POL00039880 - Fax from Jeff Triggs attaching strategy in the event of a decision to terminate

Evidence on official site

POL00039880
POL00039880

Blanehter and May 1-12-1998 ai: 42 PAGE 1/9 RightFAX (Cc)

I
0 I Kevin GORRIGAN COMPANY :POCL
I

fa

? &1 DEC 1998

SLAUGHTER AND MAY

35 Basinghall Street, Lond
Telex I

* LDE and CDE Box No.1

DEC -1 11:01

FAX TRANSMISSION

Date 1st December, 1998 Document number CA983350.042
In reply please quote JRT : Total pages (ine. this) 9
trom Jeff Triggs ‘Writers telephone

To Kevin Corrigan, POCL, London Receiving lax number

(ane ee’)
Mann
Vontr
Sounder
Cad:
\loum -

Please see attached.

THIS FACSIMILE If CONFIDENTIAL AND MAY CONTAIN LEGALLY PRIVILEGED INFORMATION. IF YOU ARE HOT NAMED ABOVE AS
AN ADORESSEK IT MAY BE UNLAWFUL FOR YOU TO READ, COPY, DISTRIBUTE, DITCLOSE OR OTHERWISE USE THE INFORMATION
INTHES FACSIMILE. 1F YOU ARE NOT THE INTENDED RECIPIENT OF THIS FACSIMILE PLEASE TELEPHONE OR FAX US IMMEDIATELY. I

Allist of the parmers and their professional qualifications is available for inspection at the above address.
The partners are either solicitors or registered foreign lawyers.

If you do not receive all the pages, please phone!

01/12 '98 12:44 TX/RX NO.4873 P.001 I

POL00039880
POL00039880

RESTRICTED - POLICY AND COMMERCIAL
LITIGATION PRIVILEGE

To: Robert Ricks HMT Copy: Sarah Graham DSS
Adam Sharples HMT
David Sibbick DTI

From: Jonathan Evans POCL 30' November 1998

BA/POCL AUTOMATION PROGRAMME:
STRATEGY IN THE EVENT OF A DECISION TO TERMINATE

As agreed at the Progress Tracking Group on Friday, I attach our submission
for consideration by the Law Officers.
We understand that a submission is being prepared by Hamish Sandison on

behalf of DSS. We should point out that he has not been instructed to do this
in his capacity as programme lawyer.

Jonathan Evans

Network Director
ice Counters Ltd

e

“a

POL00039880
POL00039880

a

ry and Ma: 1-12-1998 11:42 PAGE 2/3 RightFAX
Kevin CORRIGAN COMPANY : POCL

8Slaugh:
TO

POCL/DSS/ICL PATHWAY

STRICTLY PRIVATE AND CONFIDENTIAL - LITIGATION PRIVILEGE

TERMINATION STRATEGY

A. DOCUMENTATION

We understand that Law Officers will have access to copies of the following
agreements dated 15th May, 1996:-

“Authorities Agreement” among DSS, Post Office Counters Ltd. (“POCI") and
Pathway Group Limited (“Pathway”);

“DSS Agreement” between DSS and Pathway;

“POCL Agreement” between POCL and Pathway;

“Contract A” between DSS and POCL; and

“Contract B” between DSS and POCL.

The Authorities Agreement, DSS Agreement and POCL Agreement are together
referred to as the “Related Agreements”. They govern the contractual relationship of
the parties in relation to delivery of the Horizon Programme.

Contract A governs the provision of benefit encashment services by POCL to
DSS. Contract B governs certain aspects of the contractual relationship between POCL
and DSS as it relates to the Related Agreements.

B. BACKGROUND

The Horizon programme is well behind schedule and negotiations have been
taking place among the parties with a view to agreeing terms under which the
programme can be continued and the Horizon system duly delivered. Pathway has to
date requested very significant enhancements to the Related Agreements as a price for
continuing with the programme and negotiations have proved difficult.

Should the parties fail to reach a negotiated settlement, ministers may wish to

take steps to bring the contracts to an end. Legal advice has been sought as to the best
way of achieving termination.

207738/10582 CA983340,07S JRT 201198:1012.

01/12 '98 12:44 TX/RX NO.4873 P.002 E

POL00039880
POL00039880

Slaughter and May 1-12-1998 11:42 PAGE 3/9 RightFAXx L ‘

TO GRo Kevin CORRIGAN COMPANY:POCL

Cc. RELEVANT CRITERIA
The following criteria have been applied in seeking advice:-

@ ministers will wish to avoid engaging in time-consuming, expensive and
messy litigation if possible;

(ii) ministers will wish to avoid either of the public sector parties (the
“Authorities") being liable in damages to Pathway for wrongful
termination;

(iii) if a decision to terminate is made, Ministers would prefer to terminate
quickly, both for political reasons and to stem the ongoing costs of
continuing with the programme.

