WITNO3550100
WITNO3550100
Witness Name: Roger Gilbert
Statement No.: WITN03550100
Dated: 6 November 2024
POST OFFICE HORIZON IT INQUIRY
FIRST WITNESS STATEMENT OF ROGER GILBERT
I, ROGER GILBERT, will say as follows:
INTRODUCTION
1. lama former employee of International Computers Ltd (“ICL”) later renamed
Fujitsu Services Limited (FSL). I retired from FSL in March 2012.
2. This witness statement is made to assist the Post Office Horizon IT Inquiry
(the “Inquiry”) with the matters set out in the Rule 9 Request dated 25th
September 2024 (the “Request”) to the extent I have direct knowledge of the
matters addressed in the Request. The Request deals with events which took
place over 12 years ago, so in some cases mymemory is limited and may be
inaccurate. I have refreshed my memory as far as possible by reviewing the
documents provided to me by the Inquiry.
Page 1 of 48
WITNO3550100
WITNO3550100
3. I have had no legal support or advice in preparing his statement.
4. While preparing this witness statement, I have had no access to documents
and emails that were previously available to me during my employment with
ICL or Fujitsu Services other than documents provided to me by the Inquiry.
5. This statement covers events and my perceptions from over 12 years ago.
Since then, I have learnt more about the Horizon scandal and have become
shocked by the treatment of the Post Office’s SPMs. My sympathies are with
them and their families.
DOCUMENT STRUCTURE
6. The Inquiry has provided several documents which have helped to refresh my
memory. Some of the documents provided are relevant to my witness
statement and these documents are introduced and described before the
relevant paragraphs of my statement.
7. In my witness statement I have used the following terms and abbreviations:
POL Post Office Limited
RMG Royal Mail Group
SPMs Sub-postmasters, sub-postmistresses, counter
managers, and assistants
Fujitsu Limited I The parent Fujitsu company headquartered in
Japan
Page 2 of 48
WITNO3550100
WITNO3550100
Fujitsu UK&l Fujitsu UK and Ireland. The Fujitsu Business
Region which operated in the UK and the
Republic of Ireland
EMC Executive Management Committee
GBG Global Business Group
FSL Fujitsu Services Limited
FSH Fujitsu Services Holdings pic
CEO Chief Executive Officer
PSD Private Sector Division
HNG-X Horizon Online
BACKGROUND PRIOR TO JOINING ICL (FUJITSU SERVICES)
Please set out a summary of your career and qualifications up until joining
Fujitsu UK and Ireland.
8. I attended Queens’ College, Cambridge from 1966 to 1969 as an
undergraduate and was awarded a BA (Hons) Degree in Natural Sciences
My primary subject was Theoretical Physics.
9. From 1969 to 1972 I attended the University of Leeds to study for my PhD
and I subsequently was awarded a PHD degree in Theoretical Physics.
10. In 1972, I was appointed as a Research Fellow with the UK Atomic Energy
Authority and was based at their Harwell research facility. was promoted to
Senior Scientific Officer and undertook a number of mathematical and
Page 3 of 48
WITNO3550100
WITNO3550100
computer software assignments.
11. In 1979 I joined System Designers Limited (later System Designers plc) to
work in their Software Engineering Division. In 1988 Systems Designers plc
acquired Scicon Limited to form SD-Scicon plc. In 1991, EDS‘ won a hostile
bid to take a controlling interest in SD-Scicon which eventually became an
integral part of EDS.
12. During this period of my career with System Designers Limited and up to my
EDS employment, I worked in the following areas.
a.
Software Engineering
Operations Director, Software Products
General Manager, Manufacturing Products and Services
General Manager, Land and Secure Systems (part of EDS Defence)
Managing Director, EDS Defence
13. In 1997, I made a career change and left EDS to be Group Chief Executive
of VEGA Group plc, a public company with a full London Stock Exchange
listing. VEGA had several service streams including:
a.
b.
Space Operations,
Computer Based Training,
‘ EDS was owned by General Motors at the time.
Page 4 of 48
WITNO3550100
WITNO3550100
c. Contract Support and Consultancy.
14. While at VEGA, I received training in the role and responsibilities of a
Company Director.
15. After three years of excellent growth and profitability, Vega had a
disappointing year and, by mutual agreement, I decided to move on.
BACKGROUND AFTER JOINING ICL (FUJITSU SERVICES)
Please briefly set out what roles you held whilst employed at Fujitsu UK and
Ireland (noting the more detailed questions that follow).
16. In 2002, I was head-hunted by ICL and subsequently joined ICL reporting to
David Courtley who was then Chief Operations Officer. I had known David
from EDS. He was my predecessor as Managing Director of EDS Defence.
He wanted me to be one of the new senior managers in a major
reorganisation he was planning in preparation for the rebranding of ICL to
Fujitsu Services. I was interviewed, I think, by David Courtley, Richard
Christou, and the UK Head of HR. My role was to be Managing Director,
Central Government Business Unit. This did not include Horizon. David was
aware that my plan was to retire early and that I saw my time at Fujitsu
Services as a “project” rather than a long-term career. Nevertheless, I enjoyed
the role I was given and was determined to succeed and support David's
objectives for the rebranded business.
Page 5 of 48
WITNO3550100
WITNO3550100
I have been provided with an email thread from Nagai Atsushi to David
Courtley, 10th March 2004, subject: Major Accounts Paper for FJ EMC
(FUJO0176145)
17.
18.
19.
(FUJ00176145) was an email sent during my time as Manager of the Central
Government Business Unit. In the email, I was asked to explain 2 Red Alerts
in Major Accounts. As David Courtley points out in the email thread, the
request regarding the Post Office should have been directed to lan Lamb or
Martin Riddle. I can confirm that I had no involvement or knowledge of the
Post Office projects at that time.
After three and a half successful years as Managing Director, Central
Government Business Unit, I wanted to make some initial steps towards my
retirement and to step back from the full-time Managing Director role. Fujitsu
Services initiated a formal selection process for my successor and in July
2005, Eithne Wallis CB (now Eithne Victoria, Baroness Birt, CB) was
appointed. Following this appointment, I became part-time Chairman, Central
Government Business Unit working for 3 days per week.
In January 2007, I was appointed Group Director and Head of the Account
Management Community. This was also a part-time role with responsibilities
for staff training and development within the Account Management
Community. The aim was to establish and maintain best practice in account
management across Fujitsu Services. My remit included the Royal Mail Group
Page 6 of 48
WITNO3550100
WITNO3550100
(RMG) Account (the Account responsible for Fujitsu Services’ work on
Horizon). However, my role did not extend to any operational activity or
oversight.
20. Following David Courtleys departure in January 2009, I became a fulltime
assistant to Richard Christou to support him in David Courtley’s absence.
