oO ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 7
FUJITSU COMMERCIAL IN CONFIDENCE
Document Title: ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3
Document Reference: REQ/GEN/ACS/0002
Release: Release specific
Abstract: This document comprises the Acceptance Report for HNG-X
Acceptance Gateway 3. It provides details of the Acceptance status
of all POL requirements associated with this Acceptance Gateway
and is for submission to the HNG-X Acceptance Board.
Document Status: DRAFT
Author & Dept: Dave Cooke
HNG-X Acceptance Manager
External Distribution: Neil Williams, Phil Norton, Mark Burley, David Smith,
Liz Tuddenham, lan Trundell
Security Risk No
Assessment Confirmed
Approval Authorities:
lame Role Signature Date
Phil Norton POL Requirements and See Dimensions for record
Acceptance Manager
Dave Cooke FS HNG-X Acceptance Manager See Dimensions for record
See HNG-X Reviewers/Approvers Matrix (PGM/DCM/ON/0001) for guidance on who should approve.
© Copyright Post Office Limited GCNIANEOT. bi Seema Ref REQ/GEN/ACS/0002
2009 Version: 0.2
UNCONTROLLED IF PRINTED OR LOCALLY _ Date: 02-Nov-2009
STORED PageNo: 1 of 33
POL00032633
POL00032633
oO ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 “i
FUJITSU COMMERCIAL IN CONFIDENCE
0 Document Control
0.1 Table of Contents
DOCUMENT CONTROL
Table of Contents
Document History
Review Detail:
Associated Documents (Internal & External)
Abbre'
Glossary
Changes Expe: .
Accuracy ....
Security Risk Assessment ..
INTRODUCTION...
ic Io
IBIS In BE I= ISISISISISISISISIE
roles pol [e0 Loo Na fom lends feo lo I
Acceptance Board assessment checklist for AG3
REVIEW OF STATUS OF ACCEPTANCE CRITERIA
Functional Requirements — Use Case:
Non-Functional Requirements and Criteria
.2.1 Deferred Test status
Assessment of Status
No Run status
Not Complete Status
Not Covered / Zero defects statu:
Deferred Failed statu:
Failed Status .
be
joo
3 REVIEW OF STATUS OF ACCEPTANCE INCIDENTS...........cseceeee
3.
3.1 Acceptance Incident Aggregation...
3.2 Acceptance Incidents arising from Agreed Deferrals
3.2.1 Acceptance Incident details for type AI-AD ......
3.2.2 Aggregated Acceptance Incident details for type Al-AD
3.3 Acceptance Incident arising from non-testable criteria 27
3.3.1 Acceptance Incident details for type AI-NT... 27
3.3.2 Aggregated Acceptance Incident details for tyoe Al-NT 27
3.4 Acceptance Incident arising from Testable criteria 28
3.4.1 Acceptance Incident details for type AI-TS...
3.5 Acceptance Incident total...
A APPLICABLE POL REQUIREMENTS AND ACCEPTANCE CRITERIA............ 30
© Copyright Post Office Limited GCNIANEOT. bi Seema Ref REQ/GEN/ACS/0002
2009 Version: 0.2
UNCONTROLLED IF PRINTED OR LOCALLY _ Date: 02-Nov-2009
STORED PageNo: 20f 33
POL00032633
POL00032633
ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 af
COMMERCIAL IN CONFIDENCE
(ee)
FUJITSU
B DEFINITION OF ACCEPTANCE METHODS...
C DEFINITION OF ACCEPTANCE INCIDENT SEVERITY...
D ACCEPTANCE BOARD RECOMMENDATION OPTIONS
0.2 Document History
Version No. Date Summary of Changes and Reason for Issue Associated Change -
CP/PEAK/PPRR
Reference
0.1 28-OCT-2009 Initial version
02 02-NOV-2009 Updated following joint FS / POL review
0.3 Review Details
See HNG-X Reviewers/Approvers Matrix (PGM/DCM/ION/0001) for guidance on completing the lists below. You
may include additional reviewers if necessary, but you should generally not exclude any of the mandatory reviewers
shown in the matrix for the document type you are authoring.
Review Comments by (date by which comments should be returned)
Review Comments to
Mandatory Review
Role
Name
HNG-X Programme Manager Alan D'Alvarez
HNG-x Solution Architect Jim Sweeting
POL HNG-X Programme Manager Mark Burley
POL HNG-X Requirements Manager Phil Norton
POL HNG-X Acceptance Manager Neil Williams
POL HNG-X Design Authority lan Trundell
HNG-X Testing Manager
Debbie Richardson
POL HNG-X Testing Manager
Lee Farman
Optional Review
Role Name
Head of Programmes — Private Sector Business Mike Wood
Unit
Head of Change and IS. Dave Smith
RMGA Commercial Director Guy Wilkerson
© Copyright Post Office Limited GCNIANEOT. bi Seema Ref REQ/GEN/ACS/0002
2009 Version: 0.2
UNCONTROLLED IF PRINTED OR LOCALLY _ Date: 02-Nov-2009
STORED Page No: 3 0f 33
POL00032633
POL00032633
oO ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 "4
FUJITSU COMMERCIAL IN CONFIDENCE
POL HNG-X Senior Contracts and Service Manager Liz Tuddenham
Issued for Information — Please res' this
distribution list to a minimum
Position/Role Name
(*) = Reviewers that retumed comments
0.4 Associated Documents (Internal & External)
Reference Version Date Title Source
PGM/DCM/TEM/0001 I 5.0 03 June 2009 RMGA HNG-X Generic Document Dimensions
(DO NOT REMOVE) Template
Schedule B6.3- HNG-X Acceptance I Dimensions
Process
Unless a specific version is referred to above, reference should be made to the current approved
versions of the documents.
0.5 Abbreviations
Abbreviation Definition
0.6 Glossary
Term Definition
0.7 Changes Expected
© Copyright Post Office Limited GCNIANEOT. bi Seema Ref REQ/GEN/ACS/0002
2009 Version: 0.2
UNCONTROLLED IF PRINTED OR LOCALLY _ Date: 02-Nov-2009
STORED PageNo: 4 0f 33
POL00032633
POL00032633
oO ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 “i
FUJITSU COMMERCIAL IN CONFIDENCE
0.8 Accuracy
Fujitsu Services endeavours to ensure that the information contained in this document is correct but, whilst every
effort is made to ensure the accuracy of such information, it accepts no liability for any loss (however caused)
sustained as a result of any error or omission in the same.
0.9 Security Risk Assessment
Security risks have been assessed and it is considered that there are no security risks relating specifically to this
document.
