POL00002314 - Description of Fujitsu’s system of IT infrastructure services supporting Post Office Limited’s POLSAP, HNG-X applications throughout the period 1 April 2013 to 31 December 2013

Evidence on official site

POL00002314
POL00002314

oO
FUJITSU E>

Description of Fujitsu’s System
of IT Infrastructure Services
supporting Post Office Limited’s
POLSAP and HNG-X

applications

Throughout the Period 1 April 2013
to 31 December 2013

With the independent service auditor's assurance report including tests performed and
results thereof

FI1176.1/1
POL00002314
POL00002314

Fe)
FUJITSU

Table of Contents
1. MANAGEMENT ASSERTION.....
2. REPORT OF INDEPENDENT SERVICE AUDITOR...

3. DESCRIPTION OF FUJITSU’S SYSTEM OF IT INFRASTRUCTURE SERVICES SUPPORTING
POST OFFICE LIMITED’S POLSAP AND HNG-X APPLICATIONS THROUGHOUT THE PERIOD I
1 APRIL 2013 TO 31 DECEMBER 2013 10
Overview of Fujitsu

4 History of Fujitsu ..

2 Major Markets and pi

“3 Organisational Structure, including Business Units

4 ___Geographical Spread

4. OVERALL CONTROL COMPONENTS
4.41 Control Environment...

4.2 Integrity and Ethical Values
4.3 Structure for Serving Post Office Ltd.
4.3.1 Service Lines and Functions

4.4 Control Activities .
4.4.1 Governance and Oversight of Control Activitie:
4.4.2 Human Resources ...
4.5 Information and Communication .
4.6 Monitoring.
4.7 Risk Assessment ..
4.7.1___ Risk Policy and Implementation ...
4.7.2 Fujitsu's Risk Process .
4.8 Services provided
4.8.1 Physical and Environmental Controls...
4.8.2 Backup eee

4.8.3 Job ‘Scheduling -

4.8.4 Availability and Capacity Management . veonssnnnee
4.8.5 Incident Management... sons

4.8.6 Major Incident Process.

4.8.7 __ Security Incident Process........
4.8.8 Network Incident Management
4.8.9 Networks .......... a .
4.8.10 Change Management
4.8.11 Security...

rn)

4.8.12 Access to progi

4.8.13 External threats and access violation management ..........:....:.ss

28.13 _External threats seein nina

5. NOT USED...

6. COMPLEMENTARY USER ENTITY CONTROLS ..

7.___ DESCRIPTION OF CONTROL OBJECTIVES, CONTROLS, TESTS AND RESULTS OF TESTS

67]

7A Testing Performed and Results of Tests of Entity-Level Control...

7.2 Control Objectives, Control Activities, Testing Procedures and Results of Testing

7.2.1__ Control Objective 4

7.2.2 ___ Control Objective 2.

7.2.3 Control Objective 3.......

7.24 Control Objective 4.

7.2.5 Control Objective 5...

7.26 Control Objective 6.

7.2.7 Control Objective 7.

7.2.8 Control Objective 8.

7.2.9 Control Objective 9.

7.2.10 Control Objective 1

7.2.11 Conttol Objective Ma...

pod Gatal Giese : sososaaeassnesesenaennanonnsseeeeestanns : 88

7.2.13 Control Objective 13...

Table of Contents i

F/1176.1/2
POL00002314
POL00002314

1. Management Assertion

F/1176.1/3
POL00002314
POL00002314

(SAE 2402 Master Document .
FUPITSU Commercial in Confidence &

1. Management Assertion

Fujitea Services Limited's Management Assertion

12” Bepruary 2014

Fujiine Services Limited (Fujtsu” We". ‘we’, ‘Qompeny") has prepared the acecmpanying

Description
of Fugiten's aystem of iT <afrasteucturs services supporting Post Office Limited's POLSAP and HNGOXC
applications throughout the period 1 Apr? 2013 i 2t December 2019 ¢ Descriptan’)

‘This has been prepared for
1. Post Otfice Limited ( POL") ae users of the aystem during some or all of the period { Apri 2043 te
31 Decaniber 2073; and
2. the independent auditors of POL.
POL and se independent auditors are assumed to have @ sufficient understanding to consider it

Description, along with other information, including inferrnation about contre’s anpiementec! by POL itself,
what assessing the rks of material misstatements of POL's financie! statements.

‘The Company confirms, to the best of its knowledge and pellet, thet.

a. The Description fairly prewents the 17 support processes and controls used by und on behalf of
Fujitaa to support the POLSAP and HNG-X applications (System) made available to POL during
She period 1 April 2013 te 31 December 2013 for provicing {7 suppor to the HNG-X and POL
SAP applications, The ctitena we used in making thie aesertion went that Ihe Desoription:

<1} Presents how the System made avaliable to POL was designed and implemented, including

* the types of sarvices provided,
* the procedures, within both automated and manual systems, by which those services are
provided,

« the retaied supporting ofoemetor, this includes the porrection of incorrect information
and how information is transferred to the caports peapered for POL,

* how the System captures anc addresses signifionnt events and conditions,

» the process used to prepane reperts or other information provitied to POL as the user of
the Systern,

* specified control objectives and controls designed to achieve those objectives:

* controls fat, i designing the System, the Company contemplated woud de
ienplementad by POL in order to achieve the specified conte! objectives (Complementary
‘User Entity Controls}, and

* other aspects of the Company's contro! environment, tak assessment process.
information aad communication systems (inckaling the related busmess processes,
conbol ecliviies and mocitoring controle thal are relevant fo the services provided

FI1176.1/4
POL00002314
POL00002314

ISAE 3402 Mester Document '
FULTSU Commercial in Confidence &

{2} does not omit or distort istormation reievant to the scope of the System

b The Description includes resevant details of changes fo the System during the period from 1 Apsit
2013 fo 31 December 2013.

@ ‘The controls related @ the contrel objectives stated in the Description which together with the
complementary uter entity controls refered to above, were eullably Cesigned and operated
stfectively Uroughout the period 1 Apel 2019 te 31 December 2012 t achieve those contro!
objectives stated in the Description The criteria we used in maieng this aesertion were that

(#) the risks tat threaten the achiewament of the contro! objectives stated in the Description
have bows identified by Fujitsy,

{2} the controls identified in the Description wad, # operating a8 descrbed, provide reasonable
assurance that those risks would not orevent the contro! objectives stated in Ihe tet
frorn being achieved. and

{3) the controls wene consistently applied an designed, inefuding whether manual comrale ware
applied dy incividuals who have the appropriate competence and authority,

‘Ghent Managing Director

F/1176.1/5
POL00002314
POL00002314

2. Report of Independent Service Auditor

F/1176.1/6
POL00002314
POL00002314

EY

Building a better

SEL 2AF

working warld at

INVESTOR PY PHOPLE

Fujitsu Services Limited
Lovelace Road
Bracknell

RG12 8SN

Scope

We have been engaged to report on Fujitsu Services Limited (“Fujitsu")'s accompanying Description of
Fujitsu's system of IT infrastructure services supporting Post Office Limited’s POLSAP and HNG-X
applications throughout the period 1 April 2013 to 31 December 2013 (Description) and the suitability
of the design and operating effectiveness of controls to achieve the related control objectives stated in
the Description. The Description indicates that certain control objectives specified in the Description
can be achieved only if complementary user entity controls contemplated in the design of POL's
controls are suitably designed and operating effectively, along with related controls at the service
organisation. We have not evaluated the suitability of the design or operating effectiveness of such
complementary user entity controls.

Fujitsu uses a range of network providers to provide Wide Area Network (WAN) services to POL. The
Description includes only the controls and related control objectives of Fujitsu and excludes the control
objectives, and related controls of these network providers. Our examination did not extend to
controls of network providers.

Fujitsu's responsibilities

Fujitsu has provided the accompanying assertion titled, Management Assertion (Assertion) about the
fairness of the presentation of the Description and suitability of the design and operating effectiveness
of the controls to achieve the related control objectives stated in the Description. Fujitsu is responsible
for preparing the Description and the Assertion, including the completeness, accuracy and method of
presentation of the Description and the Assertion and stating the control objectives in the Description.
Fujitsu is also responsible for providing the services covered by the Description, specifying the control
objectives, identifying the risks that threaten the achievement of the control objectives, selecting the
criteria stated in the Assertion and designing, implementing and documenting controls to achieve the
related control objectives stated in the Description.

Service Auditor's responsibilities

Our responsibility is to express an opinion on the fairness of the presentation of the Description and on
the suitability of the design and operating effectiveness of the controls to achieve the related control
objectives stated in the Description, based on our examination. We conducted our engagement in
accordance with International Standard on Assurance Engagements 3402 Assurance Reports on
Controls at a Service Organization, issued by the International Auditing and Assurance Standards
Board. That standard requires that we comply with ethical requirements and plan and perform our
procedures to obtain reasonable assurance about whether, in all material respects, the description is
fairly presented and the controls were suitably designed and operating effectively to achieve the
related control objectives stated in the Description throughout the period 1 April 2013 to 31 December
2013.

F/1176.1/7
POL00002314
POL00002314

An assurance engagement to report on a description of a service organisation's system, and the
suitability of the design and operating effectiveness of the service organisation's controls to achieve
the related control objectives stated in the description, involves performing procedures to obtain
evidence about the fairness of the presentation of the description and the suitability of the design and
operating effectiveness of those controls to achieve the related control objectives stated in the
description. Our procedures included assessing the risks that the Description is not fairly presented
and that the controls were not suitably designed or operating effectively to achieve the related control
objectives stated in the Description. Our procedures also included testing the operating effectiveness
of those controls that we consider necessary to provide reasonable assurance that the related control
objectives stated in the Description were achieved. A reasonable assurance engagement of this type
also includes evaluating the overall presentation of the Description, the suitability of the control
objectives stated therein and the suitability of the criteria specified by the service organisation and
described in the Assertion. We believe that the evidence we obtained is sufficient and appropriate to
provide a basis for our opinion.

Inherent limitations

The Description is prepared to meet the needs of POL and its auditors and may not, therefore, include
every aspect of the system that POL may consider important in its own particular environment.
Because of their nature, controls at a service organisation may not prevent or detect and correct all
errors or omissions in processing or reporting transactions. Also, the projection to the future of any
evaluation of the fairness of the presentation of the Description or conclusions about the suitability of
the design or operating effectiveness of the controls to achieve the related control objectives, is
subject to the risk that controls at a service organisation may become inadequate or fail.

Opinion
Our opinion has been formed on the basis of the matters outlined in this report. The criteria we used in
forming our opinion are those described in the Assertion. In our opinion, in all material respects:

a. the Description fairly presents the IT support processes and controls used by and on behalf of
Fujitsu to support the POLSAP and HNG-X applications that were designed and implemented
throughout the period 1 April 2013 to 31 December 2013.

b. the controls related to the control objectives stated in the Description were suitably designed
throughout the period 1 April 2013 to 31 December 2013 if POL applied the complementary
user entity controls contemplated in the design of Fujitsu's controls and subservice
organisations.

c. the controls tested, which, together with the complementary user entity controls referred to in
the scope paragraph of this report if operating effectively, were those necessary to provide
reasonable assurance that the control objectives stated in the Description were achieved and
operated effectively throughout the period 1 April 2013 to 31 December 2013.

Description of tests of controls

The specific controls tested and the nature, timing, and results of those tests are listed in the
accompanying Description of Control! Objectives, Controls, Tests and Results of Tests (Description of
Tests and Results).

F/1176.1/8
POL00002314
POL00002314

EY

Building a better
working workd

Intended use

This report, including the description of tests of controls and results thereof in the Description of Tests
and Results, is intended solely for the information and use of Fujitsu, POL as the user of the IT support
processes and controls used by and on behalf of Fujitsu to support the POLSAP and HNG-X applications
during some or all of the period 1 April 2013 to 31 December 2013 and the independent auditors of
POL, who have a sufficient understanding to consider it, along with other information including
information about controls implemented by user entities themselves, when assessing the risks of
material misstatements of user entities’ financial statements. This report is not intended to be and
should not be used by anyone other than these specified parties.

Ererk » Yosma Lue

12 February 2014
London
United Kingdom

F/1176.1/9
POL00002314
POL00002314

Fe)
FUJITSU

3. Description of Fujitsu's system of IT
infrastructure services supporting Post Office
Limited’s POLSAP and HNG-X applications
throughout the period 1 April 2013 to 31
December 2013

3.1 Overview of Fujitsu

3.1.1. History of Fujitsu

Fujitsu has evolved through a process of acquisition and organic development to create a broad-based
technology and services organisation, with a strong record of innovation and lean service delivery.
Fujitsu has a long and successful history which has links going back more than 40 years.

Figure 1. Fujitsu’s Growth in Services through Acquisition or Organic Development

The recent history of the company in Europe began in 1968 as International Computers Limited (ICL),
formed through the merger of English Electric Computers (EEC) and International Computers and
Tabulators (ICT), in response to the increasing market dominance of the large American corporations.
The company was listed on the stock market until it was acquired by Standard Telephones and Cables
(STC pic) in 1984.

Description of Fujitsu's System 10

F/1176.1/10
POL00002314
POL00002314

Fe)
FUJITSU

In 1990, the Japanese IT Services Company, Fujitsu Ltd, acquired an initial 80% stake for £740million.
Further acquisitions were made by Fujitsu in 1993 and 1996 from STC, (then owned by Nortel), with the
remaining interest in the company being acquired in 1998.

In April 2002, ICL fully re-branded to Fujitsu Services Limited (FSL), and later as Fujitsu, as it looked to
exploit the Fujitsu Group's expertise and technology, including its extensive R&D spend. FSL (Fujitsu)
now operates as the UK and Ireland IT Services-based arm of the global Fujitsu Group.

In 2009, we integrated Fujitsu Siemens Computers (FSC) into the organisation, representing an exciting
step in Fujitsu's strategy for growth, and forming the new Technology Solutions Division (TSD). This new
division has a portfolio that encompasses Infrastructure Products and Solutions, Managed Services and
Infrastructure as a Service.

Following the creation of the new Technology Solutions Division, Fujitsu announced the formation of the
Global Business Group which involved an operating model based on the creation of 8 regions and a
number of global support functions.

The UK and Ireland (UK&l) region was formed, merging the expertise previously delivered by Fujitsu
Services and the product know-how from Fujitsu Siemens. Operating under the name of Fujitsu (UK and
Ireland) the company provides integrated technology offerings and business solutions.

3.1.2 Major Markets and Human Capital

Fujitsu UK and Ireland is a leading IT systems, services and products company employing 11,400 people
with an annual revenue of £1.8 billion. Its business is in enabling its customers to realise their objectives
by exploiting information technology through its integrated product and service portfolio. This includes
consulting, applications, systems integration, managed services and product for customers in the private
and public sectors including retail, financial services, telecoms, and government, defence and consumer
sectors.

3.1.3. Organisational Structure, including Business Units

Description of Fujitsu's System 11

F/1176.1/11
POL00002314
POL00002314

Fe)
FUJITSU

shared services.
teams

Figure 2. Fujitsu UK and I Organisation

3.1.4 Geographical Spread
Fujitsu operates in the following Regions:

«Africa.

* Central America and Caribbean.

« North America.

e South America.

© Asia.

«Australasia.

e Europe.

« Middle East.

Description of Fujitsu's System 12

FI1176.1/12
POL00002314
POL00002314

Fe)
FUJITSU

4. Overall Control Components

This section provides information about the five interrelated components of internal control at Fujitsu:

e Control Environment — sets the tone of an organisation, influencing the control consciousness
of its people. It is the foundation for all other components of internal control, providing discipline
and structure.

e Control Activities — are the policies and procedures that help make sure that management's
directives are carried out.

e Information and Communication — are systems, both automated and manual, that support the
identification, capture and exchange of information in a form and time frame that enable people
to carry out their responsibilities.

e Monitoring — is a process that assesses the quality of internal control performance over time.

e Risk Assessment — is the entity's identification and analysis of relevant risks to the
achievement of its objectives, forming a basis for determining how the risks can be managed.

Fujitsu's internal control components include controls that may have a pervasive effect on the
organisation, an effect on specific processes, account balances, disclosures, classes of transactions or
applications, or both. Some of the components of internal control include controls that have more of an
effect at the entity level, while other components include controls that are primarily related to specific
processes or applications. When assessing internal control, we consider the interrelationships among the
five components.

4.1 Control Environment

Management has established and maintains an internal control structure that monitors compliance with
established standards, policies, and procedures. The remainder of this section discusses the tone at the
top as set by Leadership and Management, the integrity, ethical values and competence of Fujitsu
employees, the standards, policies and procedures, the risk management process and monitoring and
the roles of significant control groups. The internal control structure is established and refreshed based
on Fujitsu's assessment of risk facing the organisation.

4.2 Integrity and Ethical Values

Fujitsu recognizes its responsibility to foster a strong ethical environment to determine that its business
affairs are conducted with integrity, and in accordance with high standards of personal and corporate
conduct. This responsibility is characterized and reflected in the Fujitsu Way Code of Conduct, which is
communicated to all employees of the organisation. All employees are required to maintain ongoing
compliance. Compliance checks are undertaken to help ensure that employees understand and comply
with the Fujitsu Way Code of Conduct.

Description of Fujitsu's System 13

F/1176.1/13
POL00002314
POL00002314

Fe)
FUJITSU

4.3 Structure for Serving Post Office Ltd.

4.3.1. Service Lines and Functions

The Service Lines and Functions that provide services, or support the delivery of service to PO Limited
(POL) are as follows:

e Business and Applications Services (BAS) (Direct to POL).
e End User Services Group.

e Hosting and Network Services Group.

e Technology Product Group.

« Business Operations & Business Excellence.

e Commercial and Legal Assurance.

« Finance and Strategy.

e Human Resources.

« Sales and Marketing.

The purpose of these Service Lines and Functions is to enable, organise and facilitate the requirements
placed on the Fujitsu Post Office Account (POA) by POL.

The management of the above Service Lines and Functions establish their own frameworks within their
areas for the continuous formal support of POA and enforce this through their own policies, procedures
and standards, and registers, including where applicable internal and external audits. The procedures to
support POA are set out in each area's own implementation of the Fujitsu Business Management System
(BMS). The controls in place in each of these Services Lines and Functions help ensure that the areas
have overall objectives, terms of reference, job descriptions and senior management roles. Each of these
functions has its own levels of management, staff, directors and stakeholders all of which impact the
service that POA is able to provide to POL. Each of these Service Lines and Functions is also
responsible for ensuring that their staff are appropriately trained and follow Fujitsu Corporate processes
to achieve this.

Each of the Service Lines and Functions is also controlled through its own service descriptions,
organisational controls, vision, mission and value statements, governance and control frameworks,
monitoring and review controls and performance measures.

4.4 Control Activities

4.4.1. Governance and Oversight of Control Activities

Fujitsu has established the Corporate Governance Committee (CGC) and Audit Committee responsible
to the Fujitsu UK and Ireland Board to oversee the companies’ approach to governance and control.

The directors are committed to maintaining a strong contro! environment throughout the organisation and
recognise that the control environment provides the foundation for all other components of internal control
providing discipline and structure.

The Board of Directors (the Board) is responsible for monitoring the performance of the Company on
behalf of its shareholders and ensuring that Fujitsu satisfies all regulatory and statutory requirements
related to its operations.

Description of Fujitsu's System 14

F/1176.1/14
POL00002314
POL00002314

Fe)
FUJITSU

Authority for all action and expenditure within Fujitsu Service flows from the Board and the Board has
established that the necessary control systems are in place to ensure that business is undertaken in a
responsible manner. Fujitsu's policies, operations and strategy are controlled by the Board.

The Board meets as required and its two key sub-committees the CGC and the Audit Committee meet
quarterly.

In addition Fujitsu has a systematic approach to policy and process with a set of Master Policies
approved by the CGC and sub-policies and processes determined by the relevant regional functions
underneath. The framework, known as the Business Management System (BMS) is managed by Fujitsu's
Business Assurance teams and comprises of a set of mandatory Master Policies and Business
Processes. The key Master Policies cover Ethics, Security, Human Resources, Corporate Responsibility,
Finance, Legal, Service Delivery, Quality, Project Management, Risk Management and Business
Continuity under each of which is a set of specific business processes owned by Senior Management.

Within POA each Service Line and Function follows the BMS. Where exceptions to the BMS are
necessary, local standards, procedures and work instructions are documented with a ‘Let’ from the
Corporate Process Owner where the Corporate Process Owner authorises that local departure from the
BMS.

