ICL Pathway POCL Infrastructure Acceptance __Ref.CR/ACS/007
Specification Version:2.0
Date:31/03/1999
Document Title POCL Infrastructure Acceptance Test.
Document Type Acceptance Specification
Abstract This document describes the Acceptance Test for POCL
Infrastructure
Status Issued
Author Dave Cooke
Approval By
Distribution Pathway Management Team
Test & Integration Manager
Pathway Library
POCL/DSS Tha
Horizon Bob Booth
Tony Houghton
Jeff Austin
Recommended for ICL Pathway Test Manager Authority(ies) Test Manager
Approval
Signature
Name
Date
Approved For and behalf of ICL For and behalf of Authority(ies)
Pathway
Signature
Name
Date
© 1999 ICL Pathway Ltd = COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 1 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL.
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance __Ref.CR/ACS/007
Specification Version:2.0
Date:31/03/1999
0. DOCUMENT CONTROL
0.1 DOCUMENT HISTORY
Version Date Reason
1.0 23/05/1997 I Issued to PDA
1.4 July 1997 Incorporates amendments agreed at reviews of 3
land 9" July 1997. Not issued
1.2 [06/04/1998 IRe-issued to reflect New Release 2.
1.3 [05/08/1998 IIssued to reflect changes agreed during POCL
review of 05/08/1998.
1.4 [05/11/1998 IIssued to reflect changes agreed during POCL
review of 29/10/1998.
1.5 03/12/1998 _IIssued to reflect changes agreed during POCL
review of 24/11/1998.
1.6 18/12/1998 Ilssued to reflect comments received from POCL on
v1.4 and subsequent reviews.
1.7 22/12/98 Updated to reflect final changes and caveats
lagreed with POCL on 16", 18" & 22/12/98.
1.8 26/02/99 Updated to reflect comments / agreements reached
lon criteria 469/2, 470/1 8467/3.
1.9 10/03/99 Updated to reflect changes in section 5.1.2 and
lother typographical errors.
1.10 30/03/99 (Corrections applied following POCL review.
2.0 31/3/99 Issued for approval
0.2 ASSOCIATED DOCUMENTS
© 1999 ICL Pathway Ltd COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 2 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL.
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance __Ref.CR/ACS/007
Specification Version:2.0
(03/1999
Reference \Vers. IDate Title [Source
1) IAcceptance (Acceptance Criteria Pathway
Criteria
2) IAcceptance 0.1 13/09/1996 IStandard for Raising and IPathway
Standard Progressing Acceptance
Incidents.
I3) IAcceptance 1.1. [29/5/98 Standard for documenting IPathway
Standard [Acceptance Specification
4) ‘Authorities’ 17.2 [22/05/1997 IAcceptance Procedures IDSS/POCL
[Agreement Schedule (A)AO7
5) IPOCL Agreement I7.2 (22/05/1997 IAcceptance Procedures IPOCL
Schedule (P)A11
6) IDSS Agreement 7.2 [22/05/1997 IAcceptance Procedures IDSS
ISchedule (D)A11
7) IAuthorities’ 8.1 [08/03/1998 IRequirements Schedule IDSS/POCL
[Agreement (A)BO4
I8) IAuthorities’ 8.1 I08/03/1998 ISolutions Schedule Pathway
[Agreement (A)BOS
9) IDSS Agreement 8.1 08/03/1998 IRequirements Schedule IDSS
(D)A15
10) IDSS Agreement {8.1 [08/03/1998 ISolutions Schedule Pathway
(D)A16
11) IPOCL Agreement I8.0 I13/11/1997 [Requirements Schedule IPOCL
(P)A15
12) IPOCL Agreement I8.1 {08/03/1998 ISolutions Schedule Pathway
(P)A16
13) IPOCL Agreement I6.2 {03/04/1997 IPOCL Infrastructure IPOCL
Schedule G01 - Service
Definition
14) IPOCL Agreement I6.2 03/04/1997 /POCL Infrastructure IPOCL
Schedule G10 - Service
Levels and Remedies
M5) IVI/TSC/105 2.0 [28/01/1998 ITechnical Integrity and Pathway
INetworking - High Level
\Test Plan
16) IVI/PLA/O11 2.0 [21/08/1998 IPost Office Platform Pathway
[Domain Security High
Level Test Plan
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 3 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL.
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance __Ref.CR/ACS/007
Specification Version:2.0
Date:31/03/1999
17) IVI/PLA/O10 4.0 21/08/1998 IPOCL and POCL Clients [Pathway
Domain Security High
Level Test Plan
18) IVI/TSC/034 1.0 I27/03/1998 [Business Thread RDSO1_ [Pathway
19) IVI/TSC/110 1.0 I30/01/1998 IRelease 2 Systems Pathway
Management High Level
\Test Plan
20) IVI/PLA/O09 3.0 06/03/1998 [Release 2 Central ServicesIPathway
Domain Security High
Level Test Plan
21) INot used
22) WI/TSC/113 3.0 05/02/1998 IPerformance Assurance [Pathway
High Level Test Plan for
Release 2
23) IVI/TSC/048 1.0 I13/03/1998 [Business Thread BITO3 Pathway
24) IPM/PLA/031 7.0 I19/01/1999 INew Release 2 High Level IPathway
Plan
25) IBP/DES/003 4.0 03/02/1998 ICounter Hardware Design IPathway
Specification
26) ICS/PRO/0024 10.3 I20/04/1998 Release 2 Operating Pathway
Environment Processes
land Procedures Document
27) INot used
28) IPOCL 8.0 I16/01/1998 IPOCL Agreement IPOCL
[AGREEMENT Schedule BO4 - POCL
Consumables
29) IDSS AGREEMENTI8.0 16/01/1998 IDAA Agreement Schedule IPathway
B04 - DSS Consumables
30) tba tba tba OPS Architecture Pathway
Document
31) Itba tba tba TMS Architecture Pathway
Document
32) Itba tba tba Riposte 32 API Pathway
Specification
33) ISU/MAN/003 1.0 I01/01/1997 ICFM: ICLS Sorbus Pathway
Pathway Project
Operations Manual
34) ISU/WKI/011 1.0 I04/06/1997 Horizon System Help Desk Pathway
(Work Instructions
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24,
/OL/0L
Page 4 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL.
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance __Ref.CR/ACS/007
Specification Version:2.0
Date:31/03/1999
35) ISD/STD/001 1.5 I28/02/1999 IHorizon OPS Style Guide IPathway
36) ITD-ARC-002 1.0 I29/10/1996 [Network Architecture Pathway
37) ITD-ARC-0001 4.0 I16/06/1998 ITechnical Environment Pathway
Description
(Note: A version (or
subsets thereof) approved
for external publication will
be provided)
38) IIM-SPE-0002 1.2. I15/05/1998 IThe Network Design - Pathway
[Campus Communications
39) IVI/RES/002 tba tba Declaration of conformity - IPathway
\Technical Construction File}
40) IVI/STR/001 2.0 30/09/1996 ITesting and Integration Pathway
Strategy
41) ITba tba tba [Asset Register Pathway
42) ISU/SPE/010 1.0 I26/03/1997 [Specification - Pathway [Pathway
Keyboard
43) IAP/IFS/0030 10.5 [01/10/1998 IPathway to Client Generic IPathway
ITechnical Interface
44) IBP/DES/010 1.0 11/03/99 ITP Service Design Pathway
Specification
45) ITD/ARC/0012 3.0 [24/09/1998 ITechnical Environment Pathway
Implementation for
Release 2
M6) ITba Network Infringement Pathway
Policy
47) ITba Network Infringement Pathway
Report
48) ICR/FSP/004 4.0 [30/09/1997 IService Architecture Pathway
Design Document
49) IBS/DES/001 2.0 I15/10/1998 IBPS Agents High Level Pathway
Design for Release 2
50) IES/IFS/002 2.0 15/01/1997 IRiposte Peripheral Server IPathway
51) ISU/SPE/012 1.0 I01/09/1997 IFirmware Specifications - IPathway
Pathway Keyboard
52) ICS/FSP/002 2.0 I29/10/1997 Horizon System Help Desk IPathway
Call Enquiry Matrix
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24,
/OL/0L
Page 5 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL.
ICL Pathway
POCL Infrastructure Acceptance
Specification
Version:2.0
Date:3
FUJ00001463
FUJ00001463
Ref:CR/ACS/007
(03/1999
53)
ICS/PRO/048
0.4
(04/12/1998
Horizon System Helpdesk :
Processes and Procedures
Description
Pathway
54)
tba
Pathway Environmental
Policy
Pathway
55)
tba
Performance Model
Component Calibration for
Release 2
Pathway
56)
ISU/SPE/008
1.0
(01/11/1996
Magnetic Card Reader
Specification
Pathway
57)
ICS/PRP/tba
IAPS Benchmark Counter
\Transaction Times for
Release 2
Pathway
58)
ICS/PRP/tba
IBES Benchmark Counter
[Transaction Times for
Release 2
Pathway
59)
ICS/PRP/tba
OBCS Benchmark Counter
\Transaction Times for
Release 2
Pathway
160)
ICS/PRP/tba
IEPOS Benchmark Counter
\Transaction Times for
Release 2
Pathway
64)
PA/STR/009
2.0
24/02/1998
Pathway New Release 2
Contents Description
Pathway
62)
BP/DES/008
1.0
15/12/1997
IOBCS Design
Specification
Pathway
63)
ISU/REP/003
3.1
16/04/1997
(Oracle High Level Design
IPMS/CMS
Pathway
64)
ICA/DES/009
1.0
(08/01/1998
ICAPS Access Service -
System Design
Pathway
65)
ICR/REP/012
0.1
(04/04/1998
IA2A - Boundary
Performance
Pathway
66)
IBP/FSP/004
13.8
16/02/99
IEPOSS Functional
Specification
Pathway
67)
Not used
68)
IVI/STR/O06
12.0
24/10/1997
Revisions to the Testing
land Integration Approach
for Pathway Release 2
Pathway
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 6 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL.
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance Ref:CR/ACS/007
Specification Version:2.0°
Date:31/03/1999
69) ICS/PRO/0047 10.5 04/12/1998 IPayment Card Helpline: IPathway
Processes and procedures
Description
70) ISU/PRD/004 1.0 I09/04/1997 ISMC Core Processes for IPathway
\Service Delivery
71) ICS/PRO/0025 10.4 [05/05/1998 IAccess Control and User IPathway
[Administration - Processes
land Procedures
Description
72) ISU/REP/016 2.0 I01/10/1997 IMaestro Job Schedule- Pathway
IPAS/CMS
173) ILF/BRD/O01 1.0 I20/05/1998 ILogistics Feeder System {Pathway
Business Requirement
Definition
174) INot used
175) ICS/PER/013 x.0 IMonthly Service Review - Pathway
Performance Statistics
176) ICS/MAN/004 1.0 I24/08/1998 ICustomer Services - Pathway
Service Management
(Operations Manual
77) ISU/SPE/009 1.0 I12/08/1997 ISmart Card Reader Test Pathway
Report
78) IAUTHORITIES 16.0 [04/12/1996 JAUTHORITIES BA/POCL
[AGREEMENT [AGREEMENT
79) ITD/DES/030 1.0 I25/07/1997 ITime Services Pathway
Specification
80) Itba ICL Pathway External Pathway
(Applications Procurement
Policy
81) ICR/ACR/??? (Audit Closure Report Pathway
82) IVI/PLA/007 3.0 I20/08/98 Systems Management and IPathway
Support Services Domain
Security - High Level Test
Plan
83) Itba IOPS/TMS Data Pathway
[Acknowledgement Process
84) Itba ICL Pathway Performance IPathway
land Scalability Strategy
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 7 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL.
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance __Ref.CR/ACS/007
Specification Version:2.0
Date:31/03/1999
85) ITD/ION/005 1.0 I04/11/98 IFTMS Configurations for IPathway
Pathway TPS and POCL
TIP links at Release 2
86) IRANR2(ChB) 2.2 (09/11/98 Release Authorisation of IHorizon
the NR2 (Child Benefit )
Release
87) ISD/STR/002 0.8 I15/07/98 Release 2 FTMS Pathway
Resilience and Recovery
strategy
88) IVI/TSC/082 3.0 25/11/98 IBusiness Thread EP01 Pathway
89) IPCL/TST/CLR/001 I2.0 [28/08/98 _ [DIT Closure Report - New IHorizon
\V2_0 Release 2
90) Itb.a IMOT Closure Report - NewHorizon
Release 2
191) ICR/ACR/013 IEnd to End Acceptance _—‘ [Pathway
\Closure Report
92) IAs_cav01.doc 10.1 (04/12/98 Acceptance Specification IDSS/POCL
ld Consolidated Caveats
raft
93) IVI/TSC/040 4.0 (28/10/98 High Level Test Plan Pathway
ITPSO101
94) tba 4.0 07/12/98 [Planned Evaluation Matrix IPOCL
95) ITI/IFS/008 10.3 I10/03/99 __ [Pathway to Post Office Pathway
ITechnical Interface
Specification
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24,
/OL/OL
Page 8 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL.
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance Ref:CR/ACS/007
Specification Version:2.0
Date:31/03/1999
0.3. ABBREVIATIONS
BA Benefits Agency
BT Business Thread
CMS Card Management System
cs (Pathway) Customer Services
DSS Department of Social Security
HLTP High Level Test Plan
MIS Management Information Service
OPS Office Platform Service
PAS Payment Authorisation System
PDA Programme Development Authority
PO Post Office
POCL Post Office Counters Limited
PPD Process and Procedures Document
SADD Service Architecture Design Document
SLA Service Level Agreement
SLAM Service Level Administration & Management
SMC System Management Centre
TIP Transaction Information Processing
TMS Transaction Management Service
0.4 CHANGES IN THIS VERSION
e Criterion 536/1 - reference changed from ref.(76) to ref.(74) as advised in v1.9
e Title of ref.(61) applied correctly in document
e Criterion 478/12 - Document title inserted against ref.(44)
e Section 5.1.1 - Criterion 468/1 removed
e Section 5.3 - Entries for 537/1 merged
0.5 GENERAL CAVEAT
Approval of this Acceptance Specification is subject to the relevant caveats in the
extant version of Acceptance Specification Consolidated Caveats.
© 1999 ICL Pathway Ltd COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 9 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance __Ref.CR/ACS/007
Specification Version:2.0
Date:31/03/1999
0.6 TABLE OF CONTENT
0. DOCUMENT CONTROL 2
On DOCUMENT HISTORY 2
0.2 ASSOCIATED DOCUMENTS 3
0.3 ABBREVIATIONS 10
0.4 CHANGES IN THIS VERSION 10
0.5 GENERAL CAVEAT 10
0.6 TABLE OF CONTENT il
2. ACCEPTANCE INCIDENTS 13
3. ACCEPTANCE PERIOD 14
4. DELIVERABLES & SERVICE 14
5. ACCEPTANCE CRITERIA 14
5.1 Acceptance Criteria and test Conditions 14
5.11 Description of tests conducted by Acceptance Trial 16
5.1.2 Criterion Description of tests conducted by Acceptance Review 41
3.2 Criterion for later acceptance 89
5.3 Criterion Summary 94
6. ACCEPTANCE INCIDENT SEVERITY 98
6.1 High Severity Incidents 98
6.2 Medium Severity Incidents 98
6.3 Low Severity Incidents 98
7. TEST DATA 100
8. AUTHORITY RESPONSIBILITIES 101
8.1 Appoint Test Manager 101
8.2 Acceptance Incident Reports 101
© 1999 ICL Pathway Ltd COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 10 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL.
