POL00401822 - Email from James Brett to David Cooke, Phil Norton, Sally Rush and others RE: Channel Integration Phase 1 Acceptance Report - REQGENACS2061 v0.2

Evidence on official site

POL00401822
POL00401822

Message

From: James Brett [/O=MMS/OU=EXCHANGE ADMINISTRATIVE GROUP
(FYDIBOHF23SPDLT)/CN=RECIPIENTS/CN=JAMES. BRETTBAC97F39-BDBS-4D33-85 1C-6723097A6AFA]

Sent: 08/11/2012 19:22:23

To: Cooke David Phil Norton [/O=MMS/OU=EXCHANGE ADMINISTRATIVE GROUP
(FYDIBOHF23SPDLT)/CN=RECIPIENTS/CN=Phil.nortond3bb0a4d-7a53-419d-919b-f359111d04a9]; Sally Rush
[/o=ExchangeLabs/ou=Exchange Administrative Group
(FYDIBOHF23SPDLT)/cn=Recipients/cn=ff87e1ac15864358b2c89daaa546a439-sally.rush]; Tim D Green
[/O=MMS/OU=EXCHANGE ADMINISTRATIVE GROUP
(FYDIBOHF 23SPDLT)/CN=RECIPIENTS/CN=Tim.d.green9da6574c-a056-4efe-9ba3-9afc972b274e]; Abhinav Singh
[/O=MMS/OU=EXCHANGE ADMINISTRATIVE GROUP (FYDIBOHF23SPDLT)/CN=RECIPIENTS/CN=Abhinav.singh]; Jon P
Thompson [/O=MMS/OU=EXCHANGE ADMINISTRATIVE GROUP
(FYDIBOHF23SPDLT)/CN=RECIPIENTS/CN=Jon.p.thompsonddae2d65-4eed-4ef1-9698-899b3dd00d 1c]; lan Trundell
[/o=ExchangeLabs/ou=Exchange Administrative Group
(FYDIBOHF23SPDLT)/< ‘ecipients/cn=063 1dbe659c64e2ba448a773a2306719-ian.trundel]

ce: Godeseth Torstei } Jenkins Gareth GI i

Subject: RE: Channel Integration Phase 1 Acceptance Report - REQGENACS2061 v0.2

all,

Please see below a few brief notes, actions and decisions made at today's Channel Integration Phase 1
Acceptance meeting.

Dave Cooke outlined the Acceptance criteria for progression and summarised the current position against
the 13 CI Phase 1 requirements;

7 met by Design walkthrough - completed at todays session. CI-POC-09 to 11 refer to processing of CI data
to MI, reconciliation and accounting systems. POL accepted the limitation of the CIT environment in
respect of demonstrating these requirements and accept the provisio that data demonstrated to have been
transferred to the branch database can be assumed to fall within existing BRDB extract processes.

3 met through Test - more accurately demonstration within the CIT environment. POL accept that the
demonstration provided evidence to fulfil these testable requirements

2 met through document review - POL accepted that the Phase 1 AIS had not been circulated at the time of
the meeting, but has subsequently been issued for review and approval.

DECISION: All parties present agreed that the criteria had been met and supported the recommendation to
proceed through the Acceptance Gateway.

Regards

James

James Brett I Senior Test Manager

~G\o. Fujitsu Services, BrackoelL RG12 8SN
i

{ }Postline;_____GR
I GRO 7

POSEOTFTEETCS UR
@postofficenews

oo--- Original Messag
From: Cooke David {_
Sent: 06 November
To: Phil Norton; Sally Rush; Tim D Green; James Brett; Abhinav Singh; Jon P Thompson
Cc: Godeseth Torstein; Jenkins Gareth GI; Mehta Mukesh; Greenwood Kath

Subject: Channel Integration Phase 1 Acceptance Report - REQGENACS2061 v0.2

Channel Integration Phase 1 Acceptance

By way of preparation for our meeting this Thursday, please find attached the CI Phase 1 Acceptance
Report.

This is in the same style as other Acceptance reports, but also contains the requirements that we will be
reviewing and details of the demonstration that will be used for the testable criteria.

Regards,
POL00401822
POL00401822

David Cooke

Business Consultant RMG BU

FUJITSU

Lovelace Road, Bracknell, Berkshire RG12 8SN

P Please consider the environment - do you really need to print this email?

Unless otherwise stated, this email has been sent from Fujitsu Services Limited, from Fujitsu (FTS)
Limited, or from Fujitsu Telecommunications Europe Limited, together "Fujitsu".

This email is only for the use of its intended recipient. Its contents are subject to a duty of
confidence and may be privileged. Fujitsu does not guarantee that this email has not been intercepted
and amended or that it is virus-free.

Fujitsu Services Limited, registered in England No 96056, registered office 22 Baker Street, London WluU
3BW.

Fujitsu (FTS) Limited, registered in England No 03808613, registered office 22 Baker Street, London W1U
3BW.

PFU Imaging Solutions Europe Limited, registered in England No 1578652, registered office Hayes Park
Central, Hayes End Road, Hayes, Middlesex, UB4 8FE.

Fujitsu Telecommunications Europe Limited, registered in England No 2548187, registered office solihull
Parkway, Birmingham Business Park, Birmingham, B37 7YU.