4.4.2 I Human Resources

4.4.2.1 Policies and Practices

Human resource policies and practices relate to hiring, orienting, training, evaluating, counselling,
promoting and compensating personnel. The competence and integrity of Fujitsu’s personnel are
essential elements of its control environment.

4.4.2.2 Performance Management

Performance Management is a process for managing and improving performance of teams and
individuals through proactive management of objectives / deliverables which are clearly linked to the Mid
Term Plan. It includes the identification of development needs and ongoing evaluation of achievement
and capability by the reviewer and the individual involved. Fujitsu UK & Ireland is committed to providing
the organisation and our employees with a common performance management process that is
consistently applied across the organisation and is aligned with organisational goals.

This process also defines how individual employees express their short and long term desires for career
development. The process involves the individual in planning career goals by identifying the specific
steps to develop skills to fulfil and manage career transitions.

The Fujitsu UK & Ireland's Performance process applies to all employees within Fujitsu UK & Ireland and
embodies the principle that strong business performance is most likely when employees feel they are
operating at the peak of their potential in roles that match the company's objectives.

Fujitsu's Human Resource policies are held and maintained on its CafeVik web portal and managed by
Fujitsu's HR teams. These policies operate employment policies to provide a framework for the
employment of people and provide employees with a clear and concise set of rules in which to operate.

Its policies apply to Fujitsu UK & Ireland. This means all employees, contractors and businesses carried
out by Fujitsu Services Limited and its subsidiaries and any other company or organisation that is
managed by the Chief Executive Officer, Fujitsu United Kingdom and Ireland.

Description of Fujitsu's System 15

F/1176.1/15
POL00002314
POL00002314

Fe)
FUJITSU

4.5 Information and Communication
Fujitsu UK and Ireland Service Lines and Functions have CaféVik portals to enable sharing of knowledge
across the company, and throughout their own business areas.

These portals provide information about each of the Service Lines and Functions and what products and
services they offer to the company.

Fujitsu has a robust and reliable communication framework that utilises push and pull strategies to help
ensure that all employees have the information they need to perform their roles effectively, efficiently and
ethically. Some of the mechanisms used to communicate directly with Fujitsu employees include:

« Road Shows.

«Staff Briefings.

e Team Meetings.

e Leadership and Management Cascades.

In April 2013 invitations were sent to all employees in the Group to participate in a Global wide employee
engagement survey.

Fujitsu also seeks the views of employees via representative groups in different parts of the Company.
During this year (2013) in the UK it has set up Fujitsu Voice with over 39% of employees voting in an
election for its 23 members. Fujitsu management consults regularly with these bodies, providing updates
and seeking views on important issues. In addition Fujitsu has agreements with Trade Unions that
include regular meetings with local and senior management to discuss issues affecting employees in the
unions’ area of interest.

4.6 Monitoring

Fujitsu utilises a variety of systems, processes and tools to help ensure that operations are efficient, effective
and ethical, including:

¢ Performance Dashboards.

e Standard Reporting Packs.

« Audits and Health Checks.

« Reviews and Lessons Learned.

* Customer Satisfaction Scores.
Audits by Fujitsu Business Assurance Teams, Fujitsu External ISO Accreditors (the account is itself
accredited to ISO 27001) and POL or its agents (including PCl DSS and Link Auditors) are used to
support the design, implementation and post implementation review of the controls in place and to help

ensure that the relevant governance, strategy and needs and requirements of both POL and Fujitsu are
met.

Data and information from these sources are used to identify weaknesses, inefficiencies or potential
performance issues. Performance issues are remediated and opportunities for improvement are identified,
evaluated, prioritised and managed through to appropriate implementation.

The BMS Team interacts periodically with both the internal and external auditors.

Description of Fujitsu's System 16

F/1176.1/16
POL00002314
POL00002314

Fe)
FUJITSU

4.7 Risk Assessment

4.7.1 Risk Policy and Implementation

All operating companies within Fujitsu's Global Business Group (GBG) are required to have a Risk
Management Framework. Each group is also required to have a designated Chief Risk Management
Officer (CRMO) whose responsibilities include bi-annual risk reporting and prompt escalation of
significant risks to GBG in addition to managing the risk process for the Board. Fujitsu's Risk
Management Framework centres on the Risk Management Policy which is a key management policy
overseen by the Corporate Governance Committee (CGC) of the Board chaired by the Executive
Chairman. Responsibility for implementation of the Risk Management Policy is delegated throughout the
business cycle. Fujitsu provides support and guidance to employees through the Customer Solution
Lifecycle, a repository of best practice and training. Management oversight at critical points in the
business cycle is provided through the Review Framework, a structured set of formal management
reviews. Fujitsu's management of risk is exhibited throughout these structures such that potential
problems can be planned for and managed appropriately.

4.7.2 Fujitsu’s Risk Process

The Fujitsu Risk Process is used to support the evaluation reporting and management of risks within the
business and is consistent with recognised Risk Management standards.

Fujitsu's Enterprise Risk Management System (ERM) provides clear and effective monthly risk reporting
to the regional leadership teams and forms the basis of the GBG. This helps to ensure a high level of risk
management is maintained throughout the organisation.

4.8 Services provided

4.8.1. Physical and Environmental Controls

1. Control Objective 1: Controls provide reasonable assurance that access to the data centre
and facilities with computer equipment, storage media and program documentation is
restricted to properly authorised individuals.

# Control

14 Data centre access: Data centre specific physical access security policies and procedures to
control access to the data centre and other sensitive areas, including computer equipment and
storage media, are implemented. These are made available to Fujitsu staff via the intranet.

1.2 Access within the data centre: Access beyond the security desk is protected by a key-card
system that restricts individual access to specific data processing areas. Security management
has determined appropriate levels of physical access to the data centre, which is based on the
roles and responsibilities of staff. Staff requiring access to the data centre must complete an
access form, which must be signed as approved by the line manager responsible for the zones
requested.

1.3 CCTV: The data centre(s) is controlled and monitored through the use of CCTV video cameras.
Video cameras are placed at strategic locations around the perimeter of the building to help
ensure that coverage of the data centre is obtained.

1.4 Security guards: Security guards are present at the data centre 24 hours per day, seven days
per week. The data centre can only be accessed through a central area.

15 Data centre visitors: Visitors are required to sign in at the reception areas and temporary
badges are issued. Visitors must have been pre notified to data centre security by a Fujitsu
employee.

Description of Fujitsu’s System 17

F/1176.1/17
POL00002314

POL00002314
FUJITSU
# Control
1.6 Failed access monitoring: Attempts to enter restricted areas without using authentication

devices are denied and a security alert is triggered and logged. Data centre management
proactively follows up on security alerts that are triggered.

17 Review of user access within the data centre: Periodic reviews are performed of users who
have access to the data centre to help ensure that their access rights are appropriate.

1.8 Deletion of user access: The managers of the various delivery teams are responsible for
notifying the local site facilities team of terminations or transfers of their direct reports. Upon
notification of employment changes, access through the security access control system is
revoked.

2. Control Objective 2: Controls provide reasonable assurance that computer equipment and
facilities are protected from damage by fire, flood and other environmental hazards and
maintenance agreements are in place.

Control

241 Fire Suppression: Fire detection and suppression devices, such as hand-held fire
extinguishers, are strategically placed throughout the entire data centre.

22 Maintenance Schedule: Periodic inspection and maintenance is performed on protection
devices, sensors and alarm systems.

23 Environmental monitoring: Smoke detectors and water, humidity and temperature monitoring
devices are installed to detect abnormal environmental conditions.

24 UPS Supply: A UPS system is installed to protect the facilities and computer equipment from
electrical power fluctuations and outages.

The Trident House campus comprises of a two storey office block (Phase I) with an adjoining computer
room and data / output handling area. There is also a separate single storey building (Phase II)
containing offices and another computer room. There is one main entrance to the Trident House Phase I
building and a loading bay and one main entrance to the Trident House Phase II building.

The IRE11 data centre component of the Trident House campus is composed of raised floor computer
rooms, office space and facility support (Un-interruptible Power Supply [UPS], backup generators and
power distribution equipment). The IRE11 data centre is staffed with its own security guards, who are on
duty 24 hours a day, seven days a week (1.4). Physical access to the data centre can only be obtained
through the security officer's desk at the main entrance to the campus. The Trident House campus is
also equipped with Closed Circuit Television (CCTV) cameras, monitored by the campus security guards
(for all areas) and the Data Centre Operations team for all secure Data Centre computer rooms. These
cameras are located along the IRE11 campus perimeter, entry / exit locations, main entrances and
numerous additional strategic locations within the secure computer rooms to help ensure complete
coverage of the data centre (1.3).

The IRE11 data centre has developed and implemented data centre specific physical access security
policies and procedures to control access to the data centre and other sensitive areas, including
computer equipment and storage media (1.1).

The POL computing hardware and storage media are located in secure areas of the data centre facility
with access restricted to appropriate personnel through the use of an electronic cards access system
(SAFE), the computer room employs keypad / PIN code technology as an additional level of access
control (1.2). Personnel are required to individually swipe in and where applicable, swipe out of an area.

iggy backing" off someone else swiping in is prohibited. Attempts to enter restricted areas without

Description of Fujitsu's System 18

F/1176.1/18
POL00002314
POL00002314

Fe)
FUJITSU

using authentication devices are denied and a security alert is triggered and logged. Data centre
management proactively follows up on security alerts that are triggered (1.6 and 1.7).

Access to the data centre is secured based on electronic card access systems (1.2).
This system controls entry to personnel who need it, while maintaining the security of the building.

When an employee leaves the company, the card is removed from the system database and would no
longer provide access to the cardholder. Therefore if cards are not retrieved, the security of a facility can
be maintained. Unique cards are issued for each employee, for individual control, accountability and
tracking of activity. Flexible control is accomplished by allowing each person access to different areas
and only at certain times.

An audit trail is provided for management tracking and reporting of who entered and / or left a particular
area at a particular time. Tracking of all access attempts is provided to allow management to determine if
employees are attempting to enter areas they are not permitted into, or whether employees are
attempting to get into areas at the times when they are not allowed access to those areas (1.6).

4.8.1.1 Visitor Access

Visitors (and initially new joiners who have not yet been issued their photo access card) are issued with a
visitor's access card (1.5). Visits to the IRE11 campus, and the issue of visitor access cards, must be
recorded in the local site visitors' log. The details must include: Date and time of entry, Name, Company
(where applicable), Person visiting, Unique number of the visitor access card and Time of exit.

Visitors should normally be escorted around Fujitsu sites, but they can be issued with an ‘unescorted’
access card, depending on the provisions in the Local Site Building Security Procedures.

The ‘escorted’ and ‘unescorted' badges (and lanyards) clearly distinguish visually which is which.

All access to the computer rooms is strictly controlled. To access the computer rooms an individual must
first complete a request in the data centre on-line access request system to obtain approval; if a valid
reason has not been provided for multiple accesses, the access will only allow the individual to access
the data centre once. No access is granted unless a valid reason has been provided and the on-line
access ticket has been authorized (1.5).

All visitor access cards (common areas) are handed into the issuer (normally reception or site security) at
the end of each day. All visitor access cards (computer rooms) must be handed into the issuer (IRE11
Operations team) at the end of each day.

Persons issuing visitor access cards (reception / site security / DC Operations team) must check the
records to help ensure that all visitor access cards are recovered at the end of each day. If cards are
outstanding at the end of the day they must be electronically disabled and enquiries made to the person
issued with the access card, or the person they were visiting, as to the return of the access card.

4.8.1.2 Monitoring of Individuals with Access to the Data Centre

Listings are maintained showing individuals with IRE11 data centre access. The IRE11 Data Centre
management and Fujitsu Group Security personnel periodically review reports that list user access levels
to restricted areas of the data centre to determine whether user access rights are appropriate (1.7). The
managers of the various delivery teams are responsible for notifying the local site facilities team of
terminations or transfers of their direct reports. Upon notification of employment changes, access through
the security access control system is revoked and the card key and other physical access devices are
collected (1.8).

Description of Fujitsu's System 19

F/1176.1/19
POL00002314
POL00002314

Fe)
FUJITSU

4.8.1.3. Environmental systems

The IRE11 data centre is equipped with environmental systems to safeguard POL's hardware and
information assets located within the facilities. The computer room is equipped with leak detection
systems, smoke detectors, fire suppression systems, hand held fire extinguishers and temperature
monitoring systems (2.1, 2.3). Condensing units, pumps, and chillers provide cooling for the data centre.
This equipment supports multiple computer room air conditioning units distributed throughout the raised
floors. The POL client's servers and hardware equipment are mounted in locked racks or free standing
cabinets on the raised floors.

Each computer room is supplied by separate commercial power feeds, each from a single power
generation substation. Separate diesel generators support each computer room and provide backup
power in the event that commercial power is temporarily unavailable. These generators are supplied by
additional fuel tanks that provide an operating window at full load. The power distribution equipment
consists of two uninterruptible power supply (UPS) systems providing conditioned power to a UPS Static
Switch. The UPS Static Switch provides power as the primary and alternate source of power to the
associated Static Switch Power Distribution Units (PDU). The PDUs have dual feeds designed to provide
a seamless transfer in the event of a power loss (2.4).

The IRE11 data centre is monitored by a Building Management System (BMS) located in the Site
facilities office (monitored by 3° party GS Hall engineers) in the Phase I buildings within the data centre
location, with repeater heads located in the Security office and the data centre Operations Bridge. The
BMS automatically alerts all three stations if abnormal environmental conditions occur.

The GS Hall engineers, Security and Operations teams monitor the system 24 hours a day, seven days a
week to provide rapid evaluation and response to facility problems (2.3). Scheduled inspection and
maintenance are performed on environmental protection devices, sensors, and alarm systems (2.2).
Checks are performed at varying intervals dependent on the devices being maintained; however, devices
are checked at least annually.

4.8.2 Backup

3. Control Objective 3: Controls provide reasonable assurance that programs, files and datasets
that have been identified as requiring periodic backup are backed up and retained.

# Control

3.41 Backup Definition: The Backup High Level Design documents define Backup and recovery
requirements and policy for the platform.

3.2 Backup Toolset: Backups are performed using Netbackup or RMAN (automated tools).

3.3 Backups are written to a secondary location: Backups performed are written to a separate

disk array and are simultaneously written to a disk array at the disaster recovery site.

3.4 Failed backups are tracked and monitored: Failed backups are signalled to the Master Batch
Scheduling system which raises events in a generic manner to the SMC.

The Solution Owner is responsible for ensuring that in the event of accidental deletion or corruption of
data that the data can be recovered. The Platform Physical Design document will define whether a
NetBackup client is required and the Application High Level Design will define the backup and recovery
policy and method (3.1). The Solution Owner is also responsible for defining the archive and deletion
policy and data that needs to be retained for audit purposes.

At the discretion of the Solution Owner, backups may be performed using Oracle RMAN or the
NetBackup based Backup System according to patterns defined in the Backup & Recovery High Level
Design (3.2).

Description of Fujitsu's System 20

F/1176.1/20
POL00002314
POL00002314

Fe)
FUJITSU

In the case of Oracle RMAN backups the backup data is written to disk in a separate disk array.
Simultaneously it is also written to a disk array at the disaster recovery site (3.3). Those systems which
have been identified as requiring backups via the NetBackup solution will have their backups scheduled
via the TWS scheduler, this provides automatic monitoring of the status of the backups, and will have
backups written to each data centre to provide resilience in the event of a requirement to perform
Disaster Recovery.

Depending on the size of the dataset to be backed up either a direct client backup via the network may
be performed or a split mirror backup using standard features (clones and snapshots) of the storage
arrays which are presented to the backup media server. Data is written to a virtual tape library at both the
primary and the disaster recovery sites. No tapes are exported from the system unless specifically
requested and authorised.

Note that in some circumstances, the recovery may by design be affected by replaying the data from an
upstream system rather than by performing a traditional "backup recovery" as many systems need to
keep a consistent view of each other and going backwards in time is not always appropriate.

The Backup Development team delivers appropriate NetBackup policies according to these definitions.
The Live System Test team reviews the delivered policies against the design requirement. If an RMAN
backup has been specified, the Live System Test application instance will perform those same RMAN
backups or, in the case of POLSAP application service, the Operational Acceptance Test OAT system
will be used to confirm the operation of the RMAN backup before deploying to Production.

The backup jobs are automated as defined by the Solution Owner in the Batch Scheduling High Level
Design and implemented by the Schedule Development team. If a backup does not complete or does not
backup all files it will exit with a failure status. Detection of failed backups is through job failure being
signalled to the Master Batch Scheduling system which raises events in a generic manner to the System
Management Centre (SMC). SMC uses the Known Error Log (KEL) system to identify the appropriate
team to respond to the backup failure and pass a Triole for Service (TFS) call to their call stack with a
voice prompt. Corrective action that is required beyond a simple rerun via the batch scheduler is planned
and a Managed Service Change (MSC) ticket is raised for approval. A mechanism exists to provide
emergency approval by escalating to the Duty Service Manager out of hours (3.4).

The backup and recovery methods are based on well-known industry standard solutions, and the general
operation was extensively tested during non-functional testing prior to HNG-X go-live. The responsibility
of the operational teams only extends to recovering data from tape or clone images and performing
database recovery, such as archivelog replay. There may subsequently be application support activity
required to return the service to an operational state. Recovery is tracked through the incident number of
the call raised for the original fault report, and is only performed when a MSC has been approved by
Service Management. This same process is followed for all systems that may perform backup recoveries.

Recoveries for RMAN backups are performed by the DBA team that supports those databases.
Recoveries for NetBackup backups are performed by the Unix team.

Recoveries from clones are performed by the Unix or NT team depending upon the OS type of the target
system

There is no formal periodic testing of backup recovery as the account has not provided any servers or
disk space to perform such recoveries and recovery to the live server is not permissible unless a failure
has occurred. There have in the past been operational recoveries of each type.

Audit retrievals are happening on a fairly constant basis driven by formal customer requests from POL.
Audit retrieval is tested as part of an upgrade or change to the audit infrastructure such as firmware
upgrades of the EMC Centera.

Description of Fujitsu's System 24

F/1176.1/21
POL00002314
POL00002314

Fe)
FUJITSU

POLSAP retrievals also happen on a fairly constant basis as generating a report in SAP that spans a time
period which is in the archive causes an automatic retrieval which is seamless to the user. There is no
change control process, retrievals are automatic as part of the normal user reporting process. Report
retrieval is tested as part of an upgrade or change to the audit infrastructure such as firmware upgrades
of the EMC Centera

4.8.3 Job Scheduling

4. Control Objective 4: Controls provide reasonable assurance that processing is appropriately
authorised and scheduled and that deviations from scheduled processing are identified and
resolved.

Control

44 Maintenance of Job Schedules: Access to amend job schedules is restricted to appropriate
Fujitsu personnel required to have this level of access by their role.

4.2 SAP Schedules are continuously monitored: The SAP Basis Team uses the SAP GUI and
SAP transaction code SM37 to monitor the success / failure of SAP batch jobs. The SAP Basis
team will also check and monitor the batch job start and end times and send the daily monitoring
Statistics to agreed parties.

43 Failed job schedules are monitored and alerted: Automated alerts are configured and sent to
relevant parties upon the occurrence of a batch job failure. These are investigated in line with
the incident management process.

4.8.3.1 HNG-X Job Scheduling

Scheduling of jobs within the data centre environment is an automated process using Tivoli. The Tivoli
Workflow Scheduler (TWS) is used to orchestrate the execution of jobs within the environment. Each
vertical application has its own set of tasks which are defined and TWS is used to schedule those and
maintain the dependencies within that application.

The platform architect will outline the required jobs needed for that platform as part of the High Level
Design (HLD) document. It is then the responsibility of Services Management Group (SMG) to help
ensure that these jobs are appropriately configured within TWS through creation of the TWS schedule.
SMG also performs day to day monitoring and management of the Tivoli toolsets.

If there are failures in the daily processing, alerts are raised to the Tivoli Business Service Manager
TBSM module and TWS co-ordinates the reporting of the abnormal end of those jobs that are in error.
These alerts are then identified as part of the SMC proactive monitoring of the TBSM module, further
detailed in Control Objective 6. They will then raise a TFS ticket to the Unix Team based in IRE11 and
ask them to investigate the failed schedule (4.3).

Access to maintain and amend schedules is restricted to the Systems Management Group based in
IRE11 (4.1). If changes are required to the initial schedule that has been implemented, this will follow the
standard MSC process. Please refer to Control Objective 8 for further details of this process.

4.8.3.2 SAP Job Scheduling

The POLSAP Basis team manages and maintains the batch scheduling (4.1). The details of the POLSAP
batch is held in Dimensions, documented in POLSAP/DES/APP/SCH/TBC.

