Initial Complaint Review and Mediation
Scheme
ExCo Update
13 February 2014
‘COMMERCIAL IN CONFIDENCE
POL00344511
POL00344511
Agenda
1. Background/Context
2. Programme Governance
3. Programme Plan
4. Performance Dashboard
5. Key Risks and Issues
6. Second Sight Engagement
7. Scope of the Working Group
8. Timeline of Key Events
9. Stakeholder Engagement
Decisions for this meeting
COMMERCIAL IN CONFIDENCE
POL00344511
POL00344511
1. Background/Context 2)
Background’ \ Programme \ Programme\ Performanca\ Key Risks \ SS Stakeholde!
Cot Governance / Plar Dashboard / & Issues Engagemer Engagemer
‘COMMERCIAL IN CONFIDENCE
POL00344511
POL00344511
2. Programme Governance
; \ Programme \ Programme\ Performance\ Key Risks \ SS Stakeholder
Governance / Plan Dashboard / & Issues Engagemer Engagemen
PO Ltd Board
Executive Committee
Programme Board
Mediation Independent PO Ltd Communic-
Scheme resolution of I Prosecution ations
future cases
Projects Governance
Belinda Ben Rodric Sophie
Crowe Maddison Williams Bialaszewski
‘COMMERCIAL IN CONFIDENCE
POL00344511
POL00344511
2.1 Programme Board ToR
Programme \ Programme\ Performance\ Key Risk: ss Stakeholder!
Governance / Plan Dashboard / & Issues Engagemer Engagemen
Chair & Secretariat Core Membership
+ Chris Aujard, Chair Fay Healey (NED) Belinda Crowe, Angela Van-Den-Bogerd, Charles
+ Nicky Mal, Secretariat Colquhoun, Andy Hott, Rodric Wiliams, Andy Parsons, Sophie Bialaszewski
Jess Barker, Layla Wildon, Nicky Mal, David Oliver
Frequency
+ Fortnightly
Objectives Inputs
+ To provide the overall direction and management of the programme + Programme Board reporting pack
+ Key management information from case tracker
+ Escalated risks or issues for review
+__Draft deliverables for sign-off
Responsibilities & Accountabilities Outputs:
+ Agree key programme artefacts including the programme planand comms I = Agreed programme artefacts
plan + Signed-off programme deliverables
+ Ensure the appropriate coordination across the projects that comprise the I » Agreed mitigating actions for risks /resolution to issues
programme ‘Agreed escalations to ExCo
Reviewing/signing-off deliverables ‘Success criteria for the programme
To design the permanent solution for handling future cases. Minutes and actions
Review civil and criminal cases
Define acceptable risk profile and risk thresholds for the programme & its
projects
+ Resolve issues between projects, which need the input and agreement of
senior stakeholders to ensure the progress of the programme
(Own the resolution of risks and issues that the programme faces
Ensure resource availabilty for programme activities & resolve conflicts,
Resolve dependencies across programmes
Define the success criteria for the programme
Review programme budget every month
Ensure the programme complies with Post Office data security policies
Ensure suggestions for improvementithemes arising out of the programme
are fed into the Business Improvement programme and vice versa
‘Oversight of programme communications /PR
+ Manage Second Sight's role in the programme
‘COMMERCIAL IN CONFIDENCE
POL00344511
POL00344511
3. Programme Plan (2)
Programme \ Programme\ Performance\ Key Risks \ SS Stakeholde!
Governance / Plan Dashboard / & Issues Engagemet Engagemen
tia Scheme Prog
& Case Mec 1@ Plan 2013-14
‘COMMERCIAL IN CONFIDENCE
POL00344511
POL00344511
4. Performance Dashboard (2)
Programme\ Performance\ Key Risks \ SS. Stakeholder!
Pla Dashboard / & Issues Engagemer Engagemen
I Jeteretated
RGRAMRMEANABRAHAHEGE
Hai Wei
L JeyEeI BIEL}
* The Performance Dashboard has been developed
+ Data cleansing/administration activities continue to improve the data quality
‘COMMERCIAL IN CONFIDENCE
POL00344511
POL00344511
Key Risks & ISSUES - extracted from programme re (2)
y \ Programme \ Programme\ Performance\ Key Risks \ SS Stakeholde!