21. In April 2009, following the approval by Fujitsu’s Executive Management
Committee (EMC)*, I was appointed Chief Executive Officer (CEO) of the
newly formed region of Fujitsu UK and Ireland.
ORGANISATIONAL CHANGES - FINANCIAL YEAR 2010/11
22. 2010 saw the start of Fujitsu globalisation which I understand continued for
many years after I left Fujitsu. The main changes affecting the UK and Ireland
at that time were as follows.
a. Richard Christou resigned as Executive Chairman of Fujitsu Services
Limited (FSH)° and Fujitsu Services Holdings plc (FSL)*. This, I
understand, allowed him to spend more time to focus on his role as
President of the Global Business Group (GBG).
b. In April 2009, after EMC approval, I was appointed Executive Chairman
2 The EMC was a committee of the Fujitsu Limited Board.
3 FSH was a subsidiary of Fujitsu Limited.
4 FSL was a subsidiary of FSH.
Page 7 of 48
WITNO3550100
WITNO3550100
of FSH and Executive Chairman of FSL. I held these chairmanships
alongside my CEO, Fujitsu UK&l, role.
c. The previous Fujitsu Services Management Committee (FSMC) which
had provided the EMC with oversight of FSL and FSH was disbanded.
d. Instead, a stronger Japanese representation was established on the
FSH Board to maintain EMC oversight of the UK, Ireland, and Nordic
businesses.°
23. I was appointed to the following Boards.
a. Fujitsu Telecommunications Europe Limited (as chairman)
b. Fujitsu Research of Europe Limited
c. Fujitsu (Ireland) Limited
24. I received training, while at Fujitsu UK&l, in the role and responsibilities of a
Company Chairman.
ORGANISATIONAL CHANGES - FINANCIAL YEAR 2011/12
25. In March 2011, Duncan Tait was appointed as my replacement as CEO,
Fujitsu UK&l.
5 After the reorganisation, FSH’s main subsidiaries were FSL and FSH BV; the latter had
responsibility for the Nordic countries.
Page 8 of 48
WITNO3550100
WITNO3550100
26. In April 2011 Rod Vawdrey was appointed as the new President of the Global
Business Group (GBG) replacing Richard Christou. Rod Vawdrey’s previous
role was CEO, Fujitsu Australia and was known to me though meetings of the
GBG CEO Forum. Both Duncan Tait and I reported to Rod.
27. Between April 2011 and March 2012, my employment with FSL gradually
reduced from full time to about 2 days a week. During this period, I retained
my Chairmanship roles within Fujitsu. I retired on 31st March 2012.
BACKGROUND AFTER RETIRING FROM FUJITSU SERVICES LIMITED
If applicable, please provide an overview of your professional career since
retiring from Fujitsu UK and Ireland.
28. After my retirement from FSL, I undertook no further business or consultancy
activity. After I had negotiated my exit arrangements, I had no further contact
with Fujitsu.
MY ROLE AS CHIEF EXECUTIVE, FUJITSU UK&l
Please describe the background to your appointment as Chief Executive of
Fujitsu UK and Ireland, including details of any application and interview
process. In particular, please set out the nature of your role and explain your
responsibilities.
29. In April 2009, Richard Christou recommended my appointment as CEO of
Fujitsu UK&l to the EMC. The recommendation was approved, and my
Page 9 of 48
30.
WITNO3550100
WITNO3550100
appointment was confirmed.
As CEO of Fujitsu UK&Il, my responsibilities were:
a.
To confirm or appoint members of my first line and t ensure that Fujitsu
UK&l was organised, empowered, and incentivised to create the best
possible outcome for Fujitsu UK&l and for Fujitsu as a whole,
Prior to the start of each financial year, to create a rolling medium-term
plan covering the next three financial years with a detailed budget for the
next financial year,
To manage Fujitsu UK&l against targets for revenue growth, profitability,
customer satisfaction and employee satisfaction,
To attend a Quarterly Business Review (QBR)* so that performance of
UK and Ireland against my targets and the medium-term plan can be
scrutinised and assessed by the EMC,
To review all the Divisions monthly to monitor performance and resolve
any issues,
To review and approve proposals for new bids, contract signature, and
other business activities within Fujitsu UK&l that needed my level of
delegated authority,
To arrange approval by the GBG or EMC where my level of delegated
® The QBR and the quarterly FSH Board were held at the same time in Tokyo.
Page 10 of 48
WITNO3550100
WITNO3550100
authority was exceeded,
h. To meet and build relationships with senior customers,
i. To meet employee groups to present my vision and plans and answer
questions,
j. To take a deeper look at any issues that were reported to me that created
a significant risk to the performance or success of Fujitsu UK&l,
k. To create a strategy for future development of Fujitsu UK&l.
31. I was keen to maximise the growth and profitability of Fujitsu UK&l by
introducing tighter controls to improve the performance. These included:
a. a better risk management system,
b. independent reviews of customer proposals covering all aspects of the
deal prior to bid reviews,
c. improved sales management and customer engagement,
d. matching our resources to our business.
J have been provided with an email from Roger Gilbert to Steve Clayton and
others, 1%* June 2009, subject: Enterprise Risk Management (FUJ00116747)
32. (FUJ00116747) is an instruction from me to use a standardised way of
reporting risks to make it easier for Business Assurance to improve the
standard of risk management across Fujitsu UK&l. This instruction was one
of many changes I made to improve controls as explained above.
33. Atthe time of my appointment as CEO, I had five business Divisions each led
Page 11 of 48
WITNO3550100
WITNO3550100
by a managing director:
a. Government Division
b. Private Sector Division (PSD)
c. Ireland Division
d. Technology Solutions Division’
e. Core which provided shared services across the other Divisions
SIZE AND GOVERNANCE OF FUJITSU UK&l
34. Fujitsu UK&l was a large region: £2,000M in revenues, more than 12,000
staff, more than 50 accounts with annual revenues over £5M and a similar
number of large sales campaigns®. Running such a business required:
a. an organisation which allowed the delegation of individual businesses
and accounts to competent managers, and
b. governance systems in place to make sure the CEO and other senior
managers are focussed on the big and significant issues.
35. With regard to organisation, Fujitsu UK&l business activities were split into
five divisions and, within those divisions, responsibility for individual accounts
and business activities was allocated.
7 The Technology Solutions Division was essentially a reseller of Fujitsu branded hardware.
® These are approximate figures from memory.
Page 12 of 48
WITNO3550100
WITNO3550100
36. With regard to governance, a well-established sequence of reviews was in
place to keep the CEO and other senior managers informed of performance
and risk issues. These included:
a. Monthly Divisional Reviews
These took place with each of the Divisions looking at financial
performance, business opportunities, account performance and staff
issues. It was a chance for the Division to ask for help. Divisional
performance would be judged against their targets and medium-term
plans.
b. Account Reviews
These were chaired at Divisional, Regional, or GBG level as appropriate.