Description of Fujitsu's System 22

F/1176.1/22
POL00002314
POL00002314

Fe)
FUJITSU

Dimensions has several roles in supporting services to POL including:

e Acting as a document management system.

e Acting as a software configuration repository.
The SAP Basis team performs the daily proactive monitoring of POLSAP-PLP system (4.2) which
includes:

e General health check of all systems.

e The SAP Basis team will maintain the Batch Jobs scheduling document “POLSAP BATCH
CATALOG’ so if there are changes to the batch jobs then the document will be updated. This
document is available on the project repository on the intranet.

« SAP batch jobs are maintained in the POLSAP R3 system.

e SAP batch jobs are monitored from SAP GUI through SAP transaction code SM37. This screen
is monitored on a daily basis by the SAP Basis team.

e The SAP Basis team will also check and monitor all the batch job start and end times and send
the daily monitoring statistics to agreed parties.

e The SAP Basis team will check and send the transaction response time to the agreed parties.

« The SAP Basis Team is responsible for the investigation and resolution of issues found with the
batch jobs.

If the monitoring identifies an issue with a critical job (a critical job being defined as a job that is part of
the team’s daily monitoring list) the team will ask the SMC team to raise an incident on the Post Office-
owned and managed Triole incident logging tool. The SMC team will then assign this incident to the
appropriate resolving team. These tickets would then be managed through the standard incident
management procedure that is described in Control Objective 6 (4.3).

If there is a batch job failure in POLSAP, the Solution Manager system is configured to trigger an
automated alert to the SMC team. Based on that alert the SMC team will raise an incident in the Triole
tool.

If a change in the Schedule of the Batch jobs is required or a new Batch Job is required, an MSC is
raised and once the MSC is approved the change implemented in the system by the Basis team.

4.8.4 Availability and Capacity Management

5. Control Objective 5: Controls provide reasonable assurance that system availability,
performance and capacity are routinely monitored to help ensure that potential issues are
captured and investigated.

Control

5.1 SAP Performance Monitoring: The SAP Basis team regularly monitors table space and
databases to help ensure there is sufficient system availability and capacity and that potential
issues are captured and investigated.

5.2 SAP Capacity Alerting: An automated alert will be generated in the Solution Manager System
(PLM) if the table space is more than 95% filled and the SAP Basis team will monitor and review
these alerts.

5.3 SAP Availability Alerting: Automated alerts are configured in Solution Manager to advise if a

part of the system is shutdown / not available for users. These alerts go to SMC team and they
will create an incident.

Description of Fujitsu's System 23

F/1176.1/23
POL00002314
POL00002314

Fe)
FUJITSU

Control

5.4 HNG-X Performance Monitoring: The Tivoli ITM proactively monitors CPU, Memory, Disk
utilisation and capacity of internal services on these platforms, raising alerts for investigation by
the SMC as appropriate.

5.5 HNG-X Capacity and Availability Monitoring: The Tivoli ITM tool proactively monitors the
availability of Wintel and Unix platforms, feeding platform availability data to Tivoli Business
Service Manager (via Netcool Omnibus) about the availability of platforms. Tivoli Business
Service Manager presents this data in a business context to the SMC, highlighting service
affecting issues.

5.6 Monitoring of Service Delivery: A monthly Service Review Book is provided to POL to review
its agreed Service Levels. Within this book are details of capacity, availability and incident
management performance.

4.8.4.1. SAP Availability and Capacity Management

Details of the system availability and agreed SLAs are detailed in the OLA document held on Dimensions
database. The document reference is POLSAP/SVM/SDM/OLA/874.

The SAP Basis team regularly monitors the Table space within the production databases; an automated
alert will be generated in the Solution Manager System (PLM) if the table space is more than 95% filled
(5.1 and 5.2).

The SAP Basis Team also monitor the weekly and monthly database growth for the POLSAP system and
based on that can plan the future growth of the database.

Automated alerts are configured in Solution Manager to advise if a part of the system is shutdown / not
available for users (5.3). These alerts go to SMC team and it will create an incident and assign to the
appropriate team (which again will be handled as per Incident Management process described in Control
Objective 6).

The Athene product is used to manage the Component capacity of UNIX and Wintel Hardware on POA.
This tool is located within the IRE11 data centre and its results are managed by the Capacity Manager in
the SSC. The tool looks at the CPU, Memory, Disk utilisation and capacity of internal services on these
platforms.

4.8.4.2 HNG-X Capacity and Availability Management

SYSMANS is a generic name for the set of Platforms and software that provides System and Estate
Management support to all HNG-X Platforms. This management includes the capture of availability
information for the platforms via the IBM Tivoli Monitoring system and SYSMAN3 (5.3).

SYSMANS comprises the following applications:

Application Scope

Description of Fujitsu's System 24

FI1176.1/24
POL00002314

POL00002314
FUJITSU
)
Application Scope
IBM Tivoli Monitoring (ITM) Proactive monitoring of Data centre Platforms.
Netcool Omnibus. Event collection from:
¢ Data Centre.
¢ Branch Estate.
* Networks (NNM).
e EMC Storage.
« Applications.
Tivoli Business Service Manager (TBSM) Presentation of alerts and events in a business
context.
Tivoli Provisioning Manager (TPM) e Data Centre software provisioning.
e Branch Router and Switch management.
Tivoli Endpoint Manager (TEM) ¢ Software distribution to the Branch Estate.

e Reference data delivery to Branch Estate and
Data Centre.

Tivoli Workload Scheduler (TWS) Monitors and controls workflow throughout the POL
infrastructure.
Netcool Reporter Reporting Product for SYSMAN reports.

Oracle Enterprise Manager (Oracle Grid) (OEM) I Monitoring of Oracle Databases.

SYSMANS collects events using Tivoli Omnibus Technology and presents this to the SMC using Tivoli
Business Service Manager (TBSM) views and alerts in a business’ context, correlated to the application
or system that is impacted.

WebTop an Omnibus Graphical User Interface (GUI) is used to provide a filtered view of events that are
not presented to the SMC within TBSM -— particularly for Counter and Security Alerts.

One month's historical reporting from both TBSM and WebTop is available from Tivoli Reporter.
Events collected by a SYSMAN version are sent to the Audit Server.

The SYSMAN system, an earlier version of SYSMAN3, collects events from the counter estate including:
* Quality of Service.
e Operating System.

e Application and Branch Router.
Systems within the Data Centre are proactively monitored through the use of ITM, the Tivoli Monitoring
tool. ITM agents gather the event data at regular intervals and measure the data against thresholds and
alerts are raised if the thresholds are breached (5.4). ITM includes operating system agents that alert on

CPU and Disk space events. Databases are also monitored using the ITM database agent. Custom
Agents are used within HNG-X to capture:

« Radius Authentication Events.
e Netcool Event Statistics.
e BNS Statistics.

Description of Fujitsu's System 25

F/1176.1/25
POL00002314
POL00002314

Fe)
FUJITSU

e HNG-X Application Statistics.

SYSMAN gathers alerts into Tivoli Omnibus using Omnibus event probes. Probes used within the HNG-X
solution include:

e SNMP Traps.

e Unix (Solaris and Redhat) Syslog probes.

« Unix SyslogNG (Syslog Server).

e Windows Event logs.

e Text file (Application logs).

e _ EIF Probe (Integration to Tivoli Monitoring ITM).

The SMC monitors the output from the Tivoli systems and raises appropriate alerts via the TFS toolset
and where appropriate KEL fixes, incidents or major incidents are applied.

The Athene product is used to manage the Component capacity of UNIX and Wintel Hardware on POA.
This tool is located within the IRE11 data centre and its results are managed by the Capacity Manager in
the SSC. The tool looks at the CPU, Memory, Disk utilisation and capacity of internal services on these
platforms.

The SSC receives reports from Athene detailing capacity on a regular basis.

Applications report their availability and capacity issues to the Business Systems Database and reports
are reviewed from this on a monthly basis by the SSC (5.5).
4.8.5 Incident Management

6. Control Objective 6: Controls provide reasonable assurance that significant operations
incidents are adequately reported, tracked, monitored through resolution and resolved timely.

Control

6.1 Incident policies and procedures are in place: Fujitsu has documented policies and
procedures for managing incidents impacting the in scope applications which are available via
CafeVik to Fujitsu teams.

6.2 Incident prioritisation: Incidents are assigned a priority in accordance with the severity levels
agreed with POL.

6.3 Incident resolution: Incidents are handled in a timely manner, as per priority.

6.4 Major & Security Incident review: Once a Major or Security Incident is resolved there is a

formal closure of the incident and a review including, if applicable a Root Cause Analysis.

6.5 Incident reporting: On a daily basis, the Fujitsu HSD / IMT reviews the number and severity of
outstanding incidents in TFS.

6.6 Alert handling: The Tivoli ITM and Netcool Omnibus automate the collection of events and
using Tivoli Business Service Manager highlight areas of concern to the SMC.

4.8.5.1 Incident Management Process

Fujitsu Post Office Account (POA) follows its own implementation of Fujitsu’s Corporate Incident
management process (6.1).

Description of Fujitsu's System 26

F/1176.1/26
POL00002314
POL00002314

Fe)
FUJITSU

The process applies to all Incidents raised by Fujitsu's Help Service Desk (POA HSD) or by the System
Management Centre (SMC) (out of hours or from systems monitoring tools), where they are related to the
Fujitsu outsourcing contract. POL staff raise calls at POL’s Network Business Support Centre (NBSC)
and, where relevant, they are passed to the POA HSD or SMC. Calls presented to POA HSD / SMC that
should be placed with Post Office Ltd.'s Network Business Support Centre (NBSC) are transferred/
referred from POA HSD / SMC to NBSC. Incidents are logged and managed using TFS which also
produces status reporting on incidents. On a daily basis, the Fujitsu HSD / IMT reviews the number and
severity of outstanding incidents in TFS (6.5).

The scope of the process is from the receipt of an incident by the HSD / SMC, through to the successful
workaround or resolution of the incident.

The key objectives of the process are:

Log, track and close all types of incident requests.
Respond to all types of incident requests.
Restore agreed service to the business as soon as possible.

Resolve incidents within the target timescales set for each priority level within the Service Level
Agreement(s).

Resolve a high number of requests at first contact.
Ensuring incident priorities are linked to business priorities.
Keeping the user informed of progress.

Reduced unplanned downtime.

Improved customer satisfaction

Fujitsu has defined an incident as “Any event which is not part of the standard operation of a service and
which causes an interruption to, or a reduction in, the quality of that service”.

Incidents are triggered by the following methods:

e All Incidents reported by Contact with the HSD / SMC. Contact is defined as voice or a Tivoli Alert
generated by the Tivoli Event Monitoring tool as the methods of communication with the HSD / SMC.
and fall into the following categories:

o Business process error.

Hardware or software error.

Request for information e.g., progress of a previously reported Incident.
User complaint.

Network Error.

Logging via HNG-X web interface.

o0000

Severity and Service Level Target (SLT) information.
Evidence of an Error.

System Alerts received automatically from transaction monitoring tools (6.6). Due to the urgent
nature of some of these alerts, they may be dealt with directly by the Fujitsu Software Support
Centre (SSC), with an update of workaround or resolution supplied to HSD / SMC.

The initial detection stage is the responsibility of the HSD and SMC who receive calls from Users:

Fujitsu Service Lines or Functions.
POA IT Service Management.

Third Parties.

Fujitsu Service Delivery Management.

Description of Fujitsu's System 27

F/1176.1/27
Fe)
FUJITSU

POL00002314

POL00002314

¢ Post Office Ltd, includi

ing Post Office Information Security.

These calls are recorded in TFS and are classified in one of the following ways:

¢ Advice and Guidance.
«© Out of Scope.

¢ Quality Issue.

e Incident.

The first three above are referred back to Post Office NBSC and the last follows Fujitsu’s incident

management steps.

Once the details of the incident are recorded in TFS the HSD / SMC team assigns a severity level to the
call (6.2). If the call is classed as a Security Incident or Major Incident it follows a different route detailed
below. Call Priority for Hardware and Network calls is assigned in accordance with the Priority matrix as
detailed in the agreed contractual Engineering Service Description.

The table below does not indicate resolution times as Fujitsu is required to work to POL Service Level
Agreements and availability targets and not incident resolution times (6.3). Major Incidents are therefore
resolved in as short a time as possible dependent on the nature of the incident. The high priority placed
on a Major Incident by Fujitsu’s POA management team helps to ensure that the full resources required

to resolve it are forthcoming.

A Critical e BUSINESS STOPPED, a Post Office unable to trade (where
engineering cover available), unable to process any business, or
central system failure which will result in a number of Post Offices
being unable to process work.

e Causes significant financial loss (as agreed between POL and POA
Operations).
e Results in data corruption or unrecoverable data loss.

B Major e BUSINESS RESTRICTED, a Post Office restricted in its ability to
transact business e.g., 50% of counters unable to trade or trading with
restricted business capability.

e Has an adverse impact on the delivery of service to a number of end
users.

e Causes a financial loss that impacts POL and / or POA reputation (as
agreed between POL and POA Customer Services).

e lfaPCI Major Incident process is invoked.

Cc Medium e NON-CRITICAL, a Post Office working normally but with a known

disability, e.g., an interim solution (workaround) has been provided.

e lfaPClI Minor Incident process is invoked.

« Has a minor adverse impact upon the delivery of service to a small
number of end users.

D Low e Non-urgent.

e Insignificant and usually cosmetic error, either a trivial documentation
error or spelling error on the system.

The Incident Management process contains 5 stages as detailed in the diagram below and ownership
passes between the various service lines and towers delivering the service.

Description of Fujitsu's System

28

F/1176.1/28
POL00002314
POL00002314

Fe)
FUJITSU

1,
S Incident Detecting, recording and initial
= classification
=
3
D
8
£
§
S v
z
& 2
=D SI Assign priority and initial support fc
2
6
3 >
z
&
cS
2 v ,
8 i
.§ <t =5
2 E Investigate and diagnose L__» 8 E
8 os
3 2s
= Ss
3 +t 28
B
Fk 4. p— > 82
2 id Resolution and recovery o 9
5 £
Ss
2 <
a
o v
FS
6
5.
>I Incident closure

If an incident is not a Security Incident or Major Incident then a check is made against the SSCKEL to
establish whether the problem has been seen before and if there are known actions that need to be
taken. If the KEL has information about the problem then the resolution or work around is applied and
details are linked to the Master Incident / error log for this known problem.

If it is a new issue the TFS call is passed to first line support who will attempt to resolve the incident with
the help of Product Support Engineers (PSE). If the call is resolved this is agreed with the Incident owner
and the TFS call record is closed.

If the incident is not resolved, the TFS call is passed to the appropriate Service Delivery Unit (SDU) using
the HSD / SMC Support Matrix and the Incident Management Team (IMT) are apprised of the position.
For Hardware calls, the caller is given an indication of engineer arrival time, based on the Service Level
Agreement (SLA) associated with the priority of the call.

If the incident is a known current issue then the caller is advised of the status of the problem and the TFS
Master call updated with this occurrence and the SDU(s) managing the call’s resolution are advised of
another occurrence of the issue and the IMT are apprised of the position. The SDU investigates and
diagnoses the Incident, based on the information in TFS, together with new information. The SDU also
coordinates where sub-contract third parties are involved.

Description of Fujitsu's System 29

F/1176.1/29
POL00002314
POL00002314

Fe)
FUJITSU

If the Incident has no associated KEL or it is complex and involves multiple SDUs, or if it has been
unresolved for an extended period, the IMT will alert the POA Service Delivery Manager (SDM) to the
existence of a pattern likely to produce a Problem.

The SDU will produce a workaround or resolution for the problem. The SDU then either applies the
workaround or resolution or passes it to the HSD / SMC to implement. The Master Incident Record is the
first call for an issue in TFS and is used as a tracking call for a major incident.

Where this Incident has a number of Calls referenced to it, or where there is a probability that proactive
action is required to prevent further occurrences of this Incident the IMT will alert the POA SDM to the
existence of a pattern likely to produce a Problem.

The Incident is then passed to the HSD / SMC to manage and if the call is resolved this is agreed with the
Incident owner and the TFS call record is closed.

Throughout the Incident, the HSD / SMC retains ownership for monitoring and keeping the call raiser
informed of progress, unless the incident is specifically software related, in which case SSC holds the
responsibility for confirming details of closure.

The HSD / SMC manage the complete end-to-end Incident process. Their activities include:
e Regularly monitoring the status and progress towards resolution of all open Incidents.

e Keeping affected users informed of progress without waiting for them to call, thus creating a pro-
active profile.

e Monitoring Service Level target (SLT) information and escalating accordingly if an incident looks
likely to breach SLA thresholds.

e Updating HSD /SMC knowledge database from information supplied by SSC KEL. This may be
applied as a direct copy or amended for use by the agents, dependent upon the technical
complexity of the update.

4.8.5.2 Major Incidents Definition

As a general rule a Major Incident will always be an incident rated as severity level A (critical) in the POA
BU Operations Incident Management Procedure document (SVM/SDM/PRO/0018), or a series of
connected lower severity rated Incidents, which combine to have a significant business impact. However
not all incidents rated at severity level A qualify as Major Incidents (6.4). This is because the severity
levels do not necessarily translate to the global business impact on POL's business. For example a single
counter post office which is unable to transact, regardless of its business volumes is rated as a Severity
A

For simplicity, Incidents are classified into three impact levels: High, Medium and Low.

High — An Incident that has occurred with a significant and potentially prolonged adverse impact on POL
business. Typically these Incidents will initially require a significant amount of reactive management
before they can be controlled and resolved.

Medium — An Incident that has the potential to cause significant impact to POL business but can be
controlled and mitigated against through effective management.

Low — An Incident that requires business attention but if managed effectively will not have significant
impact on POL business.

A Major Incident can be triggered by a range of causes including network triggers, application / service
outages, hardware / infrastructure failures or security issues.

Description of Fujitsu's System 30

F/1176.1/30
POL00002314
POL00002314

Fe)
FUJITSU

In the event of a Security Major Incident (which may also include PCI Incidents), the Security SDM MUST
be alerted and they will then follow the Security Incident Management procedure as detailed in both:

e¢ SVM/SDM/PRO/0018 Appendix A.

e SVM/SDM/PLA/0031 HNG-X Security Business Continuity Plan defines the actions to be taken if
security violations are identified

4.8.6 Major Incident Process

An initial impact assessment of an incident is undertaken by members of the IMT to determine if it should
be classified as a Major Incident, taking into account as described above.

The Major Incident Manager will consult with the Business Continuity Plans to identify if potential Major
Business Continuity Incident (MBCI) or MBCI triggers have been met and inform POA Business
Continuity Manager if appropriate.

POL Service Delivery (SD) will be informed by the Major Incident Manager of the incident, and the
incident will also be escalated to Fujitsu Service Delivery / Service Support team managers, if this has not
already occurred.

With agreement from POA Service Delivery Manager/s, or Duty Manager out of hours, a Short Message
(Phone text) will be sent to POA and POL Management alerting to the potential existence of a Major
Incident.

Once a Major Incident is opened the relevant internal SDUs / Third Parties are contacted to initiate
investigation and diagnosis and the Major Incident Manager opens a Major Incident Report which is held
on SharePoint.

A Technical Bridge is scheduled, with a standard agenda, with all the relevant Service Delivery Units, IMT
and Service Delivery Managers (SDM) and an agenda distributed. The Technical Bridge is technically
focused.

The Technical Bridge aims:
e To discuss & agree the recovery investigation & resolution of Major Incidents.
e To provide a forum for up-to-date progress reports.

e To aid communication and, if necessary, support the Technical Recovery Manager (TRM) in
producing a short term technical recovery plan and if appropriate longer term corrective actions.
These will be included in the Major Incident (MI) report. This ensures that Major Incident progress
is known by all, whilst also ensuring that all actions whether short term or long term is clearly
stated.

¢ To collate information for inclusion on the Service Portal.

Attendees at the Technical Bridge include, but are not limited to, POA Service Management, SDU, Third
Parties, POL, and POA Security & POL Security Managers.

If the outcome of the Technical Bridge is that the Incident is determined Business As Usual (low) then a
SMS communication will be sent stating that the Incident is not a Major Incident, and the incident is then
resolved using the standard incident management process.

The Major Incident Manager will also distribute actions (provided by the Technical Recovery Manager
(TRM)), following the conference call.

lf during the Technical Bridge a clear recovery path is identified, this is discussed and agreed on the call.
Following agreement the recovery is implemented.

