HMT00000045
HMT00000045

RESTRICTED - POLICY AND COMMERCIAL 2

7 This note provides a summary of progress on the review of the project; and background on the key issues.

I When you receive the Working Group Report at the end of June, you will need to take early decisions on the way
forward!;

I We suggest at this meeting you:

1 note the background to the project and the consequences of cancellation (pages 3 to 9 below);

2 note the Expert Panel’s assessment on the viability of the project, timing and costs (executive summary
attached);

3 discuss key criteria for choosing between options (page 10);

4 give any initial reactions to the emerging assessment of options (page 11);

5 identify any areas and issues where you would like to see further work.

7 Apart from other considerations, ICL need an urgent response to their request for a variation in contract terms. There is a risk they may withdraw unilaterally and
seek redress through the courts.
HMT00000045
HMT00000045

RESTRICTED - POLICY AND COMMERCIAL 3

Progress on the Review

I Harriet Harman sought urgent review of the project in March because it was running 2 years late, causing loss of
projected savings of over £300m. ICL are in breach of the contract, having missed a key project milestone.

Lt Following a proposal from the Chief Secretary, a Working Group was set up with officials from HMT, DTI, DSS and
Cabinet Office to look at:

- whether the project is technically viable; and if so how quickly it can be completed and at what cost to
Government;

- the direct and indirect costs of cancellation and of any alternative means available to deliver the project’s
objectives.

@ = ~—= The Working Group set up an Expert Panel to provide a balanced and independent view of the technical viability of
the project and its costs.

- the Panel consists of Adrian Montague, head of the private finance taskforce (Chairman) with Alec Wylie and
Bill Robins. PA Consultants were appointed to work with the Panel.

7 The Panel is due to finalise its report on 22 June (subject to any extra work arising out of this meeting); a summary of
its findings is attached to this paper.

Lt The Working Group is due to report by end June.
RESTRICTED - POLICY AND COMMERCIAL

Benefit payment

27 million claimants - receive 28 different benefits;
958 million transactions - value £79 billion a year (1997-98 data);
methods of payment (GB only, excluding housing benefit):
% of transactions cost to BA (pence per transaction)

1 across post office counters;

on presentation of giro 7 78p
orderbook; 80 47p
2 via ACT to claimants bank accounts 13 1.35p

problems with current arrangements:

- fraud - arising from means of payment - estimated at £190m a year ;

HMT00000045
HMT00000045

- largely because orderbook payments are not currently reconciled, so no way of knowing who has received what;

- cost to BA of administering the system £525m a year; £420m of this is payment to POCL.
RESTRICTED - POLICY AND COMMERCIAL
Post office counters

L Offers by far the largest retail network in the country - 19,000 outlets (as at May 1998)

Urban Rural
Crown offices 601 0
Other main offices (run by agents such as franchisees) 938 0
Sub post offices (run by self employed sub postmasters)
Full time 8348 6964
Community/part time 4l 2087

L Income from benefit payment is around 40% of total POCL turnover (1997-98 data)

POCL Income £ million %
BA/SSA 420 36
Royal Mail 251 21
Bill payment services 180 15
DVLA 56 5
National Savings 49 4
Other (lottery, OGDs, etc) 209 19
Total 1165 100

7 Spending by benefit claimants in POs provides wider ‘footfall’ benefits:
- £130m spent on PO services
- £200-300m on non PO sales in PO premises

HMT00000045
HMT00000045

Lt Post Office currently handles £65-70 billion of cash per year, 4 of all cash transactions; making 40 000 van deliveries

of cash per week.
HMT00000045
HMT00000045

RESTRICTED - POLICY AND COMMERCIAL 6

The BA/POCL automation project

Basic idea:

give claimants magnetic stripe card;

install networked computer terminals at all 40 000 PO counters to automate procedures to assist with delivery of
products and administration;

link network to BA computer system (CAPS - Customer Accounting and Payment Strategy);

claimant goes to nominated PO; counter staff swipe card through terminal;

computer tells staff how much benefit to pay, and prompts staff to ask appropriate anti-fraud questions;
beneficiary collects all money due.

Benefits

to BA: largely eliminates means of payment fraud (around £190m a year);
provides audit information - but little reduction in admin costs;

to POCL: counter automation system which can improve supply of existing
services, and provide platform for new services, such as banking, insurance, bureau de
change;

ICL Pathway won contract in 1996 to supply and operate system under PFI. Contract worth £1 billion.

ICLPathway is subsidiary of ICL which is UK subsidiary of Fujitsu

ICL Pathway have committed £250m to date and a further £250m to complete build phase much of which is
subject to cancellation charges. Interest costs are additional.
HMT00000045

HMT00000045
RESTRICTED - POLICY AND COMMERCIAL 7

Timetable
@ The project is now seriously behind schedule Original timetable Best estimates from Panel

Pilot in 200 post offices Apr 1997 Oct 1997

Roll out of full system to start June 1997 Jan 20007

Roll out of full system complete Nov 1998 Sept 2001

End of BA’s commitment to project 2005 2005

@ Preliminary findings of the Expert Panel are that the project is technically viable though there may be a risk of up to 9
months further delay.