© Copyright Post Office Limited CEAMANEOT, th RememaSEEE Ref REQ/GEN/ACS/0002
2009 Version: 0.2
UNCONTROLLED IF PRINTED OR LOCALLY _ Date: 02-Nov-2009
STORED PageNo: 5 of 33
POL00032633
POL00032633
o ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3
FUJITSU COMMERCIAL IN CONFIDENCE
1. Introduction
This document comprises the HNG-X Acceptance Report to the HNG-X Acceptance Board for the
assessment of the progression through Acceptance Gateway 3 (AG3) — Readiness for Pilot.
The basis for HNG-X Acceptance is defined in Schedule B6.3 and some sections are reproduced within
this report.
The POL Requirements and Criteria, contained in the HNG-X Requirements Catalogue - POL DOORS
archive v1.42, and associated with AG3 are contained in Appendix A.
The definition of the HNG-X Acceptance Methods is contained in Appendix B.
The definition of the Acceptance Incident Severity is contained in Appendix C.
1.1. Scope
The purpose of this Acceptance Board is: -
‘To agree the Acceptance status of the relevant Release (HNG-X Release 1 for AG3) and provide a
recommendation to the ‘Joint Release Authorisation Board’.’ The proposed options that this Board can
select from are described in Appendix D.
This recommendation is based on an assessment of the status of the applicable POL Requirements and
Acceptance Criteria and of the stage progression criteria for AG3 are described in Schedule B6.3.
The primary assessment concerns the status of any Acceptance Incidents as follows:-
Progression through HNG-X Acceptance Gateway 3 shall occur once all of the following have
been satisfied for the HNG-X Acceptance Criteria allocated to achieving progression through the
respective HNG-X Acceptance Gateway:
(a) subject to paragraph 4.6 (of Schedule B6.3 which refers to dispute handling, defect
aggregation and deferred tests), all such HNG-X Acceptance Criteria have been achieved;
(b) activities leading to HNG-X Acceptance Gateway 1 (named “Readiness for Router Roll—
Out (Z1)” and HNG-X Acceptance Gateway 2 (named “Readiness for Data Centre Migration”)
must be completed and these two HNG-X Acceptance Gateways passed through in accordance
with paragraph 4.5.4.2 as pre-requisites to achieve HNG-X Acceptance Gateway 3.
(b) there are no outstanding HNG-X High Severity Acceptance Incidents;
(c) the number of outstanding HNG-X Medium Severity Acceptance Incidents is five or fewer
and an agreed workaround exists for each of them; and
(d) there is an agreed workaround for all outstanding HNG-X Low Severity Acceptance
Incidents except for those which the Parties agree do not require a workaround.
(e) details of all Non Incidents are recorded, although they shall have no impact upon
Acceptance Gateway progression
These together with other supporting factors are summarised in the following checklists for AG3.
© Copyright Post Office Limited COMMERCIAL IN CONFIDENCE Ref: REQ/GEN/ACS/0002
2009 Version: 0.2
UNCONTROLLED IF PRINTED OR LOCALLY _ Date: 02-Nov-2009
STORED PageNo: 6 of 33
oO
FUJITSU
POL00032633
POL00032633
ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 “i
COMMERCIAL IN CONFIDENCE
1.2 Acceptance Board assessment checklist for AG3
References in this table refer to the HNG-X Acceptance Schedule B6.3.
Acceptance Gateways.
Schedule 6.3 paragraph 4.3 identifies three key HNG-X Acceptance Gateways controlling
progression through the HNG-X
Acceptance Process Stages plus two additional Acceptance Gateways.
Acceptance Gateway 3
First of three key HNG-X
Acceptance Gateways.
Check list.
Achievement of Requirements.
(With the exception of those Requirements covered by Acceptance Incidents or agreed to
be covered by Deferred Tests):
All AG3 Requirements
have been achieved
(4.5.1.1(a)).
The sequence of HNG-X Acceptance Process stages and the order of precedence for
Passage through both AG
Acceptance Gateways is defined in schedule 6.3 section 2.2 1&AG2
x Results in a defect that would render a key element I =
os of one or more of the Business Capabilities and g None allowed
=8 ‘Support Facilities or a key element of the & (4.5.1.1 (c)).
A 5 Infrastructure unfit for operational use. S
F Fr
é x Five or fewer allowed and
2
Bs Results in a defect that would cause problems in the 3 beads eure ive
g is 2 operational use of one or more Transaction types. € workaround and -
2
A Ezy 3 an agreed Rectification
Soy Plan.
. 355
3 3 £ 3 Contract does not specify
= 33 é a limit on the number but
8 g 2 Results in a defect that does not cause any adverse
g ul operational impact in the use of the Business A all have an agreed
eo Capabilities and Support Facilities or an element of g workaround (unless.
Be the Infrastructure, or can be addressed 3 agreed otherwise).
38 by a Fujitsu Services workaround without any Fa
go adverse operational impact for Post Office. s Contract does not
83 mention target timescale
$3 for rectification.
ge
2 Is found: 5
3 not to be a defect; not to have resulted from the 3
as introduction of HNG-X or not to fall within the high, I = Need not be counted.
Bs medium or low categories. iS
2
Deferred Tests.
If, other than as a result of a Default of Fujitsu Services, it is impossible for a test to be
carried out when scheduled in the HNG-X Acceptance Plan then that test becomes known,
as a "Deferred Test".
The total number of
Requirements with
Deferred Tests (but not
recorded as an
Acceptance Incident)
equals:
Roce tence) Disputes) . There are no unresolved
In accordance with Schedule 6.3 paragraph 4.6 the parties agree that:. eeetance DienTiess
© Copyright Post Office Limited COMMERCIAL IN CONFIDENCE Ref: REQ/GEN/ACS/0002
2009 Version: 0.2
UNCONTROLLED IF PRINTED OR LOCALLY Date: 02-Nov-2009
STORED PageNo: 7 of 33
POL00032633
POL00032633
o ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 “i
FUJITSU COMMERCIAL IN CONFIDENCE
2 Review of status of Acceptance Criteria
The POL requirements for Acceptance Gateway 3 comprise all of the functional requirements
represented by the POL Use Cases and a set of the Non-Functional requirements.
2.1 Functional Requirements — Use Cases
There are 144 Use Cases which constitute the POL functional requirements. Their summary status is as
follows: -
Count of Status Status
Service Barrel Not Zero Deferred I Failed Passed I Grand
Covered I defects Failed Total
Banking 8 10 18
Branch Accounting 1 17 18
Branch Admin 1 1 8 10
Branch Support & 17 17
Control
Bureau de Change 7 7
ETU 1 3 1 5
loP 8 11 19
Postal Services 1 8 9
Retail & Stock Sales 1 1
Shared 1 1 5 12 19
Cash & = Stock 3 18 21
Management
Grand Total 1 1 27 6 109 144
ee
The status of Deferred Failed indicates that a Use Case has one or more defects associated with it, but
that the resolution of these defects have been agreed to be deferred to beyond start of Pilot.