Description of Fujitsu's System 31

F/1176.1/34
POL00002314
POL00002314

Fe)
FUJITSU

Following the Technical Bridge the Technical Recovery Manager will liaise with the SDUs and / or third
parties during the investigation / recovery. If no clear recovery path is identified, the decision is then
taken on whether to escalate for Service Bridge direction.

The nature of the Major Incident determines which POA BU Service Team members and POL Managers
are involved in the Service Bridge.

The purpose of the Service Bridge is to:
e Provide appropriate direction on Incident resolution.
e Provide added impetus to restoration of service ASAP.
e Define communication intervals to Key Stakeholders.

« Provide focused Incident Management in line with the impact and severity of the Incident.

Once the Incident is deemed to be resolved, a final Technical Bridge is held to agree and confirm the
resolution of the Incident. The Major Incident Review date is set at the final Technical Bridge. SMS
communication is sent confirming resolution of the Incident.

A Draft Major Incident Report is distributed within 24hrs of resolution of Major Incident.
Once a Major Incident is resolved there is a Formal Closure of the Major Incident and a review of the
Incident including consideration of:

e Lessons learnt.

¢ — Incident definition.

« What went well?

° Timeline.

e Changes required to infrastructure.

e A review of the Major Incident Communication Procedure.

e Root Cause Analysis.

e Business impact.

e Action plan, including any changes requiring MSC's.

e Service Improvement Plan update.

e Review service risk(s) and update Risk Register as appropriate.

4.8.7. Security Incident Process

An information security Incident is: "an adverse event or series of events that compromises the
confidentiality, integrity or availability of Fujitsu Services Post Office Account information or information
technology assets, having an adverse impact on Fujitsu Services and/or POL reputation, brand,
performance or ability to meet its regulatory or legal obligations." This will also extend to include assets
entrusted to Fujitsu including data belonging to Post Office Ltd, its clients and its customers.

Fujitsu classifies Security incidents using one of two levels of severity:
e AMINOR incident will normally have limited and localised impact and be confined to one domain.
e AMAJOR incident will have a significant impact on the Network Banking Automation Community.

NB. For a Major Incident the POA Major Incident Process (SVM/SDM/PRO/00071) is followed.

Description of Fujitsu's System 32

F/1176.1/32
POL00002314
POL00002314

Fe)
FUJITSU

Whenever a security incident is identified which presents a serious threat to conducting normal business
it is contained and isolated as quickly as possible.

A security Incident is first notified to a person’s Line Manager. The Line Manager gathers as much detail
of the incident as possible, following Fujitsu BMS procedures. He or she will undertake an initial local
investigation into the incident, seeking to ensure that in the case of missing equipment or materials that
they have not just been misplaced. Information gathered will be entered into the initial Fujitsu case report
template (ICR).

If the severity of the Incident is considered as Minor but warrants further investigation, the Line Manager
would immediately log a call with the Horizon Service Desk, stating that they are reporting a security
incident, giving brief details. Having logged the call and obtained a call reference number, the Line
Manager may then continue with the investigation if they believe the incident warrants this, and act as a
liaison between the person reporting and all concerned parties. All Incidents reported to the HSD with a
call reference and even when classified as Minor are still forwarded to POA Security Management to
determine if there is a Security Impact.

If the severity of the Security Incident is considered as Major, the Incident details are reported directly to
the POA Security Manager immediately. Depending on the type of Incident and the severity of the
incident, POA Security makes the decision to escalate details to the POL Security team. In the case of
Data Centre incidents specifically, POA Security also informs the Data Centre Manager if this has not
already been done. Regardless of the severity of the incident, when a compromise in card data occurs,
the incident is reported to POL Security so that POL can comply with its contractual obligations with its
card acquirer.

Once a call is raised with the SSC the call is then placed on the call stack of the POA Security Team,
which monitors the incident, assists or advises the Line Manager if required, and is available to take over
the investigation should the need arise, but always be able to respond, within 2 hours of the initial call
being made.

In most cases, the initial investigation of a reported incident is carried out by a nominated investigator
normally the POA Security Manager or his nominated deputy. POA and POL Security Teams will be on
hand to provide backup and assistance if required. The investigator will endeavour to obtain as much
original evidence as possible. In the event of a court appearance the court prefers the original evidence
rather than a copy but will accept a duplicate if the original is lost or destroyed or is in the possession of a
third party who cannot be subpoenaed.

Following the initial investigation and where considered appropriate, the investigator reports to / liaises
with the local Police and / or other external Agencies; this will only be done following consultation with the
POL Head of Security and POL Head of Information Security or substitute.

Copies of the initial and follow up reports are submitted to relevant authorities and details of
investigations are held on file by POA Security to aid subsequent trend analysis.

When the final report of an investigation has been completed, it is passed to the relevant authority for
follow up action, the results of which are referred back to the POA Security Manager.

When an investigation is closed the POA Security Manager seeks to ensure that details of the
investigation have been recorded and can be made available for subsequent future analysis.

On call closure, the POA Security Team completes and notifies CPNI where required. Thereafter the
incident is reviewed to identify the lessons learnt and the processes and relevant documentation is
updated as appropriate.

Description of Fujitsu's System 33

F/1176.1/33
POL00002314
POL00002314

Fe)
FUJITSU

4.8.7.1 Security Incident Trends and Checks

POA Security Team carries out a monthly check of investigations and creates a summary report
highlighting incidents to the POL Head of Information Security.

The report highlights trends or weaknesses which may need to be raised at future Information Security
Management Forums (ISMF).

Details from the monthly reports may also be considered suitable for Line Managers.

4.8.8 Network Incident Management

Incidents relating to network problems are managed using the standard incident management processes
and controls described above.

4.8.9 Networks

7. Control Objective 7: Controls provide reasonable assurance that networks are managed to
contractual and site requirements, monitored for availability and response times and issues
are identified, tracked and resolved.

Control

5.6 Monitoring of Service Delivery: A monthly Service Review Book is provided to POL to review
its agreed Service Levels. Within this book are details of capacity, availability and incident
management performance.

7.14 Network performance criteria: Network availability and performance requirements are clearly
defined between Fujitsu and POL in the Network Service descriptions and network service is
measured and monitored using these agreed service levels.

7.2 Network change management: Network changes are managed using the standard Fujitsu
MSC process including authorisation, testing (where deemed appropriate) and approval of
changes before they are implemented.

7.3 Network availability monitoring: Network availability is monitored using several tools which
send automated alerts to the Network Operating Support Service Team (NOSS) if key
components are unavailable, or if traffic levels breach predefined thresholds.

74 Network incident management: Incidents relating to network availability are managed using
standard incident management procedures used on the POA, and are included in the standard
incident management reporting to POL.

4.8.9.1 Network Service Description

POL defines the network services it requires from Fujitsu in two contract controlled documents - the
Branch Services Network Service Description (SVM/SDM/SD/0011) and the Central Network Service
description (SVM/SDM/SD/0012) (7.1 and 7.2).

4.8.9.2 Provision of the Network Service

Fujitsu provides a network service to POL using its Hosting and Network Services (HNS) teams. These
teams provide technical support and implementation for the following products and platforms:

e The HNS Post Office Account Network team based in Warrington supports Cisco Routers,
Switches, Load balancers and Firewalls.

e A separate team also based in Warrington supports the Intrusion Detection System (IDS) and
proxy servers (McAfee Web Washer & Bluecoat Proxy SG).

Description of Fujitsu's System 34

F/1176.1/34
POL00002314
POL00002314

Fe)
FUJITSU

« Acentralised Network Operations Support Service (NOSS) overviews and monitors the systems.

Wide Area Network Services are provided through a number of third parties depending on the circuit or
communications requirement.

Controls operated by these third parties are outside the scope of this report.

4.8.9.3 Network Change Management

Fujitsu follows the MSC change management structure for all changes to Network equipment as
described below in section 5.9.9 which describes Control Objective 8 (7.3).

4.8.9.4 Network Availability Monitoring

Fujitsu has its own dedicated Network Operating Support Service to monitor the availability of Network
Services to POL using TFS to raise problems or incidents to the Network, Firewall or IDS teams and
where applicable the Incident management process (described under Control Objective 6) is used to
resolve these (7.4).

4.8.9.5 Network Service Monitoring

A monthly Service Review Book is provided to POL to review its agreed Service Levels and within this
book are details of Network performance. This book is jointly reviewed monthly at a Service Review
Board and network performance is included (7.1).

4.8.9.6 Overview of Network Technical Design

The Network that Fujitsu provides to support its services and applications to POL is divided into the
following at the top level:

e IP Network Space Data Centre Networks.
e Branch Networks.

e Transit Networks.

« Wide Area Networks.

As shown in the diagram on the next page:

Description of Fujitsu's System 35

F/1176.1/35
POL00002314

POL00002314
Fe)
FUJITSU
iP ‘Storage

Core Tier

High Speed Layer3 switching between Routing
Distnbution Tiers

Connectivity between Data Centre's

Distribution Tier
Server port density Post ‘Server
Virtualization, Client Office Support I I connectivity
Load Balancing SAN
Security (VPN, Firewalls, IDS)
Post
pccose Tee Branch Client Otee Support Client
Remote Access I I SAN
Conneotivity between Data Centers \ posing Avangamontt ‘extension
I (Peering Arrangement!
Security (VPN, Firewalls, IPS) I Le trangtLAN I

RMGA provided Wide Area Network Alien
Wide Area Networks)

Branch Wide Area Network
Services
Remote I Client Post ‘Support
Branch LAN Location: Office

[ Peering Arrangement! Transit LAN
Cient Suppor rose
letwor! letwor NetwerkActitertrebSvsd

Testing is provided through the standby data centre for Live System Test and System and Volume
Integration during normal operations. This test support would disappear if the standby data centre was
required to act as the primary. Under normal business as usual conditions the traffic is segregated with
access between production and test environments prevented by means of various physical and logical
means of separation as appropriate. Change Management is strictly controlled through a variety of
internal change & release processes and procedures — see below for more information on change
management for network components [Control Objective 8).

The network is divided into 11 Security Domains. The term Security Domain is defined to mean a
collection of platforms and network components grouped together based on type, perceived vulnerability
and risk rating. Even so, it may be necessary to restrict traffic between platforms in a common Security
Domain (intra-domain traffic) through the implementation of logical separation, (using VLANs), or physical
separation, (using separate network segments in the same domain).

Any traffic which crosses network domain boundaries (inter-domain traffic) must pass through an
enforcement point that restricts data flow based on its source, destination, protocol, port, type or content /
format. This can be a firewall, router or other in-line control point. (i.e., the control is physically part of the

data path).

The following diagram illustrates how Network Domains fit within the Network tier model.

Description of Fujitsu's System 36

F/1176.1/36
POL00002314
POL00002314

Network Domains are the basic building blocks for enforcing security in the Network.

The Domain structure places a logical ring around the logical Security Perimeter of the HNG-X Network in
the data centre, but this perimeter extends beyond the data centre in some cases and is protected by
means of IPSEC VPN technology using access lists to allow specific classes of traffic to enter HNG-X.
More specifically, this perimeter can be best described as the collection of devices managed (or
monitored) by Fujitsu Services. At the boundary of these managed devices a firewall (hardware or
software-based) will be located, and the perimeter will be secured according to firewall guidelines laid out
in ARC/NET/ARC/0001.

4.8.9.7 Network Asset Management

Network Assets are managed through Cisco Works Inventory along with an offline hardware inventory
register. Hardware and Software maintenance is on a business case basis and is based on business
availability targets.

Description of Fujitsu's System 37

F/1176.1/37
POL00002314
POL00002314

Fe)
FUJITSU

4.8.10 Change Management

8. Control Objective 8: Controls provide reasonable assurance that modifications to system
software and networks are authorised, tested, approved, properly implemented and
documented.

Control

8.4 Change management: The MSC toolset is used to manage all changes with a joint decision
between Fujitsu and POL as to which parts of the tool are relevant for a change.

8.2 Change approval: All changes must be authorised by the Fujitsu Duty Manager or technical
bridge, with approval being documented in the MSC system. Changes that cause major service
interruption must also be authorised by the Change Advisory Board (CAB), with approval being
documented in the meeting minutes and within the MSC system.

8.3 Emergency Changes: A change deemed necessary in order to resume live service will be
agreed and authorised and documented during the incident along with updates to POL at an
agreed timeframe dependent on the severity of the incident.

4.8.10.1 Business as Usual Change

All change is subject to the Managed System Change (MSC) change process whether it requires
changes to existing services or the managing of new services or functionality (8.1). Key change types
that fall into scope for this process are listed below:

« Changes that require physical access to or are making changes to POL services being hosted in
the Data Centre.

e Changes that are requested to be shared by POL data centre or Branch Counter estate by
either:
o Asupplieri.e., BT, C&W, the Data Centre utility suppliers etc.
Shared networks.
Shared infrastructure.
Account specific infrastructure.
Account specific networks.

e000

e Changes that require the release of an application software change or support patching / security
patching changes.

e POLSAP service offering change.

e Credence service server support changes (note these relate only to hosting of the service).
e On-line services changes.

« Changes as the result of an Incident.

e Changes to resolve a Problem.

These changes include POL authorised project work with Fujitsu or POL 30 Party or POL Network
Partners. These types of changes are supplied by POL and are then recorded in MSC and assessed /
reviewed by Fujitsu staff with issues or concerns fed back to POL.

The Manage Service Change (MSC) operational change process uses the Fujitsu MSC toolset to
progress the change through control gates which are described overleaf.

The MSC toolset is secure and auditable (at both system and user levels with time stamping being
employed). As changes are made to a change record and it progresses through the control gates listed
below with permissions and ownership of the change recorded at the various stages.

Description of Fujitsu's System 38

F/1176.1/38
POL00002314
POL00002314

Fe)
FUJITSU

Both POL and Fujitsu change control teams participate in tailoring the questions in the MSC toolset to
enable the relevant information to be obtained for POL's internal change process. This helps their
network partners and third party suppliers assess a Fujitsu-controlled change for risks and impacts.
These controls, along with the KPI's established by POL to monitor the MSC toolset information
standards for quality, timings of the notice of the change etc., help to ensure the efficient and effective
control and management of operational change.

Once a change is ready to be tested it becomes subject to the Manage Service Change (MSC) process.
Change Advisory Board (CAB) approvals are obtained before deployment can begin, with approvals
documented both in CAB meeting minutes and within the MSC system (although these are not formal
signoffs, for example, they can be copied in from POL e-mails).

The control gates to be established around change are:
e The request for the change from POL (projects).
« The establishment of a Design Proposal by POL (projects).
e The acceptance of the Design Proposal by Fujitsu (projects).

e POL raises a Change Request (CR) or a Contract Technical Change (CT) or Contract Change
Notice (projects).

e Fujitsu raises a Change Proposal (CP) to impact change (projects).

e Costs and Impacts are sent to POL and approved or rejected (projects).

« If accepted, then a set of Requirements is jointly agreed with POL (projects).
e A project is initiated and project plans drawn up (projects).

e Architecture, High Level Designs and Low Level Designs and interface documents are written
and where appropriate discussed with POL.

e Development of Code is undertaken (projects).
e Code is tested by development (projects).

e Code is packaged by integration into Dimensions ready for delivery to System Volume and
Integration Test or Live Systems Test (projects).

e Code is tested by Solution Validation & Integration (SV&l) and Live Systems Test (LST) based on
project plans from requirements (projects).

e Tickets are raised in the PEAK system (these are known as PEAKS) for defects identified by
SV&I and / or LST (projects).

e Defects are fixed and follow Test cycle until approved (projects).

e Consecutively to Code Development platforms are built where appropriate using current
standards (projects).

e Platforms are tested in conjunction with the code in SV&I and LST (projects)
« PEAKS are raised for defects (projects).
e Defects are fixed and follow Test cycle until approved (projects).

« To deliver integration packages to SV&I & test the recording of the change takes place in MSC.
and contains appropriate release notes and details (Projects).

e MSC is used to Record and authorise BAU changes also (Operational changes).

« The MSC systems records assessment by other potentially impacted teams to determine risks
associated with the change in their area (Operational Changes).

Description of Fujitsu's System 39

F/1176.1/39
POL00002314
POL00002314

Fe)
FUJITSU

« The MSC systems contain a plan of the change (Operational Changes).

e The MSC team agrees the change internally and with the customer where relevant at CABs,
(Operational Changes).

e The CAB review helps to ensure (Operational Changes):
othe change meets the governance requirements;
othe change does not overlap with other changes;
o that the change has considered any group or associated further risks and impacts by
doing the change; and
othe CAB follows the standard CAB Terms of Reference (TOR) which defines:
= Attendees.
= — Sign off or rejection or associated actions.
= Recording and issuing of minutes from the CAB.
= Updating the MSC toolset with the CAB decision.

« The Change Manager satisfies themselves that the change has (Operational Changes):
o Metall areas of governance.
o Considered impacts / risks.
o CAB agreement for the change to proceed is in place.

e If the above are in place, the Change Manager authorises the change within the MSC system to
proceed and implement the change (Operational Changes) (8.2).

e Post implementation outcomes of change are recorded in post implementation review and
records are updated and success criteria examined and lessons learnt are documented
(Operational Changes).

e Change close down (Operational Changes).

In summary, MSC is a Fujitsu toolset that allows a securely accessed, time stamped auditable system to
record change, provides Service Delivery Units and Service owners with audit trails and gives reasonable
assurance that modifications to software and infrastructure are assessed for risks & impacts. The
changes are authorised by the Service owner and Change Manager, are tested by appropriate methods
and teams, and are approved to be deployed to a live environment subject to testing results, they are
implemented by the authorised and approved teams and the changes are documented into new or
existing documentation.

Description of Fujitsu's System 40

F/1176.1/40
POL00002314
POL00002314

FUJITSU E

MSC Process Steps - Overview

Som Notic POL Client fe
Operational lotice sent to ient for
4 ident Approval of Changeand = MSC Request
incident understanding of impacts
Problem I with a view for authorisation POL approval of Change and
Change toproceed with change any Acceptance Criteria,
Request 7 Timings or their Rejection of
Operational Implementation
of the change

Client Project
Closure
Acceptance

Final Cost &
Service
Acceptance

» Confirmation of SDU
Testing Asset
&Configuration
Update
A= Approve to proceed further R= Optional Review A=Approve ATI - Approval to Implement
18 @Fujtsu Services 2006 Alan Fack Manage Service Change o
Description of Fujitsu's System 41

F/1176.1/44
POL00002314
POL00002314

Fe)
FUJITSU

4.8.10.2 Emergency Changes
Emergency changes are progressed through one of two methods:
e aservice incident; or

e the emergency CAB (E-CAB) process.
Both processes will document changes required in the MSC toolset.

A service-affecting incident sees a Technical Bridge convened (see the incident management section of
this document above — Control Objective 6) to analyse the cause and impacts of the incident. This team
will include service managers, an incident manager and technical staff and the Operational change
manager. Any change deemed necessary in order to resume live service will be agreed and authorised
and documented during the incident along with updates to POL at an agreed timeframe dependent on the
severity of the incident.

If the level of the emergency is at lower level such as a disk failure the resolver (often an incident
manager) will request that an E-CAB is called. The Change manager will call the E-CAB meeting together
following the process as documented in the CAB Terms of Reference (TOR) via a conference call to
discuss the change with both technical staff and service managers. The MSC record will be E-mailed
around the mandatory assessment teams with a timeframe turn round of assessments within an hour and
documented with the Incident Management documentation. The incident or change manager will contact
POL Change Contro! to discuss the emergency and ask for verbal permission to proceed during which
time the Fujitsu change Administration staff will send the change to POL Change Control for their records
(8.3).

9. Control Objective 9: Controls provide reasonable assurance that new or modified application
software development efforts are authorised, tested, approved, properly implemented and
documented.

Control

9.41 System Development and Maintenance policies and procedures: Fujitsu has a formal
Systems Development Life cycle (SDLC) which incorporates phases including initiation,
Requirements, Definition, Design, Development, Deployment and Maintenance.

92 Change Control Board: Depending on the nature, changes must either be approved by the
Change Control Board (CCB) before progressing into development or by the PEAK Targeting
Forum (PTF).

9.3 Design Proposal: Projects are outlined in a Design Proposal (DPR) that is held in DOORS or
Sharepoint and is reviewed and approved by POL as well as Fujitsu management.

9.4 Change Testing: Changes are tested in line with the defined procedure.

9.5 Ability to implement changes: Only appropriate individuals have access needed to move code
builds between environments or promote transports to live. Segregation of duties is enforced
between users able to develop and implement changes.

9.6 Approval to implement changes: POL approval is required to promote software changes to
the live environment. Approval is captured within the relevant MSC.

Fujitsu's change management process consists of two components - Project Changes and Business as
Usual (BAU) changes. Project Changes relate to the delivery of new or changed services and BAU
Changes to Operational changes to the live service provided to POL (9.1).

