FUJ00234966 - Fujitsu POA Operations Major Incident Procedure v 15.1

Evidence on official site

FUJ00234966

FUJ00234966
oO POA Operations Major Incident Procedure
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN
CONFIDENCE)

Document Title: POA Operations Major Incident Procedure

Document Type: Procedure Definition

Release: HNG-X

Abstract: This document details the POA Major incident processes which

supplements the major incident processes defined in the Fujitsu
EMEIA Business Management Systems Major Incident Procedure
with the Post Office Limited specific requirements or requests.

Document Status: APPROVED

Author & Dept: Tony Wicks — POA Operations
Matthew Hatch — POA Operations
Internal Distribution: As listed on pages 4 and 5 for

Mandatory Review
Optional Review
Issued for information

External Distribution: For information
Martin Godbold (POL)
Security Risk YES

Assessment Confirmed

Approval Authorities:

Name Signature
Steve Bansal Senior Service Delivery See Dimensions for record of approval.
Manager
SCopyright Fujitsu Services Lid 2006- FUJITSU RESTRICTED (COMMERCIAL IN Ref. SVMISDMIPRO/0001
2019 CONFIDENCE) Version: 15.0
Date: 24-January-2019

Page No: 1 of 28.
FUJ00234966
FUJ00234966

oO POA Operations Major Incident Procedure
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN
CONFIDENCE)
0 Document Control
0.1 Table of Contents
i} DOCUMENT CONTROL
0.1 Table of Contents
0.2 Document History
0.3 Review Details .
0.4 Acceptance by Document Review:
0.5 Associated Documents (Internal & External) .
0.6 Abbreviations
0.7  Glossary.....
0.8 Changes Expected
0.9 Accuracy....
0.10 Security Risk Assessment
4 INTRODUCTION
41.4 Purpose..
41.2 Owner
2 GUIDELINES AND INTERFACING TO ATOS ........ceceseesesessereseseseseseeeeneneseetsenes 10.
2.1 Guidelines
2.2 — Interfacing to Ato:
3 POST OFFICE ACCOUNT DEFINING A MAJOR INCIDENT ........--sscsssessessereene TY
3.1 Incident Classification
3.2 Influencing Factors in calling a Major Inciden' 1
3.3. Major Incident Trigger: 1
3.3.1 Network Triggers... 12
3.3.2 Infrastructure Components Triggers
3.3.3 Data Centre Triggers .

Online Service Triggers .
POLSAP Service Triggers

Security Triggers .
ident

3.4 Major Business Conti ty.
6.1 Technical Bridge .
6.2 Service Bridge ..
6.3 Communication Process Fi 16
6.4 Major Incident Communication Flow Diagram 18
6.5 Post Office Major Incident Report Requirement: 19
66 Escalation Communication Protocol ....
7 FORMAL INCIDENT CLOSURE & POST INCIDENT REVIEW ....... cscs 20
‘Copyright Fujitsu Services Ltd 2006- _ FUJITSU RESTRICTED (COMMERCIAL IN Ref. SVM/SDM/PRO/000%
2019 CONFIDENCE) Version: 15.0

Date: 24-January-2019

Page No: 2 of 28
FUJ00234966
FUJ00234966

POA Operations Major Incident Procedure

Pe)
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN
CONFIDENCE)

7.4 Post Incident Review ....

7.2 The Major Incident Report

73 Calculating potential LD liability for Major Incidents

8 FUJITSU ROLES AND RESPONSIBILITIES DURING A MAJOR INCIDENT....23

8.1 Role of the MAC Team

8.2 Role of the Major Incident Manager

8.3 Role of the Technical Recovery Manag 25

8.4 Role of the Problem Manager .... 26

8.5 Role of the Communications Manager. 26

8.6 Role of the SDUs: (Technical Teams /SMC/MAC & Third Parties) 26

8.7 Role of the Service Delivery Manager owning the affected service

8.8 Role of the Service Lead/Senior SDM......

9 APPENDICES. 27

9.1 Daytime Duty Manager Contact Details .. 27

9.2 Qut of Hours Duty Manager Contact Details 27

9.3 POA Service Delivery Contact Details 27

9.4 Special Situations .. 28
9.4.4 Personnel Absenc! 28

9.4.2 QOH
9.4.3 Duty Manager Change Over
SCopyright Fujitsu Services Lid 2006- _ FUJITSURESTRICTED (COMMERCIAL IN Ref. SVMISDM/PROTO00%
2019 CONFIDENCE) Version 15.0
Date 24-January-2019

Page No: 3 of 28.
FUJ00234966
FUJ00234966

oO POA Operations Major Incident Procedure
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN
CONFIDENCE)

0.2 Document History

Version No. — D Summary of Changes and Reason for Issue ciated Change -
CP/PEAK/PPRR
Reference
04 03-Oct-06 First draft — to detail the Major Incident Escalation process
Draft taken from Horizon Document CS/PRD/122, V1.0.
1.0 11-Oct-06 Revision following comments from Reviewers
2.0 02-Sep-08 Changes for Acceptance by Document Review: insertion of

Section (0.4) containing table of cross references for
Acceptance by Document Review and addition of note to front
page. No other content changes.

24 24-Feb-2009 —_I Changes made for Acceptance by Document Review by Fiona
Woolfenden including the removal of references to

CS/PRD/074 which has been Withdrawn and replaced by

SVM/SD/PRO/0018 and other tidying up changes

Other changes to update Contact details.

2.2 14-Apr-2009 ‘Some Personnel Name changes and POA to POA +
Abbreviations. Security Updates to sections 5.1, 6.3, 8.2.1
9.0,

23 3June-2009 I Some Personnel Changes and minor changes following review
in May 2009

3.0 7-July-2009 Following security audit 2 minor changes. Alan Simpson now
‘on distribution and 6.3, an extra bullet entry added at end of
list

3.0 7-July-2009 Following security audit 2 minor changes. Alan Simpson now
on distribution and 6.3, an extra bullet entry added at end of
list.

34 44-Jan-2010 I Changes following director failing to sign off v3.0, plus minor
contact changes.

40 26-Mar-2010 I Approval version

44 18-May-2010 _I Following team restructure, the process has been significantly
reviewed

42 03-Jun-2010 I Updated following minor comments provided during review
cycle of version 4.1. This version will be presented for approval
at v5.0

5.0 07-Jun-2010 I Approval version

6.0 14-Sep-2010 _I Approved version following updates to personnel and table in
10.4 and section 10.8

64 15 July-2011 I Updates to personnel and changes from ‘Process’ to
Procedure’

6.2 05-Sept-2011 I Updates following changes requested by Bill Membery from
6.1, plus clarification of TRM role

63 14-Oct-2011 I Cosmetic changes mainly changing RMGA with POA and also
updating abbreviations

64 21-Dec-2011 I Updating of details for a Service Bridge

Also some POL requests

Despite this being an internal POA document, all external
comments that can improve the document are considered.