Governance / Plan Dashboard / & Issues Engagemer Engagemen
Risk/Issue n(s) / Update a
There is a substantial We will be producing a paper on how we will manage the
expectation gap - the difference expectation gap for ExCo to consider.
between the amount claimed by
applicants and BD's Bond Dickinson are keeping the expected liability of cases BD
assessment of the realistic under regular review and are leading on identifying suitable
value of the claims. 25 cases for early settlement.
applicants have sought £14M (5
of those are over £1M anda Early engagement with Professional Advisors and MPs are SB
further 7 over £100K). If this is I required to manage expectations and minimise reputational
continued for the rest of the damage to POL/negative perceptions of the Scheme. Initial
applications we would expect to drop-in sessions for MPs are arranged in March.
see a gap of ~£47M.
Second Sight and JFSA Aletter of engagement has been drafted. Second Sight CA
consider the scope of Second have declined to sign the current draft and have asked for a
Sight work to extend beyond number of amendments to be made. Post Office is
the Scheme and in any event, considering these.
have taken a very wide view of
Second Sight's investigatory Apaper will be drafted for ExCo for onward transmission to
role within the Scheme the Board on the Scheme in general, covering the
heightened risk and contractual relationship with Second
Sight
‘COMMERCIAL IN CONFIDENCE
POL00344511
POL00344511
6. Second Sight Engagement (2)
Ba Programme \ Pr mme\ Performance Key Risks \ SS Stakeholde!
ont Governance / Plan Dashboard / & Issues Engagemer Engagemer
‘COMMERCIAL IN CONFIDENCE
POL00344511
POL00344511
7. Scope of the Working Group - BEN (22)
B un Programme \ Programme\ Performance\ Key Ris! ss Stakeholder!
Governance / Plar Dashboard / & Issues Engagemer Engagemen
Post Office has always been clear that the Working Group's role is to ensure the
Scheme is run in a fair and efficient manner. It will also be involved in making
decisions on how particular cases should be managed through the Scheme only.
Scope
* Providing a forum for the resolution of subpostmasters’ complaints?
* Continuously developing and monitoring the mediation scheme?
* Ensuring the Mediation Scheme is run in a fair and efficient manner*
* Confirm suitability of a case submitted by a Subpostmaster for further investigation?
* Ensuring all cases are fully investigated?
* Final decision on any cases that may not be suitable for mediation*
* Make decisions on how cases should be managed through the mediation scheme*
* Nomination of the mediation administrator and the panel of mediators*
0)
‘COMMERCIAL IN CONFIDENCE
1http://media.postoffice.co.uk/News-Releases/Post-Office-statement-on-findings-of-interim-report-into-Horizon-computer-
system-a0.aspx
2http://media.postoffice.co.uk/News-Releases/Post-Office-announces-independent-mediation-scheme-for-subpostmasters-
8d.aspx
3http://media.postoffice.co.uk/News-Releases/Sir-Anthony-Hooper-appointed-as-independent-chair-of-working-group-
overseeing-initial-mediation-sche-72.aspx
ACase Review Mediation Pack(1).pdf
POL00344511
POL00344511
8. Timeline of Key Events 2)
Background’ \\ Programme \ Programme\ Performance\ Key Risks \ SS Stakeholde!
Ce Governance / Plan Dashboard / & Issues Engagemer Engagemer
JAN FEB MAR APR MAY JUN
E ° Peston a 9 ry
rogramme
i cr" o> O & 0 Oo ©
8 anc
a fer tue
Rs pépere distbutedI First mediation case
3
g @ PV- industry & Fartiament Trust dinner
g
2
evans ® I MaovinimyI Srna ne
mtg
bz PVIAHISS mig
ba @ Din session or Lorton
ged MPS @ orop-in session
BS C aeited
Fi Dipp-in session for MPs
Edst of England
z @ Font omee deseaton procurement end
aq PO Advisdry Council
Fi ° @ sransterorFptsu Service desk to Atos
z
1
‘COMMERCIAL IN CONFIDENCE
POL00344511
POL00344511
9. Stakeholder Engagement - DAVID (2)