to confirm this position. POCL will contact Pathway should further clarification be
required. POCL to report back to this meeting.

8" Sept

6" Sept

9" Sept

9" Sept

13" Sept

ve

Pathway to review whether there are any interim checks which can be undertaken on the cash account stream - report back to this
group.

Workshop 4 Update: As part of the rectification plan (see 8 below) Pathway presented an interim proposal (see section 5.2 last 3
lines). POCL to review this proposal (including TP and TIP) and inform Pathway (John Pope) by close of play 7" Sept whether
proposal accepted.

Workshop 5 Update: Agreed that this interim proposal would not be beneficial and so should not be progressed. Agreed that no
further proposals are likely to emerge. Delete next time

7" Sept

6* Sept

9% Sept

uv

Pathway to prepare rectification plan and present to this group.

Workshop 4 Update: Pathway presented CR/ACD/376 “Acceptance Proposal Acceptance Incident 376” version 0.3. POCL to
feed back comments.

Workshop 5 Update: Pathway to update rectification plan addressing POCL comments provided. Plan to include:
the process and output for tracking and reporting incidents (along the lines of the current reports to this group)

© how POCL will be involved with on-going detailed design issues which impact the high level design

¢ development of the process/procedures for the December data integrity fix

9M Sept

6" Sept

9 Sept

13" Sept?

Page 10 of 17.

@ "dd/MMyy" I
Acceptance Workshop (5) Horizon Programme

FUJ00119869
FUJ00119869

Work
shop

Action
Date

Workshop
Date

It was agreed that the working group should continue to meet to monitor and review TIP incidents. Next meeting to have on
agenda and feed back to this group:
e any further progress on existing incidents (including PinICL 27748 - see 376/3 above)
© new incidents raised since last group meeting
commission the production of a management summary of incidents highlighting:
© summary of incidents by type of occurrence
co when related fix(es) introduced
© rate of occurrence before and after fix
© new incident types

Workshop 4 Update: Draft monitoring report was presented. Working group will update this report including:
* week 23 to be added

¢ add notes explaining position of those under investigation

© fixes forecast

Workshop 5 Update: Next report to be presented before the Workshop on 17" Sept

3" Sept

16" Sept

6" Sept

9" Sept

17" Sept

As part of the working group activity, POCL has reviewed the procedures (some of them interim) which will be in place to
manage OBC change up to CSR+. POCL to determine the acceptability of proceeding with this interim solution. Any issues to
be discussed with Pathway before the 9" Sept review by this group.

Workshop 5 Update: Interim solution acceptable. Delete next time

9 Sept

Page 11 of 17.

@ "dd/MMyy" I
FUJ00119869

FUJ00119869
Acceptance Workshop (5) Horizon Programme
378 Incomplete Cash Account Records
Work Action Workshop
shop Date Date
1 }2 POCL would like to understand how the “Non-Stock” records were lost from the TIP file. John Pope to explain to Martin Box. 6 Sept
Report back any issues to this group.
Workshop 4 Update: Explanation given. POCL to feed back any issues to this group. 9" Sept
Workshop 5 Update: POCL confirmed acceptability of fix. Delete next time.
2. 2 POCL would like to understand how Pathway have undertaken their design level review to analyse and improve the deficiencies 6" Sept
around the cash account to prevent inappropriate interruptions e.g. multiple user key/touch screen entries. Pathway to
arrange, Jeremy Folkes to arrange suitable POCL participants. Report back any issues to this group.
Workshop 3 Update: The action is focused on the cash account process, but will include possible side-effects of the
rectification elsewhere.
Note new wording agreed at Workshop 4. Pathway (Alan Ward) and POCL (Jeremy Folkes arranging appropriate participants) I 15" Sept I 17 Sept
to meet by 15" Sept - earlier if possible. Follow on meeting with designer on 20" Sept if necessary
3. 15 New incidents have occurred. Pathway to report back root cause to next meeting. 13" Sept

Page 12 of 17. [ DATE \@ “dd/MM yy" I
FUJ00119869

FUJ00119869
Acceptance Workshop (5) Horizon Programme
AI 391 - Physical Security at Bootle and Wigan
Work ‘Action Workshop
shop Date Date
2. 43 Pathway will obtain and review A&L procedures for vehicle access at Bootle. POCL to be involved in review. Pathway will Circa 8" 13" Sept
propose and gain approval to any changes noted in the review. Review to be done in time for action 391/3 by end of 10" Sept Sept update
should that be required
Workshop 4 Update: NB new workshop date.
3. [3 POCL to participate in site visit to check deployment of security procedures at Bootle if deemed necessary. 10" Sept I 13" Sept
408 HSH Performance
Work ‘Action Workshop
shop Date Date
3. 42 Pathway will arrange a workshop aimed at giving POCL confidence in their resourcing model and to confirm their analysis that a
level 3 expert domain for cash accounting is required. Report back outcome and issues to this group.
Workshop 4 Update. POCL identified a considerable number of changes to the scripts. These scripts are going to be introduced I 7" Sept 9% Sept
into the live environment on 8" Sept. POCL wish to understand how the HSH is being trained in these new scripts and how
resource levels have been specified using these scripts. Workshop on 7" Sept to cover this as well
Workshop 5 Update: POCL now understand how adequate resourcing levels will be achieved in both the short and longer term.
Action complete - delete next time.
6. 2 Pathway to produce a rectification plan for presenting to this group. This plan to include date for when target SLAs will be met. 9 Sept
Workshop 5 Update: Pathway to update rectification plan in light of actions 7 and 8 below for review by POCL. 17" Sept