Each of these defects is represented as an Acceptance Incident in section 3.
© Copyright Post Office Limited COMMERCIAL IN CONFIDENCE Ref: REQ/GEN/ACS/0002
2009 Version: 0.2
UNCONTROLLED IF PRINTED OR LOCALLY _ Date: 02-Nov-2009
STORED PageNo: 8 of 33
POL00032633
POL00032633
o ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 7
FUJITSU COMMERCIAL IN CONFIDENCE
2.2 Non-Functional Requirements and Criteria
There are 752 non functional Acceptance Criteria associated with Acceptance Gateway 3. Their
summary status is as follows: -
Status
Verification Method I NoRun I NotCompleted I Not Covered I Failed I Passed Grand
Total
Document Review 3 19 7 221 250
(19 with
concession)
Design Walkthrough 1 138 139
(11 with
concession)
Monitoring 2 2
Statement of Fact 42 42
(2 with
concession)
Statement of 90 90
Obligation
(4. with
concession)
Solution Test 10 12 29 115 166
(22 with
concession)
Release Validation 4 5 7 47 63
Test
(96 with
concession)
Grand Total 17 36 3 43 653 752
Key to Status
Failed - Each Failed Criteria is represented by an Acceptance Incident in section 3
No Run - This identifies the number of criteria whose designated tests have not been run at the time of
this Acceptance Board. A number of these are due to the status of the testing of the criteria being agreed
to deferred, with the associated criteria having the status of ‘Deferred Test’ — see section 2.2.1.
© Copyright Post Office Limited COMMERCIAL IN CONFIDENCE Ref: REQ/GEN/ACS/0002
2009 Version: 0.2
UNCONTROLLED IF PRINTED OR LOCALLY _ Date: 02-Nov-2009
STORED PageNo: 9 of 33
POL00032633
POL00032633
o ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 “i
FUJITSU COMMERCIAL IN CONFIDENCE
Not Completed — This identifies the number of criterion where either: -
a) Acceptance Evidence has been submitted by FS but not yet assessed by POL,
or
b) Test execution had started but not completed at the time of this Acceptance
Board. These will also have the status of ‘Deferred Test’.
2.2.1 Deferred Test status
The Schedule B6.3 acknowledges that there may be circumstances when previously scheduled testing
that was targeted for completion by this Acceptance Gateway cannot now take place. Providing that this
is not due to a contractual default by Fujitsu, and the parties agree, then the tests associated with a POL
requirement may be ‘Deferred’. Fujitsu are still obliged to carry out these ‘Deferred Tests’.
For this Acceptance Gateway, Fujitsu have requested that tests associated with the following
requirements are given ‘Deferred Test’ status. These are: -
SEC-3115, SEC-3135, SEC-3210, SEC-3212, SEC-3193, SEC-3161, SEC-3230, SEC-3154, SEC-3158,
SEC-3113, SEC-3177, SEC-3257, SEC-3354, SEC-3164, SEC-3210, SEC-3204, SEC-3348
These are all associated with the Security Penetration testing that is due to complete on 18/11/09.
The Joint Test Team has advised that ARC-462, ARC-463, TR471 are now scheduled to be tested in
LST and so should also be given ‘Deferred Test’ status.
© Copyright Post Office Limited COMMERCIAL IN CONFIDENCE Ref: REQ/GEN/ACS/0002
2009 Version: 0.2
UNCONTROLLED IF PRINTED OR LOCALLY _ Date: 02-Nov-2009
STORED PageNo: 10 of 33
oO
FUJITSU
POL00032633
POL00032633
ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 “i
COMMERCIAL IN CONFIDENCE
2.3 Assessment of Status
The following sections provide details of the use cases / criteria that fall into each of the ‘status’ entries in
sections 2.1 and 2.2 together with an impact statement.
2.3.1
No Run status
A status of No Run identifies those criteria whose designated tests have not been run at the time of this
Acceptance Board. There are no Use Cases with a status of No Run.
The number of non-functional criteria with a status of No Run is shown in the table 2.2 and comprises
both ‘non-testable’ and ‘testable’ criteria as follows.
2.3.1.1 No Run/non-testable criteria
The criteria and impact of the ‘No Run’ status in this category are as follows: -
Original Original Object text Acceptance Criteria I Verification Impact
Object Id Method
SEC-3138 I Risks identified in the I Evidence that all I DR This criterion cannot conclude
area of SQL injection I risks raised under until the two criteria associated
attacks (see SEC-3347) I Requirement SEC- with SEC-3347 have been
will be managed under I 3347 have been assessed.
Change Control. addressed under the
Change Control They are: -
process. SEC-3137 - see AI-NT-1001
&
SEC-3348 — see Al-TS-??
SEC-3061 I By provision of an I Review of I DR This criterion cannot conclude
appropriate architecture I documentation and until all other Security criteria
for HNG-X and
associated service
operation, Fujitsu
Services shall protect
Post Office from liability
for information security
threats to a_ similar
extent that Post Office is
protected by Baseline
Horizon unless
agreed waivers prior
to going live shows
that all other security
requirements have
either been accepted
or, where not,
waivers have been
agreed by Post Office
Information Security.
have been assessed.
© Copyright Post Office Limited
2009
COMMERCIAL IN CONFIDENCE.
UNCONTROLLED IF PRINTED OR LOCALLY
STORED
Ref: REQ/GEN/ACS/0002
Version: 0.2
Date: 02-Nov-2009
Page No: 11 of 33
POL00032633
POL00032633
ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 “i
COMMERCIAL IN CONFIDENCE
Fe)
FUJITSU
Original Original Object text Acceptance Criteria I Verification Impact
Object Id Method
SEC-3060 I By provision of an I Review of I DR This criterion cannot conclude
appropriate architecture I documentation and until all other Security criteria
for HNG-X and I agreed waivers on have been assessed.
associated service I completion of ST
operation, Fujitsu I tests shows that all
Services shall protect I other security
Post Office from liability I requirements have
for information security I either been accepted
threats to a_ similar I or, where not,
extent that Post Office is I waivers have been
protected by Baseline I agreed by Post Office
Horizon unless Information Security.
ARC-423 Fujitsu Services shall I Post Office and the I DW
adopt a quality process I Independent
and shall follow a I Assessor
recognised methodology I acknowledge that the
in the production of the I process and
Solution Baseline I methodology utilised
Documentation Set. by Fujitsu Services
are suitable —_ for
documenting the
Solution Baseline.