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance __Ref.CR/ACS/007
Specification Version:2.0
Date:31/03/1999
8.3 Acceptance INCIDENT Analysis Reports 101
8.4 Attendance At Trials And Reviews 101
8.5 Management and CO-ORDINATION 101
8.6 Progress Reviews 101
9. CONTRACTOR RESPONSIBILITIES 102
10. ACCEPTANCE TRIAL TEST CONDITIONS 102
© 1999 ICL Pathway Ltd COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 11 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL.
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance Ref:CR/ACS/007
Specification Version:2.0
P Date:3 1/03/1999
1. PURPOSE & SCOPE
This document describes the Acceptance Test for the POCL Infrastructure Service
in accordance with the Acceptance Procedures that are set out in the Schedules
referred to section 0.2, and also the Pathway document “Standard for documenting
Acceptance Specifications”. This test will determine that the POCL Infrastructure
Service meets all the Acceptance Criteria that are agreed in the Acceptance Test
Specification and that are within the scope of the “Pathway New Release 2
Contents Description” ref:(61) - document for New Release 2 if applicable.
Schedule
C3
Policy & Standards
POCLIDSS POCLIDSS POCLDSS
Implementation Implementation Implementation
Training Services Rollout
pss
Interface
PAS cos
Help Desks =
Reference 2
Data 8
Pock 2
Infrastucture
BES oBcs ee EPOSS
Figure1-1: This Acceptance Test in relation to others
2. ACCEPTANCE INCIDENTS
The standard and method for originating, progressing and resolving Acceptance
Incidents shall be as described in the associated Document “Standard for Raising
and Progressing Acceptance Incidents”.
© 1999 ICL Pathway Ltd COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 12 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL.
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance Ref:
Specification Versi
Date:3 1/03/1999.
'R/ACS/007
0
3. ACCEPTANCE PERIOD
The Acceptance Period for the Acceptance Tests which comprise the Operational
Trial is as determined by schedule BO7 of the AUTHORITIES’ Agreement.
The Pathway programme plan details the schedule for the POCL Infrastructure
Acceptance Test.
4. DELIVERABLES & SERVICE
This section details the Deliverables and Services that are the subject of this
Acceptance Test and as defined by the related Agreements.
Deliverable or Service. (Contract Method
Reference
IPOCL Infrastructure Service IPOCL Agreement Schedule Acceptance Trial
(A15 - Requirements. Acceptance Review
IPOCL Agreement Schedule
(A16 - Solutions.
IPOCL Agreement Schedule
(G01 - POCL Infrastructure
[Service Definition
Table of Deliverables and Services.
5. ACCEPTANCE CRITERIA
This section lists the identifier of each Acceptance Criterion that will be
demonstrated by the Acceptance Test. It also lists the Acceptance Test
Conditions that are used to determine whether (or not) the Acceptance Criterion
has been met together with the applicable test Phase.
5.1 ACCEPTANCE CRITERIA AND TEST CONDITIONS
Conformance of the POCL Infrastructure Acceptance Criteria will be demonstrated
through Acceptance Trials and/or Acceptance Reviews.
Tests conducted by Acceptance Trials comprise practical tests using prepared test
scripts. If applicable the Test Condition(s) appropriate to a criterion are specified
in section 5.1.1 together with a Criterion Description of the test. Detailed
composition of the test in terms of sequences of Test Conditions is contained in
Section 10. In the tables in section 5.1.1 the rows labelled Function Run entry will
be populated immediately prior to the running of the Acceptance Trials in a
© 1999 ICL Pathway Ltd COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 13 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL.
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance Ref:CR/ACS/007
Specification Version:2.0
P Date:3 1/03/1999
working version of the Acceptance Test Specification. These will provide
invigilators with references to the checklists used to monitor the progress of the
testing. The order of running of Test Conditions will not necessarily correspond to
the order presented in HLTPs because of the “physicalisation” of the testing. The
Function Run entry will allow the invigilator to read across from the criterion to the
checklist.
Tests conducted by Acceptance Review comprise typically document reviews, site
visits or presentations. If applicable the Test Condition(s) are described in section
5.1.2.
© 1999 ICL Pathway Ltd COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 14 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL.
ICL Pathway POCL Infrastructure Acceptance Ref:
'R/ACS/007
0
Specification Versi
Date:3 1/03/1999.
FUJ00001463
FUJ00001463
5.1.1 Description of tests conducted by Acceptance Trial
The table below shows which acceptance criteria will be met by Acceptance Trial.
All of the following tests will be performed during the Technical Test phase.
Requirement ID 467
{Criterion 2
Derivation Requirement
[Criterion Description
[The transfer of data between OPS and TMS shall be
lsecure, complete, accurate and robust.
IHLTP / Business
IThread Scenario
IHLTP VI/TSC/105 - Integrity and Networking - ref.(15)
la) 6.1.1.1 to 6.1.1.7
Ib) 6.1.2.1 to 6.1.2.3
Ic) 6.1.3.1 to 6.1.3.2
IHLTP VI/PLA/011 - Post Office Domain Security - ref.(16)
OPS Multiple Counter Post Office
ld) OPSO7_1
le) OPSO7_2
if) OPSO9_1.1
Also see entry in 5.3.
IScenario Description
la) Failure of ISDN Link
lb) Failure of ISDN Router
Ic) Failure of WAN Router
Id) CLI of ISDN router in PO
le) Invalid IP addresses, Invalid IP port barring, Invalid IP
protocol barring
if) Incoming calls on CLI list
Function Run
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 15 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway POCL Infrastructure Acceptance Ref:CR/ACS/007
Specification Version:2.0
Date:3 1/03/1999.
FUJ00001463
FUJ00001463
Requirement ID 467
Criterion 4
Derivation Schedule G01 - 4.2.2.6
\Criterion Description
Data and message transfers shall be resilient to either
Inetwork or node failure.
IHLTP / Business
IThread Scenario
IHLTP VI/TSC/105 - Integrity and Networking - ref.(15)
la) 4.1.1.1 to 4.1.1.8
b) 4.1.2.1 to 4.1.2.8
lc) 4.3.1.1 0 4.3.1.7
ld) 4.3.2.1 t04.3.2.7
le) 4.4.1.1 to 4.4.1.10
I) 4.4.2.1 to 4.4.2.10
lg) 4.5.1.1 to 4.5.1.12
Ih) 6.1.1.1 to 6.1.1.7
i) 6.1.2.1 t06.1.2.3
i) 6.1.3.1 t06.1.3.2
IScenario Description
la) Horizon to DSS (CAPS)
lb) DSS (CAPS) to Horizon
ic) Horizon to DSS (ESNCS)
Id) DSS (ESNCS) to Horizon
le) Horizon to POCL (TIP )
if) POCL (Reference Data) to Horizon
Ig) Horizon to POCL (HAPS)
lh) Failure of ISDN Link to Outlet
li) Failure of ISDN Router
ji) Failure of WAN Router
Function Run
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 16 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
0
Specification Versi
Date:3 1/03/1999.
Requirement ID 467
Criterion iS
Derivation Schedule G01 - 4.2.3.2
Criterion Description
IAll messages and data shall have a cyclic redundancy
Icheck applied when they are initially committed to the
journal and this shall be checked every time the message o
data is accessed.
IHLTP / Business
IThread Scenario
IHLTP VI/PLA/011 - Post Office Domain Security - ref.(16)
OPS Multiple Counter Post Office
la) OPSO6_3
HLTP VI/PLA/009 - Central Services Domain Security Test
Plan - ref. (20)
lb) CSD03_3
IHLTP VI/TSC/040 - High Level test Plan TPSO101
- ref. (93)
Ic) PO2, SH2 - tepo115
IScenario Description
Id) Audit - Riposte Message Store - Multiple tests to check
integrity and use the message store within an outlet
le) Audit - Riposte Transaction Journals - Multiple tests to
check the integrity and use of the message store of a
correspondence server
if) As per EPOSS criterion 835/1. Print EPOSS Transaction
Log containing BES, EPOSS, APS & OBCS transactions.
This test shows that various counter transactions
committed within a customer session can subsequently
be viewed within the EPOSS Transaction Log produced
in the outlet.
Function Run
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 17 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
Versi 0
Specification
Date:3 1/03/1999.
Requirement ID 467
Criterion 6
Derivation Schedule G01 - 4.2.3.4
Criterion Description
here POCL requires the origin of data to be
authenticated, the CONTRACTOR shall apply a digital
signature to the data prior to transmission and shall then
Icheck it upon receipt.
IHLTP / Business
[Thread Scenario
IHLTP VI/PLA/011 - Post Office Domain Security
OPS Multiple Counter Post Office - ref.(16)
la) OPSO5_4
IScenario Description
la) Message Protection - Tests to ensure correct operation
of payment certifications, entropy, signature verification,
filestore encryption.
Function Run
IThread Scenario
Requirement ID 472
{Criterion 4
Derivation Requirement
Criterion Description IData capture within OPS shall be accurate and robust.
IHLTP / Business IHLTP VI/TSC/105 - Technical Integrity
Failures at Outlets - ref.(15)
la) 10.1.1.1 to 10.1.1.4
Ib) 10.2.1.1 to 10.2.1.4
Ic) 10.4.2.1 to 10.4.2.2
Id) 10.4.3.1 to 10.4.3.2
le) 10.4.4.1 to 10.4.4.2
if) 10.4.5.1 to 10.4.5.3
IScenario Description
la) Failures on Single Counter Outlet
lb) Failures on Multiple Counter Outlet
ic) Failure of Keyboard / mag stripe reader
ld) Failure of touch screen
le) Failure of barcode reader
if) Failure of Weigh Scales
Function Run
© 1999 ICL Pathway Ltd
Printed on: 24/01/01
Page 18 of 1
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
Versi 0
Specification
Date:3 1/03/1999.
Requirement ID 472
Criterion 2
Derivation Requirement
Criterion Description
IThe integrity and security of data held within the OPS shall
be protected at all times.
IHLTP / Business
IThread Scenario
IHLTP VI/PLA/011 - Post Office Domain Security
OPS Multiple Counter Post Office - ref.(16)
la) OPSO5_4
lb) OPSO6_1
lc) OPS06_3
IScenario Description
la) Message Protection - Tests to ensure correct operation
of payment certifications, entropy, signature verification,
filestore encryption.
lb) Riposte Identification, Authentication and Access
Control. Checks that only authorised programs can read
/ write using Riposte interface.
ic) Audit - Riposte Message Store - Multiple tests to check
integrity and use message store
Function Run
Requirement ID 472
Criterion 3
Derivation Requirement
Criterion Description
Full logs of Events within OPS shall be maintained and an
audit trail of interactions with, and actions within, OPS shall
lbe maintained.
IHLTP / Business
IThread Scenario
IHLTP VI/PLA/011 - Post Office Domain Security
OPS Multiple Counter Post Office - ref.(16)
la) OPS06_3.5
Scenario Description
la) Audit - Riposte Message Store - Multiple tests to check
integrity and use of message store
Function Run
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 19 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
FUJ00001463
FUJ00001463
Ref:CR/ACS/007
Version:2.0
Specification
Date:3 1/03/1999.
Requirement ID 472
Criterion 4
Derivation Requirement
Criterion Description
IThe integrity and security of data held within OPS shall not
lbe compromised by any Incident nor when OPS is re-
lestablished following any Incident.
IHLTP / Business
IThread Scenario
IHLTP VI/TSC/105 - Integrity and Networking - ref.(15)
la) 10.1.1.1 to 10.1.1.4
lb) 10.2.1.1 to 10.2.1.4
lc) 10.3.1.1. to 10.3.1.2
ld) 10.4.1.1 to 10.4.1.4
le) 10.4.2.1 to 10.4.2.2
I) 10.4.3.1 to 10.4.3.2
jg) 10.4.4.1 to 10.4.4.2
lh) 10.4.5.1 to 10.4.5.3
i) 10.4.6.1 to 10.4.6.4
j) 10.4.7.1 to 10.4.7.3
k) 10.4.8.1 to 10.4.8.2
I) 10.4.3
IHLTP - VI/PLA/011 - Office Platform Domain Security -
Iref.(16)
Im) OPSOS_1
In) OPSO5_2
Scenario Description
la) Single Counter Outlet PC fails
lb) Multiple counter Outlet PC fails
ic) LAN failure
id) ISDN card failure
le) Keyboard / mag stripe reader failure
if) Touch sensitivity failure
Ig) Barcode reader failure
lh) Weigh Scales failure
li) Slip Printer failure
i) Tally Roll failure
Ik) Back office printer failure
ll) Video monitor/panel failure
Im) Post Office Desktop - Identification and Authentication
In) Access Control - Tests to validate correct operation of
access control policy
Function Run
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 20 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
Versi 0
Specification
Date:3 1/03/1999.
Requirement ID 472
Criterion 5
Derivation Schedule G01 - 2.6.1.2
ICriterion Description
All data captured at an Outlet either as part of a Counter
Position Transaction or as an administration function shall
form part of a unique Transaction which shall be givena
lunique reference number by Riposte and details stored in
ithe journal.
IHLTP / Business
IThread Scenario
IHLTP VI/PLA/011 - Post Office Domain Security
OPS Multiple Counter Post Office - ref.(16)
la) OPS06_3.5
IScenario Description
la) Audit - Riposte Message Store - Multiple tests to check
lintegrity and use of message store
Function Run
Requirement ID 472
Criterion 6
Derivation Schedule G01 - 2.6.1.3
Criterion Description
Each Counter Position PC shall contain a journal and all
journal entries shall be automatically replicated to all other
Imembers of the work group.
IHLTP / Business
IThread Scenario
IHLTP VI/PLA/011 - Post Office Domain Security
OPS Multiple Counter Post Office - ref.(16)
la) OPS06_3.5
IScenario Description
la) Audit - Riposte Message Store - Multiple tests to check
integrity and use of message store
Function Run
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 21 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
Versi 0
Specification
Date:3 1/03/1999.
Requirement ID 472
(Criterion 7
Derivation Schedule G01 - 2.6.1.6
Criterion Description
[The CONTRACTOR shall provide synchronisation facilities
hich shall automatically check the status of the journal for
ia node when it is re-established following failure.
IHLTP / Business
IThread Scenario
IHLTP VI/TSC/105 - Integrity and Networking - ref.(15)
la) 10.1.1.1 to 10.1.1.4
b) 10.2.1.1 to 10.2.1.4
c) 9.2.5.1
IScenario Description
la) Single counter Outlet PC fails
lb) Multiple counter Outlet PC fails
Ic) Failure of Counter Correspondence Server
Function Run
Requirement ID 473
(Criterion 3
Derivation Requirement
Criterion Description
It shall be possible to restrict the functionality available at
lan Outlet, to permit (inter alia) some Services not to be
offered at all Outlets.
IHLTP / Business
IThread Scenario
BT - VI/TSC/034 - Business Thread RDS01 - ref.(18)
la) 3.3.2
IScenario Description
la) Specific Outlets with various Class Elements present.
Function Run Entry
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 22 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
Versi 0
Specification
P Date:3 1/03/1999
Requirement ID 473
Criterion 4
Derivation Requirement
Criterion Description
IThere shall be support available to Users who have
forgotten their passwords. A large proportion of the Outlets
lhave only a single Counter Position. The support
Imechanism used shall not unduly reduce the effectiveness
lof access control.