Accounts would be assessed against their account plans and significant
issues would be escalated as appropriate.
c. Bid Approval Reviews (BARs)
BARs would review and, if agreed, approve a new customer proposal. It
would cover technical, financial, resourcing, risks, and resource issues.
This would be chaired at a level appropriate to the size of the deal
d. _Contract Approval Reviews (CARs)
A CAR would be called before a contract signature to confirm all the
elements of the deal. After the CAR, account plans would be created
from the BAR and CAR spreadsheets and other materials. These plans
would form the baseline for subsequent account reviews.
Page 13 of 48
37.
38.
WITNO3550100
WITNO3550100
e. Quarterly Business Reviews (QBSs)
QBRs were held quarterly at GBG/EMC level, and they coincided with
FSH Board Meetings.
There were several other mechanisms in place to ensure that senior
managers were kept informed of relevant risks, events, and other issues in a
timely fashion:
a. Business Assurance and the Red/Amber “Alert” system (see below)
b. Issues raised by the commercial and legal team which had a separate
reporting line to the CEO and Board
c. — Issues raised by the financial team which had a separate reporting line
to the CEO and Board.
d. The Japanese oversight team (see below).
The role of Business Assurance was particularly important. Their activities
included:
a. Maintaining a summary of all accounts, sales campaigns, and bids within
Fujitsu UK&l.
b. Managing the system of independent “Gold” reviews of bids and
proposals that checked the viability and profitability of submissions.
c. Managing the Customer Satisfaction and Win/Loss interviews, analysis,
and reports.
d. Organising the reviews of accounts against the quality assurance
Page 14 of 48
39.
40.
WITNO3550100
WITNO3550100
standards 1S027001 and ISO9001 as part of the wider certification of
Fujitsu UK&l by external assessors.
e. Producing a risk report for the quarterly meeting of the Corporate
Governance Committee of Fujitsu Services Holdings plc
f. Managing the alert system which identified issues that required extra
resources or attention. There were two levels of alert: Amber and Red.
An Amber Alert required a Divisional Managing Director's urgent
attention, and a Red Alert required the CEO urgent attention. Both
required the allocation of additional resources.
Representatives of Business Assurance attended and monitored actions from
Account Reviews, Divisional Reviews, Bid Approval Reviews, and Contract
Approval Reviews.
There was an independent team of Japanese employees who were tasked
with working with the larger Projects, Bids and Accounts and report back their
findings to senior managers in Tokyo. Any issues that were discovered by this
route would lead to an appropriate level of investigation.
I found the organisation and governance of Fujitsu UK&l, as described above,
to be excellent and they served me well for the time I was CEO. It was the
basis of my oversight of all the accounts and business activities that I was
responsible for. This included the RMG Account and the important HNG-X
programme within that account.
Page 15 of 48
WITNO3550100
WITNO3550100
RELATIONSHIP BETWEEN FUJITSU AND UK GOVERNMENT
Please describe the relationship between Fujitsu UK and Ireland and the UK
Government during your tenure as CEO, Fujitsu UK and Ireland.
41. In 2008, the NHS terminated their contract with Fujitsu after a dispute over
contract changes. The amounts involved were significant and a mutually
acceptable agreement was hard to find. It has been reported in the press that
this was settled long after I had left. I have no knowledge of this settlement.
However, there is little doubt in my mind that the NHS dispute lmited our
ability to do business with UK government while I was CEO.
42. In mid-2010, the cabinet office initiated a program called “The Efficiency and
Reform Group”. Their aim was to introduce more central oversight in
government contracting and to seek savings in the contracts that were
already in place. They set price reduction targets on all their major suppliers
including Fujitsu UK&l. Because of the nature of its business with
government, Fujitsu UK&l found it hard to achieve their expected targets while
retaining an acceptable profit margin. An MOU was eventually signed n 2011,
but the negotiations were difficult and would not have helped our relationship
with UK Government.
43. Notwithstanding these difficulties, UK government still provided a sizeable
proportion (over 50%) of Fujitsu UK&l’s revenue in 2011 and had some of
Fujitsu’s most important contracts and relationships.
Page 16 of 48
WITNO3550100
WITNO3550100
44. Fujitsu UK&l interfaced with Government via various trade bodies and
committees. This includes the CBI, Intellect’®, and PITCOM"
45. The difficulties with NHS and the “Efficiency and Reform Group,” were a
challenge for Fujitsu UK&l given the percentage of government business that
Fujitsu UK&l had. It was part of my long-term strategy to rebalance the
business increasing the percentage of private sector contracts. This potential
change did not influence my view of the importance of the RMG Account.
THE INTEGRITY AND ROBUSTNESS OF HORIZON
46. Many of the Inquiry’s questions refer to the “Integrity” and “Robustness” of
Horizon and its data. My interpretation of these terms is as follows.
a. I have taken the “Integrity of Data” to mean “the accuracy, completeness
and consistency of the data.”
b. I have taken the “Integrity of Horizon” to mean “how well Horizon’s code
was tested to ensure correctness against its specification.”
c. I have taken the “Robustness of Horizon” to mean “the ability of Horizon
to cope with errors during execution and to cope with erroneous input.”
° Fujitsu, UK&l was a member of CBI's Public Sector Strategy Board
10 Intellect changed it name to Tech UK some time ago.
" The Parliamentary Information Technology Committee, now part of The Parliamentary
Internet, Communications and Technology Forum
Page 17 of 48
WITNO3550100
WITNO3550100
THE PRIVATE SECTOR DIVISION (PSD)
47. PSD was responsible for many customer accounts of varying sizes mostly
from the private sector. The Royal Mail Group (RMG) Account was included
within PSD for historical reasons and was one of PSD’s larger accounts. It
included all the work done on Legacy Horizon and HNG-X. The annual
revenue of PSD would have been about £500M and I think the total annual
revenue of the RMG Account would have been close to £100M. I recall it
being about the 4" or 5" largest account in Fujitsu UK&l.
MANAGEMENT AND OVERSIGHT OF THE RMG ACCOUNT
48. As explained in paragraph 40, my oversight of the RMG Account would be
based on the organisation, delegation and governance that we had in place.
Where PSD concerns or other indications alerted me to the need for
additional oversight or resources, that would be provided.
Please describe your knowledge and understanding of the Horizon IT System
when you were first appointed as Chief Executive.
49. On my appointment, I had only a superficial knowledge of its function within
the Post Office.
50. My knowledge increased as I chaired the Monthly Divisional Reviews and as
I engaged with the RMG Account prior to Duncan’s arrival.
Did you receive any briefing(s) about the operations or robustness of
Page 18 of 48
WITNO3550100
WITNO3550100
Horizon? If so, from whom and what do you recall being told?
51.
52.
53.
