POL00038826 - Memorandum: Bird and Bird to POCL, 29 July 1998

Evidence on official site

POL00038826

POL00038826
s&s HPO IH]
~*80d STOT “ON XU/XL _ Ob2LT 86, 20/62
BIRD & BIRD
Our Refs . 90 Foner Lane
MEMORANDUM Londen EC4A TIP
Your Ref:
Hy Priyil Hi tint
TO: Pat Kelsey, BA/POCL Programme, Head of Contracts bey
Web Page
ce: Joe Ashton, POCL wewnwoblids.com
Sarah Graham, DSS
George McCorkell, BA
Dave Miller, Horizon
Ron Powell, DSS
David Sibbick, DTI
Partners «
- OD Harriss,
FROM: Hamish Sandison, Partner, Bird & Bird I, Gece
ey DM Gerdwaie
Cz
DATE: 29 July 1998 : Horan
Fiche
RE: Horizon Project - Legal Implications of Partial or Total Br aramcuch
Cancellation of the BA/POCL Automation Project GIN Smah
IRC Walkey
Oxer
MMagrionsid
DMC
cwrees
StHubooe
Introduction . Food
1 Ihave been asked to summarise my previous advice as the Joint Programme Lawyer tie.
on the legal implications of either: CM Crnonate
. NTiecking
RM BickerstsHt
(a) cancelling the Benefit Payment Card (“BPC”) element of the project (Option s skort
2 in the Treasury-led Working Group Report); or te boas
VSACeee
(b) cancelling the entire project (Option 3). Heseeriadl
Cin vere
You will find a more detailed explanation of this advice in my earlier memoranda. Deicen
IM Geel
: AR RLe
Can the DSS cancel unilaterally? . GPewdt
AD Sardenan
2. The Horizon project actually consists of three “Related Agreements:” Mii
PRBrownlew
e the Authorities’ Agreement - between the DSS, POCL and ICL Pathway, jo"
1 Sin
. the DSS Agreement - between the DSS and ICL Pathway; and PCORty
Concattants
. the POCL Agreement - between POCL and ICL Pathway. KTCamold
SNLChsinn
‘KABIBPOCLAOOI\MEMOMKELSEY E34
“8E fame
EC Ofice 2094 Avenue Loulse. 1050 Brussels, Belglum Telephone’ DIN
Hong Kong 20/F Printing House, 18 ke House Steet, ‘Cenval, Hong, not a solienor
yevea'd SSEESLTLTOS OL Gulag 8 CUId Ws EBT sE6t—Nr-6z
POL00038826

POL00038826

2£0d. 8TOT “ON XU/XL @yiLT 86, 10/62

Thus, the two public sector contracting authorities must act jointly to cancel the entire
project (Option 3); the DSS cannot pursue this option on its own.

3. However, in my opinion (although POCL’s lawyers do not agree), the DSS can
terminate the DSS Agreement unilaterally, whereupon it is free to withdraw from all of its
rights and obligations under the Authorities’ Agreement. This would result in the
cancellation of the BPC element of the project (Option 2). .

4, In addition, ] must note that there are two commercial contracts between the DSS
and POCL which govern the provision of benefit encashment services at Post Office
counters. POCL's lawyers take the view (and DSS Jawyers ayree) that, under one of these
commercial contracts, the DSS may not cancel the Related Agreements with ICL Pathway
without POCL’s consent. As the Joint Programme Lawyer, I am not privy to these

- commercial contracts, but it seems obvious to me that any question of POCL exercising a
right of consent over DSS action in relation to its contract with ICL Pathway is
fundamentally a political rather than a legal matter.

Does the DSS have grounds to cancel?

5. The grounds for cancellation are precisely the same under Options 2 and 3. They
include termination for convenience (with compensation up to £129m payable by the DSS
to ICL Pathway and up to £205m payable by POCL to ICL Pathway) and termination for
ICL Pathway’s breach (with compensation up to £200m payable by ICL Pathway to the DSS
and POCL in aggregate).

6, Termination for ICL Pathway’s breach is clearly the preferred route for the DSS
under Options 2 or 3. Equally, ICL Pathway will assert that any purported termination for
its breach is in reality a termination for convenience, and will claim compensation from the
DSS accordingly. The DSS must therefore be able to substantiate its claim of breach by ICL
Pathway, and must not take any action by word or deed to support an argument that it is
really terminating for convenience, c.g., because it thinks that ACT is a cheaper way of
paying benefits than the BPC.

7 On balance, I believe that there is sufficient evidence to justify termination on the
basis of ICL Pathway’s breach.

8. ICL Pathway admittedly failed to complete Operational Trial by the contractual due
date of 21 November 1997. Under the Authorities’ Agreement, if Operational Trial has still
not been completed at the end of a 13 week cure period, either or both of the contracting
authorities may give notice of termination of their respective contracts with immediate
effect. The DSS will be in a position to terminate because of ICL Pathway’s failure by
August 12th. (POCL consider themselves to be in that position already, but I am doubtful
of their view.)

9. However, the fact that ICL Pathway has failed to complete Operational Trial by the
contractual due date does not of course mean that it is liable for breach of contract or that
the contracting authorities are entitled to terminate. On the contrary, ICL Pathway will

KAB\BPOCLOONMEMO\KELSEY 1.M03

PO/EB"d SSGEILTLTGS OL qula 3 quid WONS GEST ss6st—WNe-62
POL00038826

POL00038826

a7

10d TOT “ON XU/XL @P:LT 86, 10/62

PO"d TWLOL

vasrB"d SSEESLTLTAS OL

argue that the DSS and POCL are responsible for the delays, and it will vigorously contest
any attempted termination.

10. To verify its belief that ICL Pathway was in breach, the BA/POCL Programme on
my advice commissioned an independent report earlier this year by Project Mentors
Limited. This found that ICL Pathway was responsible for the delays culminating in its
failure to mect the 21 November 1997 due date, and that the contracting authorities had not
caused or materially contributed to those delays. This report carries a health warning: it was
based only on access to people and documents on the government side and did not include
access to ICL Pathway’s staff or documentation. That said, it provides strong and
independent support for the government’s position.

11. Ofcourse, any litigation with ICL Pathway will be lengthy, uncertain and messy, and
the DSS must expect all of its shortcomings to be fully aired in hostile legal proceedings.
For that reason, a negotiated termination which avoids litigation is clearly the preferred
route to achieving Options 2 or 3. Nevertheless, I remain satisfied that the DSS is entitled
on the evidence available to terminate because of ICL Pathway’s breach.

Other legal implications

12, have also considered the public procurement law implications of Options 2 and 3.
There is agreement between the government lawyers involved that complete termination
presents no procurement law issue, As regards partial termination, the Treasury Solicitor
thinks that this might be viewed as a “descoping” of the contracts with ICL Pathway and
that other potential suppliers might object. For the reasons explained previously in much
greater detail, I think that this view is too cautious (and DSS lawyers agree), and I remain
satisfied that partial termination on the basis of ICL Pathway’s breach does not raise a
procurement law issue.

KABIBPOCLWOIMEMONKELSEY 1L.M03

GuId 3 duld WONS G@b:8T sé6t—INL-6z