IHLTP / Business
IThread Scenario
IHLTP - VI/PLA/011 - Office Platform Domain Security -
Iref.(16)
la) OPS05_1.20
Scenario Description
la) Forgotten Password back-up
Function Run
Requirement ID 473
(Criterion 5
Derivation Requirement
Criterion Description
IThere shall be a secure and reliable mechanism for Users
ito suspend and resume access to OPS and Services
loffered via OPS. This shall not be unduly onerous or time
Iconsuming for Users.
IHLTP / Business
IThread Scenario
IHLTP - VI/PLA/011 - Office Platform Domain Security -
lref.(16)
la) OPS05_1
IScenario Description
la) Post Office Desktop - Identification and Authentication
Function Run
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 23 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
Versi 0
Specification
Date:3 1/03/1999.
Requirement ID 473
ICriterion 6
Derivation Schedule G01 - 2.4.1.3
Criterion Description
(Only Users authorised by POCL shall be able to log-on to
the OPS at an Outlet in accordance with their defined role.
IHLTP / Business
IThread Scenario
IHLTP VI/PLA/011 - Post Office Domain Security
IOPS Multiple Counter Post Office - ref.(16)
la) OPSO5_02
Scenario Description
la) Access Control - Tests to validate correct operation of
laccess control policy.
Function Run
Requirement ID 473
Criterion 7
Derivation Schedule G01 - 2.4.1.4
{Criterion Description
(Authentication of all Users logging on to the OPS in the
Outlet shall be undertaken by the elements of the Service
Infrastructure on which OPS is based. Full access control
land password management facilities shall be provided.
IHLTP / Business
IThread Scenario
IHLTP VI/PLA/011 - Post Office Domain Security
IOPS Multiple Counter Post Office - ref.(16)
la) OPSO5_02
Scenario Description
la) Access Control - Tests to validate correct operation of
laccess control policy.
Function Run
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 24 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
FUJ00001463
FUJ00001463
Ref:
Versi
Date:3 1/03/1999
R/ACS/007
Specification 0
Requirement ID 476
(Criterion 4
Derivation Requirement
Criterion Description
IThe implementation of any Release shall not cause any
significant disruption to Users, shall not disrupt the normal
orking environment of Users and shall not require
significant involvement from Users.
IHLTP / Business
IThread Scenario
IHLTP VI/TSC/110 - Systems Management - ref.(19)
la) SDO1 to SD10
lb) ACO1 to ACO3.
IScenario Description
Software Distribution - Counter Tests. Various tests to
validate correct operation of software distribution
process. Following distribution this will include counter
tests which use previously held reference data and
transaction data.
Im) Auto configuration tests (Counter Builds) covering
Configure new single counter system, Configure new
multi-counter gateway system, Configure several
counter systems simultaneously.
D
Function Run
Requirement ID 476
{Criterion IS
Derivation Requirement
\Criterion Description
The implementation of any Release shall not cause any
corruption to data held by or on behalf of the
AUTHORITIES.
IHLTP / Business
IThread Scenario
HLTP VI/TSC/110 - Systems Management - ref.(19)
la) SDO1 to SD10
lb) SD20 to SD25 & SD30
Scenario Description
la) Software Distribution - Counter Tests. Various tests to
validate correct operation of software distribution process
in an outlet. Following distribution this will include
counter tests which use previously held reference data
and transaction data.
lb) Software Distribution - Data Centre Tests. Various tests
to validate correct operation of software distribution
process to the Pathway Data Centres.
Function Run
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 25 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
FUJ00001463
FUJ00001463
Ref:CR/ACS/007
Versi
Date:3 1/03/1999
Specification
Requirement ID 476
{Criterion 6
Derivation Requirement
Criterion Description
IThe implementation of any Release shall not cause any
significant disruption to Users, shall not disrupt the normal
orking environment of Users and shall not require
significant involvement from Users.
IHLTP / Business
[Thread Scenario
Identical to 476/4.
Scenario Description
Function Run
Requirement ID 478
{Criterion 7
Derivation Requirement
ICriterion Description
iThe collection or delivery of Data Files shall be retried
lautomatically, under parameter control, in the event of any
failure.
IHLTP / Business
IThread Scenario
IHLTP VI/TSC/105 - Integrity and Networking - ref.(15)
la) 4.1.1.1 to 4.1.1.8
b) 4.1.2.1 to 4.1.2.8
lc) 4.3.1.1 t0 4.3.1.7
ld) 4.3.2.1 t04.3.2.7
le) 4.4.1.1 to 4.4.1.10
If) 4.4.2.1 to 4.4.2.10
lg) 4.5.1.1 to 4.5.1.12
h) 4.4.3.1 to 4.4.3.6
Scenario Description
la) Horizon to DSS (CAPS)
lb) DSS (CAPS) to Horizon
Ic) Horizon to DSS (ESNCS)
id) DSS (ESNCS) to Horizon
le) Horizon to POCL (TIP )
if) POCL (Reference Data) to Horizon
Ig) Horizon to POCL (HAPS)
lh) Compaq Recovery Option Tests
Function Run
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 26 of 1
obligations between ICL Pathway and the DSS and/or POCL
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance R
Specification Versi
P Date:3 1/03/1999
f:CR/ACS/007
0
Requirement ID 478
(Criterion 13
Derivation Requirement
{Criterion Description IPathway shall maintain a full audit trail of all TMS activity
IHLTP / Business IHLTP - VI/PLA/009 - Central Services Domain Security -
IThread Scenario iref.(20)
la) CSDO3_03
lb) CSD04_03
lc) CSDO5_03
[Scenario Description ja) Correspondence Server / riposte - Audit - various tests to
validate that integrity and logging of transactions.
lb) As above for OBCS, TPS, APS, RD & CMS/PMS Agents
Ic) As above for Archive Server Agents
Function Run
© 1999 ICL Pathway Ltd COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 27 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL.
ICL Pathway POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
0
Specification Versi
Date:3 1/03/1999.
Requirement ID 478
Criterion 14
Derivation Requirement
Criterion Description
Pathway shall ensure that any transfer of Data Files or
messages to or from TMS is, and can be shown to be,
lsecure, complete accurate and robust.
IHLTP / Business
IThread Scenario
LTP - VI/TSC/105 - Integrity and Networking - ref.(15)
\Sequent to Correspondence servers
la) 5.1.1.1 to 5.1.1.2
lb) 5.1.2.1 to 5.1.2.3
Ic) 5.1.3.1 to 5.1.3.5
ld) 5.1.4.1
le) 5.1.5.1 to 5.1.5.6
If) 5.1.6.1 to 5.1.6.4
Ig) 5.1.7.1 to 5.1.7.9
Ih) 6.1.1.1 to 6.1.1.7
li) 6.1.2.1 to 6.1.2.3
j) 6.1.3.1 to 6.1.3.2
Ik) 6.1.4.1
Il) 4.4.1.1 to 4.4.1.10
IHLTP - VI/TSC/110 - Systems Management High Level Test
Definition
Im) EV01 to EVO7
Scenario Description
la) Failure of Sequent
lb) Failure of FDDI link
Ic) Failure of WAN router
id) Failure of inter campus link
le) Failure of LAN
if) Failure of Agent Server
Ig) Failure of Correspondence Server
lh) Failure of ISDN Link to Outlet
li) Failure of ISDN Router
jj) Failure of WAN Router
Ik) Failure of inter campus link
I!) Horizon to POCL(TIP)
Im) Resilience testing - Tivoli Agent to Tivoli management
system
Function Run
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 28 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway POCL Infrastructure Acceptance __Ref.CR/ACS/007
Specification Version:2.0
Date:3 1/03/1999
FUJ00001463
FUJ00001463
Requirement ID 479
Criterion 2
Derivation Requirement
Criterion Description
ITMS shall only allow connections to such elements of the
Service Infrastructure to be established with computer
Isystems which are approved by the AUTHORITIES to be
connected.
IHLTP / Business
IThread Scenario
IHLTP - Systems Management and Support Services
Domain - Security ref.(82)
ISMS09_1 to SMS09_9
IScenario Description
Cisco Routers and LAN switches - Identification &
Authentication, Access Control Policy, Audit.
Function Run
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 29 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
0
Specification Versi
Date:3 1/03/1999.
Requirement ID 479
Criterion 4
Derivation Requirement
Criterion Description
[TMS shall authenticate the identity of any computer system
ith which a link is to be established.
IHLTP / Business
IThread Scenario
IHLTP - VI/PLA/010 - POCL & POCL Clients Domain
[Security - ref.(17)
la) POCLO1_4
lb) POCLO3_4
IHLTP - VI/PLA/O11 - Office Platform Domain Security -
Iref.(16)
lc) OPS10_01
IHLTP - VI/PLA/009 - Central Services Domain Security -
iref.(20)
ld) CSDO4_1
IScenario Description
la) Data Encryption and Key Management - HAPS Access
Node
lb) Data Encryption and Key Management - TIP Access
Node
ic) ISDN Routers - external interface - Identification and
Authentication
id) CMS / PAS Agent Application - Identification and
Authentication
Function Run
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 30 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance Ref:CR/ACS/007
Specification Version:2.0
P Date:3 1/03/1999
Requirement ID 536
{Criterion 2
Derivation Requirement
ICriterion Description IPeripheral and input devices supplied as part of the
lelements of the Service Infrastructure on which OPS is
provided shall be capable of detecting contention,
remature removal/swapping of Tokens etc. as appropriate
IHLTP / Business IHLTP - VI/PLA/011 - Office Platform Domain Security -
[Thread Scenario Iref.(16)
IOPS05_01
[Scenario Description IAuthentication - various tests including validation of correct
loperation of POLO boot process.
Function Run
© 1999 ICL Pathway Ltd COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 31 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL.
ICL Pathway POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
0
Specification Versi
Date:3 1/03/1999.
Requirement ID 537
Criterion 4
Derivation Requirement
[Criterion Description
[The CONTRACTOR shall carry out system management of
lall the Services in a consistent and coherent manner to
lensure the following:
a) activities within the Services, including PAS, CMS,
TMS, OPS, BES, OBCS, APS and EPOSS, are co-+
ordinated such that, for example, changes and
faults can be tracked across Service boundaries;
b) changes to the Services can be made speedily
and accurately.
IHLTP / Business
[Thread Scenario
IHLTP VI/TSC/110 - Systems Management - ref.(19)
la) EVO1 - EVO7
lb) PTO1 - PTO3
Ic) SDO1 to SD10
Id) SD20 to SD25 & SD30
Scenario Description
la) Tivoli Event Monitoring - Various tests to validate correct
and consistent generation of events on multiple platforms!
(TMS and OPS hosts).
lb) Patrol Testing - Various tests to ensure correct operation
of the event monitoring facilities on the Sequent (PAS /
CMS hosts)
ic) Software Distribution - Counter Tests. Various tests to
validate correct operation of software distribution processI
in an outlet.
id) Software Distribution - Data Centre Tests. Various tests
to validate correct operation of software distribution
process to the Pathway Data Centres.
Function Run
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 32 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
FUJ00001463
FUJ00001463
Ref:
Versi
Date:3 1/03/1999
R/ACS/007
Specification 0
Requirement ID 537
(Criterion 2
Derivation Schedule G01 - 5.3.5.1
\Criterion Description
Software distribution facilities shall be provided by the
ICONTRACTOR which shall enable Software files and
installation scripts to be distributed across the Wide Area
Networks, part of the Service Infrastructure, to a specific
Outlet, all Outlets or a group of Outlets selected according
ito one or more particular attributes.
IHLTP / Business
IThread Scenario
IHLTP VI/TSC/110 - Systems Management - ref.(19)
la) SDO1 to SD10
lb) SD20 to SD25 & SD30
Scenario Description
la) Software Distribution - Counter Tests. Various tests to
validate correct operation of software distribution process
in an outlet.
la) Software Distribution - Data Centre Tests. Various tests
to validate correct operation of software distribution
process to the Pathway Data Centres.
Function Run
Requirement ID 538
{Criterion 4
Derivation Requirement
ICriterion Description
ISMS shall provide a facility for synchronising the date and
itime across the Services and the Service Infrastructure.
This shall cater for the handling of clock changes (e.g. at
[the beginning and end of British Summer Time).
IHLTP / Business
[Thread Scenario
IHLTP VI/TSC/110 - Systems Management - ref.(19)
la) TM01 to TMO6, TM10 to TM15, TM20 to TM23
IScenario Description
la) Time Synchronisation - Various tests to validate correct
and resilient time synchronisation across platforms.
Function Run
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 33 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
Ref:
Versi
Date:3 1/03/1999
R/ACS/007
Specification 0
Requirement ID 541
{Criterion 4
Derivation Requirement
Criterion Description
TMS shall be scaleable to meet POCL’s business needs
ifrom time to time.
IHLTP / Business
[Thread Scenario
IHLTP VI/TSC/113 - Performance Assurance - ref.(22)
la) 3.1 to 3.6 (Correspondence Server)
lb) 4.1 to 4.8 (Agent Servers)
IScenario Description
la) & b) Validation that Replication, Harvesting, Loading
land Archiving operations can be achieved for the required
olumes.
Function Run
Requirement ID 958
{Criterion 2
Derivation Requirement
ICriterion Description
IThe OPS shall be capable of supporting the entire range of
business transacted at Outlets for current volumes of
business and volumes of business as projected by POCL.
IHLTP / Business
IThread Scenario
IHLTP VI/TSC/113 - Performance Assurance - ref.(22)
la) 2.1 to 2.7 (Counter Systems)
IScenario Description
la) Various tests to validate the capacity of OPS for
replication, transmission to TMS and some local
ladministrative functions.
Function Run
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 34 of 1
obligations between ICL Pathway and the DSS and/or POCL
FUJ00001463
FUJ00001463
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance Ref:CR/ACS/007
Version:2.0
Specification
P Date:3 1/03/1999
Requirement ID i826
Criterion 4
Derivation Requirement
Criterion Description
IOPS, and the elements of the Service Infrastructure on
hich OPS is provided, shall be able to be connected, and
shall support such connection, to specialist peripherals in
lsuch a way that the specialist peripherals may be accessed
lby one, two or more terminals.
IHLTP / Business
IThread Scenario
IHLTP VI/TSC/105 - Technical Integrity and Networking -
Iref.(15)
la) 10.4.5.1 to 10.4.5.3
IScenario Description
la) Weigh Scales - Tests to validate correct operation of
eigh scale accessed by more than one counter system
Function Run
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 35 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
FUJ00001463
FUJ00001463
Ref:
Versi
Date:3 1/03/1999
R/ACS/007
Specification 0
Requirement ID 921
Criterion 4
Derivation Requirement
Criterion Description
IThe OPS and the elements of the Service Infrastructure on
hich OPS is provided shall provide a secure time-out
ifacility for each counter terminal and back office terminal.
IHLTP / Business
IThread Scenario
IHLTP VI/PLA/011 - Office Platform Domain Security -
iref.(16)
la) OPSO5_1.11
Scenario Description
la) Access Control - various tests including validation of
correct operation of inactivity time-out.
Function Run
Requirement ID 921
Criterion 2
Derivation Requirement
Criterion Description
IThe time-out facility shall allow the User to resume work
ith the minimum delay consistent with achieving security in
laccordance with the provisions hereof.
IHLTP / Business
IThread Scenario
IHLTP VI/PLA/011 - Office Platform Domain Security -
lref.(16)
la) OPSO5_1.11
Scenario Description
la) Authentication - various tests including validation of
correct operation of inactivity time-out.