D. RISK FACTOR

The major risk factor to be borne in mind when considering termination of the
Related Agreements is the risk that Pathway may successfully sue the Authorities for
wrongful termination of the Related Agreements or successfully allege that termination
fell into the contractual category of “termination for convenience” rather than
termination for Pathway’s breach. In either case, the result would be a liability for the
Authorities to pay to Pathway compensation measured in hundreds of millions of
pounds. .

A claim for wrongful termination is, therefore, something to be avoided and
any political desires around termination have to be weighed against this risk.

E. GROUNDS FOR TERMINATION

Under the Related Agreements Pathway is obliged to achieve certain contractual
milestones. One is to achieve acceptance of Operational Trial by November 1997.
That milestone has not yet been reached and this failure gives the Authorities grounds
on which they are entitled to terminate the Related Agreements.

In order to terminate the Authorities Agreement, DSS and POCL have to act
jointly. In addition, under paragraph 3 of Schedule 18 to Contract B neither Authority
is entitled to terminate its separate agreement with Pathway without the consent of the
other (except in circumstances which are not likely to apply).

The fact that there is a valid ground to terminate does not mean that Pathway !
will not allege that responsibility for the delay lies with the Authorities and that the
Authorities are, therefore, liable in damages to Pathway. Indeed, such an allegation is
a virtually certain consequence of the Authorities taking steps to terminate.

20738/10S82 CA983340.075 IAT 301198:1812

01/12 '98 12:44 TX/RX NO.4873 P.003 E
POL00039880
POL00039880

v

*Piausht rand May 1-12-1998 11:42 PAGE 4/3 RightFAx
: Kevin CORRIGAN COMPANY : POCL

ER LEADING COUNSEL'S ADVICE

Slaughter and May, acting for POCL, have sought the advice of leading Counsel,
Nicholas Strauss Q.C., as to the best way to terminate the Related Agreements should
ministers decide to take that step.

Counsel has advised that in order to achieve termination it will be necessary for
the Authorities to serve notice on Pathway making time of the essence. Provision for a
time of the essence notice is made in clause 902.2.3 of each of the Related
Agreements.

Counsel for POCL and for DSS have both agreed, in their discussion on 22nd
October, 1998, that it is not possible safely to terminate the Related Agreements with
immediate effect without a significant risk of the Authorities being in breach of
contract.

The appropriate duration of a time of the essence notice has been the subject of
some debate. Counsel have advised that it should be a reasonable period for Pathway
to achieve acceptance of Operational Trial. That currently points to a period of around
nine months on the basis of the current indicative timetable. .

Proceeding to terminate without giving a time of the essence notice would give
tise to a serious risk of the Authorities being held to have acted in breach of contract,
which could, in turn, give rise to a liability for damages of hundreds of millions of
pounds.

It is important to bear in mind that if a nine month time of the essence notice is
served on Pathway that does not necessarily mean that the Related Agreements will
continue for the full period of that notice. Faced with the prospect of continuing to
spend what we understand to be around £10 million a month without any certainty
that the system will be accepted at the end of that period (and aware that, even if the
system is accepted, the contract will be unprofitable to Pathway) we think that it is
likely that Pathway would be forced to walk away from the Related Agreements at a
much earlier date. This is all the more likely given Pathway’s current financial position
and the law relating to trading whilst insolvent. :

G. THE DSS VIEW

DSS are concerned that once ministers have decided to terminate it would be
preferable to terminate as soon as possible. This would be politically more attractive
and would save DSS the cost of continuing with the programme.

DSS's view is that it is not necessary to serve a time of the essence notice at all.
Instead termination may be effected under Schedule CS of the Related Agreements.
This, according to DSS, requires the service of a “thirteen week notice” under

Schedule CS. Such a notice was served by DSS back in May 1998. Accordingly, DSS

207738/105#2 CA983340.078 JRT 301198:1812

01/12 '98 12:44 TX/RX NO.4873 P.004 Be

POL00039880
POL00039880

Slaughter and May 1-12-1998 11:42 PAGE 5/3 RightFAX
TO RO I Kevin CORRIGAN COMPANY:POCL .

argues that it can now terminate immediately, whereas POCL first has to serve a
“thirteen week notice”.

DSS also argues that, rather than serve a thirteen week notice, POCL could
simply wait for DSS to terminate on immediate notice under Schedule C5 and then
itself terminate, not on the grounds of delay but simply on the grounds that DSS has
terminated (which entitles POCL to terminate under clause 902.10 of the Authorities
Agreement). .

H POCL’s ARGUMENTS AGAINST THE DSS VIEW

POCUs concerns in relation to the DSS's arguments for the Schedule CS route
and the clause 902.10 “Piggy-back” option are as follows:-

SCHEDULE CS .