Description of Fujitsu's System 42

F/1176.1/42
POL00002314
POL00002314

Fe)
FUJITSU

4.8.10.3 Project Changes for HNG-X and SAP

External requests for changes will be raised on a Change Request (CR) and sent electronically to
Commercial Change Management (ChM) and allocated to a Change Owner and converted into a Change
Proposal (CP).

All CPs are initially reviewed and impacted by Programme teams and impacts are returned to ChM where
they are collated and shared with the Change Owners. Where appropriate the CPs indicate that they
have the Design Authority Board (DAB) approval.

Once reviewed, CPs will be submitted to the Programme Change Control Board (PCCB) for agreement to
progress the CP. The PCCB typically meets weekly. The PCCB is chaired by ChM and brings together
representatives from a wide range of functions potentially affected by proposed changes.

Once the PCCB has assessed and agreed the progression of a CP, it will be submitted to the Change
Control Board (CCB), which includes the Account management team, with a recommendation from the
PCCB as to whether the CCB should approve or reject it (9.2).

The CCB typically meets weekly. Change Owners are required to attend to sponsor the change detailed
in their CP. The CCB consists of members who represent the key functions within the Account to help
ensure that if the CP is accepted for implementation it will:

e Commercial / Finance
o Have no adverse financial or commercial implications.
o Not increase the overall risk to the Account / Customer contract and Service
commitments.

« Customer Service
co Be operationally supportable and will meet the Account’s service obligations.

e Development
o Be developed within the agreed timescales to the required quality level.

° Architects
o Be constrained within the overall architectural solution and is technically viable.

e Testing
o Be tested and integrated to the required quality level within the agreed timescales.

e Business Management
o Not inhibit the Account in exploiting future business opportunities for the Account and its
Customers.

A minimum of three Directors are required to be in attendance for a CCB to be able to reach a decision
on CPs.

Minutes from both of these meetings showing approval of the CP are held in PVCS (Project Change
database).

Once the CCB has approved a change the following occurs:

e If the change is internal the Programme team is advised, time codes and plan activities are set-
up and work can start.

e If it is external, the change will be submitted to the customer (electronically and hard-copy) and
POL reviews the change until formal agreement which then allows the CP to be progressed.

Work on a project will not begin unless approval is in place.

Description of Fujitsu's System 43

F/1176.1/43
POL00002314
POL00002314

Fe)
FUJITSU

Project Changes are allocated unique numbers and lodged within a database (PVCS) and related
accordingly. These can be viewed by all members of the team working on that project but can only be
updated, edited and actioned by members of ChM.

All Minutes from the Change Boards (PCCB and CCB) and actions from the same are recorded in the
change history of the change vehicles in the database.

Comments and decisions around the changes are also lodged in the change history.
CP Impacts are collated into CP specific files and stored on a back-up server.

Approvals from the CCB and POL are documented in the relevant change history.

4.8.10.4 Projects for HNG-X

Fujitsu follows its Corporate Methodology outlined in the diagram below to deliver a project to POL. Each
project has clear requirements, is designed, tested and deployed prior to its acceptance into the Live
Production Estate. All projects are assigned a Project Manager to deliver the specific project with
oversight of all projects by the Programme Director.

oR svai Service

i i

Aad E==> I CIT fm] lntegration II SBI I LST I

; i

¥ or
ervcen Guat cortt II ee FM tL rota

Fea )
f Gavemance }

Customer . . I

Change Design & Development Testing H Deployment

The diagram below shows an overview of the design and builds methodology used by Fujitsu to define,
design, develop and deliver a project into the POL production environment.

This Methodology is used for HNG-X projects and projects that integrate HNG-X and SAP.

Description of Fujitsu's System 44

F/1176.1/44
POL00002314
POL00002314

Fe)
FUJITSU

HNGxDBM unex design & Build Method Lifecycle Method (v1 1)

Project
Management

a r a

Hawi as
FUjiTSU

4.8.10.5 Definition

POL defines projects according to their defined business needs and provides these to Fujitsu as
documented requirements and acceptance criteria.

4.8.10.6 Requirements

Requirements are managed within Fujitsu by the Requirements manager.

POL defines a requirements baseline and where applicable a baseline design proposal (DPR) and Fujitsu
may be requested to assist POL in the preparation of these (9.3). These requirements are stored within
the POL DOORS system and replicated within Fujitsu and exceptions, non-compliances etc. are recorded
in the Design Proposal and in the Commercial Terms response to POL. The DOORS system is jointly
managed by Fujitsu and POL and is used to contain the documentation of the requirements for changes.

The Design Proposal contains 3 key elements:

e The Acceptance Criteria.

e The Work Packages that are built to deliver the project.

« The Monitoring Criteria for the project after go live.
There is no formal POL sign off of the DPR however they are involved throughout the process and
through the use of DOORS have visibility of the detailed requirements that the project must deliver. Once

POL has approved the detailed requirements in DOORS this is taken as approval of the overall DPR by
POL.

Description of Fujitsu's System 45

F/1176.1/45
POL00002314
POL00002314

Fe)
FUJITSU

4.8.10.7 Design

Application Development for the in scope applications will be performed by a range of Fujitsu teams
depending on the nature of the project.

4.8.10.8 SDLC Methodology

POA Design and Build Methodology (DBM) engineering lifecycle was derived from the Fujitsu corporate
Applications Design and Build Methodology (ADBM), Infrastructure Design and Build Methodology
(IDBM) and Test & Validation lifecycles (9.1). This is the SDLC currently used by Post Office Account
(POA) team to modify existing or develop new applications for Post Office Limited (POL). It is defined in
the standard document sets that are specific to the in scope applications.

High level designs (HLD) and Low-level designs (LLD) are the way Fujitsu meets the relevant Design
Proposal requirements and these are stored in Dimensions or SharePoint. The HLD’s and LLD’s for
HNG-X projects are approved by one of the approvers defined in PGM/DCM/ION/0001 &
PGM/DCM/PRO/0001. SAP HLD's and LLD'’s are approved more informally within the SAP teams (9.3).

4.8.10.9 Code Build and Test

The Development Manager is responsible for the building and testing of code. Code is built in a
segregated environment using appropriate repositories. These repositories use standard code
management tools including locking, the booking of code in and out and the management of changes.
Each project will have a Development manager who will take the relevant HLDs and LLDs and allocate
these to developers. The Development manager will also develop their own project plan to track progress
of the code development and testing. Code will be booked out by developers and worked on within the
context of this project plan.

A generic code review template is used to review the code and it is approved by the Team Leader or
Senior Designer once outstanding issues are resolved. The resulting review document is stored in
SharePoint.

Individual Developers are responsible for producing Unit Test plans and reviewed by a separate
developer. The initial developer will then develop the Unit Test plan which will be signed off by the
reviewer, a developer will then execute the unit test plan and the results are recorded by the Developer
in the Unit Test plan — usually as an appendix and the combined Test plan and report is stored in
SharePoint / Dimensions. This evidence of results of testing is then signed off by a separate developer.

Component Integration Testing (CIT) is an independent testing phase that carries out initial integration of
developed components it is performed to a CIT test schedule produced by the CIT tester and the
schedule is updated with test results and stored in SharePoint / Dimensions. A formalised defect
management (JIRA / Quality Centre) is used to record and track issues to resolution. The CIT testing is
undertaken in a segregated environment under the supervision of the CIT manager.

Approval to move from the Code build and Test phase is an informal process agreed by the Development
Manager and CIT manager. Once the Development is assessed as passing CIT the Development team
will use one of the standard tools to create a deployable build of the updated / new software, they will
then place this build into Dimensions for integration to then load into the next test environment.
Development only have access to place the build into Dimensions, they cannot then move it into the next
test environment.

4.8.10.10 Integration and
Test
HNG-X has 2 test streams responsible for testing software changes to the live estate:
e Solution Validation and Integration (SV&l):

Description of Fujitsu's System 46

F/1176.1/46
POL00002314
POL00002314

Fe)
FUJITSU

co Testing against Requirements - Functional and Non Functional covering business and
infrastructure and based on testing the complete integrated solution.
o Has End-to-End capability for testing with 3rd parties e.g., Merchant Acquirer.

e Live Support Test (LST):
co Final pre-production proving and release deployment validation.

The development-written test automation framework (documented in TST/SOT/HTP/0976) has been
deployed into the SV&I environment to support testing. This automation framework offers the benefits of
unattended execution, and allows the expansion of the automation suite to encompass a larger share of
the regression test overhead.

Testing uses Quality Centre as the test management and defect management tool for defect
management. Quality Centre interfaces with Peak which is the POA Development Defect Management
System:

« Adherence to gateway criteria such as test stage entry criteria.

Entry into each test stream (or test cycle within test stream) will be subject to review against a pre-
defined and agreed set of entry criteria. These criteria are set by the Test stream manager. Similarly
testing within each stream will not be considered complete until the testing is adequately reported and a
resolution path for all outstanding issues is understood (9.4):

e Progressive, incremental development, testing and acceptance.

Each test cycle is subject to entry criteria acceptance. Quality Centre is used to store and measure
progress against project requirements. An assessment of requirements coverage is produced towards
the end of test completion. This feeds into the Acceptance Process which is a joint board (with POL) with
agreed criteria for acceptance.

4.8.10.11 SV&I Testing
Process

Test Analysis is based on Requirements and high level designs. Test cases are documented in Quality
Centre (QC) and details are extracted into a High Level Test Plan for each release. This document is
reviewed via POA document management.

Entry into Test Cycles is controlled by Test Readiness Reviews.

Test Execution is recorded in QC and defects are recorded within QC.

Daily and Weekly reports are produced using QC to produce statistics e.g., test coverage.

After the last cycle of testing (pre LST) a report is produced covering the full release.

4,8.10.12 LST Testing
Process

Testing is controlled via the Release Management team.

Release Planning sessions identify maintenance test slots and Peak targeting Forums assign defects into
appropriate maintenance releases.

Release Management engage with test via Release Notes and Deployment plans.

Description of Fujitsu's System 47

F/1176.1/47
POL00002314
POL00002314

Fe)
FUJITSU

LST put test plans together which are held in SharePoint and once testing is complete these are updated
with results. LST assess test results and determine a release sign-off or release rejection position. The
final document is attached to the release peak which is returned to Release Management.

4.8.10.13 Acceptance

The Acceptance phase is managed by the Acceptance manager. The Acceptance manager will review
the progress of the testing teams in completing the testing specified for each acceptance criterion in the
design proposal (9.6). The results of testing are summarised in the Acceptance Report. This is then
discussed by the Acceptance Assessment Board which reviews the Acceptance Report including
Acceptance Incidents. An acceptance incident is where the acceptance criteria have been tested and
either not met or are partially met.

A joint Release Acceptance Board is then held with POL to agree how to progress the Acceptance
Incidents and overall whether the project as stand-alone entity is ready to be implemented. The decision
is documented in the minutes of the Release Acceptance Board which are held in Dimensions.

The POL and Fujitsu Project Managers will then produce a slide pack for presentation to the Release
Authorisation Board; this board will then consider whether to approve implementation based on:

e The Release has passed the Release Acceptance Board.

e That Fujitsu Service teams are ready to support the new services / functionality.

e That Post Office Service teams are ready to support the new services / functionality.
e That communications to interested parties e.g., Post Masters are ready.

Approval to implement the project is documented in the meeting minutes that are held in Dimensions.

Once these approvals are in place the project can be implemented into production.

4.8.10.14 Deploy and
Support

Release management is based around the use of two documentation tools, PEAK and Managed System
Change (MSC), and two delivery tools, Dimensions and Tivoli Provisioning Manager (TPM) (9.5). A ticket
will be created in PEAK for each change or element of a project. The PEAK Targeting Forum (PTF) which
meets weekly reviews the open PEAK tickets and groups these into deployment groups each of which
contains typically no more than 20 PEAK tickets.

Development will then create a PEAK Product Version Baseline (PVB) for the deployment group and this
is effectively what is placed into production on the successful completion of the relevant testing.
Development will then perform unit and component and integration testing as outlined above, once this is
successfully completed, they will use one of the standard tools to create a build package which is placed
in Dimensions.

Integration will test that the baseline package is capable of being deployed into the existing
software/hardware environments and can be regressed off of the Integration testing rig as well as doing
some basic functional testing. Once this has taken place and the baseline package is deemed fit to
further progress into the testing environments then a PEAK Deployable Product Version Baseline (DPVB)
is created to enable further progression into the Release process.

The package created by Development (PVB) & then Integration (DPVB) is then made available to
Release management for preparation to be tested in either SV&I for project functional testing with POL
and other third parties ready to be implemented (identified by a INT suffix) or if it is for current system
maintenance for existing software security or minor bug fixes it will be implemented identified by a LT
suffix in the LST (Live Support Test) via a RM Release note (RN) will be passed to Software

Description of Fujitsu's System 48

F/1176.1/48
POL00002314
POL00002314

Fe)
FUJITSU

Configuration Management (SCM). SCM will then place this package onto the TPM server based on
receiving authority from Release Management in the Release Note. SCM are the only team with access
rights to move software onto the TPM server (9.5). SCM advise RM that the output is ready to be shipped
to the test environment by updating PEAK.RM will via Peak and the MSC process authorise the relevant
operating teams via a sub task MSC to pick up the package and place it into the relevant test
environments for further testing as outlined above, this task has a reference to the Release Note. Once
testing is complete Release Management will update the release note to reflect this. They will also create
a new release note with the same number but a PR suffix to manage the movement into production.

At the same time as Release Management release the RN to the LST team, the ticket will be created in
MSC. MSC is used by Release Management to manage the process steps that need to be completed to
move a change into production. The approvals to move the change through the various stages (both
Fujitsu and POL approvals) are logged in the MSC ticket, and are typically copies of emails pasted into
the ticket- MSC does not use formal workflow-based sign offs (9.6).

When Release Management believes the package is ready to be implemented the PR suffix Release
note will be passed to Software Configuration Management (SCM). SCM will then place this package
onto the TPM server, based on receiving authority from Release Management, in the Release Note. SCM
are the only team with access rights to move software onto the TPM server.

The final move into production is then made by the relevant deployment team, depending on the platform
the change is being made to (9.5). The authority and ability to move the change into production is given
to the deployment team when Release Management assigns the MSC and the release note ticket to the
deployment team.

Once the deployment is complete the PEAK ticket will be closed by the Change Owner who opened it.

4.8.10.15 Post
Implementation

4.8.10.15.1 Monitoring and Review

Fujitsu Project Managers monitor and control projects throughout their lifecycle through the following:

Weekly Releases report to Post Office Project Managers

A collated reporting pack issued to the Post Office Project Managers showing the RAG (Red, Amber, and
Green) status, Executive summary, key milestones, dependencies risks and issues for each of the
Releases that are currently in Delivery.

Monthly Joint Programme Board (with Post Office)

Presentation of a collated reporting pack to the Post Office Programme Manager and the Fujitsu
Programme Director showing the RAG status, Executive summary, key milestones, dependencies risks
and issues for each of the Releases that are currently in Delivery.

Monthly Demand Planning Forum (with Post Office)

A monthly meeting held with Post Office to look at the forward expected work load from Post Office
against the committed resources currently allocated to the Account to see if demand equals resource
supply or if any whitespace (not enough work for the committed resources).

Internal Fortnightly Releases Board

Presentation of a collated reporting pack to the Fujitsu Programme Manager showing the RAG status,
Executive summary, key milestones, dependencies risks and issues for each of the Releases that are
currently in Delivery.

Description of Fujitsu's System 49

F/1176.1/49
POL00002314
POL00002314

Fe)
FUJITSU

Internal Monthly Programme Board

Presentation of a collated reporting pack to the senior Fujitsu Post Office Management and Fujitsu
capability units showing the RAG status and Executive summary, plus any matters relevant at that time,
for each of the Releases that are currently in Delivery.

4.8.10.16 POLSAP
Application
Changes
4.8.10.16.1 POL SAP Application Changes Overview

POLSAP follows the account processes for change control.

The customer will draft a change request (CR) which will be sent from POL’s change management team
to the change management team in Fujitsu. It will send that CR to the relevant assessing team which will
assess:

e The level of resource needed for the change.
e How long it might take.
e How much it might cost.

e Whether it would impact anything else already being done for POL.

This assessment process is known as “impacting the change”, based on the information supplied. A
Change Proposal (CP) is drafted and sent to potentially affected teams to provide their impacts. This will
give an overview of what will be changed, what is not included, assumptions and a breakdown of effort in
man days.

Once impacts are collated, the CP is discussed at the Pre Change Control Board (PCCB), which meets
weekly. The PCCB is made up of various technical and functional team leaders.

Changes are allocated unique numbers and lodged within a database (PVCS) and related accordingly.
These can be viewed by all members of the team working on that project but can only be updated, edited
and actioned by members of ChM.

All Minutes from the Change Boards (PCCB and Change Control Board (CCB)) and any actions from the
same are recorded in the change history of the change vehicles in the database.

All comments and decision around the changes are also lodged in the change history.

All CP Impacts are collated into CP specific files and stored on a back-up server.

Approvals from the CCB and POL are documented in the relevant change history (9.2).

Once agreed at the PCCB and minuted as such (added to CP history in PVCS) a Commercial Terms
(CT) document is created and discussed at the Change Control Board (CCB), which meets weekly.
Assuming this is approved by the CCB and minuted as such (added to CP history in PVCS) the CT is
then sent to POL. This whole process has to be completed in 21 days from Change request received to
CT sent to POL.

POL then has a further 21 days to agree the CT and sign it. Once a signed CT is received by the Fujitsu
change management team (initially by e-mail, fax and then signed hard-copy — stored locally at first then

Description of Fujitsu's System 50

F/1176.1/50
POL00002314
POL00002314

Fe)
FUJITSU

transferred to a secure Fire-safe), this is announced to the Programme and relevant timesheet codes can
be created (aligned to the impacts included for the change) and work can begin on the change.

The change will be developed in the development client (PLD) and the relevant transports created. It will
be unit tested in this client before the request is raised to migrate the transports simultaneously to the
PLQ and PLE quality assurance clients. The transport requests are authorised by the POLSAP support
manager via emailed response to the Basis team and the actual migration is performed by the SAP Basis
Team.

The change will now be system tested by the relevant POLSAP Fujitsu team, and then integration, and
end to end tested by the dedicated Post Office testing team. The Post Office test team place their test
plans and any defects on their Quality Centre application (9.4).

Once all testing is completed and an emailed sign off has been received from the Post Office testing
manager, or change manager, Fujitsu will raise an MSC for onward migration to the Production client.

This MSC is usually given seven working days’ notice period uniess deemed an emergency change by
the customer. The MSC will be discussed at the weekly CCB meeting and will not proceed unless all sign
offs both internally and from the customer have been received and updated on the MSC. In the case of
minor application changes, they may not be discussed at the CCB, however they will appear on the CCB
agenda and identified as a minor change. The (Fujitsu) Post Office Account Operational Change team
determine which internal teams need to review each MSC, however as far as approvals go, it is the
customer — The Post Office Change Manager approval that is required to be on the MSC. This is
reflected in the notes section on the MSC itself and no change should go to Production without this
approval (9.6).

The development resource will then request the migration of the transport/s to the Production system in
line with the agreed timelines detailed on the MSC. Again this transport will need emailed authorisation
from the POLSAP support manager to the SAP Basis team and is carried out by the SAP Basis team
(9.5). The MSC process is described above under Control Objective 8.

4.8.10.17 Network Change
Management

All Network changes are considered in accordance with established Fujitsu operational practices. All
changes require an approved design, all changes must be impact assessed by all business and technical
stakeholders, an implementation plan is provided, and a change window is agreed and acted on. The
system used by Fujitsu for change management is the MSC system. Full details of the change
management are in the section above.

All documents concerning the architecture, design, service delivery, monitoring and review of POL
networks are held in the appropriate Fujitsu's document repositories Dimensions or SharePoint.

4.8.10.18 Exceptions to
Fujitsu. Change
Management
Process

The exception to this process is Reference Data which is supplied by POL for onwards transmission to

the POL Branch Counter estate via the Fujitsu network and is subject to a POL authorisation / POA to
release and having followed the POL / POA reference data testing process.

Description of Fujitsu's System 51

F/1176.1/51
POL00002314
POL00002314

Fe)
FUJITSU

4.8.11 Security

10. Control Objective 10: Controls provide reasonable assurance that access to system
resources, including computing platforms and operating systems, is restricted to properly
authorised individuals.

# Control

10.1 Client Security Policies: Security requirements for infrastructure and software are designed,
documented and agreed by both POL and Fujitsu.