Function Run
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 36 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
Versi 0
Specification
Date:3 1/03/1999.
Requirement ID 921
{Criterion 3
Derivation Requirement
ICriterion Description
It shall be clear that the facility is in use to remove any
confusion between a terminal with the facility activated and
a terminal that is available for use by any User.
IHLTP / Business
IThread Scenario
IHLTP VI/PLA/O11 - Office Platform Domain Security -
iref.(16)
la) OPSO5_1.11
IScenario Description
la) Authentication - various tests including validation of
correct operation of inactivity time-out.
Function Run
Requirement ID 921
(Criterion 4
Derivation Requirement
Criterion Description
Under circumstances where the facility has been activated
land the User is no longer able to cancel it, for whatever
reason, it shall be possible with appropriate authority:
(a) to complete User and Outlet balances; and
(b) to make the terminal available to another User.
IHLTP / Business
IThread Scenario
IHLTP VI/PLA/O11 - Office Platform Domain Security -
iref.(16)
la) OPSO5_1.11
Scenario Description
la) Authentication - various tests including validation of
correct operation of inactivity time-out.
Function Run
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 37 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
FUJ00001463
FUJ00001463
Ref:
Versi
Date:3 1/03/1999
R/ACS/007
Specification 0
Requirement ID 953
Criterion 4
Derivation Requirement
ICriterion Description
OPS shall support concurrent access to services provided
ia it.
IHLTP / Business
IThread Scenario
IBT VI/TSC/048 - Business Integration Thread BITO3 -
Iref.(23)
IScenario Description
IBT ref. 1 to 4. This Thread checks the correct integration of
IOBCS and BPS with the new R2 services of EPOSS and
IAPS, together with various external links.
The run-time environment for BIT includes multiple outlets
ith multiple counters. Tests covering all services will be
run concurrently on multiple nodes.
Function Run
Requirement ID 953
Criterion 2
Derivation Requirement
Criterion Description
IOPS shall ensure data integrity, e.g. reports printed at the
back office whilst serving at the front office shall be
consistent with a clearly stated policy (to be approved by
POCL) of what front office data are included in the report
IHLTP / Business
IThread Scenario
IBT VI/TSC/082 - Business Thread EP01 - ref.(88).
Test 3.3.14/5
IScenario Description
IManager 1 performs an office balance and produces an
office trial balance. One of the outlet counter PC's is
disconnected from the LAN prior to this scenario. A warning)
lis displayed to the Post Master concerning the disconnected}
counter.
Function Run
© 1999 ICL Pathway Ltd
Printed on: 24/01/01
Page 38 of 1
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance Ref:CR/ACS/007
Specification Version:2.0
P Date:3 1/03/1999
Requirement ID 953
Criterion 3
Derivation Requirement
Criterion Description Performance of OPS shall not be significantly degraded by
lother office activity, e.g. front office, back office and
communications activities shall not unduly impact each
lother.
IHLTP / Business IHLTP VI/TSC/113 - Performance Assurance - ref.(22)
IThread Scenario
[Tests 2.2 to 2.7
Scenario Description IVarious tests to validate counter performance.
Function Run
© 1999 ICL Pathway Ltd COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 39 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL.
ICL Pathway POCL Infrastructure Acceptance Ref:
'R/ACS/007
0
Specification Versi
Date:3 1/03/1999.
FUJ00001463
FUJ00001463
5.1.2 Criterion Description of tests conducted by Acceptance Review
The table below shows which acceptance criterion are to be met by Acceptance
Review. Each Acceptance Test will use the latest baselined version of any
document referred to in section 0.2 or below.
Requirement ID 463
{Criterion 4
Derivation Requirement
Criterion Description
part of the Steady State Services. Examples of these
purposes include:
la) testing by the AUTHORITIES;
lb) training;
ic) demonstrations and marketing.
The CONTRACTOR shall supply samples of all elements of
the Service Infrastructure used to provide OPS for purposes
other than (i) Roll Out and (ii) live use in POCL Premises asI
Statement of Fact or Obligation
Requirement ID 463
Criterion 2
Derivation Requirement
Criterion Description
IThe CONTRACTOR shall provide specimens of all
lelements and proposed elements of the Service
Infrastructure used to provide OPS from time to time to
lundergo destructive safety testing.
[Statement of Fact or Obligation
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 40 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
0
Specification Versi
Date:3 1/03/1999.
Requirement ID 463
(Criterion 3
Derivation Requirement
\Criterion Description
The AUTHORITIES shall notify the CONTRACTOR from
time to time of how many samples are required for the
purposes of testing such elements of the Service
Infrastructure at Operational Trial, DSS Operational Trial
land POCL Operational Trial. They shall not in total exceed
ithe equivalent of 8 post offices with a total of 50 Counter
Positions. Any requirements thereafter for samples of
lequipment for testing purposes (beyond the initial 50
(Counter Positions) shall be subject to a process approved
lby a date consistent with the project plan agreed by the
parties, such that the date does not adversely impact
contractual milestones as defined in Clause 605.1 of the
(Authorities Agreement.
[Statement of Fact or Obligation
Requirement ID 463
Criterion 4
Derivation Requirement
{Criterion Description
Unless testing demonstrates a breach of the relevant
standards in Schedule A02, the number of specimens for
destructive testing purposes shall not exceed one example
lof each component of Hardware within the elements of the
Service Infrastructure that are proposed for the OPS.
Statement of Fact or Obligation
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 41 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
FUJ00001463
FUJ00001463
Ref:CR/ACS/007
Versi
Date:3 1/03/1999
Specification
Requirement ID 463
{Criterion IS
Derivation Requirement
\Criterion Description
[The quantity of samples for training purposes depends on
ithe training methodology employed
Reason
Statement of Fact or Obligation
Requirement ID 464
Criterion 1
Derivation Requirement
\Criterion Description
Services which utilise OPS or TMS shall only be provided
isubject to the agreement of POCL
Reason [Statement of Fact or Obligation
Requirement ID 465
Criterion 4
Derivation Requirement
Criterion Description
[The livery of the elements of the POCL Service
Infrastructure to be used for OPS shall be agreed with
IPOCL before Roll Out. A single livery shall be approved for
lall Outlets that is consistent with the POCL Style Guide for
ost offices.
ITest Condition The agreed livery is documented in the Counter Hardware
Design Specification.
Method Document Inspection
References Counter Hardware Design Specification - ref.(25)
Phase [Technical Testing
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 42 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
Versi 0
Specification
Date:3 1/03/1999.
Requirement ID 465
Criterion 2
Derivation Requirement
Criterion Description
The effort required to maintain the appearance of the
Equipment to a level reasonably acceptable to the
[AUTHORITIES shall be minimal.
ITest Condition ‘Acceptance of equipment cleaning and maintenance
lprocedures as described in Operating Environment PPD.
[Absence of any outstanding problems reported to the
Horizon Service Review Forum.
Method Document Inspection
References Release 2 Operating Environment Processes and
Procedures Document - ref.(26).
(Customer Services - Services Management Operations
Manual - ref.(76).
Phase [Technical Testing
Requirement ID 466
{Criterion 4
Derivation Requirement
ICriterion Description
Pathway shall supply detailed specifications of all the
lconsumables used by the OPS
ITest Condition
Inclusion of specification in POCL and DSS Schedule B04.
Method Document Inspection
References IPOCL Consumables - POCL Agreement Schedule B04. -
lref.(28)
DSS Consumables - DSS Agreement Schedule B04 -
Iref.(29)
Phase [Technical Testing
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 43 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
Versi 0
Specification
Date:3 1/03/1999.
Requirement ID 466
{Criterion 2
Derivation Requirement
ICriterion Description
[The CONTRACTOR shall supply detailed specifications of
lall the consumables used by the OPS. The CONTRACTOR
shall provide estimates of the likely consumption of each
iconsumable and, as part of an impact assessment, the
impact on consumption of any changes, including new
Services.
ITest Condition Inclusion of specification in POCL and DSS Schedule B04.
Provision of estimates.
Method Document Inspection
References IPOCL Consumables - POCL Agreement Schedule B04. -
lref.(28)
DSS Consumables - DSS Agreement Schedule B04 -
lref.(29)
Phase [Technical Testing
Requirement ID 466
Criterion 3
Derivation Requirement
Criterion Description
[The CONTRACTOR shall be capable of supplying all
iconsumables, but the AUTHORITIES shall have the option
ito source consumables from another supplier.
ITest Condition Evidence of Agreement - POCL Agreement Schedule B04 /
DSS Agreement Schedule B04
Method Document inspection
References POCL Agreement Schedule B04 - POCL Consumables -
lref.(28)
DSS Agreement Schedule B04 - DSS Consumables -
lref.(29)
Phase [Technical Testing
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 44 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
FUJ00001463
FUJ00001463
Ref:
Versi
Date:3 1/03/1999
R/ACS/007
Specification 0
Requirement ID 467
Criterion 4
Derivation Requirement
{Criterion Description
Each instance of OPS within Outlets shall interface with
ITMS to allow the transfer, in both directions, of authorised
data files and messages.
\Test Condition Description of Technical Architecture contained in TMS and
OPS Architecture Documents, and the Riposte API
specification
[Method Document Inspection
References IOPS Architecture Document - ref.(30)
ITMS Architecture Document - ref.(31)
Riposte 32 API Specification - ref.(32)
Phase [Technical Testing
Requirement ID 467
Criterion 3
Derivation Requirement
\Criterion Description
\Within OPS it shall be possible to identify whether data
from OPS have been received by TMS or not.
ITest Condition ‘Acceptance of mechanisms described in ref.(83).
Method Document Inspection
References IOPS/TMS Data Acknowledgement Process - _ref.(83)
Phase [Technical Testing
© 1999 ICL Pathway Ltd
Printed on: 24/01/01
Page 45 of 1
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
FUJ00001463
FUJ00001463
Ref:
Versi
Date:3 1/03/1999
R/ACS/007
Specification 0
Requirement ID 468
Criterion 4
Derivation Requirement
{Criterion Description
Maintenance and repair of the elements of the Service
Infrastructure used to provide OPS involving on-site
lattendance at POCL Premises by the CONTRACTOR’s
lengineers shall not interfere unduly with the ability of an
(Outlet to serve Customers, even where Outlets have a
single Counter Position and/or extremely limited physical
space.
\Test Condition
[A maintenance call to a POCL outlet will be handled by a
suitably trained engineer. Each engineer will be targeted to
resolve all on site hardware failures within 20 minutes of
arriving on site. The appropriate level of spares will be
deployed to assist in achieving this target. The engineer will
not interfere unduly with the post office operation. Where
this is not possible a visit will be deferred and/or exemption
lsought on SLA requirements.
Method
Document Inspection
Ongoing review as part of Horizon Service Review Forum
References
CFM: ICLS Sorbus Pathway Project Operations Manual -
ref.(33)
Horizon System Helpdesk - Work Instructions. - ref.(34)
Customer Services - Services Management Operations
Manual - ref.(76).
Phase
Model Office
Requirement ID
469
Criterion
4
Derivation
Requirement
Criterion Description
[The technical documentation concerning OPS and the
lelements of the Service Infrastructure used to provide OPS
shall be suitable to allow POCL to procure applications
hich utilise OPS or hardware which interfaces with OPS.
These procurements shall not necessarily be from Pathway.
ITest Condition Provision of documents as described below.
Method Document Inspection
References ICL Pathway External Applications Procurement Policy -
Iref.(80)
Phase [Technical Testing
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 46 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
Versi 0
Specification
Date:3 1/03/1999.
Requirement ID 469
Criterion 2
Derivation Requirement
{Criterion Description
[The CONTRACTOR shall provide technical documentation
concerning the OPS and the elements of the Service
Infrastructure used to provide OPS.
ITest Condition Provision of documents as described below.
(Acceptance of the process by which additional information
Imay be provided as described in ref.(80).
Method Document Inspection
References (Counter Hardware Design Specification - ref.(25)
Riposte 32 API Specification - ref.(32)
IOPS Architecture Document - ref.(30)
ICL Pathway External Applications Procurement Policy -
iref.(80)
Phase [Technical Testing
Requirement ID 469
Criterion 3
Derivation Requirement
Criterion Description
All changes to technical documentation concerning OPS
land the elements of the POCL Infrastructure used to
provide OPS shall be the subject of the written agreement
lof POCL
Reason
Statement of Fact or Obligation
© 1999 ICL Pathway Ltd
Printed on: 24/01/01
Page 47 of 1
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
Versi 0
Specification
Date:3 1/03/1999.
Requirement ID 1470
Criterion 4
Derivation Requirement
Criterion Description
[The CONTRACTOR shall provide technical documentation
concerning TMS and the elements of the Service
Infrastructure used to provide TMS.
ITest Condition Provision of documents as described below.
‘Acceptance of the process by which additional information
Imay be provided as described in ref.(80).
Method Document inspection
References Riposte 32 API Specification - ref.(32)
ITMS Architecture Document - ref.(31)
[Technical Environment Description( sections Chapter 4,
5.2.3, 5.2.4, 6.1 to 6.5, 7.1 to 7.3, 10.1 to 10.3, 10.5.5,
10.5.6)- ref.(37)
ICL Pathway External Applications Procurement Policy -
iref.(80)
Phase [Technical Testing
Requirement ID 1470
Criterion 2
Derivation Requirement
\Criterion Description
IThis documentation shall be suitable to allow POCL to
lprocure applications which utilise TMS. These
lprocurements shall not necessarily be from the
ICONTRACTOR.
ITest Condition Provision of documents _as described below
Method Document inspection
References ICL Pathway External Applications Procurement Policy -
iref.(80)
Phase [Technical Testing
Requirement ID 1470
Criterion 3
Derivation Requirement
\Criterion Description
IAll changes to technical documentation concerning TMS
land the elements of the POCL Infrastructure used to
provide TMS shall be the subject of the written agreement
lof POCL
Reason
[Statement of Fact or Obligation
Requirement ID
472
{Criterion
3
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 48 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance __Ref.CR/ACS/007
Specification Version:2.0
Date:3 1/03/1999.
Derivation Requirement
\Criterion Description
Full logs of Events within OPS shall be maintained and an
audit trail of interactions with, and actions within, OPS shall
lbe maintained.
ITest Condition Completion of all tests in Audit Acceptance Specification
Method Document Inspection
References Audit Closure Report - ref.(81)
IOPS/TMS Data Acknowledgement Process - ref.(83)
Phase Technical Testing
Requirement ID 474
{Criterion 4
Derivation Requirement
\Criterion Description
[The CONTRACTOR shall ensure that all Equipment used inI
ithe provision of OPS is rated for continuous operation, and
capable of functioning safely and reliably for an unlimited
eriod, attended or unattended, in Outlets.
ITest Condition Acceptance of Declaration of Technical Conformity.
Method Document inspection
References Declaration of Conformity - Technical Construction File-
iref.(39)
Phase [Technical Testing
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 49 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
Versi 0
Specification
Date:3 1/03/1999.
Requirement ID 474
{Criterion 2
Derivation Requirement
ICriterion Description
Each installation of such Equipment shall be physically and
electrically safe and in compliance with relevant legislation
land recognised best practice.
(a) “Relevant legislation” includes all relevant UK
Regulations and, from the due date of UK
implementation, EC Directives. Such Equipment shall
be maintained to be compliant with any subsequent
legislation.