When I was first appointed CEO, I had early reviews with all my divisions
when I was briefed about their customers and the role that Fujitsu UK&l
played within their customers’ organisations. I probably spent about 2 hours
reviewing PSD covering finance, sales campaigns, staff and all their
accounts. Given the other agenda items, it’s likely that no more then 10-15
minutes was spent on Horizon in that first review. I cannot recall in detail what
I was told but it probably included where Horizon was used, its business
function, profitability for Fujitsu UK&I, growth opportunities and customer
satisfaction figures. There would have been little time for more. I can’t recall
who presented this information.
I would learn more about Horizon in subsequent reviews and interactions
The level of my knowledge was appropriate for my seniority and was
adequate to discuss progress and issues with PSD and the RMG Account.
I received no briefings on the “robustness” of Horizon.
Please describe your management / oversight of the Post Office Account
What were the specific oversight mechanisms in place at executive level to
monitor HNG-X’s development and deployment?
54.
When I was appointed as CEO, PSD was managed by Mike Stares. Around
the time of my appointment, Mike had accepted a new senior role leaving a
Page 19 of 48
55.
56.
57.
58.
WITNO3550100
WITNO3550100
vacancy for the Managing Director role. Peter Rowley, who was a well
respected legal & commercial director within FSL and had a detailed
knowledge of the business within PSD filled the role for a short time.
As a result of an executive search, Duncan Tait was identified as someone
we wanted to recruit. Duncan was interviewed by GBG and after obtaining
approval from the EMC, the decision was taken to appoint Duncan as
Managing Director of PSD.
There was a period of about three months before Duncan's arrival in October
2009 when the Managing Director role of PSD was vacant. In that period,
senior members of the Division provided cover, and I allocated more of my
time to support them.
The oversight of the RMG Account would normally be through the
organisation, delegation and governance systems described in paragraphs
34 to 39. However, it was apparent shortly after my appointment as CEO that
the current phase of HNG-X development required closer attention.
HNG-X was a major project in the RMG Account and had been subject to
EMC scrutiny from before my appointment as CEO. I believe this was
because of the early history of Horizon within Fujitsu and because, as far as
I can recall, the project had a Parent Company Guarantee. The EMC required
regular reports from me on the progress of the HMG-X development.
Page 20 of 48
WITNO3550100
WITNO3550100
59. Legacy Horizon, on the other hand, was seen as being trouble free. It had
been in service for a number of years; POL, as far as I understood, were
happy with the service; and the maintenance costs were broadly as expected.
How (if at all) did business objectives in relation to the Post Office Account
change following your appointment as CEO, Fujitsu UK and Ireland.
60. The top-level Business objectives (contract delivery, profit, revenue,
customer and employee satisfaction) did not change. Nevertheless, the
importance of HNG-X to our future relationship with RMG was very clear. Its
success was essential.
61. There were three distinct phases where the level of my oversight and
involvement changed quite significantly. These are addressed under the next
three headings.
OVERSIGHT OF HNG-X PRIOR TO THE PILOT PHASE
62. I remember that within afew days of my appointment, I had a discussion with
Peter Rowley about the need to replan the HMG-X programme. It was clear
that additional programme management talent would be needed to achieve a
plan that would improve the dates, make it more secure against slippage and
reduce the projected financial loss. Peter transferred in some experienced
project managers from elsewhere in Fujitsu UK&l so that the planning of a
“get well’ programme could start.
Page 21 of 48
WITNO3550100
WITNO3550100
63. I met with Mike Young’? in May 2009 to introduce myself and to explain the
need for a new baseline. I would also have explained Peter Rowley’s role at
that meeting.
I have been provided with an email from Jon Wolfe to Roger Gilbert and
others, 11th May 2009, subject: Notes from call with Mike Young
(FUJO0173733).
64. (FUJ00173733) appears to be some intelligence from Jon Wolfe’? who had
spoken to Mike Young. It gives information about Mike Young's character,
objectives and attitude towards Fujitsu. This seems to have been written
shortly before my meeting with Mike Young mentioned above and it helped
me to fix the time of that meeting.
65. I think I had a follow-up phone call with Mike Young around July 2009 to tell
him about Duncan Tait’s appointment and arrival.
66. The replan continued over the next month or so and it was inevitable that we
would be declaring a milestone delay to POL. We knew this was likely to
trigger a claim for compensation.
12 Mike Young was then Operations Director at POL
‘8 Jon Wolfe was, as I recall, a new member of the HNG-X team brought in to help with
replanning.
Page 22 of 48
WITNO3550100
WITNO3550100
I have been provided with
. A letter from Andrew Hall to Mike Young, 7th August 2009, subject:
HNG-X baseline (FUJ00174018)
. Aletter from Mike Young to Andrew Hall, 14th August 2009, subject:
HNG-X baseline (FUJ00174033)
. An annex to a letter, undated, subject: POL costs and loss of
benefits (FUJ00174034)
67. (FUJ00174018), (FUJ00174033) and (FUJ00174034) appear to be the
opening exchange in the compensation negotiation between Andrew Hall'*
and Mike Young. I don’t remember these letters in detail, but they would be
the type of letters I would expect at this time when both sides are presenting
their positions as strongly as they can.
68. I followed these negotiations but was not directly involved in them; the matter
was delegated to the RMG Account who were supported by a strong finance
and commercial teams.
I have been provided with an email thread from Alan D’Alvarez to Roger
Gilbert and others, 9th November 2009, subject: HNGX update on Weekend
‘4 Andrew Hall was the Account Director of the RMG Account
Page 23 of 48
WITNO3550100
WITNO3550100
B/C (FUJ00174232).
69. I don’t remember email (FUJ00174232), but it seems to cover a number of
things.
a. The recognition by POL that the Data Centre Migration was a complex
and critical milestone — one of the most complex attempted in David
Gray’s'® experience,
b. Recognition that the migration had been executed well,
c. A“Thank You” from POL,
d. Fujitsu and POL working together to achieve pilot and roll-out.
The tone of this email appears quite different from earlier communications
and seems to show that the negotiations were successful and the relationship
between POL and Fujitsu had become much better.
What (if any) changes occurred in the nature and frequency of Fujitsu UK and
Ireland’s interactions with the senior executive team of POL following your
appointment as CEO, Fujitsu UK and Ireland?
70. 1am not aware of the nature and frequency of theinteractions with the senior
executive team prior to my appointment. I believe the interactions after my
appointment were appropriate for the issues being tackled. Once Duncan Tait
‘S David Gray was IT Strategy and Architecture Manager at POL
Page 24 of 48
WITNO3550100
WITNO3550100
was in place, he became the prime point of contact.
OVERSIGHT OF HNG-X DURING THE PILOT PHASE
71. With Duncan in place, the primary oversight of the RMG Account would be
delegated to him and I would have started to spend less time on HNG-X.
I have been provided with an email thread from Steve Goldsmith to Allen
Graham, 16th February 2010, subject: Amber alert ref 1053 — Post Office
(HNG-X) - Update report (FUJ00093028).