2.3.1.2. No Run/ testable criteria
The criteria and impact of the ‘No Run’ status in this category are as follows: -
Original Original Object text Acceptance Criteria Verification Impact
Object Id Method
ARC-463 Fujitsu Services shall I Tests to demonstrate I ST Deferred Test
demonstrate that network I network connectivity for
connections for portable I portable office
office configurations shall I configurations are defined
be automatically selected I and contained within a
from those physically I detailed test plan, the
available without the I successful completion of
intervention of the sub- I which shall determine the
postmaster. acceptance of this
requirement. To clarify
‘successful completion’,
© Copyright Post Office Limited COMMERCIAL IN CONFIDENCE ve beeen
2009 Version: 0.2
UNCONTROLLED IF PRINTED OR LOCALLY Date: 02-Nov-2009
STORED PageNo: 12 of 33
oO
FUJITSU
ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3
COMMERCIAL IN CONFIDENCE
POL00032633
POL00032633
Original
Object Id
Original Object text
Acceptance Criteria
Verification
Method
Impact
MIG-2981
Fujitsu Services shall
ensure that the closing
position on Horizon can be
fully reconcilable to the
opening position on HNG-X
via means of reports and
the format will be agreed
during development
Migration reports
produced during ST
conform to the agreed
report specification and
contain appropriate data
ST
MIG-3069
The branch migration
process shall demonstrate:
(a) the closing trading
position for each Branch of
Baseline Horizon,
(b) proof (as defined in MIG
2980) of the successful
migration from Baseline
Horizon to HNG-X,
and
(c) any
regarding
discrepancies
Demonstration as per the
Requirement
ST
MIG-3096
The Fujitsu Services
Configuration Management
service shall make it
possible to identify which
phase (Horizon or HNG-X)
of migration a branch is in
Evidence that the status
of each counter is
correctly identifyable as
being Horizon or HNG-x
during the simulated
migration period.
RV
MIG-3162
HNG shall be capable of
regression back to Horizon,
including regression of the
full branch estate, up to the
point of Contractual
Acceptance as agreed by
the Migration Strategy
Tests to demonstrate
regression back to
Horizon are defined and
contained within a
detailed test plan, the
successful completion of
which shall determine the
acceptance of this
requirement. To clarify
‘successful completion’,
success criteria will be
iden
RV
© Copyright Post Office Limited
2009
UNCONTROLLED IF PRINTED OR LOCALLY _ Date:
COMMERCIAL IN CONFIDENCE.
STORED
Ref:
Version: 0.2
Page No:
02-Nov-2009
13 of 33
REQ/GEN/ACS/0002
POL00032633
POL00032633
ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 “i
COMMERCIAL IN CONFIDENCE
oO
FUJITSU
Original
Object Id
Original Object text
Acceptance Criteria
Verification
Method
Impact
SEC-3113
Fujitsu Services shall
provide a list of measures
that will be taken to mitigate
the risk of unauthorised
devices being connected to
any component of the HNG-
x system, with the
exception of passive
devices within the Branch. A
"passive device" is one whic
that all
achieve the
Evidence
measures
requirement
ST
Deferred Test
SEC-3115
Branch Terminals shall be
bootable only from their
primary mass _ storage
device on the terminal.
Evidence that attempts to
boot from other than the
primary mass storage
device fail.
ST
Deferred Test
SEC-3154
{CISP 8.5.1b} Unauthorised
logical access from non-
HNG-X systems and
networks shall be
prevented. This shall
include but shall not be
limited to, _ unauthorised
access from any of the
following: Any public
networks used. Networks
connecting to Third Partie
Demonstration of
protection (either by
simulation of attempts of
unauthorised access or by
other means). The exact
timing and environment
for the tests shall be
agreed in the test plan but
shall in any case be prior
to live.
RV
Deferred Test
SEC-3158
{CISP 8.5.1c} Controls shall
protect against denial-of-
service attacks originating
from non-HNG-X systems
including those listed in
Requirement SEC-3152
Demonstration of
protection (either by
simulation of attack or by
other means)
RV
Deferred Test
SEC-3177
All RADIUS servers that
authenticate network
access shall be secured
and segregated into logical
network segments by carrier
access method and be
externally visible to
authorised domain users
only.
As per the Requirement
ST
Deferred Test
SEC-3193
Any mobile backup or
secondary network
produced within the {CISP.
8.5.1k} specification of the
requirement shall be
secured to the same level
as the primary network.
As per the Requirement
ST
Deferred Test
© Copyright
2009
Post Office Limited
UNCONTROLLED IF PRINTED OR LOCALLY _ Date:
COMMERCIAL IN CONFIDENCE
STORED
Ref:
Version:
Page No:
REQ/GEN/ACS/0002
0.2
02-Nov-2009
14 of 33
Fe)
FUJITSU
ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3
COMMERCIAL IN CONFIDENCE
POL00032633
POL00032633
Original
Object Id
Original Object text
Acceptance Criteria
Verification
Method
Impact
SEC-3212
It shall not be possible to
install any application or
operating system extension
except under the control of
properly authorised and
authenticated systems
administrators carrying out
authorised and audited
changes.
As per the Requirement
ST
Deferred Test
SEC-3257
The logical security
perimeter of the HNG-X
system shall be defined and
agreed with Post Office
Information Security.
Tests to demonstrate the
security perimeter are
defined and contained
within a detailed test plan,
the successful completion
of which shall determine
the acceptance of this
requirement. To clarify
‘successful completion’,
success criteria will be
identifi
ST
Deferred Test
SEC-3354
All cryptographic key
lengths shall be at least 128
bits for symmetric keys and
at least 1024 bits for
asymmetric keys where the
associated cryptographic
control protects the integrity
or confidentiality of HNG-X
Business Data, Reference
Data or Applicati
Tests to demonstrate
compliance are defined
and contained within a
detailed test plan, the
successful completion of
which shall determine the
acceptance of this
requirement. To clarify
‘successful completion’,
success criteria will be
identified in advanc
ST
Deferred Test
© Copyright Post Office Limited
2009
UNCONTROLLED IF PRINTED OR LOCALLY
COMMERCIAL IN CONFIDENCE
STORED
Ref.
Version:
Date:
Page No:
0.2
02-1
REQ/GEN/ACS/0002
Nov-2009
15 of 33
POL00032633
POL00032633
ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 “i
COMMERCIAL IN CONFIDENCE
Fe)
FUJITSU
2.3.2. Not Complete Status
The following POL requirements have had Acceptance evidence submitted but their assessment has not
yet completed.
The number of non-functional criteria with a status of Not Complete is shown in the table 2.2 and
comprises both ‘non-testable’ and ‘testable’ criteria as follows.
2.3.2.1
Not Complete / ‘non-testable’ criteria
These criteria all have the verification method of document review. They comprise criteria where
documentary acceptance evidence has been submitted by Fujitsu but where the POL assessment has
not completed.