65 16-Jan-2012 I Updated, following review and cosmetic changes in relation to
SCopyright Fujitsu Services Lid 2006- _ FUJITSURESTRICTED (COMMERCIAL IN Ref. SVMISDM/PROTO00%
2019 CONFIDENCE) Version 15.0
Date 24-January-2019

Page No: 4 of 28
FUJ00234966
FUJ00234966

oO POA Operations Major Incident Procedure
FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN
CONFIDENCE)

Version No. Summary of Changes and Reason for Issue Associated Change -

PEAK/PPRR
Reference

version 6.4

7.0 02-Jan-2013 Changes in relation to Personnel and also Tower Leads and
other cosmetic changes

7.4 04-Feb-2013 Changes in relation to Personnel and revisions around
Communications

72 17-Sep-2013 I Major update to align with Business Assurance Management
procedures and for organisational changes

(This version was originally identified as version 8.1)

8.0 48-Oct-2013 I Updated for minor changes from Nana Parry.

8.1 10-Jun-2014 Amended to replace the HSD function with the Atos Service
Desk and replaced IMT references with the MAC team.

Also updated to reflect the introduction of Atos as POL's
Service Integrator.

9.0 14-Aug-2014 __I Implemented minor changes following 8.1 review cycle.

94 22-Jan-2015 Optional Reviewers amended to include Chris Harrison &
Shaun Stewart.

Section 3.3.5 POLSAP Service Triggers added

Section 10.1 amended to refer to the Major Incident Report
and Post Incident Review Report templates which are now
held in Dimensions.

10.0 12-Feb-2015 I Minor update to section 9.1 and issued for approval
40.1 40-Sep-2015 I Note added to Section 1.1

General revision to reflect recent organisational changes, the
removal of the Engineering service.

Created table entry 6.13 and section 8.2 to cover the
production and management of multiple versions of the Major
Incident Report

10.2 22-Sep-2015 Minor changes for comments received from informal review
and issued for formal review.

11.0 12-Jan-2016 —_I Section 4.0 updated, table entry 6.12 amended, other minor
updates and issued for approval. — This Version was
REJECTED in Dimensions.

14.4 23-Jun-2016 —_I Section 4, Security Major Incidents deleted. Re-aligned cross
references to section numbering from 5 onwards

11.2 49-Jul-2016 Revised to include feedback from Steve Bansal replacing
Tower Lead with Senior SDM and/or Service Lead and
incorporated changes requested by Bill Membery.

12.0 19-Jul-2016, Approval version

12.4 14-Dec-2016 _I Section 3.3.5 POLSAP Service Triggers modified to reflect 5"
October 2016 migration of POLSAP application support to
Accenture.

Section 7.1 modified to include recommendations to share
lessons learnt across Fujitsu, as per the Fujitsu EMEIA
Business Management System Major Incident Procedure
issued on 28" July 2016

12.2 09-Jan-2017 I Removed Sandie’s name from optional review appeared
twice
13.0 42-Jan-2017 I Approval version
13.4 20-Jul-2017 The procedure was checked and updated for CCN1602 CCN 1602; CCN1609
(section 3.3.5 amended to remove reference to Credence), CCN1614
CCN1609 (no change) and CCN1614 (section 3.3.1 amended
©Copyright Fujitsu Services Ltd 2006- _ FUJITSU RESTRICTED (COMMERCIAL IN Ref. SVM/SDM/PRO/O001
2019 CONFIDENCE) Version: 15.0
Date: 24-January-2019

Page No: 5 of 28
Fe)
FUJITSU

POA Operations Major Incident Procedure

FUJITSU RESTRICTED (COMMERCIAL IN

CONFIDENCE)

FUJ00234966
FUJ00234966

Version No,

Summary of Changes and Reason for Issue

Associated Change -
CP/PEAK/PPRR
Reference

to remove reference to the VSAT service).

Revised section 0.5.

13.2 12-Sep-2017

Revised section 9.3, Out of Hours Duty Manager Contact
Details.

14.0 12-Sep-2017

Approval version. Updated link to Dimensions web service
section 9.1

14.1 31-May-2018

Major re-write so that the Fujitsu EMEIA Major Incident
Procedure is used as the primary process and this document
contains customer specific process requirements in managing
a major incident. It also contains changes for HDCR changes
and amendment in the Acceptance by Document Review,
section 0.4. Requested internal Fujitsu Document Review

14.2 26-Oct-2108

Section 3.3.6, Security Triggers, updated to include breaches
of Data Protection Legislation

24-Jan-2019

Incorporated changes for comments raised by Steve Bansal
and Sandie Bothick.

Additionally, further changes made during Author review

0.3 Review Details

Review Comments by

Review Comments to
Mandatory Review

Role

Tony Wicks and Matthew Hatch

Name

Senior Service Delivery Manager

Steve Bansal

POA Acceptance Manager

Steve Evans

Role

Optional Review

Name

POA Infrastructure Operations Manager

‘Andrew Hemingway

POA Business Continuity Manager

Almizan Khan

POA Problem Manager

Matthew Hatch

POA Lead SDM Online Services and Risk Manager
POA Senior Ops Manager HNS

Yannis Symvoulidis

Alex Kemp

POA MAC & OBC Manager

Sandie Bothick

POA Operations Manager

Jerry Acton

POA Security Manager

Jason Muir

POA Network Infrastructure SDM

Issued for Information — Please restrict this
distribution list to a minimum

Position/Role

Chris Harrison

Name

POA CISO

Steve Godfrey

(* ) = Reviewers that retuned comments.

SCopyright Fujitsu Services Ltd 2006-
2019

FUJITSU RESTRICTED (COMMERCIAL IN Ref.
CONFIDENCE)

Version
Date:
Page No:

SVMISDM/PROTO00%
15.0
24-January-2019

6 of 28
FUJ00234966
FUJ00234966

POA Operations Major Incident Procedure

FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)

0.4 Acceptance by Document Review

The sections in this document that have been identified to POL as comprising evidence to support
Acceptance by Document review (DR) are listed below for the relevant Requirements:

POL NFR DR Internal FS POL — Document Section Document Section Heading
Acceptance Ref NFR Reference Number
SER-2200 SER-2178 Whole Document
SER-2202 SER-2179 Whole Document
SEC-3095 SEC-3266 3.3.6 Security Triggers
SEC-3095 SEC-3266 SVM/SDM/PRO/0018 Security Major Incidents
I section 8.5

0.5 Associated Documents (Internal & External)

Reference Version Date Title Source

ARC/SEC/ARC/0001 Security Constraints Dimensions

CS/IFS/008 POA/POL Interface Agreement for the Dimensions
Problem Management Interface

CS/QMS/001 Customer Service Policy Manual Dimensions

EMEIA Incident EMEIA Incident Management Process. EBMS.