72. I\'m not sure if I received (FUJ00093028) at the time. The alert system run by
Business Assurance required the CEO to be notified of Red Alerts but not
necessarily Amber Alerts.
73. I have read the alert summary to prepare my statement and noted that it
records the Alert being opened on the 23% December 2008, but I think this
must be a typo and should read 2009. The alert report shows the pilot
progressing with 30 branches trading on HNG-X and a move to the Medium
Volume Pilot scheduled for 17 February as long as the team can fix the
Branch Trading Statement issue. It notes further challenges for later phases
of pilot.
74. I can see nothing in (FUJ00093028) that would have caused me particular
concern had it been sent to me. I would have expected the HNG-X team to
work through the problems that were mentioned. Duncan was there to
Page 25 of 48
WITNO3550100
WITNO3550100
arrange additional help should it be needed. I note that there was a review
scheduled with me on 22nd February. I don't recall that review.
I have been provided with email from RED ALERTS to multiple recipients, 31st
March 2010, subject: Corporate Red Alert Ref 1112 - Post Office Limited
(RMGA) - Initial Report (FUJ00095061).
75.
(FUJ00095061) was the notification of Red Alert 1112 on the RMG Account.
I remember this alert quite well. I recall it had several aspects but the ones
that caused most concern were problems with the Oracle Database software.
The email records that the decision to suspend the pilot was because of live
operational issues affecting all HNG-X branches in the pilot. The delay and
the additional costs of the pilot was a significant issue for Fujitsu UK&l, and it
became particularly frustrating when the account team had found Oracle’s
code at fault. I recall Oracle refusing to believe that the problem was with
them but eventually they cooperated. I remember that getting a fully working
solution from Oracle took several weeks and only then could the pilot be
restarted.
I have been provided with an email from Michael Keegan to Nigel Wood and
others, 17th August 2011, subject: Oracle £500K "Gesture" Opportunity
(FUJO0168456).
76.
(FUJ00168456) shows that, sometime after the Oracle fault was fixed, Oracle
accepted that they could have supported Fujitsu better and an “ex-gratia”
Page 26 of 48
WITNO3550100
WITNO3550100
arrangement worth about £500K was being discussed to compensate Fujitsu.
The HNG-X pilot launched and was suspended shortly after, who made the
decision to suspend the HNG-X pilot and what action was taken to monitor
and rectify issues it had faced?
77. My recollection is that there was a joint Fujitsu/POL Release Authorisation
Board that took decisions regarding pilot and rol-out approvals. Although it
wasn’t my decision, I believe they had little choice but to halt the pilot.
78. The RMG Account were responsible for rectifying the issues including getting
Oracle’s cooperation to fix their software. There would have been calls to
Oracle to get senior management attention — and I probably made some of
those calls, although I cannot remember the details. In any case the problem
was escalated within Oracle and eventually they provided suitable fixes. The
RMG Account was part of PSD who provided the primary level of oversight.
The Red Alert team produced daily progress reports thatwere sent to relevant
staff including me.
J have been provided with an email thread from Roger Gilbert to Gavin Bounds
and others, 2"? April 2010, subject: Post Office Service Issues — Daily Update
(FUJ00174289)
79. I wrote (FUJ00174289) after another incident during the HNG-X pilot. This
arose because of a failure at Fujitsu’s Belfast data centre. The email’s
Page 27 of 48
WITNO3550100
WITNO3550100
purpose was to ensure that I had a proper understanding of the event. From
memory, there was a problem with the Northern Ireland Electricity Network
and the data centre ran on diesel generators for a while. I believe some large
power spikes from a night of severe weather got through the switch-over and
smoothing circuitry and damaged some servers.
1 have been provided with an email thread from Gavin Bounds to Roger
Gilbert, 9th April 2010, subject: Post Office David Smith CEO (FUJ00174292)
80. I don’t remember (FUJ00174292) but I can tell from its date that it arrived
while the pilot had been suspended because of the HNGX-Oracle issue; the
Belfast Data Centre had recently suffered a power problem; and Fujitsu was
still some way from receiving the Oracle fix. It was a report of Duncan Tait’s
meeting with POL’s CEO, David Smith. Given the problems Fujitsu were
having, it was pleasing to see the support we were getting from POL. Duncan
summed up the meeting by the comment:
“A constructive session I believe, of course focussed on the issues
of the last two weeks but ended with the CEO saying, ‘once we
have these issues sorted, we should meet and discuss futures’."
1 have been provided with an email thread from Vince Fullwood to Gavin
Bounds, and others, 10° May 2010, subject: Post Office - Open Book
(FUJO0095628).
81. I was not a recipient of the whole thread in (FUJ00095628), but I was a
Page 28 of 48
82.
WITNO3550100
WITNO3550100
recipient of the first email in the thread from Duncan Tait to myself. The email
lists three requests from Mike Young which I remember discussing with
Duncan Tait. I recollect that my views on the three requests were as follows.
a. An Open Book Arrangement
Open book was not something Fujitsu UK&l would normally agree to, it
would introduce delays, and could affect our future ability to negotiate
prices. I was not enthusiastic.
b. Independent Review of Processes, Tools and Resources
We knew that the pilot delay was largely due to failures in the Oracle
code, so it was difficult to see how a review of Fujitsu's activities could
serve much purpose. In any case, it would introduce further delays and
costs.
c. Dialogue between Dave Smith and Richard Christou
This was a reasonable request.
The passage of time and my limited memory may have led me to simplify my
explanation of the issues involved in (a) and (b) above but I think I have
captured the key points.
I believe Duncan resisted the requests (a) and (b) above and I heard no more
about them. I also remember our Executive Assistants trying to set up
meetings around that time between POL and myself and Richard Christou. I
vaguely remember diary management taking a little time, but over the
Page 29 of 48
WITNO3550100
WITNO3550100
following months, I remember there were meetings and phone calls involving
some if not all of Mike Young, David Smith, Richard Christou, Duncan Tait
and myself.
Please describe the concerns which POL raised in May 2010 about the
management of the HNG-X programme.
How did you respond to POL’s request for greater oversight of Fujitsu UK and
Ireland’s management of the HNG-X programme?
83. I assume these questions arise from the oldest email in the track referenced
as URN (FUJ00095628). I have explained my response, as far as I remember
it, in paragraph 81. My recollection is that POL’s concerns were largely
addressed after the following.
a. Fujitsu had demonstrated its ability to get HNG-X back into pilot once
Oracle had corrected their software, and
b. POL had met with Richard Christou and others about Fujitsu Limited’s
commitment in Japan and the strength of Fujitsu’s resources in the UK.
84. The Red Alert would have been cleared once it was certain that it would not
reoccur, probably in June. Nevertheless, I was aware that Fujitsu’s
relationship with POL had been damaged by the pilot delays, but I was happy
that Duncan was managing this, and from my perspective, HNG-X entered a
quieter period.