Page 13 of 17. [ DATE \@ “dd/MM yy" I
FUJ00119869

FUJ00119869
Acceptance Workshop (5) Horizon Programme
Work Action Workshop
shop Date Date
7. 12 Pathway to produce outline proposal on Service Levels for the cash accounting expert domain. 9" Sept
Workshop 5 Update: POCL (including Keith Baines, Ruth Holleran) to review Pathway’s (including Tony Oppenheim) 14" Sept 17" Sept
proposal and discuss.
8. [5 Performance Service Level statistics for August have been re-produced by Pathway to exclude the cash account calls, POCLto I 14" Sept_I 17° Sept
assure that the statistics are being appropriately reported. Pathway and POCL (including Ruth Holleran, Dave McLaughlin,
Jerome Brice, Adele Henderson) to meet to review the new service level report.
412 Service Performance Ad Hoc Reporting
Work Action Workshop
shop Date Date
a) POCL and Pathway to meet to review particular examples of concern to POCL (or review all examples on the Pathway log). 13" Sept
Report back any issues to this group.
2. 45 Pathway (Steve Muchow) to consider whether it would be appropriate to provide a targeted teach-in to appropriate POCL experts 13" Sept
to enable them to focus their ad hoc requests around the Pathway data structures.
3. 45 POCL and Pathway presented their respective draft papers explaining their view of the issue. The process for ad hoc reporting is 13" Sept
documented in CS/PRO/031. The Pathway report highlighted an issue around the availability of data at appropriate points in the
reporting cycle. Pathway to provide further information on this for POCL to review.
4. I 5 POCL to progress (Keith Baines to speak to Dave McLaughlin) the issue around the transaction times for fallback transactions.
Page 14 of 17. [ DATE \@ "dd/MM/yy" ]

FUJ00119869

FUJ00119869
Acceptance Workshop (5) Horizon Programme
Agreed Category B And Other Incidents
Work ‘Action Workshop
shop Date Date
1. 1 Of the nine Agreed Category B Faults, there are six with agreed resolution plans. It was agreed that ICL Pathway would submit 31" Aug. 6" Sept
an Acceptance Incident Analysis Form to cover the agreed resolution plan for each of the six Acceptance Incidents for POCL’s to 5" Sept
agreement. (The six incidents are 342, 361, 371, 211, 390 and 395.)
Workshop 3 Update: 342, 371, 390 and 395 Analysis forms received. POCL note the request for closure on 371 and 395.
Workshop 4 and 5 Update:
© 211 - further 7 incidents investigated. A recent fix, “F1” caused this (and the OBCS read) problem. New fix will be 17" Sept
introduced 17" Sept. See action IRP 5 for wider implication of this issue - assuring the regression testing is appropriate for
the level of fixes being applied. Pathway to submit an updated AI analysis form including these new incidents and including
an update to the rectification plan
© 342 - No further incidents. Monitoring continuing until 1 Oct
¢ 361 - No further incidents. Monitoring continuing until 1* Oct
© 371 - Reports produced. ATM review to see if appropriate to close.
e 390 - No further incidents. Monitoring continuing as per rectification plan
* 395 - No further incidents. Monitoring continuing. ATM review to see if appropriate to close.
2. 3 Pathway (John Dicks) and POCL (Jeff Austin) to arrange a review of all remaining Low Severity incidents to resolve any 21" Sept
Low/None differences of opinion and to determine the plan for closure. Complete review by 21" Sept.
Integrated Rectification Plan (IRP)
Work Action Workshop
shop Date Date
lL I 4 POCL (Ruth Holleran) to confirm dates for monitoring the fix and feed back to Pathway. 7" Sept
2°44 POCL (Jeremy Folkes) to review 391 plan and feed back to Pathway. 7" Sept
Page 15 of 17. @ "dd/MMiyy" I

FUJ00119869

FUJ00119869
Acceptance Workshop (5) Horizon Programme
Work Action Workshop
shop Date Date
3. 4 POCL (Andrew Simpkins) and Pathway (Mike Coombes and Lawrence Price) to compare plans and resolve issues. Update
Pathway plan.
© Feedback issues to this group 9M Sept
¢ Issue plan for review by this group 9% Sept 13" Sept
4. 5 POCL (John Meagher) to speak to Pathway (Mike Coombes) about Pathway’s wider regression testing plans which are currently 13" or 17%
being developed to assure the stability of the system going forward. Sept
Other Actions
Work ‘Action Workshop
shop Date Date
1. 4 POCL (Ruth Holleran and Keith Baines) to determine the management forum to oversee the implementation of the rectification 13" Sept
plan.

Page 16 of 17. [ DATE \@ "dd/MM/yy" ]
FUJ00119869
FUJ00119869

Acceptance Workshop (5) Horizon Programme

The meeting summarised the intended topics for the next Workshop giving guideline times for some topics.
13 September Workshop (Renaissance Hotel 10:00)

Morning
© 391
372
298
376
378

ecee

Lunch in restaurant at 12:30

369

412

Integrated Rectification Plan

Management forum for the rectification plan

coee

17" September Workshop (Gavrelle House)

e check to ensure all incidents have been appropriately documented (including rectification plan and AI analysis form)
© 298

© 376

e Integrated Rectification Plan

Min Burdett