FUJ00058349 - Live Trial Wales South West Weekly Progress Report (version 1.0).

Evidence on official site

FUJ00058349

FUJ00058349
ICL Pathway Live Trial South Wales South West v Ref: MUREPIO38
‘ersion:

Weekly Progress Report Date: 08/06/98

Document Title: Live Trial South Wales South West Weekly Progress
Report

Document Type: Report
Issue: 1
Abstract: This weekly report summarises the progress of the

implementation of the Live Trial post offices in the
SWSW & Midlands regions.

Status: Issued

Distribution: ICL Pathway POCL
Bob McDermott Paul Kirk
Barry Hancill Dawn Green
Dave Howells Clive Winward
Claire Roberts Fiona Anderson
Steve Melvin
Reg Barton
Jacqui Haxton
Mark Fisk
Steve Burgess
Billy Herd
Library

Author: Paul Underwood

Comments to: Paul Underwood

Comments by: NA

© 1998 ICL Pathway Ltd

COMMERCIAL IN CONFIDENCE Page 0 of 6
FUJ00058349

FUJ00058349
ICL Pathway Live Trial South Wales South West vi Ref: MUREPIO38
‘ersion:
Weekly Progress Report Date: 08/06/98
0 Document control
0.1 Document history
Version Date Reason
1.0 08/06/98 First report
0.2 Approval authorities
Name Position Signature Date
Paul Underwood Implementation 09/06/98
Programme Manager G RO Hl
0.3 Associated documents
Reference Vers Date Title Source
0.4 Abbreviations

COMMERCIAL IN CONFIDENCE

Page 1 of 6
FUJ00058349

FUJ00058349
ICL Pathway Live Trial South Wales South West vi Ref: MUREPIO38
‘ersion:
Weekly Progress Report Date: 08/06/98
0.5 Changes in this version
First Issue.
0.6 Table of content
A INTRODUCTION... eee cceeeceeeceeeeeeeeeeseeeeeeeeecececseeeeeceseeeeeeeeeececeeeeeeeseeeneneeee 4
2 SCOPE.
3 PROGRESS FOR Monday 1 June to Friday 5" Jun :
4 PLANNED FOR Monday 8" June to Friday 12" JUne@.........ceeceeeeeeeees 5
5 NEW SUNDRIES... ececceeecescseseseseeeeecscsesesecacsesesenevecscecsesecacseeeseneeeeseaeseees 6
6 OUTSTANDING SUNDRIES. ...0......0...:ccce esses cesesseseeseseeseseseeseeieeeeneeeeneeeees 6
AA NSSS) 0) ahs Sa 6

COMMERCIAL IN CONFIDENCE Page 2 of 6
ICL Pathway Live Trial South Wales South West
Weekly Progress Report

Ref:
Version:
Date:

FUJ00058349
FUJ00058349

IM/REP/036
1.0
08/06/98

1 INTRODUCTION

This weekly report summarises the progress of the implementation of the
Horizon Live Trial into post offices in the South Wales South West region.
The purpose of this report is to provide the POCL region with a summary
of the progress to date against the planned activity in this region; a
summary of the planned activities in the following week; outstanding

sundry activities; and general issues that may arise.

2 SCOPE

This report only covers the implementation activities for this phase within
the region and is not intended to include any reporting requirements for

outlets in steady state within the region.

3 PROGRESS FOR Monday 1* June to Friday 5" June

(Note; Actuals/planned figures are for up to close of play Friday)

Events

Data Lines Installed
Staff Trained
Equipment Installed

ACTIVITY PLANNED I ACTUAL
MIB Events 0 0
Schedule Site Surveys 0 0
Site Surveys 33 32!
Re-Surveys 0
Site Preparations 0
User Awareness ie}

‘ One office suspended as a result of the Site Survey event.

COMMERCIAL IN CONFIDENCE

Page 3 of 6
ICL Pathway Live Trial South Wales South West
Weekly Progress Report

Ref:
Version:
Date:

IM/REP/036
1.0
08/06/98

FUJ00058349
FUJ00058349

CUMMULATIVE TO DATE

ACTIVITY PLANNED I ACTUAL
MIB Events 3 3
Schedule Site Surveys 70° 644
Site Surveys 48 475
Re-Surveys
Site Preparations
User Awareness
Events
Data Lines Installed
Staff Trained
Equipment Installed 0

4 PLANNED FOR Monday 8" June to Friday 12" June

Staff Trained
Equipment Installed

ACTIVITY PLANNED

MIB Events 0
Schedule Site Surveys 0
Site Surveys 9
Re-Surveys 0
Site Preparations 0
User Awareness 0
Events

Data Lines Installed 0

? Of the 75 offices, 5 offices attending earlier MIB events. Of the remaining 70 offices, 7
offices did not attend a MIB event.

3 Five offices surveyed during previous programme.

4 Six offices became suspended as a result of the Survey call event.

° One office became suspended as a result of the Site Survey event.

COMMERCIAL IN CONFIDENCE

Page 4 of 6
FUJ00058349

FUJ00058349
ICL Pathway Live Trial South Wales South West Ref: IM/REP/036
Version: 1.0
Weekly Progress Report Date: 08/06/98
5 NEW SUNDRIES
OUTLET FAD I DESCRIPTION STATUS
Tredworth 233523 I Change of Postmaster planned. I Removed from programme.
Removed following survey call
Hewlett Road 345523 I Planned refurbishment. Removed from programme
Removed following survey call.
Paulton 272511 Planned refurbishment. Removed from programme
Removed following survey call.
Montpellier 154523 I Planned refurbishment. Removed from programme
Removed following survey call.
Longlevens 199523 I Planned refurbishment. Removed from programme
Removed following survey call.
Kingswood 011511 I Planned office closure. Removed from programme
Removed following survey call.
Lower Barton 200523 I Office undergoing Removed from programme
Street refurbishment, discovered
upon arrival of surveyor.
Removed following site survey.
6 OUTSTANDING SUNDRIES
First issue.
7 ISSUES

« Counter number discrepancies. A very high percentage of offices have
incorrect counter numbers recorded in reference data.

« Two offices have refused to sign survey packs although compliant
solutions have been found. Issue being progressed by POCL.

e Issue has been escalated from WTplc regarding task force members
becoming involved in surveyor activities. Issue has been escalated into
POCL and situation is being monitored by WTplc.

e A letter has been written to POCL, WTplc and copied to other Pathway
staff to clarify the definition of counter numbers and back office system +
how such information should be presented to ICL Pathway.

e ISD did not identify the offices that had planned refurbishment or other
events that have caused 7 offices to be removed from the live trial
programme.

e Processes surrounding out-of-hours site preparation authorisation and
Postmasters refusing to sign compliant solutions are being progressed
between ICL Pathway and POCL.

COMMERCIAL IN CONFIDENCE Page 5 of 6