(b) “Relevant legislation and recognised best practice”
includes mandatory standards, including all relevant
UK Regulations and, from the due date of UK
implementation, EC Directives. Such Equipment shall
be maintained to be compliant with any subsequent
legislation or mandatory standards.
ITest Condition (Acceptance of Declaration of Technical Conformity.
Method Document inspection
References Declaration of Conformity - Technical Construction File-
Iref.(39)
Phase [Technical Testing
Requirement ID 474
{Criterion 3
Derivation Requirement
Criterion Description
[Such installation shall not cause interference with other
devices.
ITest Condition (Acceptance of Declaration of Technical Conformity.
Method Document inspection
References Declaration of Conformity - Technical Construction File-
lref.(39)
Phase [Technical Testing
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 50 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
Ref:
Versi
Date:3 1/03/1999
R/ACS/007
Specification 0
FUJ00001463
FUJ00001463
Requirement ID 474
Criterion 4
Derivation Requirement
Criterion Description
Such Equipment may be required to be installed in
residential premises.
ITest Condition (Acceptance of Declaration of Technical Conformity.
Method Document inspection
References Declaration of Conformity - Technical Construction File-
iref.(39)
Phase [Technical Testing
Requirement ID 474
Criterion IS
Derivation Requirement
\Criterion Description
IAll Equipment used in the provision of OPS shall comply
ith BS EN60950 : 1992 (BS7002 :1992) and any
subsequent amendments.
ITest Condition (Acceptance of Declaration of Technical Conformity.
Method Document inspection
References Declaration of Conformity - Technical Construction File
Phase [Technical Testing
Requirement ID 474
Criterion 6
Derivation Requirement
\Criterion Description
IAll Equipment used in the provision of OPS comprising AC
lpower adaptors shall comply with BS EN60065 : 1993
(BS7002 :1992).
ITest Condition (Acceptance of Declaration of Technical Conformity.
Method Document inspection
References Declaration of Conformity - Technical Construction File-
lref.(39)
Phase [Technical Testing
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 51 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
FUJ00001463
FUJ00001463
Ref:CR/ACS/007
Versi
Date:3 1/03/1999
Specification
Requirement ID 474
Criterion 7
Derivation Requirement
Criterion Description
[The workstation aspects of all Equipment used in the
provision of OPS shall comply with the Health and Safety
(Display Screen Equipment) Regulations 1992, which
implement Council Directive 90/270/EEC on working with
display screen equipment.
[Test Condition (Acceptance of Declaration of Technical Conformity.
Method Document inspection
References Declaration of Conformity - Technical Construction File-
iref.(39)
Phase Technical Testing
Requirement ID 474
(Criterion 8
Derivation Requirement
{Criterion Description
Any Equipment used in the provision of OPS containing
laser emitters (including, without limitation, laser printers
land laser barcode scanners) shall comply with BS EN
160825:1992.
ITest Condition (Acceptance of Declaration of Technical Conformity.
Method Document inspection
References Declaration of Conformity - Technical Construction File-
Iref.(39)
Phase [Technical Testing
Requirement ID 474
(Criterion 9
Derivation Requirement
ICriterion Description
‘Any telecommunications Equipment used in the provision of
OPS shall comply with Council Directive 91/263/EEC (the
\Telecommunication Terminal Equipment Directive) and
Ihave a current BABT certificate or equivalent for connection
ito the public telephone network.
ITest Condition (Acceptance of Declaration of Technical Conformity.
Method Document inspection
References Declaration of Conformity - Technical Construction File-
iref.(39)
Phase [Technical Testing
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 52 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
FUJ00001463
FUJ00001463
Ref:CR/ACS/007
Versi
Date:3 1/03/1999
Specification
Requirement ID 474
Criterion 10
Derivation Requirement
{Criterion Description
All Equipment used in the provision of OPS which is defined
las machinery shall comply with the Supply of Machinery
(Safety) Regulations 1992, which implement the Machine
Directive 89/392/EEC as amended by 91/368/EEC.
[Test Condition (Acceptance of Declaration of Technical Conformity.
Method Document inspection
References Declaration of Conformity - Technical Construction File-
lref.(39)
Phase [Technical Testing
Requirement ID 474
Criterion 11
Derivation Requirement
ICriterion Description
IAll Equipment used in the provision of OPS shall comply
ith the Electrical Equipment (Safety) Regulations 1994,
hich implement the Low Voltage Directive 73/23/EEC as
lamended by 93/68/EEC.
[Test Condition (Acceptance of Declaration of Technical Conformity.
[Method Document inspection
References Declaration of Conformity - Technical Construction File-
Iref.(39)
Phase [Technical Testing
Requirement ID 474
{Criterion 12
Derivation Requirement
Criterion Description
IAll Equipment used in the provision of OPS and connected,
lor intended for connection, to weighing devices shall meet
ithe requirements of the Non-automatic Weighing
Instruments (EEC Requirements) Regulations 1992
Schedule 3 Applications.
ITest Condition
‘Acceptance of Declaration of Technical Conformity.
Method Document inspection
References Declaration of Conformity - Technical Construction File-
Iref.(39)
Phase [Technical Testing
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 53 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance Ref:
'R/ACS/007
Versi 0
Specification
Date:3 1/03/1999.
FUJ00001463
FUJ00001463
Requirement ID 474
Criterion 13
Derivation Requirement
{Criterion Description
All visual display terminal Equipment (including, without
limitation, keyboards) used in the provision of OPS shall
icomply with the relevant requirements of either BS
7179:1990 or ISO 9241:1992.
[Test Condition (Acceptance of Declaration of Technical Conformity.
Method Document inspection
References Declaration of Conformity - Technical Construction File-
lref.(39)
Phase [Technical Testing
Requirement ID 474
Criterion 14
Derivation Requirement
Criterion Description
IAll Equipment used in the provision of OPS which falls
ithin the scope of The Electromagnetic Compatibility
(EMC) Regulations 1992, which implement Council
Directive 89/336/EEC (as amended by 92/31/EEC), shall
Icomply with such Regulations.
ITest Condition (Acceptance of Declaration of Technical Conformity.
Method Document inspection
References Declaration of Conformity - Technical Construction File-
Iref.(39)
Phase [Technical Testing
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 54 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
Versi 0
Specification
Date:3 1/03/1999.
Requirement ID 474
Criterion 15
Derivation Requirement
Criterion Description
All Equipment used in the provision of OPS shall meet the
minimum EMC requirements of both residential and
commercial installations, including compliance with BS EN
50081 and BS EN 50082 with the following amended test
severity levels and with no degradation of performance:
« IEC 801 part 2 class 3, 6kV contact discharge;
« 1EC 801 part 3 3V/m;
« IEC 801 part 4 +/- 1kV injected onto mains AC supply;
+ IEC 801 part 5 +/- 2kV.
[Test Condition (Acceptance of Declaration of Technical Conformity.
Method Document inspection
References Declaration of Conformity - Technical Construction File-
iref.(39)
Phase [Technical Testing
Requirement ID 474
Criterion 16
Derivation Requirement
ICriterion Description
IAll Equipment used in the provision of OPS and covered by
IEN45501:1992 shall comply with clause A4.5 (voltage
ariations) and Annex B of that standard.
ITest Condition ‘Acceptance of Declaration of Technical Conformity.
Method Document inspection
References Declaration of Conformity - Technical Construction File-
lref.(39)
Phase [Technical Testing
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 55 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
Versi 0
Specification
Date:3 1/03/1999.
Requirement ID 474
Criterion 17
Derivation Requirement
Criterion Description
All items of Equipment used in the provision of OPS shall
lhave an Index of Protection rating of IP3X as defined in BS
EN 60529:1992.
ITest Condition (Acceptance of Declaration of Technical Conformity.
Method Document inspection
References Declaration of Conformity - Technical Construction File-
Iref.(39)
Phase Technical Testing
Requirement ID 474
Criterion 18
Derivation Requirement
Criterion Description
[The Equipment used in the provision of OPS and its
installation shall not constrain the AUTHORITIES or the
\Agents from meeting their legal safety responsibilities as
lemployers.
ITest Condition (Acceptance of Declaration of Technical Conformity.
Method Document inspection
References Declaration of Conformity - Technical Construction File-
Iref.(39)
Phase [Technical Testing
Requirement ID 474
ICriterion 19
Derivation Requirement
\Criterion Description
It shall be possible to prove compliance with legislation or
Imandatory standards as and when necessary.
ITest Condition (Acceptance of Declaration of Technical Conformity.
Method Document inspection
References Declaration of Conformity - Technical Construction File-
Iref.(39)
Phase [Technical Testing
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 56 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
Versi 0
Specification
Date:3 1/03/1999.
Requirement ID 475
Criterion 4
Derivation Requirement
\Criterion Description
The CONTRACTOR shall draw up the POCL Style Guide
land agree this with the AUTHORITIES by a date consistent
ith the project plan agreed by the parties, such that the
date does not adversely impact contractual milestones as
defined in Clause 605.1 of the Authorities Agreement. Any
Services to be offered via the OPS shall be provided in
laccordance with the POCL Style Guide.
ITest Condition [Acceptance of Horizon OPS Style Guide _- ref.(35)
Method Document Inspection
References Horizon OPS Style Guide
Phase [Technical Testing
Requirement ID 475
{Criterion 2
Derivation Requirement
ICriterion Description
(The POCL Style Guide shall set out, inter alia, general
guidelines for the Human Computer Interface, including
iscreen layouts, system navigation routes and help and
manual entry facilities.
ITest Condition [Acceptance of Horizon OPS Style Guide
Method Document Inspection
References Horizon OPS Style Guide - ref.(35)
Phase [Technical Testing
Requirement ID 475
{Criterion 3
Derivation Requirement
ICriterion Description
{The Human Computer Interface shall be intuitive and easy
ito use, to minimise errors and delays.
\Test Condition [Acceptance of Horizon OPS Style Guide
Absence of Usability incidents relating to the HCI at the end
lof Operational Trial
Method Document Inspection.
Analysis of results of Outlet Satisfaction reports from Live
Trial.
References Horizon OPS Style Guide - ref.(35)
Planned Evaluation Matrix - ref. (94)
Phase (Operational Trial
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 57 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
Versi 0
Specification
Date:3 1/03/1999.
Requirement ID 475
(Criterion 4
Derivation Requirement
ICriterion Description
The Human Computer Interface shall provide a consistent
look and feel across all Applications and be easy to adapt
ito facilitate the introduction of new Applications.
ITest Condition (Acceptance of conformance to Horizon OPS Style Guide
Method Document Inspection
References Horizon OPS Style Guide - ref.(35)
Phase Technical Testing
Requirement ID 476
Criterion 4
Derivation Requirement
{Criterion Description
[The following shall be approved by the AUTHORITIES
before any Release, this approval not being unreasonably
lwithheld:-
a) the contents of any Release;
b) the upgrade path for any Release;
c) the timing of the distribution of any Release;
d) the timing of the activation of any Release.
ITest Condition Completion of Release Authorisation Board and production
lof Sign-Off sheet for ref.(86)
Method Document Inspection
References
Phase Technical Testing
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 58 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
0
Specification Versi
Date:3 1/03/1999.
Requirement ID 476
{Criterion 2
Derivation Requirement
Criterion Description
IThe CONTRACTOR shall provide proof of sufficient and
satisfactory pre-testing of each Release, including the
following aspects:-
(a) at individual component (unit test) level;
(b) of all components of the Release, both changed and
unchanged, working together (system test);
(c) of all components in combination with different
hardware and software combinations which may be
encountered when the Release is in live, non-training, use
hereunder.
ITest Condition
[Acceptance of Pathway Testing Strategy.
[That the MOT, E2E, BIT Closure reports contains no non-
conforming entries for the ICL Pathway specific elements.
[That the Release Authorisation Board are satisfied with the
status of testing for Release 2.
Method
Document Inspection.
References
iTesting and Integration Strategy - ref.(40)
Revisions to the T&l approach for release 2 - ref.(68)
Release Authorisation of the NR2 (Child Benefit) Release -
iref.(86).
DIT Closure Report - New Release 2 - ref.(89)
IMOT Closure Report - New Release 2 - ref.(90)
IE2E Closure Report - New Release 2 - ref.(91)
Phase
[Technical Testing
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 59 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
FUJ00001463
FUJ00001463
Ref:
Versi
Date:3 1/03/1999
R/ACS/007
Specification 0
Requirement ID 476
Criterion 3
Derivation Requirement
ICriterion Description
The CONTRACTOR shall provide proof of sufficient and
satisfactory preparation for the implementation of a
Release. This shall include testing the implementation,
reversion and regression from the Release.
\Test Condition Availability of approved High Level Test Plans.
Testing phases are documented and completed as shown
lin R2 programme plan.
‘That the Release Authorisation Board are satisfied with the
status of testing for Release 2.
Method Document Inspection
References HLTPs - various.
New Release 2 High Level Plan - ref.(24).
Release Authorisation of the NR2 (Child Benefit ) Release -
ref.(86).
Phase Model Office
Requirement ID 476
(Criterion 7
Derivation Requirement
(Criterion Description
IThe CONTRACTOR shall maintain a detailed record of all
Releases and where they are deployed.
ITest Condition The asset management function of Tivoli records the
contents, version and revision levels of all software
installed on counter equipment and is updated as a result ofI
lany software distribution undertaken under Tivoli control on
lagreed supported systems.
Method ICL Pathway Tivoli and Configuration Management
Systems will be inspected as part of the site visit.
References
Phase IModel Office
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 60 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway POCL Infrastructure Acceptance Ref:CR/ACS/007
Specification Version:2.0
P Date:3 1/03/1999
FUJ00001463
FUJ00001463
Requirement ID 477
(Criterion 4
Derivation Requirement
{Criterion Description
The CONTRACTOR shall maintain a detailed list of all
physical components installed at Premises (an asset
register) and make it available to the AUTHORITIES on
request.
Reason
Statement of Fact or Obligation
Subject to request from AUTHORITIES.
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 61 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
FUJ00001463
FUJ00001463
Ref:CR/ACS/007
Versi
Date:3 1/03/1999
Specification
Requirement ID 477
Criterion 2
Derivation Requirement
Criterion Description
From the list it shall be possible to identify all elements of
the Service Infrastructure installed at any location.
ITest Condition
(Asset database - Dispatch-1 will be fed information on
iserialised whole units from the post office counter Roll Out
database. It will be maintained (additions, deletions and
lamendments) by information provided by Pathway Central
Operations or by asset movements recorded by ICL
System Service staff during maintenance operations.
IMethod Site Visit
Document Inspection
References Asset Register- ref.(41)
Phase Model Office
Requirement ID 478
{Criterion 4
Derivation Requirement
Criterion Description
[TMS shall link into each instance of OPS that is to be used
ifor live work.
ITest Condition (Acceptance of Pathway Technical Architecture
Method Document Inspection
References [Technical Environment Description (sections 4.1 to 4.5) -
Iref.(37)
Phase [Technical Testing
Requirement ID 478
Criterion 3
Derivation Requirement
Criterion Description
TMS shall provide links into other POCL systems, including
ithout limitation TIP as required to support POCL.