Management Process

EMEIA Major Incident EMEIA Major Incident Procedure EBMS

Procedure

EMEIA Root Cause EMEIA Root Cause Analysis (RCA) Process I EBMS

Analysis (RCA)

Process

ISSC-11a Information Security Incident Management I ATOS
Procedure

PA/PRO/001 Change Control Process Dimensions

PGM/DCM/TEM/0001 Fujitsu Services Post Office Account HNG-X I Dimensions

(00 NoT REMOVE) Document Template

SVMI/SDM/INR/2693 Major Incident Report Template Dimensions

SVM/SDM/PLA/0001 HNG-X Support Services Business Dimensions
Continuity Plan

SVM/SDM/PLA/0002 HNG-X Services Business Continuity Plan Dimensions

SVM/SDMIPLA/0031 HNG-X Security Business Continuity Plan Dimensions

SVM/SDM/PRO/0018 POA Operations Incident Management Dimensions
Procedure

SVM/SDM/PRO/0025 POA Problem Management Procedure Dimensions

SVM/SDM/SD/0011 Branch Network Services Service Dimensions
Description

SVM/SDM/SD/0023 POA Incident Enquiry Matrix Dimensions

©Copyright Fujitsu Services Ltd 2006- FUJITSU RESTRICTED (COMMERCIAL IN Ref. SVM/SDM/PRO/0001
2019 CONFIDENCE) Version: 15.0

Date 24-January-2019
Page No: 7 of 28
FUJ00234966
FUJ00234966

POA Operations Major Incident Procedure

FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)

Reference Version Date Source

SVMSDM/TEM/2531 Post Incident Report Template Dimensions

Unless a specific version is referred to above, reference should be made to the current approved
versions of the documents.

0.6 Abbreviations

Abbreviation Definition

AtG Advice & Guidance

BCP Business Continuity Plan

BMS Business Management System

EMEIA Europe, Middle East, India and Africa

Iso International Standards Organisation

ITIL Information Technology Infrastructure Library

KEDB Known Error Database

KEL Known Error Log

MAC. Major Account Controllers

MBCI Major Business Continuity Incident

MIM Major Incident Manager

MICM Major Incident Communications Manager

MIR Major Incident Report

MSU Management Support Unit

OOH Out Of Hours

PCI Payment Card Industry (as per Security Standards Council)

PO Post Office

POA Fujitsu Post Office Account

POL Post Office Limited

RFC Request For Change

SCT Service Continuity Team

SDM(s) Service Delivery Manager(s)
(NB: Throughout this document SDM refers to a person responsible for the Service,
and the SDM could work in, but not limited to, the Service Delivery, Service Support,
and Release Management or Security teams).

SDU Service Delivery Unit

SLT Service Level Targets

siSD Service Integrator Service Desk (Atos Service Desk)

SMC Systems Management Centre

SMS Short Message Service (as known globally within Mobile Telephone Networks)

SRRC Service Resilience & Recovery Catalogue

ssc ‘System Support Centre

TB Technical Bridge

©Copyright Fujitsu Services Ltd 2006- FUJITSU RESTRICTED (COMMERCIAL IN Ref. SVM/SDM/PRO/0001
2019 CONFIDENCE) Version: 15.0

Date 24-January-2019
Page No: 8 of 28.
FUJ00234966
FUJ00234966

POA Operations Major Incident Procedure

FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)

Abbreviation inition

TIS (TISNow) Triole for Service — Hosts Incident, Problem and Change databases
TP Third Party or Third Parties

TRM Technical Recovery Manager

vip VIP Post Office, High Profile Outlet

0.7 Glossary

Tel

EMEIA Business
Management System

Definition

The EMEIA Business Management System (EBMS) is the central library for all
Policy, Process and associated assets which provides Fujitsu with the responsible
way of working that keeps the company, its employees and the services we deliver
efficient, effective and compliant

Fujitsu EMEIA Refers to Fujitsu Services Holdings PLC, Fujitsu Technology Solutions (Holding) BV
and their subsidiaries, whether they be incorporated within the EMEIA Region or not,

and any other company or organization that is managed by the EVP, Head of EMEIA

Region.
T Time of incident occurring
T+3 Time Incident Occurred plus 3 minutes

0.8 Changes Expected

Changes to reflect process and organisational changes

This is expected to be changed for the OSR Messaging release

0.9 Accuracy
Fujitsu Services endeavours to ensure that the information contained in this document is correct but, whilst every

effort is made to ensure the accuracy of such information, it accepts no liability for any loss (however caused)
sustained as a result of any error or omission in the same.

0.10 Security Risk Assessment

Security risks have been assessed and it is considered that there are no security risks relating specifically to this
document.

©Copyright Fujitsu Services Ltd 2006- _ FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVMISDM/PROI000%
2019 CONFIDENCE) Version: 15.0
Date 24-January-2019
Page No: 9 of 28
FUJ00234966
FUJ00234966

POA Operations Major Incident Procedure

FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)

1. Introduction

1.1 Purpose

The purpose of this Post Office Account major incident procedural document is solely to supplement the
major incident processes defined in the Fujitsu EMEIA Business Management Systems Major Incident
Procedure with any Post Office Limited specific requirements or requests.

This document outlines the management guidelines to be used for Major Incidents impacting the live
estate in communicating with Atos and Post Office Limited.

1.2 Owner

The owner of the Major Incident Management process at the local POA level is the Fujitsu POA Senior
SDM, Problem and Major Incident.

2 Guidelines and Interfacing to Atos

2.1 Guidelines

It is important to maintain a balance between:
a) Allowing the technical teams the right amount of time to diagnose and impact an incident
b) Avoiding unnecessary alerting of the customer

c) Assessing which incidents are major
2.2. Interfacing to Atos

¢ During the MAC Core Hours (Monday — Friday 08:00 — 20:00, Saturday 08:00 — 17:00) and Bank
Holidays 0800 — 1400 excluding Christmas Day. The MAC should be the first point of operational
contact between Fujitsu and the Atos Service Desk. The SMC are responsible for escalation of
incidents to the POA OOH Duty Manager. The POA OOH Duty Manager may initiate
communications with the Atos OOH Duty Manger. The SMC operate on a 24 x 7 x 365 basis.

e Any activity detailed in this document which is assigned to the MAC team is handed over to the
SMC outside the MAC Core Hours, with the exception of the above.

e The relevant technical teams who are aware of and monitoring a potential major incident must
call the appropriate Major Incident Manager (Duty Manager out of hours) as soon as possible.
This is not limited to major incidents alone, but applies wherever a state other than Business as
Usual has been detected. The Major Incident Manager must in turn communicate the potential
incident, to the Atos Service Desk for awareness and monitoring in Atos. This is usually done via
the MAC team in core hours.

e The Major Incident Manager (or Duty Manager out of hours) is responsible for communicating
both up the Fujitsu organisation and across (see appendix 9.3) to their counterpart in Atos.
Where this is impractical (e.g. leave, out of hours, unavailable), the initiative should be taken to
jump up the organisation. Of prime importance is that the customer is informed in a timely
manner and at the correct touch point. This communication should be by voice or direct SMS.

