POL00028208 - Schedule A11 - Acceptance Procedure for Core System (undated)

Evidence on official site

SCHEDULE A11 - ACCEPTANCE PROCEDURES-

11

1.2

1.3

21

ACCEPTANCE PROCEDURE FOR CORE SYSTEM

ACCEPTANCE TESTING

‘The Acceptance Procedure for Acceptance of the Core System (“CSR
Acceptance”) shall be as set out in this Schedule.

in respect of CSR Acceptance there will be agreed:-
(i) a set of Acceptance Criteria;

(ii) a set of Acceptance Specifications (the “CSR Acceptance Specifications”)
as described in Annex 1 to this Schedule;

(iii) a set of Acceptance Tests (the “CSR Acceptance Tests”) being Acceptance
Trials or Acceptance Reviews as described in Annex 1 to this Schedule;

(iv) an Acceptance timetable including, inter alia, a CSR Core Observation
Period;

(v) a Final Deadline for CSR Acceptance; and

(vi) a CSR Operational Trial Review Period (being the three week period
immediately following the end of the CSR Core Observation Period).

For the purposes of paragraph 1.2 above:-

1.3.1 all Acceptance Specifications have been agreed and are contained in the
CCNs listed in Annex 2 to this Schedule; and

1.3.2 the Acceptance timetable for CSR shall be consistent with Schedule BO?

and the Final Deadline for CSR Acceptance and the CSR Operational
Trial Review Period shall be as set out in Schedule BO9.

REQUIREMENTS FOR CSR ACCEPTANCE

Subject to any extension pursuant to paragraph 2.4 of this Schedule CSR.
Acceptance will occur once:-

(i) the CSR Acceptance Tests have been carried out successfully;

did the CSR Core Observation Period and the CSR Operational Trial Review
Period have expired;

POL00028208
POL00028208
2.2

2.3

2.4

2.6

(iii) the thresholds referred to in paragraph 2.2 of this Schedule have been
met as at the end of the CSR Core Observation Period taking into
account all substantive faults raised by POCL beyond those defined in
the CSR Acceptance Specifications, as described in paragraph 7,1(d) of
this Schedule; and

(iv) a timetable has been agreed between the parties to resolve all
outstanding faults falling within the category described in paragraph
7.1(b) of this Schedule (“category (b) faults”).

The thresholds will not be met if in respect of CSR Acceptance there are:

(i) one or more high severity deficiencies as categorised in paragraph
7.1(a) of this Schedule ( “category (a) faults”);

(ii) more than 20 category (b) faults; or

(iii) more than 10 category (b) faults in respect of any one CSR Acceptance
Specification.

It is acknowledged that if a CSR Acceptance Test is repeated following
corrective work by the Contractor, POCL shall have the right to test for and
raise new faults which may be caused by that corrective work or may come to
light only as a result of that corrective work.

It is agreed that, notwithstanding the provisions of paragraph 2.1 of this
Schedule, if at the end of the CSR Core Observation Period all CSR Acceptance
Tests have been carried out and the thresholds referred to in paragraph 2.2 of
this Schedule have not all been met, POCL shail permit the Contractor to repeat
the relevant CSR Acceptance Tests in the two week period following the end of
the CSR Core Observation Period provided that POCL is given sufficient
opportunity to review the results of such CSR Acceptance Tests to its reasonable
satisfaction prior to the end of the CSR Operational Trial Review Period.

Subject to paragraph 2.3 of this Schedule, once all Acceptance Tests have been
successfully carried out and the CSR Core Observation Period has expired, no
new Acceptance Incidents may be raised. For this purpose, a “new Acceptance
Incident” is an Acceptance Incident which had not occurred before the end of
the relevant CSR Core Observation Period and does not include Acceptance
Incidents which occurred before the end of the CSR Core Observation Period
but were not reported until after that date, provided always that POCL shall
report to the Contractor an Acceptance Incident within seven days of the
relevant POCL test manager identifying or being notified of the same.

If, at the end of the CSR Operational Trial Review Period the parties do not
agree as to whether the Core System Release should be accepted, the provisions
of paragraph 6 of this Schedule shall apply.

POL00028208
POL00028208
3.1

3.2

3.3

3.4

5.1

5.2

POL00028208
POL00028208

_ CONSEQUENCES OF FAILURE TO ACHIEVE CSR ACCEPTANCE

If CSR Acceptance is not achieved at the end of the CSR Operational Trial
Review Period the Contractor shall be entitled to a period of three months in
which to remedy the defaults, which (subject to paragraph 6.9 of this Schedule)
it shall do at its own expense. Upon the expiry of that period, or at such earlier
date as the parties shall agree, the Core System Release shall be re-submitted in
its entirety for Acceptance testing (the “Second CSR Acceptance Test”).