ITest Condition
Acceptance of Pathway Technical Architecture
Method
Document Inspection
References
[Technical Environment Description (sections 4.1 to 4.4) -
Iref.(37)
FTMS Configurations for Pathway TPS and POCL TIP links
lat Release 2 - ref.(85)
Pathway to Post Office Technical Interface Specification -
ref. (95)
Phase
Technical Testing
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 62 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
Versi 0
Specification
P Date:3 1/03/1999
Requirement ID 478
Criterion 4
Derivation Requirement
ICriterion Description [TMS shall provide links into PAS and CMS
ITest Condition (Acceptance of Pathway Technical Architecture
Method Document Inspection
References [Technical Environment Description (sections 4.1 to 4.4) -
Iref.(37)
Phase [Technical Testing
Requirement ID 478
Criterion IS
Derivation Requirement
Criterion Description
ITMS shall provide Data File collection and Data File
delivery Services. It shall be possible to collect Data Files
from or deliver Data Files to any computer system attached
to TMS.
\Test Condition [Acceptance of Pathway Technical Architecture.
[Acceptance of TMS Agent High Level Design.
Method Document Inspection
References [Technical Environment Description (sections 5.1 to
5.2.1.1.1, 5.2.3, 9.4) - ref.(37)
Phase [Technical Testing
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 63 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
FUJ00001463
FUJ00001463
Ref:
Versi
Date:3 1/03/1999
R/ACS/007
Specification 0
Requirement ID 478
(Criterion 6
Derivation Requirement
(Criterion Description
Data File collection and Data File delivery Services
provided by TMS shall be triggerable by any of:
+ User action;
+ time;
le in response to a message from an attached computer
system or generated within TMS.
\Test Condition [Acceptance of Pathway Technical Architecture.
‘Acceptance of TMS Agent design as contained in TED.
‘Acceptance of Riposte 32 API.
Use of Maestro job scheduling.
Method Document Inspection
References Riposte 32 API Specification. - ref.(32)
[Technical Environment Description (sections 5.1 to
5.2.1.1.1, 5.2.3, 9.4) - ref.(37)
Maestro Job Schedule - PAS/CMS - ref.(72)
Phase Technical Testing
Requirement ID 478
{Criterion 7
Derivation Requirement
Criterion Description
[The collection or delivery of Data Files shall be retried
lautomatically, under parameter control, in the event of any
failure.
ITest Condition
[Acceptance of mechanisms described in FTMS Resilience
& Recovery Strategy.
Method Document Inspection
References Release 2 FTMS Resilience and recovery strategy - ref.(87)
Phase [Technical Testing
[Requirement ID
478
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 64 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance __Ref.CR/ACS/007
Specification Versi 0
Date:3 1/03/1999.
[Criterion 8
Derivation Requirement
ICriterion Description
It shall be possible for POCL to specify a pre-defined list of
computer systems to which a Data File is to be delivered or
from which a Data File is to be collected.
ITest Condition Use of Change Control to introduce new sources /
destinations of Data Files for operation across Generic
[Technical Interface.
Method Document Inspection
References Pathway to Client Generic Technical Interface Specification
Iref.(43).
Phase Technical Testing
Requirement ID 478
Criterion 12
Derivation Requirement
Criterion Description
TMS shall include the following processing capabilities:
+ validation of Data Files;
/ consolidation of many Data Files into one Data File;
/ generating many Data Files from one Data File;
+ reformatting the contents of Data Files;
l/ generating control totals through access to the contents
lof Data Files;
le reconciliation of control totals;
l/ produce reports summarising financial transactions.
ITest Condition ‘Acceptance of Pathway Technical Architecture.
‘Acceptance of exemplar file handling capability as
described in TPS Service Design Specification.
Method Document inspection.
References \Technical Environment Description (sections 5.1 to 5.2) -
Iref.(37)
ITP Service Design Specification - ref.(44)
Phase [Technical Testing
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 65 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
FUJ00001463
FUJ00001463
Ref:
Versi
Date:3 1/03/1999
R/ACS/007
Specification 0
Requirement ID 478
Criterion 13
Derivation Requirement
(Criterion Description IPathway shall maintain a full audit trail of all TMS activity
ITest Condition (Completion of all tests in Audit Acceptance Specification
Method Document Inspection
References ‘Audit Closure Report - ref.(81)
Phase Technical Testing
Requirement ID [479
{Criterion 4
Derivation Requirement
{Criterion Description
No computer system shall be connected to the elements of
ithe Service Infrastructure on which TMS is provided without
the approval of the AUTHORITIES.
Statement of Fact or Obligation
Requirement ID 479
Criterion 2
Derivation Requirement
\Criterion Description
ITMS shall only allow connections to such elements of the
Service Infrastructure to be established with computer
isystems which are approved by the AUTHORITIES to be
connected.
ITest Condition
(Acceptance of measures described in Technical
Environment Description
Method Document Inspection.
References (Technical Environment Description (sections 9.1 to 9.3) -
Iref.(37)
Phase [Technical Testing.
© 1999 ICL Pathway Ltd
Printed on: 24/01/01
Page 66 of 1
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
FUJ00001463
FUJ00001463
Ref:CR/ACS/007
Versi
Date:3 1/03/1999
Specification
Requirement ID 479
{Criterion 3
Derivation Requirement
\Criterion Description
Pathway shall maintain a register of computer systems with
connections to such elements of the Service Infrastructure
ito be established with computer systems which are
lapproved by the AUTHORITIES to be connected.
ITest Condition (Acceptance of configuration details recorded in Technical
Environment Implementation.
Method Document Inspection
References ‘Technical Environment Implementation for Release 2. -
ref.(45)
Phase Technical Testing
Requirement ID 479
(Criterion iS
Derivation Requirement
ICriterion Description
ITMS shall produce reports detailing any attempt to
establish a link which is rejected. The CONTRACTOR shall
rovide these reports to the AUTHORITIES on request.
ITest Condition Acceptance of Network Infringement Policy.
Provision of Network Infringement Report.
Method Document Inspection
References Network Infringement Policy- ref.(46)
Network Infringement Report- ref.(47)
Phase [Technical testing
Requirement ID 480
Criterion 4
Derivation Requirement
Criterion Description
ITMS shall be logically discrete from other Services such
jthat other services can be separately procured that make
luse of TMS and such that, in extremis, a replacement
service for TMS could be separately procured.
ITest Condition ‘Acceptance of Pathway Technical Architecture
Method Document Inspection
References Service Architecture Design Document- ref.(48)
Phase [Technical testing
Requirement ID
480
{Criterion
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 67 of 1
obligations between ICL Pathway and the DSS and/or POCL
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance __Ref.CR/ACS/007
Specification Versi
Date:3 1/03/1999.
Derivation Requirement
Criterion Description
In particular there shall be a clear and documented
linterface between PAS and TMS functions and CMS and
TMS functions. These interfaces shall include:
(a) specification of any programming interface that exists;
(b) specification of any shared data and data standards;
(c) specification of any other protocols that exist to allow
communication between functions within the Services;
(d) specification of any other constraint that enables
interoperability between Services.
ITest Condition Acceptance of Pathway Service architecture and TMS to
PAS/CMS Agent Specification.
Method Document Inspection
References. Service Architecture Design Document. - ref.(48)
IBPS Agents - High Level Design for Release 2. - ref.(49)
Phase [Technical Testing
Requirement ID 536
(Criterion 1
Derivation Requirement
Criterion Description
Peripheral and input devices supplied as part of the
elements of the Service Infrastructure on which OPS is
rovided shall be reliable, robust and easy to use.
ITest Condition
(Acceptance of Counter Hardware Design Specification,
PPD - Operating Environment and Horizon OPS Style
iGuide.
IMethod
Document Inspection
On-going review as part of Horizon Service Review Forum.
References
(Counter Hardware Design Specification. - ref.(25)
PPD - Operating Environment. - ref.(26)
Customer Services - Service Management Operations
Manual - ref.(76)
Horizon OPS Style Guide - ref.(35)
Phase
[Technical Testing
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 68 of 1
obligations between ICL Pathway and the DSS and/or POCL
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance __Ref.CR/ACS/007
Specification Version:2.0
Date:3 1/03/1999
Requirement ID 536
(Criterion 2
Derivation Requirement
Criterion Description
Peripheral and input devices supplied as part of the
lelements of the Service Infrastructure on which OPS is
provided shall be capable of detecting contention,
remature removal/swapping of Tokens etc. as appropriate
[Test Condition Acceptance of functionality provided within Riposte
Peripheral Broker. Acceptance of functionality provided by
Ismart-card reader in Pathway keyboard.
Method Document Inspection
References Riposte Peripheral Broker overview. - ref.(50)
Firmware Specifications - Pathway Keyboard. - ref.(51)
Phase [Technical Testing
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 69 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
0
Specification Versi
Date:3 1/03/1999.
Requirement ID 537
{Criterion 4
Derivation Requirement
Criterion Description
[The CONTRACTOR shall carry out system management of
all the Services in a consistent and coherent manner to
lensure the following:
a) activities within the Services, including PAS, CMS,
TMS, OPS, BES, OBCS, APS and EPOSS, are co+
ordinated such that, for example, changes and
faults can be tracked across Service boundaries;
b) changes to the Services can be made speedily
and accurately.
ITest Condition ICL Pathway will carry out system management or service
reviews of all the Services to met the above criterion.
(Conformance to this can be demonstrated in a site visit and
la walk through of the procedures.
Method Site Visit
Document Inspection
References ISMC Core Processes for Service Delivery - ref.(70)
Horizon System Helpdesk Call Enquiry Matrix - ref.(52)
Horizon System Helpdesk : Processes and Procedures
Description - ref.(53)
Payment Card Helpline : Processes and Procedures
Description - ref.(69)
ICL Pathway Customer Services - Service Management
Operations Manual - ref. (76)
Phase Model Office
© 1999 ICL Pathway Ltd = COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 70 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
FUJ00001463
FUJ00001463
Ref:
Versi
Date:3 1/03/1999
R/ACS/007
Specification 0
Requirement ID 537
(Criterion 2
Derivation Schedule G01 - 5.3.5.1
{Criterion Description
Software distribution facilities shall be provided by the
ICONTRACTOR which shall enable Software files and
installation scripts to be distributed across the Wide Area
Networks, part of the Service Infrastructure, to a specific
Outlet, all Outlets or a group of Outlets selected according
jto one or more particular attributes.
ITest Condition (Acceptance of Systems Management mechanisms (Tivoli
land Auto-Config) to control software configurations in
outlets.
Method Document Inspection
References [Technical Environment Description (section 12) - ref.(37)
Phase [Technical Testing.
Requirement ID 538
{Criterion 4
Derivation Requirement
Criterion Description
ISMS shall provide a facility for synchronising the date and
time across the Services and the Service Infrastructure.
This shall cater for the handling of clock changes (e.g. at
ithe beginning and end of British Summer Time).
ITest Condition Acceptance of mechanisms described in Time Services
Specification and of GMT as the standard for timestamps as
stated in TED.
Method Document Inspection
References [Time Services Specification - ref.(79)
Technical Environment Description(section 12.7.10) -
Iref.(37)
Phase [Technical Testing
© 1999 ICL Pathway Ltd
Printed on: 24/01/01
Page 71 of 1
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
FUJ00001463
FUJ00001463
Ref:
Versi
Date:3 1/03/1999
R/ACS/007
Specification 0
Requirement ID 540
\Criterion 4
Derivation Requirement
Criterion Description
IThe CONTRACTOR shall give due attention to the effects
of the Equipment used in the provision of OPS on the
environment during manufacture, installation and use. This
includes:
(a) use of CFCs;
(b) energy consumption;
(c) recyclability of components;
(d
recyclability of consumables;
(e) waste minimisation;
(£) use of sustainable resources;
(g) disposal of displaced equipment and waste;
(h
making appropriate use of recycled materials.
ITest Condition
Acceptance of Pathway Environmental Policy
Method Document Inspection
References Pathway Environmental Policy - ref.(54)
Phase [Technical Testing
Requirement ID 540
Criterion 2
Derivation Requirement
Criterion Description
[The CONTRACTOR shall adhere to relevant environmental
legislation such as the Environmental Protection Act 1990
land publication ‘Waste Management: The Duty of Care -A
Code of Practice’.
ITest Condition Acceptance of Pathway Environmental Policy
Method Document Inspection
References Pathway Environmental Policy - ref.(54)
Phase [Technical Testing
Requirement ID 541
{Criterion 1
© 1999 ICL Pathway Ltd
Printed on: 24/01/01
Page 72 of 1
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance __Ref.CR/ACS/007
Specification Version:2.0
Date:3 1/03/1999.
Derivation Requirement
\Criterion Description
ITMS shall be scaleable to meet POCL’s business needs
ifrom time to time
ITest Condition (Acceptance of results detailed in Performance Model
[Component Calibration for Release 2.
Method Document Inspection
References Performance Model Component Calibration for Release 2. -
iref.(55)
ICL Pathway Performance and Scalability Strategy - ref.(84)
Phase [Technical Testing
Requirement ID 541
Criterion 2
Derivation Requirement
Criterion Description
[This capability shall include the ability to support any Client
ITransactions re-engineered by POCL, new capabilities
developed by POCL and considerable volumes of
\Transactions needing authorisation from a Client system or
la central point in POCL.
ITest Condition (Acceptance of results detailed in Performance Model
(Component Calibration for Release 2.
Method Document Inspection
References Performance Model Component Calibration for Release 2. -
Iref.(55)
ICL Pathway Performance and Scalability Strategy - ref.(84)
Phase Technical Testing
Requirement ID 542
Criterion 1
Derivation Requirement
Criterion Description
The CONTRACTOR shall fully support the Software in the
Service Infrastructure during the life of the elements of the
Service Infrastructure on which such Software is utilised in
providing the Services.
Reason
Statement of Fact or Obligation
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 73 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
Versi 0
Specification
Date:3 1/03/1999.
Requirement ID 555
(Criterion 1
Derivation Requirement
Criterion Description
In each Outlet, at each automated Counter Positions, from
Roll Out at such Outlet, OPS shall support the reading of
track 2 from magnetic stripe cards complying with ISO 7811
arts 1-4
ITest Condition Acceptance of Counter Hardware Design Specification.
Acceptance of Magnetic card Reader Specification.
Method Document Inspection
References (Counter Hardware Design Specification. - ref.(25)
Magnetic Card Reader Specification. - ref.(56)
Phase [Technical Testing
Requirement ID 995
{Criterion 2
Derivation Requirement
ICriterion Description
In each Outlet, at each automated Counter Positions, from
Roll Out at such Outlet support the reading from and writing
ito Smart Tokens complying with
:ISO 7816 parts 1 and 2;
land /or ISO 7816 parts 1, 2 and 3;
ITest Condition Acceptance of Counter Hardware Design Specification.
(Note: There is no requirement for POCL Client Smart
[Tokens at Release 2).
Method Document Inspection
References (Counter Hardware Design Specification- ref.(25)
Smart Card Reader Test report - ref.(77)
Phase [Technical Testing
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 74 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
FUJ00001463
FUJ00001463
Ref:CR/ACS/007
Versi
Date:3 1/03/1999
Specification
Requirement ID 555
{Criterion 3
Derivation Requirement
Criterion Description
In each Outlet, at each automated Counter Positions, from
Roll Out at such Outlet, OPS shall be capable of supporting
future applications reading from and writing to Smart
[Tokens which comply with
:ISO 7816 part 4.
\Test Condition Acceptance of Counter Hardware Design Specification.
(Note: There is no requirement for POCL Client Smart
[Tokens at Release 2).