Object Id
Original Object text
Acceptance Criteria
Impact
ARC-422
Fujitsu Services shall make
available to POL an accurate
and technically complete set of
documentation describing the
Solution Baseline
Documentation Set, excluding
legacy components where
existing Horizon documentation
may be retained.
The Solution
documentation shall be
provided to POL in
accordance with the timetable
stated in B6.2 and_ shall
comprise the documents or
other artifacts that are agreed
between Post Office and
Fujitsu Services according to
Schedule B6.2.
Baseline
ARC-499
For the portable configuration,
Physical connection to
available fixed network end
points is manual and presumed
to be achieved by the
subpostmaster. Fujitsu
Services will define with Post
Office the process that the
postmaster needs to follow to
correctl
DR- Documents provided to
describe the agreed process
for connecting the device to
each type of fixed network
endpoint and for dealing with
all network faults arising from
the connection of the device
DEV-375
HNG-X shall support parallel
development streams and,
except where there are
unavoidable dependencies,
these streams shall be
implementable in any
sequence or combination.
Fujitsu will describe how
parallel development and
implementation will be
supported.
© Copyright Post Office Limited
2009
UNCONTROLLED IF PRINTED OR LOCALLY
Ref.
Version:
Date:
Page No:
COMMERCIAL IN CONFIDENCE
STORED
REQ/GEN/ACS/0002
0.2
02-Nov-2009
16 of 33
Fe)
FUJITSU
ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3
COMMERCIAL IN CONFIDENCE
POL00032633
POL00032633
Ori
inal Object text
Acceptance Criteria
Impact
MIG-3017
Physical security of any
infrastructure components,
including Branch base units,
which contain any business or
security sensitive information,
shall not be compromised by
processes developed and
implemented for the migration
from Baseline Horizon to HNG-
x
Evidence of joint agreement to
the migration processes
affecting the security of
physical infrastructure and the
risks to business or security
sensitive information.
MIG-3020
Fujitsu. Services and Post
Office shall jointly produce a
Migration Plan, which shall
detail how Security
requirements at MIG-3015 &
MIG-3216 are to be met
As per the Requirement
MIG-3033
Fujitsu Services shall
implement a reporting process
informing Post Office Ltd of
branches successfully migrated
to HNG X
As per the Requirement
SEC-3170
All proposals for encrypted
data to pass through any HNG-
X firewall layer shall be subject
to risk assessment to
determine if the requirement for
confidentiality outweighs the
requirement for system
availability and integrity.
Approval of the Risk
assessment process
SEC-3172
Cases requiring encrypted data
to pass through any HNG-X
firewall layer shall only be
authorised by Post Office
where a risk assessment has
identified that the requirement
for confidentiality outweighs the
requirement for system
availability and integrity
Approval of the authorisations
process
SEC-3178
Any end-user messaging
components or services, and
their dependent systems or
services shall be usable by
authorised users from within
the HNG-X environment only.
“End-user messaging" shall be
interpreted as the Branch
Message Broadcast Service
and any ot
Evidence of the Requirement
in the Design.
© Copyright Post Office Limited
2009
UNCONTROLLED IF PRINTED OR LOCALLY
Ref.
Version:
Date:
Page No:
COMMERCIAL IN CONFIDENCE
STORED
REQ/GEN/ACS/0002
0.2
02-Nov-2009
17 of 33
POL00032633
POL00032633
oO ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 7
FUJITSU COMMERCIAL IN CONFIDENCE
Original Object text Acceptance Criteria Impact
SEC-3180 I In the event that e-mail I Evidence of review if e-mail is
facilities are added to HNG-X, I incorporated.
additional security features
shall be agreed with Post
Office Information Security
prior to implementation.
SEC-3185 IThe provision of messaging I Evidence of the Requirement
capability shall not permit I in the Design.
active or scripted code to be
carried within the message
body that may be executed
upon Branch Terminals or
intermediate systems.
SEC-3190 I {CISP 8.5.1k} The use of I Design Documents Comply
wireless technologies within or I with the Security Policy and
associated with HNG-X I state that the Counter
systems or services shall be I Terminals and the Branch
excluded with the sole I Routers cannot be configured
exception of mobile public I for Wi-Fi or for Bluetooth.
telecommunications services
provided by UK licensed public
telecommunications operators
or as oth
SEC-3223 It shall be possible to recover I Examination of Key
the system to a _ secure I Compromise and Key Change
operating state from the I Procedures: NB/PRO/O08
compromise of any key that
could directly or indirectly
expose plain text PIN values.
This represents no change to
the current Horizon system.
SER-2168 Fujitsu. shall develop and I An entry in an artefact within
publish a documented process I the Solution Baseline
for the updating of Known Error I Documentation Set will be
Logs, relating these to I supplied which cross
Configuration Items within a I references this requirement
given release and sharing them I with the appropriate document
with PO Ltd. The process will I and the relevant clause within
conform to Fujitsu corporate I the document will be supplied.
standards and will not b The document will describe
how this
© Copyright Post Office Limited COMMERCIAL IN CONFIDENCE ve beeen
2009 Version: 0.2
UNCONTROLLED IF PRINTED OR LOCALLY Date: 02-Nov-2009
STORED PageNo: 18 of 33
Fe)
FUJITSU
POL00032633
POL00032633
ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 “i
COMMERCIAL IN CONFIDENCE
Ori
inal Object text
Acceptance Criteria
Impact
SVC-806
Transaction Time Benchmark
evaluation shall be conducted
in accordance with the process
described in the document
‘Counter Transaction Time
Performance - measurement
and results(CS/PER/046)'.
An entry in an artefact within
the Solution Baseline
Documentation Set will be
supplied which cross
references this requirement
with the appropriate document
and the relevant clause within
the document will be supplied.
The document will describe
how this
© Copyright Post Office Limited
2009
UNCONTROLLED IF PRINTED OR LOCALLY
COMMERCIAL IN CONFIDENCE
Ref:
Version:
Date:
STORED Page No:
REQ/GEN/ACS/0002
0.2
02-Nov-2009
19 of 33
POL00032633
POL00032633
oO ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 7
FUJITSU COMMERCIAL IN CONFIDENCE
2.3.2.2 Not Complete / ‘testable’ criteria (ST or RV)
The criteria with this status are shown below together with an impact statement.
Original Original Object text Acceptance Criteria Impact
Object Id
ARC-470 Any single failure within the I Tests to demonstrate
Data Centres shall notI business continuity are
cause loss of any of the I defined and contained within
Business Capabilities &Ia detailed test plan, the
Support Facilities successful completion of
which shall determine the
acceptance of this
requirement. To clarify
‘successful completion’,
success criteria’ will be
identified
ARC-474 Confirmation messages for I As per the requirement
online transactions will only
be harvested in batch mode
at end of day. This means
that the TES will not
receive C2 messages in
near real time, and
Streamline payment file(s)
will only be produced
overnight.