If CSR Acceptance is not successfully achieved at the end of the Second CSR
Acceptance Test then POCL shall have the right to terminate the Codified
Agreement, but without prejudice to all other remedies available to POCL under
the Codified Agreement and otherwise and without prejudice to paragraph 3.3
of this Schedule.

Schedule L5 of this Codified Agreement (liquidated damages to a maximum of
13 weeks of delay) shail apply on failure to achieve CSR Acceptance by 30th
September, 1999 and on failure to achieve the CS Completion Date by 31st
March, 2001 (as such date is adjusted to reflect any delay in CSR Acceptance),
in both cases where such delay is due to Default by the Contractor.

If CSR Acceptance has not been achieved by the Final Deadline for CSR
Acceptance as listed in Schedule BO9 then POCL shall be entitled to serve a
notice upon the Contractor under this paragraph, whereupon the Contractor
shall be deemed to have failed the Second CSR Acceptance Test in accordance
with paragraph 3.2 of this Schedule.

CONSEQUENCES OF ACHIEVING CSR ACCEPTANCE

Upon Acceptance of the Core System Release the Release Authorisation Board
shall decide whether or not to authorise national rollout of the Core System.

APPOINTMENT OF EXPERT
The parties have agreed to appoint an expert (the “Expert”) as soon as
reasonably practicable to assist in resolving disputes relating to CSR

Acceptance.

The Expert shall be Peter Copping of PA Consulting or, if he has a conflict of
interest or is unavailable, such other partner of PA Consulting as shall be:

qi) qualified to resolve such disputes;
(ii) independent of both parties; and

Gii) approved by both parties, such approval not to be unreasonably
withheld.
5.3

5.4

6.1

6.2

6.3

6.4

6.5

6.6

6.7

In the event that no other partners of PA Consulting shall be available and meet
the Criteria in paragraphs 5.2(i) and (ii) above, the Expert shall be appointed at
the request of POCL or the Contractor by the President for the time being of the
Institute of Electrical Engineers so long as such appointee shall meet the criteria
in paragraphs S.2(i) and (ii) above.

The Expert shal! act as an expert and not an arbitrator and his fees shall be
borne by the parties in equal shares.

ACCEPTANCE DISPUTES

If paragraph 2.6 of this Schedule applies and/or POCL and the Contractor do
not agree on:

(i) the CSR Acceptance Specifications;
(ii) whether an event or occurrence is an Acceptance Incident; or
(iit) the assigned severity of an Acceptance Incident;

the parties will refer such dispute (the “Dispute”) to the Expert to obtain initial
guidance. The parties do not expect that the identification and notification of
the Dispute, reference of the Dispute to the Expert and obtaining his initial
guidance should take longer than seven days.

Once the Expert has given to the parties his initial guidance on the Dispute, the
Managing Director of POCL and the Commercial Director of ICL shall meet and
attempt to resolve the Dispute with the advice and guidance of the Expert.

If the Dispute is not resolved during the meeting pursuant to paragraph 6.2
above, then the Expert shall be required to make a decision (the “Decision”) as
to how the Dispute should be resolved.

Once the Decision has been made, the Managing Director of POCL and the
Commercial Director of ICL shall meet to review and respond to the Decision.

The Decision shall be binding unless vetoed by POCL in accordance with
paragraph 6.6 below.

POCL may veto the Decision if:

fa} POCL disagrees with the Decision and provides to the Contractor written
reasons for such disagreement; and

(b) asserts a Veto Ground (as defined in paragraph 6.8 of this Schedule).

If POCL vetoes the Decision, the Managing Director of POCL and the
Commercial Director of ICL shall meet and attempt to resolve the Dispute. If

POL00028208
POL00028208
6.8

6.9

they fail to resolve the Dispute within three working days of either party
requesting a meeting for that purpose then the Chief Executives of the Post
Office and of ICL shall meet and attempt to resolve the Dispute. However,
unless and until otherwise agreed, the veto will stand.

Each of the following shall be a Veto Ground, namely if the issue:-

(i) materially affects POCLs ability to settle with clients in a timely and
accurate way;

(ii) materially affects POCLs ability to transact with sub-postmasters in a
timely and accurate way;

(iii) is likely to materially and adversely affect POCL customers in areas
covered by service level agreements;

(iv) materially affects critical operational! processes necessary for the running
of POCL;

(v) materially compromises the integrity of Post Office accounting systems;
or

(vi) is likely to lead to the qualification of Post Office accounts or those of its
subsidiary companies.