Page 30 of 48
WITNO3550100
WITNO3550100
I have been provided with a slide set, Roger Gilbert, June 2010, subject:
Fujitsu UK&l, Contracts Update (FUJ00097198).
85. (FUJ00097198) was written by me but I’m not sure where it was used. It
contains a summary of the HNG-X contract performance in June 2010. It
mentions additional delays and compensation because of the Oracle issues,
and it shows the loss-making nature of the contract in FY 2009/10. There isa
major forecast improvement for FY 2010/11 showing the confidence I had in
the project's future.
86. By July 2010 I felt that the HNG-X problems were largely over. Roltout had
started and every indication was that it was going well. No more alerts were
seen, and I had the impression that all was well, and that POL were happy
with HNG-X performance.
What steps were taken to ensure that HNG-X was fit for purpose before its
rollout?
87. I am aware that Horizon was subjected to a Fujitsu/POL agreed set of
acceptance tests and pilot phases which would provides confidence that
Horizon was “fit for purpose”. I further understand that a joint Fujitsu/POL
Release Authorisation Board approved all decisions regarding the start of any
pilot and rol-out phase and this would be contingent on thorough acceptance
and readiness tests.
Page 31 of 48
WITNO3550100
WITNO3550100
88. I had no detailed knowledge of Horizon’s acceptance test and pilot regime,
but I can make some comments, based on my general understanding ofthe
issues.
a.
Acceptance tests will aim to exercise as many routes through the
software as possible, but they can never guarantee to find all the
software faults that are present. With a complex system like HNG-X,
there will be thousands of different execution paths through the software
to handle all the combinations of functions, timing and interfacing that
will be encountered. Acceptance tests can, in practice, only exercise a
percentage of these paths and will focus on paths that are expected to
be the most heavily used.
Pilots are an essential next stage and will expose the software to “real
life” situations. This will test many more of the execution paths and
should give confidence that the software is “fit for purpose”. Faults found
during pilot should be expected and seen in a positive light— they are
faults that will be fixed and tested and will not be allowed to continue to
the live system.
However, it is not possible for the combined acceptance test and pilot
process to catch every fault that may be present. It is therefore essential
that all sides are alert to any remaining issues or suspected issues in the
live system.
Page 32 of 48
WITNO3550100
WITNO3550100
OVERSIGHT OF HNG-X THROUGH ROLL-OUT AND BEYOND
Please describe the nature and extent of your knowledge of, or involvement
with, the issues relating to the roll out of HNG-X.
89. My knowledge of rol-out was appropriate for my seniority and was enough to
allow the discussion of issues between the RMG Account and myself.
90. After the pilot phase was over and rollout was underway, all indications that
I received from PSD were positive. There seemed no need for additional CEO
attention other that that provided by the delegation and governance that we
had in place (paragraphs 34 to 39).
I have been provided with the following.
. An email from Gavin Bounds to Roger Gilbert and others, 22nd
July 2010, subject: Channel 4 doc next week re POL and our
Horizon system (FUJ00174378)
. An email from Gavin Bounds to Roger Gilbert and others, 6th
August 2010, subject: Post Office faces legal action over accounts
IT (FUJ00156195)
91. Both (FUJ00174378) and (FUJ00156195) were about the dispute between
the Post Office and a number of SPMs. I do not recall the July email which I
see does not mention SPM prosecutions. It was followed up by the August
email which I do remember. I can see that the thread was started when the
Page 33 of 48
WITNO3550100
WITNO3550100
SPMs'’ dispute was picked up in an Accountancy Age article which, in turn,
was spotted probably by the press office in Tokyo. I remember deciding that
no action on my part was required. Thinking back, I can see several reasons
why I might have come to that conclusion.
a. The article must have been about Legacy Horizon which was seen as a
very stable system. No Amber or Red alert had been raised on Legacy
Horizon for some time, and I had not been aware of any concerns from
PSD or POL.
b. We had developed a strong working relationship with POL, and it would
have been difficult to believe that their assurances regarding the integrity
of Horizon and the care taken prior to any prosecutionwere anything but
genuine.
c. Gavin had recommended “no cause for immediate concern.”
d. Channel 4 had apparently withdrawn their programme.
92. lam confident that the email (FUJ00156195) was the only time that the issue
of SPM prosecutions was raised with me during my time at Fujitsu.
1 have been provided with a Post Office/Fujitsu Note, 29° September 2010,
subject: Receipts/Payments Mismatch Issue. (POL00028838).
93. I have no knowledge of (POL00028838) or any of its contents. I am confident
that I have had no contact with any of the attendees listed.
Page 34 of 48
WITNO3550100
WITNO3550100
I have been provided with an email from Mike Young to Duncan Tait and
others, 8th February 2011, subject: Inside Out South. (FUJ00174417).
94. I note that I wasn’t on the recipient list for (FUJO00174417), and I have no
recollection of it. It would appear that Mike Young gave Duncan a link to an
“Inside Out South” programme dated 7" February 2011. I had no knowledge
of this programme during my time at Fujitsu.
95. After receiving the Request, I have found a copy of the program on You Tube
and watched it. It is impossible not to feel angry about the way the SPMs were
treated.
What (if any) concerns did you have during your tenure about
° the existence of bugs, errors or defects in Horizon,
. the integrity of the data processed and recorded by Horizon,
. the risk that faults in Horizon could cause apparent shortfalls or
discrepancies in the branch accounts of SPMs, and
. whether the processes and procedures relied upon to identify and
rectify accounting errors caused by faults in Horizon were robust.
96. The management of the pilots and rol-out was delegated to PSD and the
RMG Account. Paragraphs 75 and 79 describe two issues that I was made
aware of during pilot and there may have been other bugs, errors, defects,
data integrity issues, shortfalls or discrepancies discovered during the pilots.
Page 35 of 48
WITNO3550100
WITNO3550100
These issues would have been managed and resolved by the RMG Account,
and would have been part of the normal activity of a pilot. They would only
have given me concern if they started to cause significant delays and
overspend, as indeed happened with the Oracle issues (see paragraph 75).
97. The role of the pilot phase is described in more detail in paragraph 88.
98. In live running, the absence of any issue from PSD or from elsewhere would
lead me to believe that everything was being managed successfully, and I
would have had no concerns. I would be assuming that PSD and POL were
working together to resolve any problems that arise.
What (if any) steps did I take to obtain assurance about the integrity of
Horizon data?
Please confirm whether and, if so, by whom you were given assurances about
the integrity of Horizon data.
99. Since there was no concern from PSD or from elsewhere, I did not seek or
receive specific assurances about the integrity of Horizon data.
Please set out your knowledge of Fujitsu’s ability remotely to insert, edit or
delete data in branch accounts and whether that developed over time.