Method Document Inspection
References Counter Hardware Design Specification- ref.(25)
[Smart Card Reader Test report - ref.(77)
Phase [Technical Testing
Requirement ID 555
{Criterion 4
Derivation Requirement
ICriterion Description
In each Outlet, at each automated Counter Positions, from
Roll Out at such Outlet, OPS shall support magnetic stripe
cards and Smart Tokens that do not match the above
standards in all respects (e.g. where embossing is not in
ithe correct position, or the magnetic stripe does not adhere
fully to the standards set out in paragraph 1.1) save to the
lextent specified in the Solution to this Requirement;
\Test Condition
‘Acceptance of flexibility enabled using FLASH RAM
Imechanism of Pathway keyboard.
‘Acceptance of flexible token validation mechanism
isupported using Riposte Peripheral Broker.
(Note: There is no requirement for POCL Client Smart
[Tokens at Release 2).
Method
Document Inspection
References
Counter Hardware Design Specification. - ref.(25)
Specification - Pathway Keyboard. - ref.(42)
Firmware Specifications - Pathway Keyboard. - ref.(51)
Riposte Peripheral Broker overview. - ref.(50)
Phase
[Technical Testing
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 75 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
Versi 0
Specification
Date:3 1/03/1999.
Requirement ID 555
Criterion 5
Derivation Requirement
Criterion Description
In each Outlet, at each automated Counter Positions, from
Roll Out at such Outlet, OPS shall support the reading of
lone dimensional bar-codes. The maximum bar-code width
to be read shall be 10.9 cm at a resolution of 9 mils. OPS
ishall support, at minimum code 128, EAN 8, EAN 13, code
39.
ITest Condition (Acceptance of Counter Hardware Design Specification.
Method Document Inspection
References (Counter Hardware Design Specification- ref.(25)
Phase Technical Testing
Requirement ID S57
(Criterion 4
Derivation Requirement
Criterion Description
IOPS and the elements of the Service Infrastructure on
hich OPS is provided shall have the flexibility for
additional peripheral equipment to be added in the future,
including input devices and printers.
ITest Condition ‘Acceptance of additional connectivity described in Counter
Hardware Design Specification.
‘Acceptance of peripheral support mechanisms provided by
Riposte Peripheral Broker.
Method Document Inspection
References Counter Hardware Design Specification- ref.(25)
Riposte Peripheral Broker overview- ref.(50)
Phase [Technical Testing
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 76 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
Versi 0
Specification
Date:3 1/03/1999.
Requirement ID S57
Criterion 2
Derivation Requirement
Criterion Description
[The AUTHORITIES shall have the option to add up to three
itypes of additional peripheral equipment during the five (5)
ear period from execution hereof.
\Test Condition (Acceptance of additional connectivity described in Counter
Hardware Design Specification.
[Acceptance of peripheral support mechanisms provided by
Riposte Peripheral Broker.
Method Document Inspection
References (Counter Hardware Design Specification- ref.(25)
Riposte Peripheral Broker overview- ref.(50)
Phase [Technical Testing
Requirement ID 557
Criterion 3
Derivation Requirement
Criterion Description
[The AUTHORITIES shall have the option to require OPS to
support the reading of OCR to interpret code lines on bills
letc. If such option is exercised, the Charges for such
Service shall be as set out in the Solution to this
Requirement.
ITest Condition (Acceptance of additional connectivity described in Counter
Hardware Design Specification.
Acceptance of peripheral support mechanisms provided by
Riposte Peripheral Broker.
Method Document Inspection
References (Counter Hardware Design Specification- ref.(25)
Riposte Peripheral Broker overview- ref.(50)
Phase [Technical Testing
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 77 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
FUJ00001463
FUJ00001463
Ref:CR/ACS/007
Versi
Date:3 1/03/1999
Specification
Requirement ID S57
Criterion 4
Derivation Requirement
Criterion Description
IThe AUTHORITIES shall have the option to require OPS to
isupport the reading of two dimensional bar-codes. If such
loption is exercised, the Charges for such Service shall be
las set out in the Solution to this Requirement.
ITest Condition ‘Acceptance of additional connectivity described in Counter
Hardware Design Specification.
(Acceptance of peripheral support mechanisms provided by
Riposte Peripheral Broker.
Method Document Inspection
References (Counter Hardware Design Specification- ref.(25)
Riposte Peripheral Broker overview- ref.(50)
Phase [Technical Testing
Requirement ID S57
Criterion iS
Derivation Requirement
Criterion Description
The AUTHORITIES may, as an Additional Service, require
IOPS and the elements of the Service Infrastructure on
hich OPS is provided to be linked to teller cash
dispensers. Such Additional Service shall be subject to
lagreement with the CONTRACTOR.
\Test Condition Acceptance of additional connectivity described in Counter
Hardware Design Specification.
[Acceptance of peripheral support mechanisms provided by
Riposte Peripheral Broker.
Method Document Inspection
References Counter Hardware Design Specification- ref.(25)
Riposte Peripheral Broker overview- ref.(50)
Phase [Technical Testing
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 78 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
Versi 0
Specification
Date:3 1/03/1999.
Requirement ID 558
Criterion 4
Derivation Requirement
Criterion Description
[The OPS shall support the POCL imperative of keeping
[Transaction times to a minimum.
\Test Condition
Acceptance of benchmark counter transaction times for
IOBCS, APS, BES and EPOS.
Method Document Inspection
References IAPS Benchmark Counter Transaction Times for Release 2-
Iref.(57)
IBES Benchmark Counter Transaction Times for Release 2 -
lref.(58)
IOBCS Benchmark Counter Transaction Times for
Release 2 - ref.(59)
IEPOS Benchmark Counter Transaction Times for
Release 2 - ref.(60)
Phase Live Trial
Requirement ID 558
Criterion 2
Derivation Requirement
{Criterion Description
[The OPS shall be capable of supporting the entire range of
business transacted at Outlets for current volumes of
business and volumes of business as projected by POCL.
\Test Condition ‘Acceptance of adequacy of OPS disc capacity and
archiving policy.
Method Document Inspection
References ICL Pathway Performance and Scalability Strategy - ref.(84)
Technical Environment Description (sections 15.9.2) -
Iref.(37)
Phase [Technical Test
Requirement ID 559
Criterion 4
Derivation Requirement
Criterion Description
IOPS shall be provided in each Outlet
Reason
Statement of Fact or Obligation
[Requirement ID
[659
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 79 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance __Ref.CR/ACS/007
Specification Versi 0
Date:3 1/03/1999.
[Criterion 2
Derivation Requirement
\Criterion Description
IOPS shall have the ability to support the automation of all
[Transactions performed at Counters Positions.
ITest Condition ‘Acceptance that the applications architecture used to
lprovide OPS provides the mechanisms to support the
automation / re-engineering of POCL Transactions.
Method Document Inspection
References IOPS Architecture Document- ref.(30)
Phase [Technical Test
Requirement ID S59
{Criterion 3
Derivation Requirement
Criterion Description
From Roll Out in each Outlet OPS shall be capable of
supporting APS, BES and OBCS and EPOSS in that Outlet.
ITest Condition
[Acceptance that the scope of Release 2 comprises support
lof APS, BES, OBCS and EPOSS on OPS.
IThat the MOT Closure reports contains no non-conforming
lentries for the ICL Pathway specific elements concerning
ithe support of APS, BES, OBCS and EPOSS on OPS.
Method
Document Inspection
References
Pathway New Release 2 Contents Description - ref. (61)
IMOT Closure Report - New Release 2 - ref.(90)
Phase
[Technical Test
Requirement ID 560.
Criterion 4
Derivation Requirement
Criterion Description
[The AUTHORITIES wish to take advantage of the changes
lin technology during the term of the Related Agreements.
INo change shall be made to the specification of equipment
ito be used within the Service Infrastructure, without the
lapproval of the AUTHORITIES.
Reason
[Statement of Fact or Obligation
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 80 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
Versi 0
Specification
Date:3 1/03/1999.
Requirement ID 560
(Criterion 2
Derivation Requirement
Criterion Description
The specification of the equipment being used and installed
ithin the Service Infrastructure shall be reviewed by the
parties at times reasonably agreed by them, to ensure that
ithe most appropriate technology is being deployed.
ITest Condition Equipment Specification may be raised within the regular
Service Management review forum.
Method Document Inspection
References (Customer Services - Services Management Operations
[Manual - ref.(76).
Phase [Technical Test
Requirement ID 561
{Criterion 4
Derivation Requirement
Criterion Description
Pathway shall indemnify the AUTHORITIES against any
dispute of Pathway’s or the AUTHORITIES’ right to utilise
ithe Hardware, Software or any information used for any of
ithe Services (e.g. third party challenges with reference to
licensing or Intellectual Property Rights)
ITest Condition IThis is contained in Clause 805 of the Authorities
Agreement.
Method Document Inspection
References (Authorities Agreement - ref.(78)
Phase [Technical Test
Requirement ID 561
(Criterion 2
Derivation Requirement
Criterion Description
In the event of any dispute of Pathway’s or the
AUTHORITIES’ right to utilise the Hardware, Software or
lany information used for any of the Services, Pathway shall
lensure that there is no impact on the level of the Services.
ITest Condition
[This is contained in Clause 805 of the Authorities
Agreement.
Method Document Inspection
References (Authorities Agreement - ref.(78)
Phase [Technical Test
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 81 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
FUJ00001463
FUJ00001463
Ref:CR/ACS/007
Versi
Date:3 1/03/1999
Specification
Requirement ID i826
Criterion 4
Derivation Requirement
\Criterion Description
IOPS, and the elements of the Service Infrastructure on
hich OPS is provided, shall be able to be connected, and
shall support such connection, to specialist peripherals in
lsuch a way that the specialist peripherals may be accessed
lby one, two or more terminals.
ITest Condition ‘Acceptance of facilities provided by Riposte Peripheral
Broker
Method Document Inspection
References Riposte Peripheral Broker overview. - ref.(50)
Phase Technical Testing
Requirement ID 826
Criterion 2
Derivation Requirement
{Criterion Description
here specialist peripherals may be accessed by one, two
lor more terminals it shall be possible to restrict access to a
subset of the terminals in each Outlet
ITest Condition (Acceptance of facilities provided by Riposte Peripheral
Broker
Method Document Inspection
References Riposte Peripheral Broker overview. - ref.(50)
Phase [Technical Testing
Requirement ID 827
Criterion 4
Derivation Requirement
Criterion Description
It is likely that, in due course, re-engineered POCL
Products shall require specific authorisation, either through
laccess to a computer system external to the Services or
ithin the Services.
{Test Condition (Acceptance of flexibility and capability described in
Pathway Technical Architecture.
Method Document Inspection.
References [Technical Environment Description(Chapter 17)- ref.(37)
IOPS Architecture Document- ref.(30)
ITMS Architecture Document- ref.(31)
Phase [Technical testing.
Requirement ID 1827
Criterion 2
Derivation Requirement
© 1999 ICL Pathway Ltd
Printed on: 24/01/01
Page 82 of 1
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance Ref:CR/ACS/007
Specification Version:2.0
P Date:3 1/03/1999
[Criterion Description [The Services and the Service Infrastructure shall be able to
be developed to support the maintenance and use of:
(a) stop lists;
(b) go lists;
(c) other authorisation types;
lin relation to such POCL Products.
\Test Condition (Acceptance of exemplar functionality contained in OBCS
land CMS.
Method Document Inspection
References IOBCS Design Specification - ref.(62)
(Oracle High Level Design PMS/CMS - ref.(63)
Phase Technical Testing
© 1999 ICL Pathway Ltd = COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 83 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL.
ICL Pathway
POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
Versi 0
Specification
Date:3 1/03/1999.
Requirement ID i869
Criterion 1
Derivation Requirement
\Criterion Description
The AUTHORITIES primary concern is with the overall
performance of the Services as they impact upon the
AUTHORITIES’ own systems, clients, staff, agents and
customers.
Therefore, targets for the level of internal performance
between services shall not be set by the Authorities.
However, internal service performance shall be judged by
ithe Authorities as it affects overall performance of the
services.
ITest Condition
Production of test results as described in Boundary
Performance.
Method Document Inspection
References IA2A Resolution - Boundary Performance- ref.(65)
Phase Live Trial
Requirement ID i869
{Criterion 2
Derivation Requirement
Criterion Description
la) The CONTRACTOR shall specify the internal
performance requirements of any Service that potentially
Imay be re-tendered. B) The CONTRACTOR shall maintain
land report actual measured performance for TMS as it
linterfaces to other Services.
ITest Condition Production of test results as described in Boundary
Performance.
Method Document Inspection
References IA2A Resolution - Boundary Performance- ref.(65)
Phase Live Trial
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 84 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
Versi 0
Specification
Date:3 1/03/1999.
Requirement ID i869
Criterion 3
Derivation Requirement
Criterion Description
For the TMS, the CONTRACTOR shall specify the
lperformance requirements and tolerances for:
(a) hours of operation of TMS
\(b) response time required between TMS and :-
PAS
le CMS
le OPS
\(c) the number of outages of TMS, identifying types of
outages monitored
\(d) the availability of TMS
ITest Condition
la) TMS must be available 24hrs a day / 365 days a year
lb) There is no concept of response time between TMS and
PAS, CMS or OPS. The TMS to OPS interface is
immediate since they are co-located on the counter PC.
The boundary performance of TMS to PAS/CMS is
provided via 869/2
Ic) TMS must be continuously available and resilient to
multiple system and geographic failures.
ld) See above.
Acceptance of above statements and of characteristics
described in Chapter 13 - “Availability” of the Technical
Environment Description.
Method
Document Inspection
References
\Technical Environment Description (Chapter 13) -
iref.(37).
Phase
[Technical Testing
Requirement ID i869
Criterion 4
Derivation Requirement
\Criterion Description
[The CONTRACTOR shall report against all performance
requirements identified in Requirement 869 Criterion 3.
ITest Condition Production of monthly Performance Statistics.
Method Document Inspection
References Service Review - Performance Statistics - ref.(75)
Phase [Technical Testing
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 85 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
0
Specification Versi
Date:3 1/03/1999.
Requirement ID i869
{Criterion IS
Derivation Requirement
ICriterion Description
IThe CONTRACTOR shall maintain detailed technical
\documentation of the interfaces from TMS to PAS, CMS,
OPS and all attachable elements of the Service
Infrastructure
\Test Condition (Acceptance of interface documentation and connection
Imechanisms as described in Technical Environment
Implementation.
Method Document inspection
References Riposte 32 API Specification- ref.(32)
Service Architecture Design Document- ref.(48)
Oracle High Level Design PMS/CMS- ref.(63)
[Technical Environment Implementation for Release 2 -
Iref.(45)
ITechnical Environment Description (Sections 4.4.7, 9.3,
9.4) - ref.(37).
Phase [Technical Testing
Requirement ID 912
Criterion 4
Derivation Requirement
Criterion Description
Pathway shall carry out regular Portable appliance testing
lof the elements of the service infrastructure installed as part}
lof the Services in post offices and on any other DSS or
POCL premises as required by legislation
Reason
Statement of Fact or Obligation
© 1999 ICL Pathway Ltd
COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 86 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
FUJ00001463
FUJ00001463
Ref:CR/ACS/007
Versi
Date:3 1/03/1999
Specification
Requirement ID 921
Criterion 4
Derivation Requirement
Criterion Description
Under circumstances where the facility has been activated
land the User is no longer able to cancel it, for whatever
reason, it shall be possible with appropriate authority:
(a) to complete User and Outlet balances; and
(b) to make the terminal available to another User.
ITest Condition (Acceptance of procedures
Method Document Inspection
References ‘Access Control and user Administration - Process and
Procedures Description ref.(71)
Phase Technical Testing
Requirement ID 922
Criterion 4
Derivation Requirement
ICriterion Description
The acoustic noise emission of any element of the Service
Infrastructure used in the provision of OPS shall not exceed
I60dB(A) measured at a distance of one metre.