10.2 Baseline Operating System Standards: Platforms in operational use have defined baseline
standards that document their set up and configurations, as agreed by Post Office Limited.

10.3 Baseline Operating System Standards Implementation: Platforms in operational use are set
up and configured in line with documented and agreed baseline standards. Variances from the
baseline standard are fully documented and appropriately approved.

10.4 User (Fujitsu) Set-up and Amendment: Fujitsu users requiring new or modified access to Post
Office Limited systems are set up appropriately and approved by an appropriate Fujitsu line
manager.

10.5 User (Fujitsu) Deletion: Access to Post Office Limited systems for Fujitsu users is removed in
a timely manner once no longer required.

10.6 Periodic User Reviews: Fujitsu and POL meet regularly in the ISMF to review whether user
access to systems remains appropriate, with changes then processed as necessary by POL.

10.7 Two-Factor Authentication: Access to Post Office Limited systems for Fujitsu users is
controlled using two-factor authentication.

4.8.11.1 Policies and Procedures

The Community Information Security Policy (CISP) provides governance and direction in information
security for those responsible for initiating, implementing or maintaining security for POL infrastructure.
The document describes end-to-end security management process and physical and technical
requirements for the in scope systems. This document is authored by POL and shared with relevant third
parties. Fujitsu is required, where appropriate, to adhere to the requirements outlined within the
document.

The SVM/SEC/POL/0003 document is Fujitsu's interpretation of the CISP document. This policy complies
with POL’s CISP; the Fujitsu Manage Information Security Policy and the Fujitsu Security Master Policy.
SVM/SEC/POL/0003 is reviewed annually and / or by request of POL as a result of a major change.
Immediate issues will be dealt with through addendums. The policy is reviewed against POL's CISP,
regulatory standards and methodologies (10.1).

The ARC/SEC/ARC/0003 document provides a technical standard to the architects and designers to
assist them in implementing and maintaining the solutions they provide to POL. The ARC/SEC/ARC0003
is reviewed in line with the above SVM/SEC/POL/003; changes in the latter would result in changes
required in the former.

4.8.11.2 General System Security Settings

Each Operating System and Databases in use by Fujitsu to support both POLSAP and HNG-X (e.g.,
Windows, Red Hat Linux, Solaris, Oracle), has its own High Level Design (HLD) documentation in place.
This sets out the required settings and configuration specific to that Operating System (OS) or Database
(DB) at a high ‘requirement driven’ level. For example, the document might specify that Red Hat Linux
servers are required to disallow remote shell access attempts (10.2).

Description of Fujitsu's System 52

F/1176.1/52
POL00002314
POL00002314

Fe)
FUJITSU

A corresponding Low Level Design (LLD) document details the OS or DB specific configuration settings
needed to meet the requirements set out within the HLD document. These configuration settings are fully
documented at a granular level, for example including extracts of OS / DB configuration code and
initialisation files (10.3).

Both the Operating System / Database HLD and LLD are subject to mandatory review and must be
approved by relevant approval authorities documented within Dimensions. All new device builds must
conform to specifications set out within the HLD and LLD. Deviations again must be reviewed, risk
assessed and approved by POL prior to configurations being implemented or updated.

New devices must be set up in line with the HLD for the required OS / DB. If an HLD does not exist (for
example if a new server type is being implemented), an HLD document must first be created, reviewed
and approved by the individuals defined in the Reviewers and Approvers Role Matrix. This document is
owned and managed by the Fujitsu Document Manager. This document is reviewed upon changes to in
key members of staff, i.e., major document owners, as well as on an annual basis.

4.8.11.3 Platform Physical Design (PPD) Document

Each infrastructure element is initially set up from an agreed baseline configuration. Elements of the
infrastructure (for example servers) are grouped by type — based on the role they perform within the IT
environment — this is defined within Platform Hardware Instance List which is managed and maintained
by Infrastructure Lead on the Post Office Account. An example of this is ‘ACD’, a server type for servers
providing directory services for support staff. Each server type has its own technical requirement, and a
PPD document is created by the Solution Architects detailing these requirements. The PPD sets out
exact hardware specifications, software requirements and configuration requirements for that particular
device type.

In short, the PPD sets out the exact requirements that a server must cater for prior to it being set up.
Before a server is set up, the PPD must be reviewed and approved by the individuals defined in the
Reviewers and Approvers Role Matrix.

There is entry for each server instance within Platform Hardware Instance List stored within Dimensions
and this also includes a link to the PPD that was used to initially set up that server. Note that this is a
historic document, and remains a record of the initial server configuration rather than necessarily
reflecting its current state.

4.8.11.4 Technical Interface Specification Document

As part of a project where a POL third party is involved, both POL and the third party agree a technical
interface specification that defines the connectivity between the third party and Fujitsu managed
infrastructure. This document is held within Dimensions, once formally agreed by Fujitsu, POL and
relevant third parties. This is a historical document that is updated upon changes in requirements of the
discussed interface. Changes will have to be agreed by Fujitsu, POL and relevant third parties.

4.8.11.5 Baseline Implementation

Acombination of the aforementioned documents dictates the initial configuration of a server added to the
Fujitsu POL account infrastructure - this initial configuration is scoped out by the solution architects. It is
then the responsibility of the network architects to register application software and products to the
identified hardware. A baseline is then sourced and configured using the aforementioned documentation.
This configuration is uploaded into Dimensions. This step in turns creates a Package Virtual Baseline
(PVB) for the platform. The discussed platform is then set for “Ready for Build” within Dimensions.

The task is then handed over to the Integration Team. It is the responsibility of this team to convert the
discussed PVB into a Deployment Package Virtual Baseline (DPVB). This includes a number of
packaging exercises, as well as rigorous unit testing. Once a DPVB is established, server definitions are

Description of Fujitsu's System 53

F/1176.1/53
POL00002314
POL00002314

Fe)
FUJITSU

outlined by the Integration team — essentially deciding which DVPB is applied to the differing technologies
within the platform.

In order to deliver the DPVB into the Fujitsu managed POL estate, the DPVB is handed to Release
Management who are responsible for ensuring the outlined configuration is applied to the appropriate
technologies. They will formulate the release note(s) for application of the DPVB to both the test and
production environments - the team manages the overall release process from receipt of request for
delivery of PSPID / DPVB to authorising deployment for all test rigs and live. The Release Management
team act as an escalation point area for the Test team for issues falling within the Release Mechanism.

Once the relevant MSCs have been raised to issue the platform, the release note will be delivered to the
relevant Core Service Delivery Unit (Core SDU) — in this case either the Windows NT or UNIX teams. It is
the responsibility of the Core SDU to action the release note. They will apply the DPVB to the appropriate
technologies, initially to a test rig which will be handed over to the test team.

The test team will accept rig handover from Core SDU and begin their testing procedures — comprising of
composition of High Level Test Plans which will act as the base for any Error Logging and Test Reports
that are produced once testing is complete. The final sign off from the test team results in liaising with
Release Management and the Core SDU to agree deployment of fixes, top-ups or to schedule a rig
rebuild. They will also liaise with Customer Services and POL to agree deferments, if applicable.

Once testing sign off is received, the release note will then be passed back to the Core SDU will deliver
the baseline via TPM to the relevant technologies.
4.8.11.6 Changes of Configuration to Existing Infrastructure

Once a device is set up, configured, and added to the Fujitsu infrastructure following the process detailed
above, its configuration remains static until the need for a configuration change is identified. The server
configuration is not by default updated when (for example) the relating OS HLD or LLD documents are
modified. Configuration changes made to in-service devices must follow change / incident management
processes described elsewhere in this report (include obtaining approval from POL).

The exception to this rule is for the application of standard OS / DB patches and security fixes, which
Fujitsu are (in many cases) contractually obliged to apply. Such patches do not bypass approval, as they
are reviewed by a Patch Approval Board (PAB) (attended by POL) prior to their application.

Changes to in-service infrastructure configurations can be identified in a number of ways, for example:
e Change Projects.
e New Application Development.
e Patch Application.
¢ — Infrastructure Refresh.

« Fixes identified through the Incident Management process.

Note that these changes follow the formal change and incident management processes.

4.8.11.7 Password Settings

Password configuration requirements are defined in the relevant baselines for infrastructure components.
If a component cannot implement the relevant baseline this exception is notified to POL who must
authorise it. Passwords are stored in a one-way encrypted form and are protected against substitution or
dictionary attack.

Description of Fujitsu's System 54

F/1176.1/54
POL00002314
POL00002314

Fe)
FUJITSU

Passwords shall conform to the following criteria (unless POL has approved a deviation from these
criteria):

e Where passwords are used for authentication, the user must be forced to change the initial
password before any other access to the system is permitted.

e Passwords must expire in 30 days.

e Re-use of the same password must not be permitted for either a specified time or until at least 4
other passwords have been used.

« Passwords must be a minimum of 7 characters long and must be alphanumeric (i.e., a mix of
letters and numbers). There must not be more than two consecutive identical characters. The
password must not be the same as the username.

e After 3 consecutive unsuccessful attempts to log-on, the user must be locked out for at least 30
minutes or until reset by an administrator.

« In general, system users must be subject to the controls specified above. The following
exceptions are permitted

e The username and password used to automate application login may be held in ‘clear’ i.e.,
readable format or unencrypted, if it is only accessible to authorised operational management
staff for that system and the potential damage from misuse of that username is minimised.

The password may expire less frequently than the 30 days for human users where suitably obscure
passwords are used, e.g., strong passwords consisting of upper case, lower case characters, numbers
and symbols and the risk of external access to such accounts is very low however this concession must
be documented and approved by the POL CISO.

4.8.11.8 User Administration

The principle of “least privilege” is used to restrict the access rights of users whether human or non-
human. The User Access Process details how access is gained to both physical and technical assets
within the PO Account and Fujitsu supporting functions and is managed by a POA Security Operations
Team (SOT).

4.8.11.9 New Joiners / Transfers

Detailed below are the steps that must be followed for an individual who is new to Fujitsu Services and
joining the POA and these are shown in the Figure 1.0 below. Users who have transferred internally onto
the Post Office Account from another part of the Fujitsu business will follow a similar process, illustrated
in Figure 1.1 (10.4).

Description of Fujitsu's System 55

F/1176.1/55
POL00002314
POL00002314

Fe)
FUJITSU

Figure 1.0 Diagram of User System Access Process Flow for New Joiner:
Post Office New Joiners

Figure 1.1 Diagram of User system access flow for Moving, Transferring, and Amending access
a me:

ERICIRIO
process approved

The Line Manager contacts POA Security Operational Team (SOT) and requests that system access
forms are provided. The POA SOT provides the New User Access Forms to the Line Manager and
requests they are completed and returned to the POA SOT both as a soft and hard copy. These forms
are filed and stored in the security operations secure room and kept for audit purposes.

POA SOT check the form is completed correctly, and in line with PO Account Security Policy. POA SOT
then notifies the relevant system owners (Windows NT Team, Unix Team, POLSAP Team) via an e-mail
containing the completed request form and a TFS call is raised and suspended whilst access is granted.

Once System Owners configure the user they will update the TFS call on completion of this configuration.
POA SOT shall then close the TFS call and update the register.

Description of Fujitsu's System 56

F/1176.1/56
POL00002314
POL00002314

Fe)
FUJITSU

4.8.11.10 Leavers
The steps that are followed for an individual leaving Fujitsu Services and the PO Account are shown in
the Figure 1.2 Diagram of User system access flow for Leavers (10.5).

The Line Manager contacts POA SOT by voice prompt and e-mail, providing the leaver's details and
requesting a revocation form. The POA SOT provides the revocation form and asks that it is completed
and returned to the POA SOT both as a soft and hard copy. These forms are filed and stored in the
security operations secure room and kept for audit purposes.

POA SOT check the form is completed correctly, and in line with PO Account Security Policy. POA SOT
notify the relevant system owners (Windows NT Team, Unix Team, POLSAP Team) via an e-mail
containing the completed removal form and a TFS call is raised and suspended whilst access is
removed.

Once System Owners remove the user they will update the TFS call on completion of this configuration.
POA SOT shall then close the TFS call and update the register.

Figure 1.2 Diagram of User system access flow for Leavers
Post Office Leavers Process — Leavers with immediate effect — Follow red steps

4.8.11.11 Information Security Monthly Forum

The Information Security Monthly Forum (ISMF) is a formalised monthly forum where Post Office and
Fujitsu Security production risk and control concerns / issues are raised and progressed with the
necessary stakeholders. The purpose of the meeting is to:

e To help ensure the early identification of issues together with timely & effective resolution by
those attendees with functional responsibility.

e Review Security Operations monthly reporting on common security contro! objectives e.g., Patch
& Vulnerability Management; Anti-virus / Malware; Configuration Management of Security
Infrastructure etc. as agreed between Fujitsu and Post Office.

The Security Operations monthly reporting pack will be compiled and circulated one week in advance of
the forum by Fujitsu. This pack will include:

e Agenda for current forum.

e Minutes from previous forum and progress against previous actions.

e Open or new Security Risks and Issues.

e Changes to Information Security Architecture relating to joint venture products.

Description of Fujitsu's System 57

F/1176.1/57
POL00002314
POL00002314

Fe)
FUJITSU

e Upcoming developments.
e Active Directory User Access Review (10.6).

4.8.11.12 User Authentication Technologies

User authentication is two-factor, including dynamic password authentication (known as an iKey) against
an external database - TACACS+, RADIUS or similar technology for access (10.7). Once authenticated,
remote access connections are established via a VPN using an encrypted session. Authorised users
should not provide their login token (iKey token) or associated information to anyone at any time for any
reason, other than to surrender it when no longer required or when their relationship with Fujitsu has
ceased as an employee.

The exception to this would be if they needed to have their account or token reset or a temporary
passcode allocated. If this was the case then this information could be given to an authorised person
(i.e., member of the Security Operations team) to validate the user.

iKey access is granted to those users who support the HNG-X platform / application. Users must connect
to SSN Terminal Servers in order to access to HNG-X platforms within the data centre. As such, all HNG-
X SSN Servers must be a member of the Windows AD (MSAD Domain). Remote users must be granted
the Allow log on through Terminal Services right, or be a member of Remote Desktop Users group.

4.8.12 Access to databases, data files and programs

11. Control Objective 11: Controls provide reasonable assurance that access to databases, data
files and programs is restricted to properly authorised individuals.

# Control

444 Patch Management: In-scope platforms are maintained with vendor released security updates
and patches in line with agreed procedures and timescales.

11.2 System Administrators: Access to perform system administrator functions restricted to
appropriate Fujitsu personnel required to have this level of access by their role.

11.3 Database Administrators: Access to administer POL databases is restricted to appropriate
Fujitsu personnel required to have this level of access by their role.

11.4 Administration Tools and System Utilities: Access to administration tools and system utilities
on Post Office Limited infrastructure is restricted to appropriate Fujitsu personnel required to
have this level of access by their role.

11.5 Unauthorized changes are monitored: The TripWire system is configured to monitor and alert
on changes made to in-scope applications and underlying data.

11.6 Access to Data Files / Programs Access is restricted to production program and data files
through the use of user groups to restrict and allow access.

4.8.12.1 Patch management

Fujitsu's POA SOT and the Service Delivery teams subscribe to relevant vendor information feeds to
receive details of patches from vendors that provide critical operating systems, applications, databases
and network equipment to POL.

Details of patches are reviewed and documented in the Patch Deployment Spreadsheet. This
spreadsheet will be held within Sharepoint.

The Deployment Spreadsheet is reviewed by the SDUs and Application Support teams on a regular
basis; they assess whether the patch applies to equipment they manage. They will then update the

Description of Fujitsu's System 58

F/1176.1/58
POL00002314
POL00002314

Fe)
FUJITSU

spreadsheet with the reasoning behind their decision to apply or not to apply a patch in readiness for
submission to the Path Approval Board (PAB (11.1)).

The PAB consists of members of the Infrastructure Services division, Applications Solutions Team,
Operational Security Team and a POL Security representative. The PAB is held on a monthly basis. The
PAB will review the Patch Deployment Spreadsheet and seek agreement on the patch set to be deployed
and in what timescale (e.g., deploys patches as an emergency fix or include at next release).

4.8.12.2 System Administrators & Database Administrators

The user management database utilised by the POA SOT holds details of all the support teams and the
system access the team resources have (11.2 and 11.3). This document is monitored on a regular basis
to provide assurances against contractual requirements and obligations against the Unit's Roles
Responsibilities and Access Requirements.

Access and resources in the teams are reviewed and confirmed as appropriate on a monthly basis by the
line managers (11.4 and 11.6). The POA SOT then completes the monthly access report for privileged
users and presents at the monthly ISMF with POL.

Throughout the POL infrastructure the same authoritative source of authentication and authorisation data
is used to manage access control for all operational support users. The purpose of this approach is to:

1) Reduce the number of passwords required for support purposes.

2) Help ensure better audit and logging facilities for authentication and authorisation.

3) Streamline the process for adding, changing and removing authentication and authorisation
information.

4) Provide a standard method of authentication and authorisation throughout the estate.

Database access control also requires individual role-based accounts for each class of user, both for
controlling the actions a user can perform and for helping to ensure administrative and other actions are
traceable to an individual to provide a valid and informative audit trail.

The main classes of database users will be:

1) Application - Accounts used by applications for database access to either Oracle or SQL Server
Databases.

2) System Administrators — Operational support users with responsibility for managing the database
systems.

3) Database Administrators —- Operational support users with responsibility for specific databases.

4) Non-administrative Database support users - Operational support users with responsibility for
specific databases.

4,8.12.3 Unauthorised changes are monitored & reviewed

Tripwire compares files and directories against a baseline database of file locations, dates modified, and
other data. It generates the baseline by taking a snapshot of specified files and directories in a known
secure state. After creating the baseline database, Tripwire compares the current system to the baseline
and reports modifications, additions or deletions (11.5). Tripwire helps to ensure the integrity of critical
system files POA SOT who monitor the console.

On a monthly basis, the POA SOT reviews alerts that have been raised from Tripwire. Monthly reports
are produced detailing alert statuses and a root cause analysis for each alert. The reviews are available
for POL management, in order to monitor unauthorised attempts to modify datasets. The Tripwire alert

Description of Fujitsu's System 59

F/1176.1/59
POL00002314
POL00002314

Fe)
FUJITSU

report is included in the ISMF Security Operational Reports. In cases where no alerts are raised within
the month, a report may not be produced and this will be noted within the next month's report.
4.8.13 External threats and access violation management

12. Control Objective 12: Controls provide reasonable assurance that networks and system
resources are protected from external threats and access violations are detected, reported

and investigated.
# Control
6.4 Major & Security Incident review: Once a Major or Security Incident is resolved there is a

formal closure of the incident and a review including, if applicable a Root Cause Analysis.

12.1 Configuration Access: Access to set-up and configure firewalls is restricted to appropriate
Fujitsu personnel required to have this level of access by their role.

12.2 Configuration Changes: Changes to firewall configuration are managed using the standard
Fujitsu MSC process including authorisation, testing (wnere deemed appropriate) and approval
of changes before they are implemented.

12.3 Anti-virus software: Anti-virus software is installed on critical networked Windows and Red Hat
Linux platforms as agreed with POL. Installed anti-virus software is up to date in line with agreed
contractual requirements.

4,8.13.1 Overall network security design

Within each Data Centre, the POL network is segmented following the Security Domain model. The
Security Domain model provides a framework for the network architecture and designs, such that the flow
of data around the network is controlled following the principle of least privilege. The applied
segmentation is furthered developed within the Network Architecture document and Network High Level
and Low Level Design documents — stating the specific details that have been configured on the network.

The purpose of network segmentation is to reduce the scope of a potential attack. By restricting the
‘attack surface’ to a limited number of systems, damage caused as a consequence of an attack, can be
kept to a minimum.

The network segmentation is achieved using a combination of physical and virtual controls. Dependent
on the Security Domain and specific contractual agreements with third parties, the network segmentation
is enforced using VLANs, IP's and Stateful Inspection Firewalls, ACLs, AES Encryption and physical
separation.

Network segmentation will also be used to provide separation between environments. Each test
environment will be separated from other test environments, as well as from the live environment. This
will be enforced through the use of Firewall and Router access control lists, VLAN restrictions and user
and network access control. These controls will be monitored using the event management system to
verify that access control lists and configuration settings are not changed in a way that may allow a
network path from one environment to another except under strictly controlled conditions.

4.8.13.2 Firewalls

Direct access between the internet and systems or system components in areas of the network that have
been classified as “sensitive” is prohibited and all traffic is routed through a DMZ - a logical subnetwork
that contains and exposes a Fujitsu's external-facing services to the internet. Firewalls are configured to
perform stateful inspection in that only established connections are permitted to connect to the network.