100. This was a matter that was delegated to PSD. However, I can confirm that,
during my tenure, I had no knowledge of Fujitsu’s ability or lack of ability
remotely to insert, edit or delete data in branch accounts and whether that
Page 36 of 48
WITNO3550100
WITNO3550100
developed over time. I can further confirm that, during my tenure, I was never
made aware of any statements made about remote access to SPMs.
101. It seems to me that a level of (infrequent) remote access by Fujitsu was
necessary. This access might be needed, for example, if the Fujitsu
maintenance team discovered that a Horizon software fault had created an
error in the branch accounts. It seems hard to believe that there weren't staff
within POL that knew this. Of course, the checks, audits and transparency
associated with any access is a complex area which deserves the Inquiry’s
close attention. I don’t personally understand why any SPM was told that
remote access was “impossible”.
How often were you briefed on HNG-X’s performance / issues and by who?
102. I was briefed from time to time as part of the PSD Monthly Divisional Review
LITIGATION SUPPORT
Please describe the nature and extent of your knowledge of and/or
involvement with:
. any negotiations and / or discussions with POL concerning the
nature or extent of litigation support that would be provided by
Fujitsu (including the provision of data, witness statements and/or
expert evidence),
. Fujitsu’s involvement in providing litigation support to POL,
Page 37 of 48
WITNO3550100
WITNO3550100
including providing data, witness statements and/or evidence that
was relied on as expert evidence in criminal litigation,
. the training and / or legal support provided to those within Fujitsu
involved in litigation support and / or giving evidence to court, and
. executive oversight of Fujitsu’s litigation support services.
103. This was a matter that was delegated to PSD. However, I can confirm that I
had no knowledge or involvement with any of the activities listed in the
question above except for reading Gavin Bounds’ comment in the email dated
6th August 2010 (FUJ00156195) This email included the sentence:
“Fujitsu is obligated to support Post Office, where requested to do
so, by either providing system information to support the cases or,
in some cases, expert witnesses to testify as to the measures within
the systems to ensure that the data being relied on is as originally
entered. This has been going on for a number of years with little
incident.”
When I read this extract, I believe I would have taken it to mean that we were
doing no more or no less than the contract required. I did not understand
about the legal implications of being an expert witness or whether Gavin was
using the term “expert witness” loosely to mean a witness who is an expert in
some topic. In any case, I thought no more about it. Further commentary on
(FUJ00156195) is contained in paragraph 91.
Page 38 of 48
WITNO3550100
WITNO3550100
Please describe the nature and extent of your knowledge of Fujitsu’s
involvement in specific pieces of litigation, including but not limited to, the
prosecution of Seema Misra.
104. I had no knowledge of Fujitsu's involvement in specific pieces of litigation.
ARQ DATA
Please describe the nature and extent of your knowledge of ARQ data and its
use in litigation support? In particular, please set out to what extent, if at all,
you were aware of:
. any issues with the integrity and/or accuracy of ARQ data
. whether Fujitsu employees had the ability to insert, edit or modify
ARQ data (whether at source or the data provided to POL); and
. whether any such matters were communicated to POL?
105. I had no knowledge of ARQ data or any of the issues listed in the question.
SPMs CLAIMS ABOUT HORIZON INTEGRITY
When did I first become aware that SPMs were attributing apparent shortfalls
and discrepancies in their branch accounts to faults in Horizon?
106. I became aware that there was a dispute between POL and a group of SPMs
on reading an Accountancy Age article in August 2010 (FUJ00156195). POL
issued a statement that Horizon was not the underlying problem. Please see
paragraph 91 above for a detailed explanation of my response.
Page 39 of 48
WITNO3550100
WITNO3550100
What processes, if any, were in place to escalate issues raised by SPMs to
the board. Would these issues be regularly monitored by the board.
107. I was not aware of any contractual or formal mechanism for the SPMs to
escalate matters to the FSL or FSH boards. I have no recollectionof an SPM
ever requesting a meeting with an FSL or FSH Director.
When did you first become aware of the Computer Weekly article raising
issues with Horizon; what was your initial reaction to the claims? What steps
did you take to ensure the claims in the article were investigated?
108. I became aware of the Computer Weekly Horizon campaign after I retired,
probably in 2013.
109. While I was CEO or Chairman, I did not read any articles from Computer
Weekly covering the Horizon story.
110. Fujitsu's press office would scan the press for mentions of “Fujitsu” and
produce a press digest for senior managers. Interestingly, they missed
Computer Weekly's pieces on Horizon during my tenure. I have recently
looked at Computer Weekly's articles on Horizon and discovered that “Fujitsu”
was mentioned once in 2009 and then not again until 2013. The mention in
2009 was very brief and the connection was not clear without careful reading.
I assume the press office did not scan for “Horizon” — possibly not on their
radar at the time. That may explain why I was unaware of Computer Weekly's
Page 40 of 48
WITNO3550100
WITNO3550100
campaign.
111. Unlike Computer Weekly, Accountancy Age (FUJ00156195) had a clear
“Fujitsu” reference, so it was easy for the press office to pick it up.
In retrospect, do you believe your response to the article was adequate. If not,
what would you have done differently?
112. I did not see the article, so the question does not apply.
MY ROLE AS CHAIRMAN OF FSH AND FSL.
Please describe the background to your appointment as Chairman of Fujitsu
UK and Ireland.
113. Paragraphs 22 describes the background to my appointments as Executive
Chairman of both FSH and FSL and the relationship between FSH and FSL.
Please set out the nature of your role and explain your responsibilities.
114. As chairman of FSH and FSL, I had two primary roles.
a. Ensure that the companies were being managed competently in the
interest of their shareholders and that they met their statutory legal,
financial, and reporting obligations.
b. Ensure that the corporate structure provided the key reporting line from
the relevant Fujitsu Regions to the EMC and parent Fujitsu company.
The board papers of FSH were essentially reports to the EMC.
Page 41 of 48
WITNO3550100
WITNO3550100
115. I chaired the Board meetings of FSH and FSL which were held four times a
year. I was responsible for issues such as
a. Overseeing all board meetings, including meeting agendas
b. Facilitating discussion between the board directors
116. FSH had a Corporate Governance Committee and an Audit Committee. I
chaired both these committees which sat a few weeks after each board
meeting.
117. The FSH Corporate Governance Committee was responsible forissues such
as
a. Ensuring effective corporate governance
b. Reviewing the policies and process for managing risk
c. Ensuring that directors have the appropriate skills, and training
118. The FSH audit committee was responsible for issues such as
a. Audit and Compliance
b. Policies relating to the reporting of financial statements
9
Investigating claims of bribery, corruption, etc
d. Health and safety
e. Data security and data protection
f. Whistleblowing.
119. The Corporate Governance and Audit Committees had a remit for all FSH
Page 42 of 48
WITNO3550100
WITNO3550100
Group Companies including FSL.