There is no “thirteen week notice” requirement in Schedule C5. What Schedule
CS says is that if Acceptance of the Operational Trial is delayed, because of Pathway’s
default, for more than 13 weeks, then the Authorities are entitled to terminate. The
right is an immediate right which arises when, as a result of Pathway’s default,
acceptance is more than 13 weeks overdue. Nothing in Schedule C5 requires any
period of notice to be given.

Acceptance is clearly much more than 13 weeks overdue. On the assumption
that Pathway is responsible for the delay one might reasonably consider, at first blush,
that the Related Agreements are therefore now terminable by immediate notice.
However, there are four main arguments against this view:-

(a) Contractual Interpretation

The contracts provide a number of different routes to achieve termination. One
route is under clauses 402.6.2.3 and 902.2, which requires the giving of a “time
of the essence” notice. Another is the schedule C5 route, which does not
expressly require such a notice. DSS’s argument rests on the assumption that
one can terminate under the schedule C5 route and effectively ignore the time
of the essence requirement in Clause 402.6.2.3. Though arguable, Counsel
have advised that this is a dangerous argument. They think that there is a
significant risk that a court will regard the time of the essence requirement
under 402.6.2.3 and 902.2 as one which the Authorities are not entitled to
ignore but must comply with. Indeed they have described that view as the
more credible.

(b) Waiver

Since 21st November, 1997 (the date for acceptance of the Operational Trial)
Pathway has continued to work under the Related Agreements under what has

207736/10582 CA983240,075 JRT 301198:1812

01/12 '98 12:44 TX/RX NO.4873 P.005 ay
POL00039880

POL00039880

‘

aOR EST, and May 1-12-1998 11: 542 PAGE 6/93 RightFAX

(c)

(d)

_/Kevin CORRIGAN COMPANY:POCL

effectively been an open-ended extension of time. In the circumstances it is
likely chat a court would hold that, regardless of their stated reservations of
rights, the Authorities have effectively waived their rights to terminate the
Related Agreements without now giving a further reasonable time for
completion of the Operational Trial. w

Counsel do not believe that the DSS has effectively protected its position in this
regard by its so-called thirteen week notice served back in May 1998.

Burden of Proof

If the Authorities were to seek to terminate by immediate notice (or thirteen
weeks’ notice) under Schedule CS they would have the burden of proving that
the delay was due to Pathway’s default. Although there appears to be some
confidence that this burden can be discharged it is dangerous to be too
confident before we have seen Pathway’s allegations and evidence in their
pleadings.

Pathway’s likely reaction

If the Authorities were to seek to terminate by immediate (or thirteen weeks’)
notice under Schedule C5 there is every likelihood that Pathway would serve a
writ alleging wrongful termination (or, effectively, describing the Authorities’
action as termination for convenience) and accordingly claim hundreds of
millions of pounds in damages.

If instead the Authorities were to serve a reasonable time of the essence notice
it would be much more difficult for Pathway to claim that the Authorities had
terminated. Indeed, in these circumstances Pathway may well be forced to
walk away, placing the Authorities in a much stronger position in any litigation,
for the following reasons:

di) Pathway would have the burden of proving that the Authorities were in
repudiatory breach of the Agreements, which would be fairly difficult;

ii) assuming Pathway failed to carry out its contractual obligations and
failed to establish repudiatory breach by the Authorities, there should be
relatively little argument about the Authorities’ right to bring the
contract to an end.

These are all fairly technical arguments but our view is that they argue strongly

in favour of giving the time of the essence notice of nine months (or whatever is
established as a reasonable period to achieve Acceptance of the Operational Trial),
especially when one bears in mind the unlikelihood of Pathway continuing with the
contracts for the full period of the notice.

207799710582 CA983349.075 JRT 301198:1812

01/12 '98 12:44 TX/RX NO.4873

P.006

POL00039880
POL00039880

Slaughter and May 41-12-1998 11:42 PAGE 7/9 RightFAX .

TO: GRO ‘Kevin CORRIGAN COMPANY:POCL

CLAUSE 902.10 “PIGGY-BACK” OPTION

The risk of POCL relying on its right to terminate under clause 902.10 as a
result of DSS terminating is that Pathway may successfully allege that DSS was not
entitled to terminate without further notice under Schedule CS, and therefore that its
termination amounted to termination for convenience. In those circumstances Clause
902.10 expressly provides that POCLs termination under 902.10 will also be treated as
termination for convenience, thus exposing POCL to the same claim for damages.

To put it another way, if DSS's termination were wrongful, POCLs would be
wrongful too.

IL DSS’S ARGUMENTS AGAINST THE POCL VIEW,

The DSS argues that the giving of a time of the essence notice is unnecessary.
Its arguments as to why it is an undesirable route for the DSS are, however, political
and financial rather than legal. There are three arguments of which we are aware:-

(a) “Risk” of Programme Success

DSS argues that if a nine month time of the essence notice is served there is a
“risk” that Pathway might successfully achieve the deadline set, so that at the

end of the nine month period the Related Aggements would not be capable of
termination. .