©Copyright Fujitsu Services Ltd 2006- FUJITSU RESTRICTED (COMMERCIAL IN Ref. SVM/SDM/PRO/0001
2019 CONFIDENCE) Version: 15.0
Date: 24-January-2019

Page No: 10 of 28
FUJ00234966
FUJ00234966

POA Operations Major Incident Procedure

FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)

The communication should include the date, time, name, nature of the incident, priority, if service
affecting, likely impact, and the Fujitsu owner to contact.

e The Major Incident Manager (Duty Manager OOH, who covers Monday to Friday 17:30 to 09:00
and from 17:00 Friday though to 09:00 Monday) should also initiate communication using SMS
via the MAC team (see operational hours above.). Outside of these hours the SMS should be via
the SMC. The SMS distribution list used is titled ‘SMS Internal’ and amongst others includes the
appropriate members of the POA Operations Management Team.

3 Post Office Account defining a Major Incident

3.1. Incident Classification

As a general rule a Major Incident will be an incident rated as a Business Critical Incident as shown in the
following

- The ‘CONTRACT’
- Sections 3.2 and 3.3 below.
- POA Operations Incident Management Procedure document (SVM/SDM/PRO/0018).

- Aseries of connected lower priority incidents which combine to have a significant business
impact.

However not all incidents rated as priority 1 qualify as a Major Incident as the priority levels do not always
reflect the overall business impact to POL. For example a single counter post office which is unable to
trade, regardless of its business volumes, is rated as a priority 1 incident.

For incident classification on Post Office Account refer to the POA Incident Enquiry Matrix
SVM/SDM/SD/0023.

3.2. Influencing Factors in calling a Major Incident

It is important that a Major Incident is defined in accordance with section 3.3 Major Incident Triggers, as
such, because of its business impact on the day when it occurs, rather than simply being defined as a
Major Incident because it appears on a list. However the following parameters will also feed into the
consideration of whether a major incident should be called:

e Duration, i.e. how long has the vulnerability to service already existed?

e Impact across the estate, including consideration of whether a service is merely degraded or
actually stopped

e Time at which the event occurs in relation to the 24 hour business day
e Time of year — e.g. Christmas / Easter / End of month / quarter

« Anticipated time before service can be resumed

e Impact to POL branches, customers, clients or brand image

e Business initiatives e.g. product launches

3.3 Major Incident Triggers

The following criteria could trigger a major incident, however as detailed in 3.2, the influencing factors
must also be considered. As such the list below is not exhaustive, whilst if an incident occurs which is
not detailed below, e.g., legislative, it should not necessarily be precluded from being declared a major
incident.

©Copyright Fujitsu Services Ltd 2006- FUJITSU RESTRICTED (COMMERCIAL IN Ref. SVM/SDM/PRO/0001
2019 CONFIDENCE) Version: 15.0
Date: 24-January-2019

Page No: 11 of 28
FUJ00234966
FUJ00234966

POA Operations Major Incident Procedure

FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)

It should be noted that any call trends in relation to the following, should be reported to the POA Duty
Manager as soon as the agreed threshold levels have been breached.

3.3.1 Network Triggers
Network Major Incident triggers are as follows:

e Complete or significant outage of the Central network, e.g. failure of both 3750 stack Catalyst
switches in totality for the Core layer in IRE11.

3.3.2 Infrastructure Components Triggers
Infrastructure component Major Incident Triggers are as follows:
e Total loss of environments providing individual online service capability
¢ Breach of access to data centres
« Breach of security
e Virus outbreak.

3.3.3. Data Centre Triggers
Data Centre Major Incident triggers are as follows:
e Network / LAN outage
e Loss of Data Centre, or significant loss of Data Centre Components

e Breach of security.

3.3.4. Online Service Triggers
Online services Major Incident Triggers are as follows:
e Online service unavailable within the Data Centre (not counter level)
e Third party provided service failure —- e.g. DVLA, Link, Moneygram, Santander etc.

N.B Once the third party service provider has been deemed to be the source of the Major
Incident; it will be managed by either POA or Atos Service Desk in accordance with whichever
organisation manages that supplier relationship.

3.3.5 POLSAP Service Triggers

POLSAP services Major Incident Triggers are as follows:

e Business stopped for any Fujitsu controlled reason, e.g. infrastructure failure/outage that would
render Post Office unable to process POLSAP business transactions.

e Outage of key Fujitsu infrastructure which affects the POLSAP services.

e APOLSAP infrastructure security incident

Whilst the POLSAP servers are maintained as a part of Fujitsu infrastructure, the cut over point of
POLSAP services migrated to Accenture on 5' October 2016 and incidents relating to POLSAP
application should be routed to the third party via the ATOS Service Desk. Accenture support would
include, among others, the below which were previously solely Fujitsu responsibility:

©Copyright Fujitsu Services Ltd 2006- FUJITSU RESTRICTED (COMMERCIAL IN Ref. SVM/SDM/PRO/0001
2019 CONFIDENCE) Version: 15.0
Date: 24-January-2019

PageNo: 12 of 28
FUJ00234966
FUJ00234966

POA Operations Major Incident Procedure

FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)

e APOLSAP local environment failure resulting in Post Office departments being unable to
process work, e.g., FSC (POL settling with clients and tracking stock and cash for Post Office
Ltd), Supply Chain (Cash Services Business Unit) or Cash Services CMS System (Quotations
and Client Management)

e Complete loss of a POLSAP application.
e APOLSAP application security incident.

3.3.6 Security Triggers
Security major incident triggers are as follows:

e Actual or suspected attacks on the Fujitsu Services Buildings and its resources, POA Network or
Information Systems

e = Theft of IT equipment / property
° Theft of software

« Either Cardholder Data or Sensitive Authentication Data not being handled as described in the
CCD entitled “Security Constraints” (ARC/SEC/ARC/0001) or as required by PCI -DSS.

e Breach of Data Protection Legislation — inclusive of the GDPR, the Privacy and Electronic
Communications (EC Directive) Regulations 2003 and all other Applicable Law in respect of data
protection and data privacy including any applicable guidance or codes of practice that are
issued by the Information Commissioner, Working Party 29 and/or the European Data Protection
Board (and each of their successors);

In the event of a Security Incident, minor or major (which also include GDPR and PCI Incidents), the POA
Operational Security Manager MUST be informed.