ITest Condition
Acceptance of equipment specifications.
Method Document Inspection
References (Counter Hardware Design Specification- ref.(25)
Phase [Technical testing
Requirement ID 953
Criterion 2
Derivation Requirement
Criterion Description
OPS shall ensure data integrity, e.g. reports printed at the
back office whilst serving at the front office shall be
consistent with a clearly stated policy (to be approved by
IPOCL) of what front office data are included in the report
ITest Condition
‘Acceptance of functional constraints due to isolated node or]
lunavailable node.
Method Document Inspection
References EPOSS Functional Specification - ref.(66)
Phase [Technical Testing
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 87 of 1
obligations between ICL Pathway and the DSS and/or POCL
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance __Ref.CR/ACS/007
Specification Versi
Date:3 1/03/1999.
5.2 CRITERION FOR LATER ACCEPTANCE
Requirement ID 463
Criterion 6
Derivation Schedule G01 - 2.3.1.7
Criterion Description
[The CONTRACTOR shall provide OPS Equipment which
shall be required to demonstrate and market Office Platform
Services to Clients and prospective Clients. The
Equipment that is required shall be set out in marketing
plans which are agreed jointly between the POCL and the
ICONTRACTOR.
Reason Subject to A2A
Requirement ID 471
Criterion 4
Derivation Requirement
Criterion Description
Using TMS and OPS it shall be possible to broadcast short
messages to all or a subset of Outlets. As a guide, a
imessage length of approximately 2000 bytes is likely to be
lacceptable.
Reason Excluded from NR2
Requirement ID 471
Criterion 2
Derivation Requirement
Criterion Description
Short messages broadcast using TMS and OPS to all or a
isubset of outlets shall be brought to the attention of staff
orking at automated Counter Positions in the Outlet at the
earliest practical opportunity.
Reason Excluded from NR2
Requirement ID 471
Criterion 3
Derivation Requirement
Criterion Description
OPS shall enable staff at the Outlet to produce a hard copy
lof the short messages within the Outlet.
Reason Excluded from NR2
Requirement ID 471
Criterion 4
Derivation Requirement
Criterion Description
TMS and OPS shall have the capability to be developed to
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 88 of 1
obligations between ICL Pathway and the DSS and/or POCL
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance Ref:CR/ACS/007
Specification Version:2.0
Date:31/03/1999
lallow (subject to change control) staff working Outlets to
igain access to information held electronically on the
Service Infrastructure such as is currently published in
Counter News’ and the operations manuals provided
Ihereunder by Pathway
Reason Excluded from NR2
Requirement ID 473
Criterion 4
Derivation Requirement
Criterion Description
‘Any remote access to OPS shall be restricted to Users
specifically authorised by the AUTHORITIES and shall only
itake place via TMS.
Reason
INo remote User access to OPS is required at Release 2.
INon-testable.
Requirement ID 478
Criterion 2
Derivation Requirement
ICriterion Description
TMS shall provide links into Client systems operated on
behalf of Clients as required to support POCL
Reason
INo Client links required at Release 2.
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 89 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
FUJ00001463
FUJ00001463
Ref:CR/ACS/007
Version:2.0
Specification
Date:3 1/03/1999.
Requirement ID 478
(Criterion 9
Derivation Requirement
Criterion Description
ITMS shall provide a message switching capability, where a
imessage consists of electronic data which shall be passed
from one computer system to another (“switched”) with
minimal delay.
Reason Excluded from NR2
Requirement ID 478
Criterion 10
Derivation Requirement
{Criterion Description
It shall be possible to switch messages between any two
lattached computer systems (including without limitation
between elements of the Service Infrastructure in individual
(Outlets).
Reason Excluded from NR2
Requirement ID 478
Criterion 11
Derivation Requirement
ICriterion Description
\Where TMS is unable to deliver a message it shall notify
ithe originating computer system.
Reason Excluded from NR2
Requirement ID 538
Criterion 2
Derivation Requirement
\Criterion Description
ISMS shall permit Transactions to be processed using local
time and/or GMT, and all the relevant elements of the
Service Infrastructure shall be able to derive both local time
land GMT.
Reason
Not required at Release 2
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 90 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance Ref:
FUJ00001463
FUJ00001463
'R/ACS/007
Versi 0
Specification
Date:3 1/03/1999.
Requirement ID 556
Criterion 3
Derivation Requirement
Criterion Description
In any Outlet requiring the capability of reading from and
ithe writing to Schlumberger Smart Keys it shall be
lacceptable to use an external peripheral device, and to
share this device between Counter Positions where
ractical.
Reason
Support for Schlumberger Smart Keys is not required at
INR2.
Requirement ID i822
Criterion 1
Derivation Requirement
(Criterion Description
[The Service Infrastructure shall be designed such that it
ican interface to any POCL Inventory Management system,
land shall have sufficient capacity not to preclude such
interfacing.
Reason
Not required at NR2.
Requirement ID 827
Criterion 3
Derivation Requirement
Criterion Description
[The Services and the Service Infrastructure shall support
Isuch authorisations through access to external computer
systems.
Reason
INo authorisations to external computer systems required at
R2.
Requirement ID 831
Criterion 3
Derivation Requirement
{Criterion Description
Pathway shall support the interfaces between TIP / TMS
interface for authorisation data.
IReason
INo requirement for authorisation data at Release 2. Not
testable at Release 2.
© 1999 ICL Pathway Ltd
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 91 of 1
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
FUJ00001463
FUJ00001463
Ref:CR/ACS/007
Version:2.0
Specification
Date:3 1/03/1999.
Requirement ID i896
(Criterion 4
Derivation Requirement
{Criterion Description
[The POCL Service Infrastructure shall be able to support
electronic communications for access to User
\documentation. The feature shall not be essential for initial
limplementation, and its later implementation shall be
subject to the mutual agreement of POCL and the
ICONTRACTOR.
Reason
Excluded from NR2.
Requirement ID 952
{Criterion 4
Derivation Requirement
\Criterion Description
[The OPS shall support a reliable, secure means for the
transfer of encrypted data that may subsequently be used
ifor cryptographic applications
Reason
Final Key Management facilities excluded from NR2
Requirement ID (952
Criterion 2
Derivation Requirement
Criterion Description
In order to use the encrypted data, a key management
isystem shall be in place so the encrypted data can be
deciphered without risk of the cryptographic key being
lexposed.
Reason
Final Key Management facilities excluded from NR2
© 1999 ICL Pathway Ltd
Printed on: 24/01/01
Page 92 of 1
COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
ICL Pathway
POCL Infrastructure Acceptance
Specification
FUJ00001463
FUJ00001463
Ref:CR/ACS/007
Version:2.0
Date:3 1/03/1999
5.3
CRITERION SUMMARY
IReq. ID
\Criterion
Trial
Review
Later Acceptance.
463
463
463
463
463
NINININEN
463
Loa
465
65
66
466
466
67
NININININENEN
167
167
<
67
467
TP EPOPS =] 2] RS] =P ST] =] a] TSOP =
67
NINES
468
469
469
469
470
470
470
NININININENES
471
L71
BP ST=PopR] =I mo] Sp =p=
471
SISA
472
472
NININININENEN
aS
AVN
© 1999 ICL Pathway Ltd COMMERCIAL IN CONFIDEN
CONTRACT CONTROLLED
ICE
Printed on: 24/01/01
Page 93 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance Ref:CR/ACS/007
Specification Version:2.0
P Date:3 1/03/1999
73
173
73
174
174
74
74
v
v
v
74
174
74
174 9
ZPaApapay SI] oP et=faypay or
74 Tl
174 12
174 1B
74 14
174 15
74 16
174 17
174 18
74 19
175 I
75
75
75
76
176
176
176
176
L76
176
177
b77
78
1478
78
78
78
78 6
78 7 v
78 is
78 9 v
78 10 v
NINININININININESINININENININESENININENININENENINEN
BPR} =Pspops
NINEN
ap EP =PST=[ 3] =] STS] y=
NININEN
NININENENIN
© 1999 ICL Pathway Ltd COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 94 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL.
ICL Pathway
POCL Infrastructure Acceptance
Specification
Ref:CR/ACS/007
Version:2.0
Date:3 1/03/1999
FUJ00001463
FUJ00001463
478
11
v
#78
12
478
13
478
179
479
479
aS a
NININ
479
80
480
536
536
NINININININENIN
NININEN
S41
542
555
NINININININININENEN
BP ALEP RP] =I =I ST =P RP =I SR =T RT =P RP =pRy =I ay =
S58
S58
559
559
559
560
560
S61
S61
NM
NINININININININENINININENEN
[822
826
<
<
826
BT=TEPRT HPSS RSIS OTST ORT =
© 1999 ICL Pathway Ltd COMMERCIAL IN CONFIDENCE
CONTRACT CONTROLLED
Printed on: 24/01/01
Page 95 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance Ref:CR/ACS/007
Specification Version:2.0
P Date:3 1/03/1999
827
827
827
831
869
869
869
869
869
896
912
921
21
921
921
[922
952
[952
[953
953
[953
NEN
PS
<
NINININEN
NININEN
SN
© 1999 ICL Pathway Ltd COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 96 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL.
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance Ref:
Specification Versi
P Date:3 1/03/1999
'R/ACS/007
0
6. ACCEPTANCE INCIDENT SEVERITY
This section identifies the guidelines to be applied during the analysis of
Acceptance Incidents, in order to establish the severity of such Acceptance
Incidents.
6.1 HIGH SEVERITY INCIDENTS
Failure to meet an Acceptance Criterion which would have a substantive impact on
the service received by the Customer, e.g. failure to pay benefits to the right
person, at the right place, at the right time.
Failure to meet an Acceptance Criterion which would have a major impact on the
ability of the AUTHORITY or AUTHORITIES to perform their business, or where
there was a major impact on the resources of the AUTHORITY or AUTHORITIES
necessary to overcome that impact on their business, e.g. failure to support
accurate POCL accounting.
Failure to meet an Acceptance Criterion which would impact the security of the
service where there is no procedural workaround.
Consistent failure to meet Minimum Acceptable Thresholds for Service Levels, e.g.
where particular transactions do not meet the minimum Acceptable Threshold
under normal loading.
6.2 MEDIUM SEVERITY INCIDENTS
Failure to meet an Acceptance Criterion which is visible to the Customer and is
likely to give rise to an adverse public perception of the service, but does not
substantively impact the service received by the Customer, e.g. incorrect spelling
on a receipt.
Failure to meet an Acceptance Criterion which would have a medium impact on
the ability of the AUTHORITY or AUTHORITIES to perform their business, or
where there was a medium impact on the resources of the AUTHORITY or
AUTHORITIES necessary to overcome that impact on their business, e.g. non-
production of a weekly report, resulting in its manual transcription, which causes
additional resource or effort at every outlet of the average duration of one hour per
week per outlet.
Occasional failure to meet Minimum Acceptable Thresholds for Service Levels,
e.g. at peak loading, some transactions fail to meet Minimum Acceptable
Thresholds, but on average all transactions within the service do achieve Minimum
Acceptable Thresholds.
6.3 LOW SEVERITY INCIDENTS
Failure to meet an Acceptance Criterion that is neither visible to nor has
substantive impact on the service received by the Customer e.g. presentational,
style and other cosmetic faults that are only visible to the user.
© 1999 ICL Pathway Ltd COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 97 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL.
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance __Ref.CR/ACS/007
Specification Version:2.0
Date:3 1/03/1999
Failure to meet an Acceptance Criterion which would have a minor impact on the
ability of the AUTHORITY or AUTHORITIES to perform their business, or where
there was a minor impact on the resources of the AUTHORITY or AUTHORITIES
necessary to overcome that impact on their business, e.g. non-production of a
weekly report, resulting in its manual transcription, which causes additional
resource or effort at ten or fewer outlets of the average duration of one hour per
week per outlet.
Failure to meet an Acceptance Criterion which would impact the security of the
service but where the workaround is as secure as the original solution (i.e. the
only impact on risk is in ensuring that the workaround is performed, but where
procedures have been agreed and are in place).
© 1999 ICL Pathway Ltd COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 98 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL.
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance Ref:CR/ACS/007
Specification Version:2.0
P Date:3 1/03/1999
7. TESTDATA
The test data and the overall test environment used for the technical tests will be
specified in a set of Test Reports that will be referenced within the POCL
Infrastructure Closure Report.
© 1999 ICL Pathway Ltd COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 99 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL.
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance Ref:
Specification Versi
Date:3 1/03/1999.
'R/ACS/007
0
8. AUTHORITY RESPONSIBILITIES
This section describes the AUTHORITIES’ Responsibilities in relation to this
Acceptance Test. Particular Acceptance Tests may also require additional
participation and responsibility by the Authorities.
8.1 APPOINT TEST MANAGER
The AUTHORITIES shall nominate a Test Manager and other representatives to
review the tests prior to commencement of the test.
8.2. ACCEPTANCE INCIDENT REPORTS
The AUTHORITIES’ nominated representatives and Test Manager shall be diligent
in raising complete, accurate and timely Acceptance Incident Reports as set out
within this Acceptance Test specification.
8.3. ACCEPTANCE INCIDENT ANALYSIS REPORTS
The AUTHORITIES’ Test Manager shall be diligent in returning signed
Acceptance Incident Analysis Reports with their decision (e.g. Accept, Reject,
Discuss) normally within five working days, or when urgency is requested by
Pathway, within two working days of receipt from Pathway. A copy of all
correspondence will be faxed to reduce delay.
8.4 ATTENDANCE AT TRIALS AND REVIEWS
The AUTHORITIES’ nominated representatives shall attend Acceptance Test
Trials and Reviews including repeat Tests at times and locations specified and
with reasonable advance notice by Pathway.
8.5 MANAGEMENT AND CO-ORDINATION
The AUTHORITIES’ nominated Test Manager shall be the single point of
communication and co-ordination with Pathway’s nominated Test Manager for all
matters concerning this Acceptance Test from its initial planning through to
Acceptance.
8.6 PROGRESS REVIEWS
Unless otherwise waived by both parties, Pathway’s Test Manager and the
AUTHORITIES’ Test Manager shall meet each week to review the progress and
actions of both parties until Acceptance of the Acceptance Test is achieved. The
time and location of review meetings will be scheduled with at least one week
advance notice by Pathway.
9. CONTRACTOR RESPONSIBILITIES
Upon receipt of a signed Acceptance Incident Analysis Report from the Authority,
where correction is required to be re-tested within the same phase of Acceptance
© 1999 ICL Pathway Ltd COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 100 of 1
Nothing contained herein shall be deemed or construed as affecting existing contractual obligations or creating new contractual
obligations between ICL Pathway and the DSS and/or POCL.
FUJ00001463
FUJ00001463
ICL Pathway POCL Infrastructure Acceptance Ref:CR/ACS/007
Specification Version:2.0
P Date:3 1/03/1999
Test, Pathway will return the amended component(s), on average, within 4 days.
This will include re-testing necessary as per the agreed test strategies.
10. ACCEPTANCE TRIAL TEST CONDITIONS
Not required for this Acceptance Specification since the Test Conditions are
individually included in each Criterion.
© 1999 ICL Pathway Ltd COMMERCIAL IN CONFIDENCE Printed on: 24/01/01
CONTRACT CONTROLLED Page 101 of 1