(b) Costs of Continuing

DSS argues that to give a time of the essence notice would involve continuing I
to incur the costs of managing the programme throughout the period of notice.

(c) Publicity
DSS argues that if it were to give a time of the essence notice it would not yet
be able to make a public announcement to the effect that ministers were

terminating the Related Agreements.

J. POCLUS REBUTTALS OF DSS’S ARGUMENTS AGAINST THE POCL VIEW

POCL responds to these DSS arguments as follows:-

(a) “Risk” of Programme Success
Against the background of the current negotiations POCL considers it virtually
inconceivable that, if those negotiations broke down and nothing further were
offered to Pathway, Pathway would simply go ahead with the programme and
achieve acceptance of Operational Trial.

20738/10S82 CA983340.075 JRT301198:1812

01/12 '98 12:44 TX/RX NO.4873 P.007 &
POL00039880

POL00039880

Slaughter and May 1-12-1998 11:42 PAGE 8/9 RightFAX
TO"GRO } Kevin CORRIGAN COMPANY:POCL

@

(b)

(c)

Pathway has made it clear that it would not be able to proceed with the
programme even with the public sector concessions which have been offered to
date. In particular, Pathway has made it clear that it could not continue to
commit £10 million ‘a month to the programme without significantly greater
concessions than have been made to date over commercial terms, acceptance
issues and its funding requirements. To suggest that if all the current -
concessions were taken off the table Pathway would then knuckle down to
spending £10 million a month to arrive at what at worst would be a failure to
achieve acceptance (so throwing away a further £90 million for nothing and
still suffering termination) and at best would be achieving acceptance and so
perpetuating a heavily loss-making contract, appears somewhat fanciful.

It may be suggested that Pathway could continue to work on the programme

throughout the nine month period on the assumption that it could ultimately be °

funded by a damages claim against the Authorities. We have seen no evidence
that Pathway considers its case to be sufficiently strong to justify such action, in
the light of Pathway’s current financial condition.

In any case, POCL would argue that the prospect, however fanciful, of Pathway
achieving acceptance within nine months without any contractual concessions
from the public sector would be something to be warmly welcomed, not treated
as an unacceptable “risk”.

Costs of Continuing

For the reasons stated above, it is unrealistic to assume that the giving of a nine
month time of the essence notice would result in work on the programme
actually continuing for that nine month period. -It is far more likely that
Pathway would be forced to bring the contract to an end much earlier. The
alternative for Pathway would be to spend a further £90 million or so without
much greater certainty that the Related Agreements would not in any case be
terminated for failure to achieve acceptance of Operational Trial in nine
months’ time. That would, for Pathway, amount to throwing good money after
bad. In any case, continuing the contract would cost Pathway a great deal more
than it would cost DSS.

DSS should thus weigh.the small risk of having to continue to incur such costs

against the greater risk of being sued for a much greater sum on the grounds of
wrongful termination.

Publicity
It is accepted that if a time of the essence notice is served on Pathway it would
be wrong for the Government to issue a press release saying that the Related

Agreements were being terminated. However, it would be possible (subject to
contractual confidentiality restraints) to announce that Pathway had been given

1207738/10582 CAV8II40.075 JRT 201198:1812

01/12 198 12:44 TX/RX NO.4873

P.008

POL00039880
POL00039880

Slaughter and May 1-12-1998 11:42 PAGE 9/9 RightFAK
TO} GRO I Kevin CORRIGAN COMPANY :POCL ®

a notice to complete by a specified deadline and that the Authorities had
reserved the right to terminate upon failure to meet that deadline. It is
suggested that such an announcement would in practice have materially the
same effect as an announcement that ministers had decided to terminate the
Related Agreements.

In any case it is suggested that the nature of the announcement should be
determincd by the route which ministers choose to take and not vice versa.

K. CST LETTER

It is suggested that the Chief Secretary of the Treasury need not send a
substantive letter to Pathway should POCI's proposal of sending a time of the essence
notice be adopted. All he would need to do would be to indicate his regret that+
negotiations had broken down and to inform Pathway that it might expect to hear
further from the Authorities in due course.

The Chief Secretary could suggest to Pathway that it would be better to
negotiate an agreed basis for termination rather than indulge in litigation. Our view is
that that would not be appropriate. It is almost inevitable that the parties will seek to
negotiate and in the event that Pathway wished to litigate rather than negotiate such a
suggestion is unlikely to deter it. Indeed, it may even encourage Pathway, if Pathway
were to interpret such a suggestion as a sign of weakness. This is, however, more a
question of tactics than substantive risk.

Slaughter and May (JRT)
30th November, 1998