The POA Incident Management procedure SVM/SDM/PRO/0018 Appendix A provides further guidance
on security incidents and the contact details for the POA Operational Security Manager is contained in
Appendix B.

From a corporate perspective the Fujitsu EMEIA SECURITY INCIDENT REPORTING PROCEDURE is.
to be followed.

3.4 Major Business Continuity Incidents (MBCl)
For HNG-X the MBCI triggers are listed in:
« _HNG-X Support Services Business Continuity Plan (SVM/SDM/PLA/0001)
« HNG-X Services Business Continuity Plan (SVM/SDM/PLA/0002)
« HNG-X Security Business Continuity Plan (SVM/SDM/PLA/0031)

These documents should be referred to as appropriate in the event of Major Incident to determine if
Business Continuity needs to be invoked.

4 Calling the Major Incident

During business hours the Major Incident Manager declares and manages the Major Incident (with
handovers to the POA OOH Duty Manager where applicable.)

Where the impact of the incident is not immediately obvious, and it is not clear if a Major Incident should
be called, escalation and discussion with the POA Operations Management Team should occur, and a

©Copyright Fujitsu Services Ltd 2006- FUJITSU RESTRICTED (COMMERCIAL IN Ref. SVM/SDM/PRO/0001
2019 CONFIDENCE) Version: 15.0
Date: 24-January-2019

PageNo: 13 of 28
FUJ00234966
FUJ00234966

POA Operations Major Incident Procedure ~

FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)

collective decision made. If a Major Incident is not called, the incident should be monitored until closure,
to ensure that the impact does not increase to that of a Major Incident.

In the event that multiple services are impacted, multiple Major Incident Managers may be appointed by
any Service Lead or Senior SDM and will remain in their roles until incident closure.

Out of hours the POA OOH Duty Manager is responsible for declaring a Major Incident.

Section 8 of this document specifies the roles and responsibilities during a major incident. The Major
Incident Manager, see section 8.2, is referred to the Manage Major Incident Procedure and must
endeavour throughout the life of a major incident to adhere to the principles of that procedure.

©Copyright Fujitsu Services Lid 2006- _ FUJITSURESTRICTED (COMMERCIAL IN Ref. SVMISDM/PROI000%
2019 CONFIDENCE) Version: 15.0
Date 24-January-2019

PageNo: 14 of 28
FUJ00234966
FUJ00234966

POA Operations Major Incident Procedure

FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)

5 Process Flow

As stated in section 1.2 Purpose, this Post Office Account Major Incident Procedural document is solely
to supplement the major incident processes defined in the Fujitsu EMEIA Business Management
Systems Major Incident Procedure so please refer to the EMEIA procedure and utilise the templates
provided within that procedure. These include the Major Incident Report and e-mail templates.

Section 6.4 of this Post Office Account process details the normal Major Incident Communication Flow
agreed with Post Office and ATOS the Post Office Limited Service Integrator.

When initiating the Major Incident Report, as required by the Fujitsu EMEIA Business Management
Systems Major Incident Procedure, take into consideration the Post Office specific reporting requirements
detailed in the Post Office Major Incident Report Requirements contained in section 6.5 below.

6 Communications

6.1 Technical Bridge

This is a Fujitsu technical conference for Technical experts and SDU's to discuss and analyse the
incident and to formulate an action plan to restore the service to POL without delay. It should enable the
Technical Recovery Manager to baseline the anticipated response, covering resolution, time and
resources required. This will also include the appropriate owning SDU of the service affected by the
Major Incident.

The Technical Bridge will be set up as required by the Major Incident Manager.

Invitations to the Technical Bridge will be via SMS, email, various Skype functions or voice. The SMS will
be sent to the distribution list titled ‘Technical Bridge’. The SMS text or Skype meeting request will be
sent to technical experts on the POA account and will include outline details of the Major Incident. Also
dial in details and the start time will be provided as part of the meeting invitation.

The Technical Bridge will be started at T + 15, and reconvened at regular intervals during the Major
Incident; the exact scheduling will be discussed and agreed at each preceding Major Incident Call.

The Technical Bridge is chaired by the Major Incident Manager with the recovery managed by the
Technical Recovery Manager.

A request for a Technical Recovery Manager (TRM) will be made to the appropriate Service Delivery Unit
or Development Leads, who will appoint one of his team to be the TRM.

Following each Technical Bridge, it is the responsibility of the TRM to agree any actions as follows
-Recovery / restoration actions (which should normally include the TfSNow Change numbers),
-Service Improvement Plan recommendations
-Risk Register recommendations
-Recommendations for any improvements to KELS / Alerting / Configuration changes

The above will be documented in the Major Incident Report which is produced using the MIR Report
template contained within the Fujitsu EMEIA Business Management Systems Major Incident Procedure

6.2 Service Bridge

This is a service focussed call for Service Management (including the Technical Recovery Manager if
appropriate) and POL to discuss the service impact of the Major Incident and to receive updates on the
progress towards resolution. Atos Service Management may also be the initiators of a Service Bridge.

©Copyright Fujitsu Services Ltd 2006- FUJITSU RESTRICTED (COMMERCIAL IN Ref. SVM/SDM/PRO/0001
2019 CONFIDENCE) Version: 15.0
Date: 24-January-2019

Page No: 15 of 28
FUJ00234966
FUJ00234966

POA Operations Major Incident Procedure

FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)

The purpose of the Service Bridge is to provide a focussed area from which strategic decisions can be
made regarding a Major Incident.

As a guide the attendance is made up of the following or their designated representative:
e Atos (Personnel as instructed by Atos Duty Manager or Live Systems Service Manager)
e The Senior SDM (Chair Person)
*° POA other Service Leads or Senior SDMs
e POALead SDM, Problem and Major Incident
e POA Security Manager (If required)
e POASDM owning the affected service
e Third Party Executives (if appropriate)
Service Bridge responsibilities include:
e Agreement of a containment plan
e Documentation of all agreed actions and timescales with owners
e Consistent management of the Major Incident across all the locations involved
* Management of potential Major Business Continuity Incidents (MBCI's) within Atos and the POA
e Co-ordinate meeting times and locations

In the event of a Major Incident requiring a Service Bridge, it is envisaged that this will be in place at T+60
(or earlier if required by Atos). Participants required in the Service Bridge will be contacted via SMS as
appropriate.

The Senior SDM will send out a text via the MAC team in order to organise a Service Bridge.
Invitations to the Service Bridge will be via SMS, email, Skype or voice.
The SMS text, email or Skype invitation should state such details as;

oAn outline of the ongoing incident,

oDial in details

oStart time.