MIG-2987 The capability to provide I As per the Requirement
prosecution support relating
to incidents on Baseline
Horizon shall _—_ continue
unimpaired during and
following completion of
migration.. In Baseline
Horizon this refers to
ARQs. . This may be
interrupted during data
centre move for
MIG-3078 Fujitsu Services shall I Evidence that tools will
provide any tools I ensure achievement
necessary to ensure that all
requirements for migration
to HNG-X are achieved.
© Copyright Post Office Limited COMMERCIAL IN CONFIDENCE ve beeen
2009 Version: 0.2
UNCONTROLLED IF PRINTED OR LOCALLY Date: 02-Nov-2009
STORED Page No: 20 of 33
Fe)
FUJITSU
ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3
COMMERCIAL IN CONFIDENCE
POL00032633
POL00032633
Original
Object Id
Original Object text
Acceptance Criteria
Impact
MIG-3109
Fujitsu shall ensure that
during migration (when
client data comprises of
both Horizon and HNG
sourced data) if failures
occur, that the resulting
Client data feeds are
complete and accurate
subject to agreed service
levels (i.e. no omissions
and no dupli
ST displays that Interface
specifications for all
outbound data feeds are
adhered to, irrespective as to
the source system (e.g.
Horizon or HNG). ST also
conforms that no data is lost
or duplicated in the outbound
data files during the
migration period.
MIG-3119
Except where dual
interfaces have been
agreed reference data
changes will be applied
consistently to both
Baseline Horizon and HNG
via a single interface to the
counter estate. This
includes Product, Branch
and AP (including AP_LADC
reference data driven
ST confirms that a single
source of reference data
changes can be consistently
applied to both Horizon and
HNG, in effect simulating the
operational requirement
during migration
MIG-3154
Prior to and during
migration to HNG-X, Fujitsu
Services shall provide a
Live Reference Data
Proving environment
capable of validating
Horizon and HNG-X
reference data prior to its
release into the live
environment. This shall
include the ability to conf
Proof that Horizon or HNG-X
data will operate as expected
in the appropriate
environment
MIG-3155
FS and PO shall establish a
reference data verification
process using the LRDP
environment to determine
that reference data
distributed to the HNG-X
and Horizon environments
will have the same or
where agreed equivalent
functional or operational
effect
Evidence that either Horizon
or HNG produces equivalent
outcomes to the existing live
Horizon data (except where it
is agreed that outcomes will
not be equivalent).
© Copyright Post Office Limited
2009
UNCONTROLLED IF PRINTED OR LOCALLY
Ref.
Version:
Date:
Page No:
COMMERCIAL IN CONFIDENCE
STORED
REQ/GEN/ACS/0002
0.2
02-Nov-2009
21 of 33
oO
FUJITSU
POL00032633
POL00032633
ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 “i
COMMERCIAL IN CONFIDENCE
Original
Object Id
Original Object text
Acceptance Criteria
Impact
MIG-3161
It shall be possible to make
software changes to
Baseline Horizon during
the Migration period ,
although Post Office has no
current plans for this.
Tests to demonstrate
changes to horizon baseline
during migration are defined
and contained within a
detailed test plan, the
successful completion of
which shall determine the
acceptance of this
requirement. To clarify
‘successful completion’,
success crit
MIG-3164
Baseline Horizon branches
installed during the Branch
migration roll out period
shall be scheduled for
subsequent conversion to
HNG.
Evidence that Branches
installed as Baseline Horizon
can be converted to HNG-X.
Tests to demonstrate this are
defined and contained within
a detailed test plan, the
successful completion of
which shall determine the
acceptance of this
requirement. To c
MIG-3256
Following migration to
HNG-X, Fujitsu Services
shall provide a _ Live
Reference Data Proving
environment capable of
validating HNG-X reference
data prior to its release into
the live environment. This
shall include the ability to
confirm the expected busi
Proof that HNG-X data will
operate as expected in the
HNG-X environment All BAU
processes in place and
agreed with PO Ltd.
SEC-3144
The HNG-X system shall
not retrieve data from any
external web service unless
additional security features
are agreed with Post Office
Information Security. For
the avoidance of doubt, no
security change is required
to the connection to the
DVLA web servi
Demonstration of protection
(either by simulation of attack
or by other means). Tests
are only required if HNG-X
supports browsing of external
web servers.
Deferred Test
© Copyright Post Office Limited
2009
UNCONTROLLED IF PRINTED OR LOCALLY
COMMERCIAL IN CONFIDENCE
Ref:
Version:
Date:
Page No:
STORED
REQ/GEN/ACS/0002
0.2
02-Nov-2009
22 of 33
POL00032633
POL00032633
oO ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 7
FUJITSU COMMERCIAL IN CONFIDENCE
Original Original Object text Acceptance Criteria Impact
Object Id
SEC-3224 It shall be possible to I As per the Requirement
recover the system to a
secure operating state from
the compromise of any key
that could directly or
indirectly expose plain text
PIN values. This
represents no change to
the current Horizon system.
SEC-3234 Sensitive Cardholder Data I As per the Requirement
(see Definitions) shall be
rendered unreadable
anywhere it is stored
(including data on portable
media, backup media, and
in logs) by using any of the
following approaches:
One-way hashes (hashed
indexes), such as SHA-1
Truncat
SEC-3309 All Sensitive Authentication I Tests show that all specified I Deferred Test
Data (see Definitions) and I data is protected by
Sensitive Cardholder Data I encryption or other method
shall be encrypted using I that makes it impractical to
approved algorithms and I deduce
encryption protocols whilst
in transit over any public
network unless specifically
agreed in writing by the
client.
Approve
SER-2195 Fujitsu Services shall I Tests to demonstrate the
define a Software Delivery I migration to HNG-x are
Management processes I defined and contained within
such that distribution, I a detailed test plan, the
activation, Business I successful completion of
enablement and I which shall determine the
Regression activities are I acceptance of this
known and controlled by I requirement. To clarify
Post Office, by branch and I ‘successful completion’,
for the whole estate as I success criteria will be
described in Systems Ma identifi
© Copyright Post Office Limited COMMERCIAL IN CONFIDENCE ve beeen
2009 Version: 0.2
UNCONTROLLED IF PRINTED OR LOCALLY Date: 02-Nov-2009
STORED PageNo: 23 of 33
POL00032633
POL00032633
o ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 7
FUJITSU COMMERCIAL IN CONFIDENCE
Original Original Object text Acceptance Criteria Impact
Object Id
TR471 To support external training I As per the requirement
activities including
migration, the solution shall
be capable of running on a
pre-defined portable
platform.