Perimeter firewalls and router components are configured to masquerade internal addresses to the
internet using NAT technologies.

Description of Fujitsu's System 60

F/1176.1/60
POL00002314
POL00002314

Fe)
FUJITSU

Access to set-up and configure firewalls is restricted to appropriate Fujitsu personnel required to have
this level of access by their role (12.1). MSC is used to raise rule set changes for the firewall
configurations (12.2). Upon operational change process invocation an appropriate deployment plan is
uploaded to the file store within the MSC system which is subjected to peer review prior to deployment,
this plan is also used to facilitate change regression if appropriate.

Should any protocols that have been deemed as insecure be required to be included in the configuration
then additional information must be supplied that details the security features that have been
implemented.

4.8.13.3 Rule Set Review Process

In order to verify the current configuration of network security enforcement devices that manage the POL
estate, all configurations are manually inspected at least every 6 months.

Authorised firewall configuration elements in relation to network security enforcement are in document
reference SVM/SEC/STD/1985 stored securely in Dimensions. This document is compared against the
appropriate device's active configuration helping to ensure these are in line with the standards in the
document. SVM/SEC/STD/1985 is updated when operational configurations are changed through the
completion of MSCs. As such SVM/SEC/STD/1985 reflects the secure elements of appropriate
operational devices at all times.

If discrepancies are found between SVM/SEC/STD/1985 and the operational configuration these are
investigated to help ensure the environment has not been compromised and ascertain why correct
process was not followed in relation to inconsistencies.

The review page of SVM/SEC/STD/1985 is updated every 6 months with the new version and contains
the date carried out, name and reason for review. This document is stored in a secure area in
Dimensions.

4.8.13.4 Anti-Virus Software

The ESET Anti-virus product is a real-time and performs automatic, scheduled and manual scans on all
managed clients, in order to identify and contain and eliminate the spread of malicious code (12.3).

For the in-scope Wintel systems, real-time file system protection is implemented. All files are scanned for
malicious code at the moment they are opened, created or run on the computer.

For the in-scope Linux systems (DXC, DGI and DGE), an on demand daemon has been created using
the ESET SDK that can scan files as they are transferred through the respective platforms. ESET is not
installed on all Linux systems, by agreement with POL.

In cases where a specific vulnerability or virus stream constitutes a high risk threat to the systems, a
scheduled scan is set up from the management console and the client configuration updated accordingly.

ESET provides regular updates of both signatures and engines. For engine updates, these are
distributed to clients using the existing Tivoli software distribution management system after having been
verified and tested in the test environment to help ensure that no system functionality is compromised by
the updated.

The ESET AV System is based on a central Management Server (ERAS) where all the updates
(signatures) are stored and managed. ERAS receives the updates from ESET, via an Intemet
connection, and makes them available for clients to install.

Description of Fujitsu's System 61

F/1176.1/61
POL00002314
POL00002314

Fe)
FUJITSU

Whenever a virus, vulnerability or suspicious event is detected, the ESET Antivirus system will react
according to a configuration that will be enabled using ESET antivirus policies. The workflow describing
the process followed is as follows:

1. Windows
a. On access (read, copy, execute, etc) every item will be scanned by the AV system.

2. Linux
a. OnDemand scanning is performed by the ESET Scanner Daemon.

3. If a threat is identified, the AV system will try to automatically clean the item. If the cleaning is
successful, an alert event is logged in the ESET Notification manager - which has the ability to
take actions when configurable alerts are identified within the ESET environment. This
functionality provides an integration point between ESET and the Tivoli Netcool event system.
The ESET Notification Manager is monitored proactively by the POA SOT.

4. If the cleaning is not successful, an alert event is logged and an incident is raised in TBSM, with
alerts going through to SMC start a remediation action (refer to Control 6 for further information
around the incident process):

a. If development is needed to solve the issue, a PEAK is raised.

b. A fix is produced and assessed according to normal procedure:
i. If the fix is rejected, a risk is raised on the Risk register.
ii. If the fix is approved, the fix is deployed on Test and Live environment.

The following is a diagram of the workflow to be applied. Tivoli and KELS are integrated with ESET in
order to automate the alerting process in the event of a High/Critical virus being identified by ESET, and
start the appropriate remediation activities.

Possible raise
PEAK if
development
is required

/ \
la \
Alett to
Tivoli A
and
Virus }-—Yes—B>I raise call I} ——>I
via TFS
and
raise
Incident

Assess Deploy
fe Fr Deploy-by OE

Reject fix

Raise Risk on
Risk Register

4.8.14 Remote Access

Description of Fujitsu's System 62

F/1176.1/62
POL00002314
POL00002314

Fe)
FUJITSU

Control Objective 13: Controls exist to provide reasonable assurance that remote access is
appropriately restricted to authorised personnel.

# Control

10.4 User (Fujitsu) Set-up and Amendment: Fujitsu users requiring new or modified access to Post
Office Limited systems are set up appropriately, and approved by an appropriate Fujitsu line
manager.

10.7 Two-Factor Authentication: Access to Post Office Limited systems for Fujitsu users is
controlled using two-factor authentication.

13.1 Remote Access Authorisation: The use of Radius Authentication and CHAP (Challenge
Handshake Authentication Protocol) for Counters accessing the data centre ensures that access
is restricted to approved devices.

As noted above, remote access for individual users is managed through issuing iKey tokens.

CHAP is used to authenticate the Post Office counters at the outlets when they connect to the data
centre. Each counter is authenticated using a dedicated RADIUS server instance for network device
access, with different CHAP credentials per Branch Router (13.1).

Counters and external devices accessing the data centre can only do so via an ADSL connection utilising
the CHAP (Challenge Handshake Authentication) Protocol. CHAP requires that both connecting parties
(the data centre and the counter) know the plaintext of a secret string of text (the CHAP secret). During
the ‘handshaking’ phase, (which must take place prior to any other data being communicated), the data
centre ‘challenges’ the counter with a unique calculated value, and expects a particular response.

This expected response must be generated by the counter using both the CHAP secret, and the data
centre challenge value, helping to ensure that:

e The counter is the same device that sent the initial connection request.

« The counter is an authorised device, as only authorised devices have knowledge of the CHAP
secret.

Note that the CHAP secret is:
e Never shared across the network as part of the handshaking process.
« Securely stored, always in obfuscated or encrypted form.
e 11 characters long and complex.

« Changed at least every two years.

If the counter returns an unexpected value, the connection is immediately terminated. For added security,
the handshaking process is repeated at set time intervals, requiring the counter to re-authenticate with the
data centre regularly. The CHAP secret is not known by or accessible to users, as it is automatically and
randomly generated offline, and encrypted prior to being supplied to specific servers that act as
‘distributors’ of the secret.

RADIUS (remote authentication dial in user service) provides an additional layer of security, through a
centralised Authentication, Authorisation, and Accounting management system. A RADIUS server within
the network keeps track of devices approved to connect to the data centre, along with their credentials.
These are stored in a secure embedded database. Connection attempt credentials are compared to the
RADIUS server, which allows or denies access to the data centre based on whether the connecting
device is listed as approved within the database.

Description of Fujitsu's System 63

F/1176.1/63
POL00002314

POL00002314
2
FUJITSU
5. Not used
Description of Fujitsu's System 64

F/1176.1/64
POL00002314
POL00002314

Fe)
FUJITSU

6. Complementary User Entity Controls

In designing its system, Fujitsu has contemplated that certain complementary controls would be
implemented by POL to achieve certain control objectives included in this report. The complementary
user entity controls are as follows:

e Organisation and Administration
Controls should be established to:

o Evaluate that contracted processes and controls have been implemented.

o Evaluate and monitor Fujitsu's delivery of services for conformance with contractual
obligations.

o Designate their own internal client representative to determine adequate maintenance of
controls over Fujitsu services.

o Implement and monitor proper segregation of duties exist at POL owned / managed
facilities.

e Physical Access
Controls should be established to:

o Appropriately restrict access to terminals, workstations, and other computing equipment
at POL sites, which can also allow access to infrastructure located in the Fujitsu data
centre.

o Request and approve employee access to computer rooms in a fashion that limits access
to only those employees requiring it based on job function.

« Computer Operations
Controls should be established to:

o Approve additions, modifications or deletions to scheduled jobs if necessary.

o Inform Fujitsu of critical scheduled jobs and the appropriate escalation procedures are
associated to those jobs.

o Define SLAs for availability, capacity and performance management in the agreement
with Fujitsu.

o Review and take action on reports on availability, capacity and performance
management, supplied by Fujitsu, where required.

o Data Retention requirements are documented and agreed with Fujitsu.

o Periodically, request restores from backup to validate that programs, files and data are
recoverable.

« Networks
Controls should be established to:

o Review network performance statistics (e.g., response time, availability) periodically and
that the service levels received are in compliance with the service levels specified in their
contracts.

o Compare metrics in network availability and performance reports to user experience to
determine whether availability and performance statistics are accurate.

e Change Control
Controls should be established to:

co Ensure that application changes follow a formal change process and are approved.

o Ensure that requests for Fujitsu to implement changes to systems come from authorised
individuals.

o Ensure that a POL representative participates in, or has input to, the system
development activities that are relevant to POL, including participation in testing
activities, if applicable.

Description of Fujitsu's System 65

F/1176.1/65
POL00002314
POL00002314

Fe)
FUJITSU

o Ensure that POL individuals who are permitted to authorise firewall changes have an
understanding of the impact the change could have and carry out a risk assessment prior
to authorising a change.

e Logical Access
Controls should be established to:

o Establish and implement procedures and documentation for authorising user access to
terminals and application functions.

o Periodically, review access granted to users at the application layer, to confirm that such
access remains appropriate based on users’ job functions.

o Establish and implement procedures to ensure additions, changes, and deletions in client
organisations’ personnel and their associated job responsibilities are authorised and
communicated to Fujitsu in a timely manner (if applicable). Where it is the responsibility
of POL to remove users, POL should implement procedures to review that all leavers are
removed in a timely manner.

o Where Fujitsu is asked to implement compensating controls to address situations where
infrastructure cannot be configured to meet agreed baselines (e.g. additional monitoring
controls), ensure they are comfortable that such controls are being operated whether it
be by Fujitsu or POL's employees or contractors.

o Establish and implement procedures to prohibit the use of shared user IDs or user IDs
whose passwords are not changed on a regular basis.

o Advise POL employees regularly of the importance of security and to report suspicious
personnel, transactions or activity to management.

o Establish and implement procedures to review operating system configurations to ensure
settings are providing adequate security, particularly where security parameters are
maintained at the original client settings when transferred to Fujitsu.

e Applications Development
Controls should be established to:

o Document, review and sign off user requirements by the business, prior to commencing a
change.

o Ensure that requests for Fujitsu to implement changes to POL systems come from
authorised individuals.

o Ensure that where POL or its other suppliers administer POL infrastructure, the
application's developers have appropriate access.

o Review reporting received from Steria about the use of the SCC4 transaction to unlock
the SAP production environment and to check that these are part of changes that POL
has authorised.

The list of client control considerations presented above is not a comprehensive list of all internal controls
that should be applied by POL. Other internal controls may be needed at POL.

Description of Fujitsu's System 66

F/1176.1/66
POL00002314
POL00002314

Fe)
FUJITSU

7. Description of Control Objectives, Controls,
Tests and Results of Tests

7.1. Testing Performed and Results of Tests of Entity-Level
Control

In planning the nature, timing and extent of our testing of the controls specified by Fujitsu, we considered
the aspects of Fujitsu's control environment, risk assessment processes, information and communication
and management monitoring procedures and performed such procedures as we considered necessary in
the circumstances.

7.2 Control Objectives, Control Activities, Testing
Procedures and Results of Testing

On the pages that follow, the description of control objectives and the controls to achieve the objectives
have been specified by, and are the responsibility of, Fujitsu. The description of the testing performed by
Ernst & Young and the results of tests are the responsibility of the service auditor.

The service auditor's examination was limited to the IT general controls relevant to Fujitsu's operations
supporting IT services provided to POL to support the POLSAP and HNG-X applications. Accordingly,
the service auditor expresses no opinion on the operating effectiveness of any aspects of application
processing and application controls, individually or in the aggregate. POL may need to gain information
about application processing and application controls through other means.

Description of Tests and Results 67

F/1176.1/67
89/VOZbL/A

FUSITSU

POL00002314

POL00002314

7.2.1 Control Objective 1

7 :
i

Te

chats

Results of Tests

Control Objective 1: Controls provide reasonable assurance that access to the data centre and facilities with computer equipment, storage media and program

documentation is restricted to properly authorised individuals.

1.1 Data Centre Access

Data centre specific physical access security
policies and procedures to control access to the
data centre and other sensitive areas, including
computer equipment and storage media, are
implemented. These are made available to
Fujitsu staff via the intranet.

Through discussion with management, identified the
documents that define the data centre specific physical
access security policies and procedures for the in scope
data centre. Observed that these documents existed and
were held on the Fujitsu intranet.

Determined whether these were available to relevant
Fujitsu employees.

No deviations noted.

1.2 Access Within the Data Centre

Access beyond the security desk is protected by
a key-card system that restricts individual
access to specific data processing areas.
Security management has determined
appropriate levels of physical access to the data
centre, which is based on the roles and
responsibilities of staff. Staff requiring access to
the data centre must complete an access form,
which must be signed as approved by the line
manager responsible for the zones requested.

Observed the computer rooms and determined whether
access doors are equipped with a card key lock or
equivalent to restrict access to sensitive areas.

Selected a sample of Fujitsu new starters to the site and
determined that the access granted has been authorised in
accordance with the defined procedure.

As there have been no new starters to the
Fujitsu data centre for the period covered by
this report, no occurrences of this control
noted.

1.3 CCTV

The data centre is controlled and monitored
through the use of CCTV video cameras. Video
cameras are placed at strategic locations around
the perimeter of the building to help ensure that

coverage of the data centre is obtained.

Observed that CCTV video cameras are placed at key
locations around the data centre to monitor activity.
Observed that these screens are monitored by security
staff at the data centre.

No deviations noted.

Description of Tests and Results

68
69/V OZbL/A

FUSITSU

POL00002314

POL00002314

Control Objective 1: Controls provide reasonable assurance that access to the data centre and facilities with computer equipment, storage media and program
documentation is restricted to properly authorised individuals.

1.4 Security Guards

Security guards are present at the data centre
24 hours per day, seven days per week. The
data centre can only be accessed through a
central area.

Through discussion with management and observation,
determined that security guards (or equivalent) are in
place at the data centre (24 hours a day and seven days
per a week) and that the data centre can only be accessed
through a central point (front desk), which has security
guards (or equivalent) in place.

No deviations noted.

1.5 Data Centre Visitors

Visitors are required to sign in at the reception
area and temporary badges are issued. Visitors
must have been pre-notified to data centre
security by a Fujitsu employee.

Observed that visitors are granted access based on the
pre-approval and that they are required to sign in at the
reception area and temporary badges are issued.

No deviations noted.

1.6 Failed Access Monitoring

Attempts to enter restricted areas without using
authentication devices are denied and a security
alert is triggered and logged. Data centre
management proactively follows up on security
alerts that are triggered.

Inspected a sample of the monthly security alert logs
reviews performed by Fujitsu and determined whether
these were reviewed and followed up.

No deviations noted.

1.7 Review of User Access within the Data
Centre

Periodic reviews are performed of users who
have access to the data centre to help ensure
that their access rights are appropriate.

Obtained a sample of periodic reviews of access levels
and determined whether assigned access levels remain
appropriate based on job responsibilities and appropriate
actions had been taken as necessary.

No deviations noted.

Description of Tests and Results

69
OL/V'OLbL/A

FUSITSU

POL00002314
POL00002314

Ci is La
oe jedbyFujitsu

_

Testing Performed by Emmet é Young lip I

esate oF Tests

Control Objective 1: Controls provide reasonable assurance that access to the data centre and facilities with computer equipment, storage media and program
documentation is restricted to properly authorised individuals.

1.8 Deletion of User Access

The managers of the various delivery teams are
responsible for notifying the local site facilities
team of terminations or transfers of their direct
reports. Upon notification of employment
changes, access through the security access

control system is revoked.

Selected a sample of Fujitsu employees who were
terminated during the period under review and determined
whether their access to the data centre had been revoked
in the access control system in a timely manner.

No deviations noted.

Description of Tests and Results

70
LV OLE WA

FUSITSU

POL00002314

POL00002314

7.2.2 Control Objective 2

aq i

Control Objective 2: Controls provide reasonable assurance that computer equipment and facilities are protected from damage by fire, flood and other environmental

hazards and maintenance agreements are in place.

2.1 Fire Suppression

Fire detection and suppression devices, such as
hand-held fire extinguishers, are strategically
placed throughout the entire data centre.

Observed the existence of fire detection and suppression
devices (e.g., gaseous fire suppression devices, hand-held
fire extinguishers, smoke detectors and monitoring
devices, dry pipe sprinklers and two-hour firewall).

No deviations noted.

2.2 Maintenance Schedule
Periodic inspection and maintenance is

performed on protection devices, sensors and
alarm systems.

Enquired about the monitoring and inspection controls
used to protect computer equipment from environmental
hazard.

Inspected the maintenance schedules (including backup
generators, UPS, fire detection and suppression & heating,
ventilation and air-conditioning) and service reports for a
range of devices supporting environmental monitoring
controls in each data centre and determined whether
equipment had been maintained during the period.

No deviations noted.

2.3 Environmental Monitoring

Smoke detectors and water, humidity and
temperature monitoring devices are installed to
detect abnormal environmental conditions.

Observed that smoke detectors and water, humidity and
temperature monitoring devices have been installed to
detect abnormal environmental conditions at each data
centre.

No deviations noted.

2.4 UPS Supply

A UPS system is installed to protect the facilities
and computer equipment from electrical power
fluctuations and outages.

Observed that a UPS system had been installed to protect
the facilities and computer equipment from electrical power
fluctuations and outages at each data centre.

No deviations noted.

Description of Tests and Results

71
CLIVOLLLA

FUSITSU

POL00002314

POL00002314

7.2.3. Control Objective 3

7 :
i

Results of Tests

Control Objective 3: Controls provide reasonable assurance that programs, files and datasets that have been identified as requiring periodic backup are backed up

and retained.

3.1 Backup Definition
The Backup High Level Design documents
define Backup and recovery requirements and
policy for the platform.

Selected a sample of platforms and determined whether
the Backup High Level Design documents for these
platforms defined backup and recovery requirements and
policy for the platforms.

No deviations noted.

3.2 Backup Toolset

Backups are performed using NetBackup or
RMAN (automated tools).

Selected a sample of platforms and determined whether
NetBackup or RMAN were installed to perform back-ups.

No deviations noted.

3.3. Backups are Written to a Secondary
Location

Backups performed are written to a separate

disk array and are simultaneously written to a
disk array at the disaster recovery site.

Selected a sample of servers and determined whether
backups performed are written to a separate disk array
and are simultaneously written to a disk array at the
disaster recovery site.

No deviations noted.

3.4 Failed Backups are Tracked and Monitored

Failed backups are signalled to the Master
Batch Scheduling system which raises events in

a generic manner to the SMC.

Selected a sample of failed backups and determined
whether these had been signalled to the Master Batch
Scheduling system which had then raised events in the
SMC.

No deviations noted.

Description of Tests and Results

72
eL/V OLE b/s

FUSITSU

POL00002314

POL00002314

7.2.4 Control Objective 4

“conta Specie by Futeu I

ia Paved en Young LP

are identified and resolved.

Control Objective 4: Controls provide reasonable assurance that processing is appropriately authorised and scheduled and that deviations from scheduled processing

4.1 Maintenance of Job Schedules
Access to amend job schedules is restricted to

appropriate Fujitsu personnel required to have
this level of access by their role.

Obtained listings of access rights within the tools used to
maintain HNG-X and POLSAP job schedules and
determined who had access to amend job schedules.
Assessed whether this access is restricted to appropriate
Fujitsu personnel required to have this level of access by
their role.

No deviations noted.

4.2 SAP Schedules are Continuously Monitored
The SAP Basis team uses the SAP GUI and
SAP transaction code SM37 to monitor the
success / failure of SAP batch jobs. The SAP
Basis team will also check and monitor the batch
job start and end times and send the daily
monitoring statistics to agreed parties.

Observed the SAP Basis team monitoring SAP schedules
and that monitoring statistics were sent to agreed parties.

No deviations noted.

4.3 Failed Job Schedules are Monitored and
Alerted

Automated alerts are configured and sent to
relevant parties upon the occurrence of a batch
job failure. These are investigated in line with
the incident management process.