The chairperson's code is held by the POA Senior SDM and the Problem and Major Incident Managers.
The chairperson, normally the Senior SDM will initiate the call.

The TRM will attend meetings as required and provide appropriate root cause analysis and corrective
action detail.

6.3 Communication Process Flow

e On suspicion or confirmation of a Major Incident, the MIM will escalate to the Senior SDM for the
area, Problem and Major Incident Management SDM, and to the POA Service Leads.

e The MIM will inform the Atos Service Desk, via the MAC team, of the start of the service incident
alerting of potential issues — including date, time, nature of the incident, priority and impact if
known and then directly inform the Atos Live Service Manager

e All updates to the Atos Service Desk are via the MAC team, within agreed timescales controlled

by the MICM
©Copyright Fujitsu Services Lid 2006- _ FUJITSURESTRICTED (COMMERCIAL IN Ref. SVMISDM/PROI000%
2019 CONFIDENCE) Version: 15.0
Date 24-January-2019

Page No: 16 of 28
FUJ00234966
FUJ00234966

POA Operations Major Incident Procedure

FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)

e The MICM will issue an SMS text to the POA, alerting of potential issues — including date, time,
nature of the incident, priority, impact and name

e APOA Service Lead or Senior SDM will inform the following within 10 minutes of start of the
service incident
o POA Delivery Executive
o POL Senior Service Delivery Managers
And will coordinate and ensure consistency of response to Atos and POA Senior Management
via The Service Bridge

« Periodic (interval to be determined depending on the nature of the issue but approxiamately 30
minutes as appropriate for Major Incidents) SMS updates to be sent to the original SMS Dist list

e On final service restoration, an SMS text message must be sent to the original SMS Dist list

« The POA Senior SDM, will confirm understanding of Major Incident closure with Atos
management and POA senior management, and agree next steps

©Copyright Fujitsu Services Lid 2006- _ FUJITSURESTRICTED (COMMERCIAL IN Ref. SVMISDM/PROI000%
2019 CONFIDENCE) Version: 15.0
Date 24-January-2019

Page No: 17 of 28
ON e6eq

6102

-900Z PI] seomes nsying ySukdog@

(3ONACIANOO
Ni TWIOMSWWOOS) GSLOLSSY NSLIPAS

ayeg
UOISIO/\,

ost

610z-Auenuer-pz,
4000/O8d /NGS/NAS

384

I Technical

Fujitsu Management

Atos Management

t

pooee nn ----------5,
I One update
— : 1. Update master
Service Bridge TFSNow call
U ! 2. Update Service
ay ' i
Pp fo} \ Bridge
Net’ Atos I 3. Voice update
D FUJITSU Live I Atos SD
A Senior Service I 4. Email update to
T SDM Manager Atos SD and
+1 +1 ! Live Service
E & POL 1 and Continuity
I Manager
MICM
update on
call ot {4}

Atos SD

< Voice.

weibeig Moj4 uolediuNWWOD JUuap!oU] sofew "9

FUJ00234966
FUJ00234966

(SONSGISNOO NI IWIONAWWOD) GSLOLS3aY NSN nsln J

(os

aunpasodg JUap!ou Jofew suonesedo YOd
FUJ00234966
FUJ00234966

POA Operations Major Incident Procedure ~

FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)

6.5 Post Office Major Incident Report Requirements

POL agreed template to base MI updates on.

Questions POL need to understand

What has happened?

Where in the system has a fault occurred?

\/s this in the Fujitsu domain or third party (ie. TTB)?

©Copyright Fujitsu Services Ltd 2006- FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVM/SDM/PRO/0001
2019 CONFIDENCE) Version: 15.0
Date: 24-January-2019

PageNo: 19 of 28
FUJ00234966
FUJ00234966

POA Operations Major Incident Procedure

FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)

6.6 Escalation Communication Protocol

The primary principle:

“Up and Across”

Example:

The Major Incident Manager would escalate up to POA Lead SDM, Problem and Major Incident
Management, and across to the Atos Service Desk.

7 Formal Incident Closure & Post Incident Review

7.1 Post Incident Review

The Post Incident Review is chaired by the Major Incident Manager and follows a set agenda which is
distributed with the Post Incident Review meeting invitation, along with the draft copy of the Major
Incident Report (if available).

The template for writing a Post Incident Review Report is stored in Dimension (hyperlink below) under
SVM/SDM/TEM/2531.

http://europevuk459.europe fs.fujitsu.com/ccmweb/ProjectHome1 .aspx

The purpose of a Post Incident Review is:

* To understand the incident that prevented a Service or Services from being delivered.

* To confirm the impact to the business during and after the Incident and agree the number of
branches impacted and duration of Major Incident.

* To confirm the end-to-end recovery process and timeline, and identify that all documented
processes were followed.

* To analyse the management of the incident and the effectiveness of the governance process.
* To identify corrective actions, including agreed Third Party actions, to:
© prevent recurrence of the incident

co minimise future business impact
o improve the procedure for the management of incidents

Output: To confirm details provided in the draft MIR provided to Atos, update with corrective actions and
redistribute. To also include any of the following as appropriate

- any activities for a Service Improvement Plan
- any Changes and associated TfSNow Change reference.

- any follow up that requires to be progressed via Problem Management

©Copyright Fujitsu Services Ltd 2006- FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVM/SDM/PRO/0001
2019 CONFIDENCE) Version’ 15.0
Date: 24-January-2019

Page No: 20 of 28.
FUJ00234966
FUJ00234966

POA Operations Major Incident Procedure

FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)

- any improvements to KELS, alerting and /or event management

The agreed impact of the Major Incident must be provided for inclusion in the Counter Availability SLT
Figures.

If this review highlights areas where improvements can be made, an agreed Service Improvement Plan
will be produced, using the EMEIA SIP template, with appropriate actions, owners and timescales. It will
also identify any ongoing risks to the service, together with any changes. Service Management will track
all actions to resolution. Third party actions will be reviewed at Service Review meetings.

Consideration should be given as to whether the improvements can be shared across Fujitsu as lessons
learnt, in accordance with Fujitsu EMEIA Business Management System document: Major Incident
Procedure (28/07/2016). These are to be documented on the Lessons Learnt portal to help other
Accounts to learn from the failures or success of the major incident activities. As stipulated in the
document, there may be situations when the lessons cannot be shared due to confidentiality reasons.

Itis important that the number of branches impacted and the duration of the Major Incident is agreed at
the Major Incident Review. This information is required to calculate the impact on Branch and Counter
Availability and any associated Liquidated Damages (LD) liabilities

7.2 The Major Incident Report

A first draft of the Major Incident Report is to be produced within 24 hours and on the approval of the
POA Senior Service Delivery Manager sent to ATOS Service Management.