If POCL vetoes a Decision and that Decision was in favour of the Contractor
then sub-paragraph 3.1 of this Schedule shall apply save that the direct costs of
and associated with such extra work as shall be required as a consequence of
the exercise of the veto shall be dealt with in accordance with paragraph 6.10
of this Schedule. If, but for POCL vetoing a Decision in favour of the Contractor,
CSR Acceptance would have been achieved, and the Acceptance Test in
question was the Second CSR Acceptance Test, it shall be deemed to have been
the first.

The direct costs of and associated with the extra work referred to in paragraph
6.9 of this Schedule shall initially be borne by POCL. However, POCL shall be
entitled to refer the Expert's decision in relation to the Dispute to an arbitrator
in accordance with paragraphs 6.11 and 6.12 of this Schedule. If the arbitrator
rules in favour of POCL in respect of the Dispute then the Contractor shall,
within seven days of the arbitrator’s decision, refund to POCL the amount so
borne by POCL, together with interest thereon from the date when the Dispute
was referred to the arbitrator until the date of payment thereof at a commercial
rate determined by the arbitrator.

Any matter referred to arbitration by POCL pursuant to paragraph 6.9 of this
Schedule shall be finally settled under the Rules of Arbitration of the
International Chamber of Commerce (“ICC”) by one arbitrator appointed in

POL00028208
POL00028208
6.12

71

7.3

accordance with the said rules (or under such other arbitration procedure as the
parties shall agree).

The place of arbitration shall be London, the governing law of the arbitration
shall be English and the language of the arbitration shall be English.

ACCEPTANCE DEFICIENCIES

The Contractor shall analyse each Acceptance Incident in accordance with the
guidelines defined in the relevant Acceptance Specification, and categorise each
Acceptance Incident within the following principles: _ ~

(a) failure to meet an Acceptance Criterion essential to the Deliverable or
POCL Service shall be designated a high severity deficiency;

(b) failure to meet an Acceptance Criterion which is highly desirable for the
Deliverable or POCL Service shall be designated a medium severity
deficiency;

(c) failure to meet an Acceptance Criterion which is desirable for the
Deliverable or POCL Service shall be designated a low severity
deficiency;

(d) an Acceptance Incident which does not relate to an Acceptance
Criterion, but which identifies a failure to meet any other obligation
under this Codified Agreement and, in the reasonable opinion of POCL,
represents a substantive fault equivalent to, and categorised according
to, part (a), (b) or (c) of this paragraph; or

(e) none of the above.

Other than for category (e) above, the analysis of an Acceptance Incident shall
not of itself be sufficient to resolve the Acceptance Incident. Resolution of an
Acceptance Incident shall only occur when the deficiency or fault has been
corrected by the Contractor and the relevant parts of the Acceptance Test have
been repeated without further category (a), (b) or (c) Acceptance Incidents
arising.

POCL may, at its sole discretion and in accordance with Clause 612, waive in
writing the resolution of an Acceptance Incident and deem it resolved.

POL00028208
POL00028208
21

is)
to

3.1

POL00028208
POL00028208

Annex 1 to Schedule All
ACCEPTANCE TESTS
An Acceptance Test shall take the form of one or more Acceptance Trials as
defined in paragraph 2 of this Annex, one or more Acceptance Reviews as
defined in paragraph 3 of this Annex, or combinations thereof.
ACCEPTANCE TRIALS
An Acceptance Trial shall consist of one or more of the following:
(a) inspection of any system used to provide a POCL Service;

(b) demonstration of any system used to provide a POCL Service;

(ec) running a real or simulated operational workload on any system used to
provide a POCL Service;

(d) monitoring provision of a POCL Service over a trial period to verify
performance to the Service Levels specified in the POCL Service.

The scope and conduct of any Acceptance Trial proposed shall be documented
in the Acceptance Specification and the Acceptance Trial shall not commence
until the Acceptance Specification has been approved by POCL.
ACCEPTANCE REVIEWS

An Acceptance Review shall consist of one or more of the following:

(a) inspection of a Deliverable (e.g. a document) by one or more competent
reviewers nominated by POCL;

(b) inspect by one or more competent reviewers nominated by POCL of
documentary evidence that a POCL Service has been provided;

(ce) a meeting between POCL and the Contractor at which one or more of
the following occur:

i. Deliverables or documentary evidence are inspected;
it. a presentation is given by the Contractor;

iii. the results of prior inspections, visits or presentations are
reviewed and the outcome agreed
POL00028208
POL00028208

3.2 The scope and conduct of any Acceptance Review proposed shall be
documented in an Acceptance Specification and the Acceptance Review shall
not commence until th: Acceptance Specification has been approved by POCL.
POL00028208
POL00028208

Annex 2 to Schedule All

CCNs Containing Agreed Acce ptance Specifications for CSR

0338

0340

0342

0343

0344

0345

0346

0361

0362

0370

0378

0379

0380

0381

0382

0383

0388

0458