2.3.3 Not Covered / Zero defects status
I
2.3.4 Deferred Failed status
This status identifies those Use Cases where one or more defects have been identified and agreed to be
deferred. An Acceptance incident has been raised for each defect and these are contained in section 3.
2.3.5 Failed Status
This status identifies those Use Cases or non-functional criteria where one or more defects have been
identified. An Acceptance incident has been raised for each defect and these are contained in section 3
© Copyright Post Office Limited COMMERCIAL IN CONFIDENCE Ref: REQ/GEN/ACS/0002
2009 Version: 0.2
UNCONTROLLED IF PRINTED OR LOCALLY _ Date: 02-Nov-2009
STORED PageNo: 24 of 33
POL00032633
POL00032633
oO ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 “i
FUJITSU COMMERCIAL IN CONFIDENCE
3 Review of status of Acceptance Incidents
The Acceptance Incidents listed below have been raised because the acceptance evidence has failed to
meet the acceptance criteria. They have been classified into three groups: -
e Those arising from defects whose resolution has been agreed to be deferred until after
the start of Pilot. These have an identifier of Al-AD-nnn
e Those arising from defects that have been raised during the assessment of the non-
testable criteria - in this case Document Review. These have an identifier of AI-NT-nnn.
e Those arising from defects that have been raised during testing and where no formal
deferral discussions have taken place. These have an identifier of Al-TS-nnn.
3.1 Acceptance Incident Aggregation
Schedule B6.3 (4.6.3) recognises that HNG-X Acceptance Incidents that are agreed to result from the
same failure or deficiency, or to affect the same operational process or business function, may be
aggregated into a single HNG-X Acceptance Incident for the purposes of the thresholds identified in
section 1.2. The following sections contain details of all of the individual Acceptance Incidents and then
identifies where aggregation has occurred.
3.2 Acceptance Incidents arising from Agreed Deferrals
There are 105 Als of this type of with the following severity: -
Acceptance Individual Als
Incident Severity
Low 117
Medium 0
High 0
Total 117
Of these, 30 of the Low Severity Als have been aggregated into 8 Low Severity Als giving a net figure as
follows: -
Acceptance Net Individual Als I Aggregated Als Net Total
Incident Severity
Low 87 8 95
Medium (e)
High 0
Total 87 8
© Copyright Post Office Limited COMMERCIAL IN CONFIDENCE Ref: REQ/GEN/ACS/0002
2009 Version: 0.2
UNCONTROLLED IF PRINTED OR LOCALLY Date 02-Nov-2009
STORED PageNo: 25 of 33
POL00032633
POL00032633
oO ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 “i
FUJITSU COMMERCIAL IN CONFIDENCE
3.2.1 Acceptance Incident details for type Al-AD
Details of these Acceptance Incidents are contained in the embedded WORD document here.
aE
D:\PROFILES\cooked’
My Documents\My Dc
3.2.2. Aggregated Acceptance Incident details for type Al-AD
Details of these Aggregated Acceptance Incidents are contained in the embedded WORD document
here.
D:\PROFILES\cooked’
My Documents\My Dc
© Copyright Post Office Limited COMMERCIAL IN CONFIDENCE Ref: REQ/GEN/ACS/0002
2009 Version: 0.2
UNCONTROLLED IF PRINTED OR LOCALLY Date 02-Nov-2009
STORED PageNo: 26 of 33
POL00032633
POL00032633
oO ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 “i
FUJITSU COMMERCIAL IN CONFIDENCE
3.3. Acceptance Incident arising from non-testable criteria
There are 14 Als of this type of with the following severity: -
Acceptance Individual Als
Incident Severity
Low 14
Medium
High
Total 14
Of these, 10 of the Low Severity Als have been aggregated into 1 Medium Severity Al giving a net figure
as follows: -
Acceptance Net Individual Als I Aggregated Als Net Total
Incident Severity
Low 4 0 4
Medium 0 1
High 0 0 0
Total 4 1
3.3.1. Acceptance Incident details for type Al-NT
Details of these Acceptance Incidents are contained in the embedded WORD document here.
ea)
D:\PROFILES\cooked’
My Documents\My Dc
3.3.2 Aggregated Acceptance Incident details for type Al-NT
Details of these Aggregated Acceptance Incidents are contained in the embedded WORD document
here.
D:\PROFILES\cooked’
My Documents\My Dc
© Copyright Post Office Limited GCNIANEOT. bi Seema Ref REQ/GEN/ACS/0002
2009 Version: 0.2
UNCONTROLLED IF PRINTED OR LOCALLY _ Date: 02-Nov-2009
STORED PageNo: 27 of 33
POL00032633
POL00032633
o ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 “i
FUJITSU COMMERCIAL IN CONFIDENCE
3.4 Acceptance Incident arising from Testable criteria
There are (41) Als of this type of with the following severity: -
Acceptance Individual Als
Incident Severity
Low (41)
Medium
High
Total (41)
3.4.1. Acceptance Incident details for type Al-TS
Details of these Acceptance Incidents are contained in the embedded WORD document here.
ra
D:\PROFILES\cooked
My Documents\My Dc
© Copyright Post Office Limited COMMERCIAL IN CONFIDENCE Ref: REQ/GEN/ACS/0002
2009 Version: 0.2
UNCONTROLLED IF PRINTED OR LOCALLY _ Date: 02-Nov-2009
STORED PageNo: 28 of 33
POL00032633
POL00032633
o ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 7
FUJITSU COMMERCIAL IN CONFIDENCE
3.5 Acceptance Incident total
The overall status of all Acceptance Incidents is as follows: -
Severity AI-AD - Agreed AI-NT - Non AI-TS - Test Total
Deferred Testable
Low 95 4 (41) (140)
Medium () 4 1
High ie) 0 te)
© Copyright Post Office Limited COMMERCIAL IN CONFIDENCE Ref: REQ/GEN/ACS/0002
2009 Version: 0.2
UNCONTROLLED IF PRINTED OR LOCALLY _ Date: 02-Nov-2009
STORED PageNo: 29 of 33
POL00032633
POL00032633
oO ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 “i
FUJITSU COMMERCIAL IN CONFIDENCE
A Applicable POL Requirements and Acceptance
Criteria
The POL Requirements and Criteria, contained in the HNG-X Requirements Catalogue - POL DOORS
archive v1.42, and associated with AG3 are contained in the embedded spreadsheet.
This contains references to any Concessions.