The first formal version of the Major Incident Report is to be produced within five working days and on the
approval of the POA Senior Service Delivery Manager is sent to ATOS Service Management. Generally
this report will be produced after a Post Incident Review is held and the actions for the Major Incident
Report identified.

If applicable a Problem Record is to be opened for tracking the corrective actions and managed through
the POA Problem Management Process. The formal Major Incident Report version 1.0 is to be attached
to the TfSNow problem record and sent formally for storing in Dimension.

One or more formal versions of the Major Incident Report is to be produced which will also be sent to
either ATOS Service or Problem Management, after the approval of the POA Senior Service Delivery
Manager, providing feedback on the corrective actions. These major incident reports are also to be
attached to the TfSNow problem record and sent formally for storing within Dimension

Please use the link below for the EMEIA Standard Major Incident Report
https://emeia fujitsu.local/emeia/c/P0004/Process_Maps/Major_Incident_Management_Process.pdf

You may need to amend the report template, so it covers the specific requirements of the customer i.e.
timeline.

©Copyright Fujitsu Services Ltd 2006- FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVM/SDM/PRO/0001
2019 CONFIDENCE) Version: 15.0
Date: 24-January-2019

PageNo: 21 of 28
FUJ00234966
FUJ00234966

POA Operations Major Incident Procedure

FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)

7.3 Calculating potential LD liability for Major Incidents

Major Incidents which qualify as Failure Events are detailed in the Branch Network Service Description
(SVM/SDM/SD/0011). A Failure Event is defined in this document as an event or series of connected
events which causes one or more Counter Positions to be deemed to be Unavailable due to a Network
Wide Failure or a Local Failure. Ongoing failures will be deemed to be part of such a Failure Event until
the Failure Event is closed in accordance with the Incident closure and Major Incident Review process as
detailed in section 6.0.

For a Failure Event the Incident Closure & Major Incident Review Process will require Atos and Fujitsu to
agree the number of branches and counter positions affected and the duration of the outage (rounded to
the nearest 30 minutes as detailed in the Network Wide Rounding Table).

Network Wide Rounding Table

30 minutes or less 30 minutes

More than 30 minutes 1 hour
but less than 1 hour

1 hour or more but less 1 hour
than 1 hour 30 minutes

1 hour 30 minutes or 2 hours
more but less than 2
hours

N hours or more but N hours
less than N hours 30
minutes

N hours 30 minutes or (N+1) hours
more but less than
(N+1) hours

©Copyright Fujitsu Services Ltd 2006- FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVM/SDM/PRO/0001
2019 CONFIDENCE) Version: 15.0
Date: 24-January-2019

Page No: 22 of 28.
FUJ00234966
FUJ00234966

POA Operations Major Incident Procedure

FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)

8

Fujitsu Roles and Responsibilities during a Major

Incident

This section defines the roles and responsibilities individuals and teams have as part of the Major
Incident Escalation Procedure. The following roles will be laminated and available for the MIM to assign
during a Major Incident.

8.1

Role of the MAC Team

The role of the Major Account Controllers team in the event of a Major Incident is as follows:

Receive phone calls and log incidents from Atos Service Desk, and communicate the progress of
investigations to the Atos Service Desk.

Notes:

1, There is also a HDI interface between Atos SDM12 and Fujitsu TfSNow systems so incidents
and updates may be automatically transferred as well

2, These incidents are generally considered ‘software’ incidents as branch engineering incidents
are no longer managed by Fujitsu.

Escalation of any Call Threshold Breaches to the POA Duty Manager
Confirming times and details to Major Incident Manager (MIM)

Send/update service impact details from the Atos Service Desk (e.g., trend analysis, which the
MAC is dependent upon Atos supplying) to the Major Incident Manager. These details will be fed
into the Technical Bridge in real time as requested, whilst details for the overall Major Incident will
be provided to the Major Incident Manager post the incident.

Be responsible for sending communications as provided by the Major Incident Communications.
Manager for the following:-

. If ATOS Incident Management or POL Senior Management send through Technical Bridge
requests through to the MAC team and not the POA Duty Manager, to ensure that they are
forwarded onto the POA Duty Manager mailbox and the call through if it is short notice.

To inform of new Major Incidents and provide MI updates of progress to the following
o E Mail Atos Service Desk

o Voice Atos Service Desk

The above communications will be as per instructed by the Major Incident
Communications Manager

ALL should be identical, in order to avoid any misunderstandings.

This also of course includes notification to Atos Service Desk and POA Management of
the restoration of service.

©Copyright Fujitsu Services Ltd 2006- FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVM/SDM/PRO/0001
2019 CONFIDENCE) Version’ 15.0
Date: 24-January-2019

PageNo: 23 of 28
FUJ00234966
FUJ00234966

POA Operations Major Incident Procedure

FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)

8.2 Role of the Major Incident Manager

Major Incident Manager (MIM). This will by default be either the Day Time Duty Manager or OOH Duty
Manager (hours shown in 9.3). However a separate member of the Service Management team may be
appointed as the MIM depending on the situation. The primary role of the MIM in a Major Incident is to
facilitate the management of the Incident through investigation and diagnosis to resolution, with the aim
of making the process as efficient and effective as possible. Upon determining that a Major Incident has
been called, a request for a Technical Recovery Manager (TRM) will be made to the appropriate POA
Service Lead or Senior SDM who will appoint one of his team to be the TRM. The Major Incident
Manager acts as the central point for communication and non-technical information flow, allowing the
TRM to focus on the technical situation and the resolution of the Incident. The Major Incident Manager is.
also responsible for creating and maintaining all the associated documentation. For the process to be
effective, all updates and information regarding the incident must be fed to the MIM to update the
timelines and report.

The Major Incident Manager:
e Calls and chairs the Technical Bridge

e Has responsibility for creating the Major Incident Report, using the template defined in section9.1
and ensuring that the applicable information is captured.

e Records the Technical Bridge attendees names so they can be documented in the Major Incident
Report.

e Identifies Business and Service impact though discussions with the users, the Atos Service Desk
and the MAC team — providing this input into the Tech Bridge.

e Distributes the Technical Bridge actions provided by the TRM (if appropriate).

e In conjunction with the TRM considers if escalation into the Corporate Alert process is desirable
and recommends this when required, see section 6.8 above.

e Assists with communication internally within the POA
«Track time lines

e Along with the POA Problem Manager, ensures that the TRM provides regular updates on any
longer term corrective actions.