2
? Current plans are for Apr. ‘99 and Oct. ‘00. The Panel believes these are unlikely to be met.
HMT00000045
HMT00000045

RESTRICTED - POLICY AND COMMERCIAL 8

Consequences of cancellation
L serious blow to POCL

- loses counters automation; damages commercial prospects; could take 2-3 years longer to get a substitute
platform commissioned and installed;

- threatens major loss of income to POCL in medium term; in extreme case with 100% of benefits paid through
ACT, estimate 5000 to 13,000 post offices could close and annual subsidy of up to £280m would be needed
(this could be mitigated if POCL can develop banking services) with associated job losses of up to 43 000;

- could be liable for up to £245m in compensation to ICL ( on worst case scenario).

I serious blow to ICL

- has incurred over £500m in development costs so far; originally anticipated £125m profits. May seek to recover
all or part through courts;

- severe blow to commercial reputation; damaged ability to sell similar solutions abroad; some 270 jobs likely to
be lost at Pathway, many others at their contractors; could affect Fujitsu’s view of investment in UK.

I for Benefits Agency

- short term costs: continues to suffer deficiencies of current system; and may face costs for compensation to ICL
of up to £150m (DSS estimates) or £200-250m (Panel estimates).

- loss of considerable investment in the project: £200m invested to date, 32 000 staff trained, 1375 people
HMT00000045
HMT00000045

RESTRICTED - POLICY AND COMMERCIAL 9

working on the project.

L for Government generally
- blow to PFI;

- potentially a set back to implementation of electronic government if it was decided to use the project technology
to handle smartcards;

- potentially a set back to social banking;

- a second loss making business within the PO (POCL’s underlying position is already very weak), with possible
knock-on effects on the possibility of implementing options coming out of the Post Office review;

- political fall-out of any adverse impact on post office network.

Against all these disadvantages is to be set the long term opportunity to make administrative savings of up to £500m a year
from 100% switch over to ACT and realise longer term welfare reform objectives more quickly.
HMT00000045
HMT00000045

RESTRICTED - POLICY AND COMMERCIAL 10

Key criteria and questions

- the effect on the Post Office network. Could you envisage it shrinking significantly in the next 5 to 10
years?

- overall effect on public spending of each option - taking into account savings from DSS compared to a
possibly explicit subsidy for POCL to keep the network going and possible compensation to ICL from
project cancellation.

- the Government’s objectives for welfare reform and social exclusion.

- the acceptability of making benefit payments receivable only through a bank account.

- could you envisage a large switch to payment through bank accounts 2-3 years after the benefit payment
card was fully rolled out?

- should benefit payments be available over post office counters for the foreseeable future?
HMT00000045
HMT00000045

RESTRICTED - POLICY AND COMMERCIAL 11

Options for ways forward

Project continues; contract end date extended to allow ICL to earn return and POCL to prepare to offer banking and
financial services using the Horizon platform; BA prepares for rapid growth of ACT after end of contract;.

- likely to be acceptable to POCL and ICL.

- unacceptable to DSS and BA given longer term/wider objectives for welfare reform since uncertainty about
completion of roll out and extended commitment to benefit payment card;

- may expose BA (and possibly POCL) to risk of legal challenge from other suppliers and EC Commission for
breach of EC procurement rules.

Project continues in modified form; benefit payment card element of project cancelled; BA develops ACT at rate

compatible with POCL’s introduction of banking services; ICL continue to develop Horizon system as automation

platform for POCL with bolt on banking services provision.

- likely to be unacceptable to ICL unless large compensation was paid;

- possibly acceptable to POCL if they believed alternative applications of Horizon platform including banking
services could provide adequate return to compensate for loss of BA business. Full ACT by 2005 likely to

threaten stability of post office network.

- acceptable to BA provided post offices can offer basic banking services to benefit recipients in time for full
switch to ACT.

Project cancelled; BA strengthens existing anti fraud measures; encourages voluntary take up of ACT or moves to full
HMT00000045
HMT00000045

RESTRICTED - POLICY AND COMMERCIAL 12

ACT including negotiations with banks to provide accounts for the unbanked; POCL seeks to develop banking
services with partner and appropriate technology platform in time to provide banking service to benefit claimants in
parallel to switch to ACT.

- eases blow for POCL if voluntary ACT route is chosen because loss of BA business would be more gradual;
would be serious doubts whether POCL could afford fully automated platform if rapid loss of income from BA
under full ACT route. In the medium term raises doubts over viability of current network if returns from
banking activities are not as large as estimated;

- BA would not achieve full potential savings available through ACT under voluntary route; would mean
continuing with paper-based systems for some time;

- quick switch to full ACT delivers large DSS admin savings over a shorter timescale but poses serious risk to
stability of post office network;

- unacceptable to ICL, who would seek large compensation payments.