BOARD OVERSIGHT
Please describe how the Board maintained oversight of the following matters:
the integrity of the Horizon IT System (including both Legacy
Horizon and Horizon Online,
. the quality of technical support services relevant to the Horizon IT
System that were provided by Fujitsu UK and Ireland to POL,
. the prosecution and litigation support services provided by Fujitsu
UK and Ireland to POL, RMG or RMH,
. POL and Fujitsu UK and Ireland’s relationship.
120. I have no access to board minutes or papers so I am relying only on memory
to answer this question.
121. From memory, the only topics relevant to the RMG Account that I can
remember being discussed in an FSL or FSH Board meeting were.
a. RMG Red Alerts
b. IThe HNG-X pilot, progress and delays
c. Roll-out
d. Financial performance
122. From the list of topics given in the question, the only one that might have been
discussed was the POL and Fujitsu relationship as part of a discussion about
Page 43 of 48
WITNO3550100
WITNO3550100
delays in the HNG-X pilot. I do not recall if any actions were placed regarding
this topic.
Please describe your management / oversight of the Post Office Account
during your tenure as chairman.
123. This would be the same as my oversight as CEO except that after Duncan
Tait’s appointment as CEO, my role would have been mostly limited to
corporate, structural, fiscal, and legal matters and not involve operational
matters.
How did you ensure that Fujitsu UK and Ireland was fulfilling its obligations
to POL regarding Horizon?
124. It was an important obligation of the Board to ensure that FSH fulfilled its
obligations to all its customers and the CEO's report had a section covering
contractual issues which would form the initial basis for discussion. The CEO
and FSH’s Commercial and Legal Director would be major contributors toany
discussion in this area.
GENERAL
Please reflect on your time at Fujitsu UK and Ireland and set out whether there
is anything you would have handled differently with hindsight in relation to
the Horizon IT System. Please address the following issues in particular:
. the extent to which you maintained effective oversight of the Post
Page 44 of 48
WITNO3550100
WITNO3550100
Office Account and its response to challenges to the integrity of
Horizon,
. whether you took adequate steps to gain an appropriate level of
understanding about the operation of and known faults in Horizon,
and
. whether opportunities were missed to obtain an accurate
assessment of the integrity of Horizon during your employment
with Fujitsu UK and Ireland.
125. I have reflected on my time at Fujitsu and with hindsight the only issue that I
regret is Fujitsu’s provision of prosecution support to POL. I do not believe
Fujitsu should have provided this support and should not have provided
expert witnesses.
126. I maintained effective oversight of the RMG Account through the organisation,
delegation and governance systems that were in place. Challenges to the
integrity of Horizon were never visible to me either directly or viaother means.
127. I had an understanding about the operation of Horizon appropriate to my
seniority in Fujitsu. Neither POL nor PSD had escalated to me any concern
about Horizon faults during live running. Nor had Fujitsu UK&l governance
flagged the need for CEO attention concerning any fault in Horizon. I did not
have any knowledge of “known faults” in Horizon.
Page 45 of 48
WITNO3550100
WITNO3550100
128. There was no reason, during my tenure, for me to obtain an accurate
assessment of the integrity of Horizon since the integrity of Horizon was never
raised to me as an issue by POL, PSD or via any other means.
STATEMENT OF TRUTH
I believe the content of this statement to be true.
Dated: G November 2o2u
Page 46 of 48
WITNO3550100
WITNO3550100
INDEX TO FIRST WITNESS STATEMENT OF ROGER GILBERT
No
URN
Document Description
Paragr
aphs
Control Number
FUJ00176145
An email thread from Nagai
Atsushi to David Courtley, 10"
March 2004, subject: Major
Accounts Paper for FJ EMC.
17
POINQ0230379F
FUJ00116747
An email from Roger Gilbert
to Steve Clayton and others,
14t June 2009, subject:
Enterprise Risk Management
32
POINQ0122918F
FUJ00173733
An email from Jon Wolfe to
Roger Gilbert and others, 11!
May 2009, subject: Notes
from call with Mike Young
64
POINQ0179914F
FUJ00174018
A letter from Andrew Hall to
Mike Young, 7‘ August 2009,
subject: HNG-X Baseline.
67
POINQ0180199F
FUJ00174033
A letter from Mike Young to
Andrew Hall, 14" August
2009, subject: HNG-X
Baseline
67
POINQ0180214F
FUJ00174034
An annex to a letter, undated,
subject: POL costs and loss of
benefits
67
POINQ0180215F
FUJ00174232
An email thread from Alan
D'Alvarez to Roger Gilbert
and others, 9 November
2009, subject: HNG-X update
on Weekend B/C.
69
POINQ0180413F
FUJ00093028
An email thread from Steve
Goldsmith to Allen Graham,
16th February 2010, subject:
Amber alert ref 1053 — Post
Office (HNG-X) — Update
report
72, 74
POINQ0099199F
FUJ00095061
An email from RED ALERTS
to multiple recipients, 31%t
March 2010, subject:
Corporate Red Alert Ref 1112
- Post Office Limited (RMGA)
- Initial Report
75
POINQ0101232F
Page 47 of 48
WITNO3550100
WITNO3550100
No
URN
Document Description
Paragr
aphs
Control Number
10
FUJ00168456
An email from Michael
Keegan to Nigel Wood and
others, 17 August 2011,
subject: Oracle £500K
"Gesture" Opportunity
76
POINQ0174637F
11
FUJ00174289
An email thread from Roger
Gilbert to Gavin Bounds and
others, 2"4 April 2010, subject:
Post Office Service Issues —
Daily Update
79
POINQ0180470F
12
FUJ00174292
An email thread from Gavin
Bounds to Roger Gilbert, 9"
April 2010, subject: Post
Office David Smith CEO
80
POINQ0180473F
13
FUJ00095628
An email thread from Vince
Fullwood to Gavin Bounds,
and others, 10" May 2010,
subject: Post Office - Open
Book.
81, 83
POINQ0101799F
14
FUJ00097198
Slide set, Roger Gilbert, June
2010, subject: Fujitsu UK&l,
Contracts Update
85
POINQ0103369F
15
FUJ00174378
An email from Gavin Bounds
to Roger Gilbert and others,
22"4 July 2010 subject:
Channel 4 doc next week re
POL and our Horizon system
91
POINQ0180559F
16
FUJ00156195
An email from Gavin Bounds
to Roger Gilbert and others,
6% August 2010, subject: Post
Office faces legal action over
accounts IT
91, 92,
103,
106,
111
POINQ0162389F
17
POL00028838
Post Office/Fujitsu Note, 29"
September 2010, subject:
Receipts/Payments Mismatch
Issue
93
POL-0025320
18
FUJ00174417
An email from Mike Young to
Duncan Tait and others, 8"
February 2011, subject: Inside
Out South.
94
POINQ0180598F