FUJ00168180 - Programme LIGHT Executive Conference Call v1 Presentation

Evidence on official site

FUJ00168180

FUJ00168180

Programme LIGHT

xecutive Conference Call

V1.0 28" June 2007 13:00

SLIGHT Exec Call v1.0 070628.ppt

FUJ00168180
FUJ00168180

Key Points / Overall Progress

More Letters screens are active and some fixes have been identified — but
we have not yet get the Letters estate up and running (thus still failing first
demand from 1/6 call)

Circa. 120 unknown problems remain

Database remains unreliable — configuration mgmt ‘going back to grass
roots’ (reported on joint Red Alert call of 13/6)

FJS team working hard, but in 5 weeks we have achieved relatively little

RMG has concern of FUJS true attention to ‘RED’ status :

Key FJS resources shifting off to other things

Tasks agreed on daily call not being performed e.g. daily dashboard
Insufficient resourcing e.g. engineers for problem site visits

Early draft of Recovery Plan has unrealistic timescales

RMG consider we only move out of RED when the Recovery Plan is
delivered, not when it is agreed (FJS have failed to deliver to plan on
numerous occasions already)

IT Exec Call v1.0 070628. ppt
FUJ00168180
FUJ00168180

RMG Demands (as at 28/6/07)

1.

No relaxation of RED ALERT - likely to end July (i.e.
o the point when RED actions on the Recovery Plan
are delivered)

Finalised Recovery Plan by 29/6 (this was originally
agreed to be 8/6!)

Recovery Plan supported by named Resource Plan

an Terblanche to take RED ALERT PM lead whilst
Anthony Lamoureux is absent

Do the balance of 205 DMB’s now

v1.0 070628.ppt