Reviewed the TWS tool, which manages all batch jobs for
in scope applications, and determined that it is configured
to raise an alert if a batch job fails and to then pass this
alert to the Tivoli ITM tool.

See control 6.6 for testing of alert handling.

No deviations noted.

Description of Tests and Results

73
pLIVOLL A

FUSITSU

POL00002314
POL00002314

7.2.5 Control Objective 5

aq i

Testing Pato y inst Young LP

are captured and investigated.

Control Objective: 5 Controls provide reasonable assurance that system availability, performance and capacity are routinely monitored to ensure that potential issues

5.1 SAP Performance Monitoring

The SAP Basis team regularly monitors table
space and databases to help ensure there is
sufficient system availability and capacity and
that potential issues are captured and
investigated.

Observed the SAP Basis team monitoring SAP table space
and databases and where applicable, issues are captured
and investigated appropriately..

No deviations noted.

5.2 SAP Capacity Alerting

An automated alert will be generated in the
Solution Manager System (PLM) if the table
space is more than 95% filled and the SAP
Basis team will monitor and review these alerts.

Identified a SAP server that exceeded the defined alerting
parameters and determined whether the expected alerts
had been generated and sent to the SAP Basis team.

No deviations noted.

5.3 SAP Availability Alerting

Automated alerts are configured in Solution
Manager to advise if a part of the system is
shutdown / not available for users. These alerts
go to the SMC team and they will create an
incident.

Determined whether automated alerts are configured in
Solution Manager to advise if part of the system is
shutdown / not available for users. Followed through an
alert and determined if this was sent to the SMC team who
then created an incident if appropriate.

No deviations noted.

5.4 HNG-X Performance Monitoring

The Tivoli ITM proactively monitors CPU,
Memory, Disk utilisation and capacity of internal
services on these platforms, raising alerts for
investigation by the SMC as appropriate.

Determined whether the Tivoli ITM tool was implemented
on the HNG-X platforms and whether it is configured to
look at the CPU, memory, disk utilisation and capacity of
internal services on these platforms.

Selected an alert from the Tivoli ITM tool and determined if
this went to the SMC for review.

No deviations noted.

Description of Tests and Results

74

SLIVOLL L/S

FUSITSU

POL00002314
POL00002314

F
L

Control Objective: 5 Controls provide reasonable assurance that system availability, performance and capacity are

are captured and investigated.

routinely monitored to ensure that potential issues

5.5 HNG-X Capacity and Availability Monitoring

The Tivoli ITM tool proactively monitors the
availability of Wintel and Unix platforms, feeding
platform availability data to Tivoli Business
Service Manager (via Netcool Omnibus) about
the availability of platforms. Tivoli Business
Service Manager presents this data in a
business context to the SMC, highlighting
service affecting issues.

Obtained evidence of Tivoli
determined whether:

*° These showed that the Tivoli
availability and capacity of servers.

e Thresholds were defined which, if breached, would
send alerts as described.

See control 6.6 for testing of alert handling.

ITM configurations and

ITM tool monitors

No deviations noted.

5.6 Monitoring of Service Delivery
A monthly Service Review Book is provided to
POL to review its agreed Service Levels. Within
this book are details of capacity, availability and
incident management performance.

Selected a sample of months and determined whether the:
Monthly Service Review Book is provided to POL to
review its agreed Service Levels.

e Monthly Service Review Book contains details of
capacity, availability and incident management
performance.

No deviations noted.

Description of Tests and Results

75
OLIV OLE L/S

FUSITSU

POL00002314

POL00002314

7.2.6 Control Objective 6

[eentrers Speciied by Fujtau

_____Testing Performed by Ernst & Young LLP

Resale of Tess

Control Objective 6: Controls provide reasonable assurance that significant operations incidents are adequately reported, tracked, monitored through resolution and

resolved timely.

6.1 Incident Policies and Procedures are in
Place

Fujitsu has documented policies and procedures
for managing incidents impacting the in scope
applications which are available via CafeVik to
Fujitsu teams.

Through discussion with management, identified the
documents that define the incident management for the
POL account.

Determined whether these were available to relevant
Fujitsu employees.

No deviations noted.

6.2 Incident Prioritisation

Incidents are assigned a priority in accordance
with the severity levels agreed with POL.

Selected a sample of incidents and determined whether
these had been assigned a priority in accordance with the
severity levels agreed with POL.

No deviations noted.

6.3 Incident Resolution
Incidents are handled in a timely manner, as per
priority.

Selected a sample of incidents and determined whether
these had been handled in a timely manner, as per priority.

No deviations noted.

6.4 Major & Security Incident Review

Once a Major or Security Incident is resolved
there is a formal closure of the incident and a
review including, if applicable, a Root Cause
Analysis.

Selected a sample of Major and Security Incidents and
determined whether a Formal Closure of the Major Incident
took place and a review of the Incident, including, if
applicable, a Root Cause Analysis.

As there have been no Major or Security
Incidents in the period covered by this report,
no occurrences of this control noted.

6.5 Incident Reporting

On a daily basis, the Fujitsu HSD / IMT reviews
the number and severity of outstanding incidents
in TFS.

Discussed with management that the Fujitsu HSD / IMT
had reviewed the number and severity of outstanding
incidents in TFS.

No deviations noted.

Description of Tests and Results

76
LLIVOLE LA

FUSITSU

POL00002314
POL00002314

iby Emst a YoungilP I

ee

resolved timely.

Control Objective 6: Controls provide reasonable assurance that significant operations incidents are adequately reported, tracked, monitored through resolution and

6.6 Alert Handling

The Tivoli ITM and Netcool Omnibus automate
the collection of events and using Tivoli
Business Service Manager highlight areas of
concern to the SMC.

Selected a sample of events and determined whether the
Tivoli ITM and Netcool Omnibus tools automated the
collection of events and used Tivoli Business Service
Manager to highlight areas of concern to the SMC.

No deviations noted.

Description of Tests and Results

7
SL/VOLbL/A

FUSITSU

POL00002314
POL00002314

7.2.7. Control Objective 7

“Controls Speciod by Fate

gq i

esting Pvormed by Est & Young

ne

Control Objective: 7 Controls provide reasonable assurances that networks are managed to contractual and site requirements, monitored ‘ef availabilty and
response times and issues are identified, tracked and resolved.

5.6 Monitoring of Service Delivery

A monthly Service Review Book is provided to
POL to review its agreed Service Levels. Within
this book are details of capacity, availability and
incident management performance.

Selected a sample of months and determined whether the:

e Monthly Service Review Book is provided to POL to
review its agreed Service Levels.

e¢ Monthly Service Review Book contains details of
capacity, availability and incident management
performance.

No deviations noted.

7.1 Network Performance Criteria

Network availability and performance
requirements are clearly defined between Fujitsu
and POL in the Network Service descriptions
and network service is measured and monitored
using these agreed service levels.

Through discussion with management, we confirmed that
documents that define the network availability for the POL
account are in place.

Determined whether these were available to relevant
Fujitsu employees.

No deviations noted.

7.2 Network Change Management

Network changes are managed using the
standard Fujitsu MSC _ process __ including
authorisation, testing (where deemed
appropriate) and approval of changes before
they are implemented.

Selected a network change and determined whether this
change was managed using the standard Fujitsu MSC
process including authorisation, testing (where deemed
appropriate) and approval of the changes before it was
implemented.

No deviations noted.

7.3 Network Availability Monitoring

Network availability is monitored using several
tools, which send automated alerts to the
Network Operating Support Service Team
(NOSS) if key components are unavailable, or if

traffic levels breach predefined thresholds.

Observed the HP Openview, CACTI and Tivoli Netcool
tools monitoring network availability, including that they are
configured to send automated alerts to the Network
Operating Support Service Team (NOSS).

No deviations noted.

Description of Tests and Results

78

POL00002314
POL00002314

FUSITSU

( oe Ey S Pe he ui So SS . Ss SOE . eS
I Gontrols Specitied by Fujitsu I [by Emst & Young LLP Results of Tests
Control Objective: 7 Controls provide reasonable assurances that networks are managed to contractual and site requirements, monitored for availability and

response times and issues are identified, tracked and resolved.

7.4 Network Incident Management Selected a network incident and determined whether it was No deviations noted.
Incidents relating to network availability are I Managed using standard incident management procedures
managed using standard incident management I Used on the POA, and are included in the standard
procedures used on the POA, and are included I incident management reporting to POL.

in the standard incident management reporting
to POL.

6L/V OLE

Description of Tests and Results 79
Os/VOZbL/A

FUSITSU

POL00002314
POL00002314

7.2.8 Control Objective 8

“Controls Specied by Fats

"Fein Promo by int & Young UP

implemented and documented.

Control Objective 8: Controls provide reasonable assurance that modifications to system software and networks are auersed (esd apace: Bosal

8.1 Change Management

The MSC toolset is used to manage all changes
with a joint decision between Fujitsu and POL as
to which parts of the tool are relevant for a
change.

Selected a sample of changes and determined whether the
MSC toolset had been used to manage these changes in
accordance with the defined procedures.

No deviations noted.

8.2 Change Approval

All changes must be authorised by the Fujitsu
Duty Manager or technical bridge, with approval
being documented in the MSC system. Changes
that cause major service interruption must also
be authorised by the Change Advisory Board
(CAB), with approval being documented in the
meeting minutes and within the MSC system.

Selected a sample of changes and determined whether
these had been authorised, with approval being
documented in meeting minutes and/or within the MSC
system.

No deviations noted.

8.3 Emergency Changes

Any change deemed necessary in order to
resume live service will be agreed and
authorised and documented during the incident
along with updates to POL at an agreed
timeframe dependent on the severity of the

incident.

Selected a sample of emergency changes and determined
whether these had been agreed and authorised and
documented during the incident along with updates to POL,
at an agreed timeframe dependent on the severity of the
incident.

No deviations noted.

Description of Tests and Results

80

Le/POZb WA

FUSITSU

POL00002314
POL00002314

7.2.9 Control Objective 9

“ConrlsSpecied by Fults

___Testing Performed by Ernst & Young LLP

Control Objective 9: Controls provide reasonable assurance that new or modified application software development efforts are allvoraed ested Tr appraved Bonet

implemented and documented.

9.1 System Development and Maintenance
Policies and Procedures

Fujitsu has a formal Systems Development Life
Cycle (SDLC) which incorporates phases
including Initiation, Requirements, Definition,
Design, Development, Deployment and
Maintenance.

Through discussion with management, we confirmed that
the documents that define the SDLC for the POL account
are in place.

Determined whether these were available to relevant
Fujitsu employees, and whether these included phases
including:

Initiation

e Requirements
¢ Definition

e Design

e Development
e Deployment

e Maintenance.

No deviations noted.

9.2 Change Control Board

Depending on the nature, changes must either
be approved by the Change Control Board
(CCB) before progressing into development or
by the PEAK Targeting Forum (PTF).

Selected a sample of changes and determined whether
these had been approved by either the Change Control
Board (CCB) or the PEAK Targeting Forum (PTF) before
progressing into development.

No deviations noted.

9.3 Design Proposal

Projects are outlined in a Design Proposal
(DPR) that is held in DOORS or Sharepoint and
is reviewed and approved by POL as well as

Fujitsu management.

Selected a sample of projects and determined whether
these had a Design Proposal (DPR) document that had
been reviewed and approved by POL as well as Fujitsu
management.

No deviations noted.

Description of Tests and Results

81
ze/VOLbbA

FUSITSU

POL00002314
POL00002314

Bani Special by jis I
fo led I 7 ie

ae
a

_Teting oid ne Young LLP

.

ES HE ( ae ce
.

implemented and documented.

Control Objective 9: Controls provide reasonable assurance that new or modified application software development efforts are authorised tested, approved, properly

9.4 Change Testing

Changes are tested in line with the defined
procedure.

Selected a sample of changes and determined whether,

where applicable, for these changes:

e Testing had been done by the relevant Fujitsu team
and Post Office team.

e Test plans had been placed in the Quality Centre
application.

e The POL testing manager had emailed to indicate their

approval that all testing has been successfully
completed.

No deviations noted.

9.5 Ability to Implement Changes

Only appropriate individuals have access
needed to move code builds between
environments or promote transports to live.
Segregation of duties is enforced between users
able to develop and implement changes.

Selected a sample of application servers and determined
who had access to implement changes, and assessed
whether these users were appropriate and that
segregation of duties is enforced between users able to
develop and implement changes.

No deviations noted.

9.6 Approval to Implement Changes

POL approval is required to promote software
changes to the live environment. Approval is
captured within the relevant MSC.

Selected a sample of changes and determined whether
PO approval to implement the change was recorded within
the relevant MSC.

No deviations noted.

Description of Tests and Results

82
es/P OLE b/s

FUSITSU

POL00002314

POL00002314

7.2.10 Control aon 10

7 c

Festina Perey Ens Young LLP

Control Objective 10: conse erage easreble assurance that access to system resources, including computing platforms and ASE Seene is restricted ©

properly authorised individuals.

10.1 Client Security Policies

Security requirements for infrastructure and
software are designed, documented and agreed
by both POL and Fujitsu.

Through discussion with management, identified the
documents that define the information security architecture
and procedures for the POL account.

Determined whether these were available to relevant
Fujitsu employees, and whether these had been reviewed
and approved in line with contractual requirements.

No deviations noted.

10.2 Baseline Operating System Standards

Platforms in operational use have defined
baseline standards that document their set up
and configurations, as agreed by Post Office
Limited.

Selected a sample of platforms in operational use and
determined whether baseline standards had been defined
and agreed with POL.

No deviations noted.

10.3. Baseline Operating System Standards
Implementation

Platforms in operational use are set up and
configured in line with documented and agreed
baseline standards. Variances from the baseline
standard are fully documented and appropriately
approved.

Selected a sample of platforms in operational use and
determined whether the platforms had been set up and
configured in line with documented and agreed baseline
standards.

Determined whether variances from the baseline standard
had been documented and approved in accordance with
defined procedures.

No deviations noted.

10.4 User (Fujitsu) Set-up and Amendment

Fujitsu users requiring new or modified access
to Post Office Limited systems are set up
appropriately, and approved by an appropriate

Fujitsu line manager.

Selected a sample of Fujitsu users given access to POL
systems during the period under review and determined
whether these users had been set up in accordance with
the access request, and that the request had been
approved by an appropriate Fujitsu line manager.

No deviations noted.

Description of Tests and Results

83
POL00002314
POL00002314

FUSITSU

aay Objective 10: Controls TESTES EEE assurance that access to system resources, including computing platforms and operating systems, is restricted to
properly authorised individuals.

10.5 User (Fujitsu) Deletion Selected a sample of Fujitsu staff that left the POL account I No deviations noted.
Access to Post Office Limited systems for I during the period under review and determined whether
Fujitsu users is removed in a timely manner I their access had been removed on a timely basis.

once no longer required.

10.6 Periodic User Reviews Selected a sample of ISMF meeting minutes and No deviations noted.
Fujitsu and POL meet regularly in the ISMF to I determined whether roles and access rights had been
review whether user access to systems remains I 'eviewed as defined.

appropriate, with changes then processed as
necessary by POL.

10.7 Two-Factor Authentication Observed Fujitsu staff logging on to POL systems and No deviations noted.
Access to Post Office Limited systems for I determined whether this required two factor authentication.
Fujitsu users is controlled using two-factor
authentication.

pSV OLL b/s

Description of Tests and Results 84
S8/LOLbb/S

FUSITSU

POL00002314

POL00002314

7.2.11 Control Objective 11

Testing Pertormed by mst Young LLP

Control Objective 11: Controls provide reasonable assurance that access to databases, data files, and programs is restricted to properly authorised individuals.

11.1 Patch Management

In-scope platforms are maintained with vendor
released security updates and patches in line
with agreed procedures and timescales.

Selected an in scope platform and determined whether the
most recent patches had been applied to the server
operating system.

Determined that patches are applied using the same
change process and controls as tested for Control
Objective 8.

No deviations noted.

11.2 System Administrators

Access to perform system administrator
functions restricted to appropriate Fujitsu
personnel required to have this level of access
by their role.

Selected a sample of servers and determined whether
access to perform system administrator functions was
restricted to appropriate Fujitsu personnel required to have
this level of access by their role.

No deviations noted.

11.3 Database Administrators

Access to administer POL databases is
restricted to appropriate Fujitsu personnel
required to have this level of access by their
role.

Selected a sample of in scope databases and determined
whether access to administer those databases was
restricted to appropriate Fujitsu personnel required to have
this level of access by their role.

No deviations noted.

11.4 Administration Tools and System Utilities

Access to administration tools and system
utilities on Post Office Limited infrastructure is
restricted to appropriate Fujitsu personnel
required to have this level of access by their
role.

Selected a sample of platforms and determined whether
access to administration tools and system utilities on Post
Office Limited infrastructure is restricted to appropriate
Fujitsu personnel required to have this level of access by
their role.

No deviations noted.

Description of Tests and Results

85
POL00002314
POL00002314

FUSITSU

_____Comtrois Specitiod by Fujitsu dbyEmst&Youngite I Results of fests

Control Objective 11: Controls provide reasonable assurance that access to databases, data files, and programs is restricted to properly authorised individuals.

11.5 Unauthorized Changes are Monitored Selected a sample of application servers and determined No deviations noted.
The TripWire system is configured to monitor I whether the TripWire system was configured to monitor
and alert on changes made to  in-scope and alert on changes made to in-scope applications and
applications and underlying data within the I underlying data.

HNG-X estate.

11.6 Access to Data Files / Programs Selected a sample of platforms and determined whether I No deviations noted.
Access is restricted to production program and I access to significant production program and data files
data files through the use of user groups to I Was appropriately restricted.

restrict and allow access.

98/ OLE b/s

Description of Tests and Results 86
LZ8/VOLL L/S

FUSITSU

POL00002314

POL00002314

7.2.12 Control Objective 12

Results of Tests

detected, reported and investigated.

Control Objective 12: Controls provide reasonable assurance that networks and system resources are protected from external threats and access violations are

6.4 Major & Security Incident Review

Once a Major or Security Incident is resolved
there is a formal closure of the incident and a
review including, if applicable, a Root Cause
Analysis.

Selected a sample of Major and Security Incidents and
determined whether a Formal Closure of the Incident took
place including a review of the Incident with, if applicable,
a Root Cause Analysis.

As there have been no Major or Security
Incidents in the period covered by this report,
no occurrences of this control noted.

12.1 Configuration Access

Access to set-up and configure firewalls is
restricted to appropriate Fujitsu personnel
required to have this level of access by their
role.

Selected a sample of firewalls and determined who had
access to set up and configure these devices. Assessed
whether personnel with these rights were appropriate.

No deviations noted.

12.2 Configuration Changes

Changes to firewall configuration are managed
using the standard Fujitsu MSC _ process
including authorisation, testing (where deemed
appropriate) and approval of changes before
they are implemented.

Selected a change to firewall configuration and determined
whether this:

e had been authorised, tested (where deemed
appropriate) and approved before being implemented;
and

* was managed using the MSC process tested under
Control Objective 8.

No deviations noted.

12.3 Anti-virus Software

Anti-virus software is installed on critical
networked Windows and Red Hat Linux
platforms as agreed with POL. Installed anti-
virus software is up to date in line with agreed
contractual requirements.

Selected a sample of servers and determined whether AV
software was installed and up to date.

No deviations noted.

Description of Tests and Results

87
88/VOZbL/A

FUSITSU

POL00002314
POL00002314

7.2.13 Control Objective 13

"Tang Patomed by inst 8 Young LP

7

Control Objective 13: Controls exist to provide reasonable assurance that remote access is appropriately restricted to authorised personnel.

10.4 User (Fujitsu) Set-up and Amendment

Fujitsu users requiring new or modified access
to Post Office Limited systems are set up
appropriately, and approved by an appropriate
Fujitsu line manager.

Selected a sample of Fujitsu users given access to POL
systems during the period under review and determined
whether these users had been set up in accordance with
the access request, and that the request had been
approved by an appropriate Fujitsu line manager.

No deviations noted.

10.7 Two-Factor Authentication

Access to Post Office Limited systems for
Fujitsu. users is controlled using two-factor
authentication.

Observed Fujitsu staff logging on to POL systems and
determined whether this required two factor authentication.

No deviations noted.

13.1 Remote Access Authorisation

The use of Radius Authentication and CHAP for
Counters accessing the data centre ensures that

access is restricted to approved devices.

Obtained network documentation and determined whether
Radius Authentication and CHAP for Counters validation is
in place for remote access requests.

No deviations noted.

Description of Tests and Results

88