D:\PROFILES\cooked
My Documents\My Dc
© Copyright Post Office Limited COMMERCIAL IN CONFIDENCE Ref: REQ/GEN/ACS/0002
2009 Version: 0.2
UNCONTROLLED IF PRINTED OR LOCALLY Date: 02-Nov-2009
STORED PageNo: 30 of 33
POL00032633
POL00032633
o ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3
FUJITSU COMMERCIAL IN CONFIDENCE
B_ Definition of Acceptance Methods
The set of HNG-X Acceptance methods are defined in Appendix D of Schedule B6.3 HNG-X Acceptance
Process and reproduced below.
Type Description
HNG-X HNG-X Acceptance Criteria that cannot be objectively verified by a test of HNG-X
Document may be satisfied by Post Office undertaking a HNG-X Document Review. The
Review outcome of any such review will be documented by Post Office in the HNG-X
Acceptance Tracking Document. Fujitsu Services will supply a list of documents.
(and any specific references within such documents) for Post Office review,
which may satisfy the agreed HNG-X Acceptance Criteria.
HNG-X HNG-X Acceptance Criteria may be satisfied by Post Office participating in an
Design HNG-X Design Walkthrough led by Fujitsu Services of the Fujitsu Services’
Walkthrough I design. The outcome of any such HNG-X Design Walkthrough will be
documented by Post Office in the HNG-X Acceptance Tracking Document.
HNG-X Tests that are owned and managed by Fujitsu Services with significant
Solution Test I Collaborative support from Post Office, for the purpose of verifying that the Fujitsu
Services’ solution for the HNG-X System satisfies the relevant HNG-X
Acceptance Criteria. The collaborative team will produce a joint test report
presenting the results of the tests.
HNG-X Tests that are run and managed by Post Office with significant collaborative
Release support from Fujitsu Services, for the purpose of verifying that the HNG-X
Validation Release satisfies the relevant HNG-X Acceptance Criteria. The combined team
will produce a joint test report presenting the results of the tests and provide
evidence on any areas of non conformance.
Post Office shall specify any need beyond the level of support that Fujitsu
Services are required to provide under normal operational practice (such as a
report etc). Duration, nature and characteristics to be agreed in advance between
Post Office and Fujitsu Services and will take place during Live Pilot or
exceptionally during Live Monitoring. The total duration of HNG-X Monitoring and
the obligations on Fujitsu Services to produce data/reports to support Post Office
monitoring to be agreed between Post Office and Fujitsu Services (each acting
reasonably and in good faith) for a particular HNG-X Requirement.
HNG-X Where the solution to an HNG-X Acceptance Criterion is self-evident and does
Statement of I "0t lend itself to formal proving.
Fact
HNG-X Relates to HNG-X Acceptance Criterion that represents an ongoing contractual
Statement of I obligation for HNG-X.
Obligation
Other Used by exception, to be agreed between the Parties.
© Copyright Post Office Limited COMMERCIAL IN CONFIDENCE Ref: REQ/GEN/ACS/0002
2009 Version: 0.2
UNCONTROLLED IF PRINTED OR LOCALLY _ Date: 02-Nov-2009
STORED PageNo: 31 of 33
POL00032633
POL00032633
o ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 “i
FUJITSU COMMERCIAL IN CONFIDENCE
C Definition of Acceptance Incident Severity
The definition of the severity of an HNG-X Acceptance Incident is defined in Appendix A of Schedule
B6.3 HNG-X Acceptance Process and reproduced below.
High The HNG-X Acceptance Incident was caused by the introduction of changes arising
from Project HNG-X and/or the Associated Change Activities that are subject to the
HNG-X Acceptance Process and results in a defect that would render a key element of
one or more of the Business Capabilities and Support Facilities or a key element of the
Infrastructure unfit for operational use, which could include:
a) not allowing Post Office to undertake one or more Transaction types;
b) not allowing Post Office to undertake one or more Transaction types using the
required business inputs or generating the required business outcome;
c) creating system performance issues which are in, or are likely to cause a, breach
of Service Level Targets.
Medium The HNG-X Acceptance Incident was caused by the introduction of changes arising
from Project HNG-X and/or the Associated Change Activities that are subject to the
HNG-X Acceptance Process and results in a defect that would not prevent operation of
one or more of the Business Capabilities and Support Facilities or elements of the
Infrastructure, but would cause problems in the operational use of one or more
Transaction types.
Low The HNG-X Acceptance Incident was caused by the introduction of changes arising
from Project HNG-X and/or the Associated Change Activities that are subject to the
HNG-X Acceptance Process and results in a defect that does not cause any adverse
operational impact in the use of the Business Capabilities and Support Facilities or an
element of the Infrastructure, or the HNG-X Acceptance Incident can be addressed by
a workaround without any adverse operational impact for Post Office.
Non An incident raised by either Party which, following investigation is found:
Incident
> not to be a defect;
> not to have resulted from the introduction of changes arising from Project HNG-X
and/or the Associated Change Activities that are subject to the HNG-X
Acceptance Process; or
» not to fall within the high, medium or low categories set out in this column.
© Copyright Post Office Limited COMMERCIAL IN CONFIDENCE Ref: REQ/GEN/ACS/0002
2009 Version: 0.2
UNCONTROLLED IF PRINTED OR LOCALLY _ Date: 02-Nov-2009
STORED PageNo: 32 of 33
POL00032633
POL00032633
ACCEPTANCE REPORT FOR HNG-X ACCEPTANCE GATEWAY 3 “i
FUJITSU COMMERCIAL IN CONFIDENCE
D Acceptance Board recommendation options
It is proposed that the decision of the HNG-X Acceptance Board should comprise one of the following
options: -
1. Proceed through Acceptance Gateway.
i. Acceptance Gateway criteria have all been met.
ii. There no Acceptance Incidents that would prevent progression through this Acceptance
Gateway
2. Proceed through Acceptance Gateway
i. Not all Acceptance Criteria have been met and consequently there are Acceptance Incidents.
ii. The severity of these Acceptance Incidents is within the limits for progression through this
Acceptance Gateway.
iii. Each Acceptance Incident has an agreed workaround.
iv. Where required by the contract, all Acceptance Incidents have an agreed rectification plan or a
target timescale for rectification
3. Proceed at risk through Acceptance Gateway
i. Not all Acceptance Criteria have met and consequently there are Acceptance Incidents.
ii. The severity of these Acceptance Incidents is within the limits for progression through this
Acceptance Gateway.
iii. One or more workaround, rectification plan or target timescale, is not yet agreed.
4. Do not proceed through Acceptance Gateway
i. Not all Acceptance Criteria have been met and consequently there are Acceptance Incidents.
ii. The severity of these Acceptance Incidents exceeds the limits for progression through this
Acceptance Gateway
iii. Remedial actions are required to address the Acceptance Incidents and / or workarounds.