« Following the resolution of the Incident, schedules and chairs the PIR

©Copyright Fujitsu Services Ltd 2006- FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVM/SDM/PRO/0001
2019 CONFIDENCE) Version: 15.0
Date: 24-January-2019,

PageNo: 24 of 28
FUJ00234966
FUJ00234966

POA Operations Major Incident Procedure

FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)

8.3 Role of the Technical Recovery Manager

The primary functions of the Technical Recovery Manager are to co-ordinate and manage the restoration
of service, manage the technical teams, and act as the communication point for the technical teams and
third parties. The function will also include managing all longer term technical corrective actions, e.g.
recommendations for improvements to KELs, eventing and configuration.

The Technical Recovery Manager:

« Manages the technical recovery of the Incident — liaising with SDUs and third parties.

« Provides updates on the recovery, when technicians / representatives of technical teams are
unable to attend the Technical Bridge.

e Is the only person to liaise directly with the technical teams, including technical third parties.

e Provides summarised actions from Technical Bridge to the Major Incident Manager, including:

°

°

°

°

Current status including impact and risk
Advising on potential workarounds.
Planned recovery activities including timelines

Root Cause Analysis’, corrective actions, and their corresponding action owners and
timelines (where known)

The TRM will be responsible for attending any meetings and providing appropriate root cause analysis
and corrective action detail. This will also include managing any longer term technical corrective actions
that are documented in the Major Incident Report and will include where appropriate

- Any activities for a Service Improvement Plan

- Any Changes / TfSNow Change references

- Any Risks

- Any Configuration changes

- Any improvements to KELS, alerting and /or events

- Any associated Peak or TfSNow calls

* For Root Cause Analysis refer to the Fujitsu EMEIA Conduct Root Cause Analysis Procedure.

©Copyright Fujitsu Services Ltd 2006- FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVM/SDM/PRO/0001
2019 CONFIDENCE) Version: 15.0
Date: 24-January-2019

PageNo: 25 of 28
FUJ00234966
FUJ00234966

POA Operations Major Incident Procedure

FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)

8.4 Role of the Problem Manager

The Problem Manager ensures that corrective actions / investigations are tracked and completed
following the major incident.

Any corrective actions arising from the Major Incident Review will be added to the Major Incident Report
and also a Problem Record if appropriate, and tracked with POL through to completion. The updates will
be distributed to Atos as required, and in the case of a Security Major Incident associated with PCI
failures, the POL Security team will also receive a copy of the report.

8.5 Role of the Communications Manager

The Major Incident Communications Manager (MICM) will attend the Technical Bridge and produce each
update, where possible trying to ensure that updates are provided on time and following the agreed Major
Incident Progress Template. This will reduce any miscommunication and ensure all parties follow
process.

e Above all ensuring only one update is circulated

e Will ensure that updates are provided within the agreed times

* Updates will adhere to the agreed Major Incident Progress Template
« Update the master TfSNow call with all updates

e Ensure update is provided to MAC to circulate through to Atos SD

« Supply update to Service Bridge

* Manages all communication internally within the POA

* Communicate to Fujitsu Core Major Incident Management team

e Manages via MAC, the communication with the Atos Service Desk on the progression of the
incident

8.6 Role of the SDUs: (Technical Teams /SMC/MAC & Third
Parties)

The role is to investigate the Incident, monitor the progress and feed into the Technical Bridge. Also in
the event of no pre-determined recovery options, suggest and evaluate potential recovery options to
resolve the Incident.

The technical teams should not be contacted by any party other than the Technical Recovery Manager.

The Technical Teams / SMC/ MAC team & Third Parties should send an attendee to the Tech Bridge and
the associated Major Incident Review meeting. Where attendance on the Tech Bridge is not possible, a
suitable alternative resource should attend. If neither is possible then a full update MUST be provided to
the TRM to ensure that the Bridge can be updated.

8.7 Role of the Service Delivery Manager owning the
affected service

©Copyright Fujitsu Services Ltd 2006- FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVM/SDM/PRO/0001
2019 CONFIDENCE) Version’ 15.0
Date: 24-January-2019

Page No: 26 of 28.
FUJ00234966
FUJ00234966

POA Operations Major Incident Procedure

FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)

e Attends Technical Bridge
e Attends PIR

e — Responsible for any further action proposed by the Problem Manager that falls outside the
Major Incident closure criteria.

e — Responsible for any Service Improvement Plan actions

8.8 Role of the Service Lead/Senior SDM

e Appoint a Technical Recovery Manager

« POA Service Lead or Senior SDM will inform within 10 minutes of the start of the service
incident the following-
o POA Delivery Executive
o POL Senior Service Delivery Managers

eWill coordinate and ensure consistency of response to Atos and POA Senior Management via
the Service Bridge

9 Appendices

9.1 Daytime Duty Manager Contact Details

¢ Steve Bansal +
¢ — Matthew Hatch

e Tony Wicks
« — Sandie Bothick =.
e — Piotr Nagajek -

9.2 Out of Hours Duty Manager Contact Details

The OOH Duty Manager provides cover between 17.30 - 09.00 Monday PM to Thursday AM and 17.00 -
09.00 Friday PM to Monday AM. The OOH Duty Manager can be contacted on the phone number
detailed in the Post Office Account Service Delivery Contact Details on Share Point (see 9.4 below) or on
the date relevant POA OOH Duty Manager rota.

Outside these times, please contact the POA Duty Manager

Note: Names and phone numbers are correct at the time of document issue and subject to change. In the
event of difficulties refer to the Fujitsu Services Global Address List for the latest details.

9.3 POA Service Delivery Contact Details

The Post Office Account service delivery contact details can be found on the Post Office Account Share
Point under Operations > BCP in a folder named Post Office Account Service Delivery Contact Details.

©Copyright Fujitsu Services Ltd 2006- FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVM/SDM/PRO/0001
2019 CONFIDENCE) Version’ 15.0
Date: 24-January-2019

Page No: 27 of 28
FUJ00234966
FUJ00234966

POA Operations Major Incident Procedure

FUJITSU FUJITSU RESTRICTED (COMMERCIAL IN CONFIDENCE)

9.4 Special Situations

9.4.1 Personnel Absence

e In the absence of a POA Service Lead or Senior SDM, an alternative Lead will be appointed.
e — Role cards have been produced and will be available to expedite the process.

9.4.2 OOH

e¢ The OOH Duty Manager will act as the Major Incident Manager.

9.4.3. Duty Manager Change Over

« The Duty Manager at the beginning of the incident will be by default responsible for all MIM
communications responsibilities unless a different arrangement is made between the
outgoing and incoming Duty Managers.

©Copyright Fujitsu Services Ltd 2006- FUJITSU RESTRICTED (COMMERCIAL IN Ref: SVM/SDM/PRO/0001
2019 CONFIDENCE) Version’ 15.0
Date: 24-January-2019

Page No: 28 of 28