FUJ00094305 - HNG Post Office Highlight Report, 03/03/2010

Evidence on official site

FUJ00094305

FUJ00094305
HNG — Post Office Highlight Report (for Joint Release Board) €&
Project/Release HNG Reporting Period: To 3° March 2010
Stage: Deployment Programme Manager: Mark Burley / Will Russell

1. Tracking Summary

Measurable

Comments

TIME

The Horizon Online pilot has been extended and is now operational
in 144 live branches.

However due to a number of live issues experienced across the
network, further migrations have been temporarily suspended.

The intention is to re-start the pilot w/c 8" March, subject to the
successful implementation of fixes to improve the service
experienced by branches, and evidence of improvements in the level
of support provided, in particular by the HSD.

An action plan has been developed to track progress and success
against these items. However it is essential that meaningful data can
be supplied to show that improvements have been made before the
continuation of the pilot can be agreed. This data has started to
come through but needs further refinement before it can be acted on.

In addition, serious live issues were encountered today (3° March),
and these have further undermined confidence in the readiness of
the solution. This has also caused further negative feedback from
the Network and NFSP, and we are in danger of losing any
remaining goodwill from the frontline.

As a result of the above, the end date of rollout has already gone
back into June, but given the current level of ongoing problems this
may be an optimistic position.

A full discussion is therefore required at the Board of how the
programme can be brought back on track — or what assurance
Fujitsu can provide that further slippage will be minimised. At
present, Post Office has little confidence that the solution is stable, or
that the problems highlighted are under control.

Reverted to Amber (from Green) due to likely over-run of programme
and additional costs incurred.

QUALITY

operational
issues

e User opinion. This has deteriorated significantly since the last
meeting, and we are in danger of losing remaining goodwill. This
is down to the number of live issues experienced, some concerns
around transactions, and continued changes to migration dates.

e Screen Freezes, Re-boots and Recoveries. The rate of screen
freezes and recoveries has been significantly greater than
expected and needs to reduce rapidly in order to extend rollout.
This is under urgent investigation and action by Fujitsu

* System Outages. There have been full system outages on 2
days in the last 2 weeks; this is unsustainable and losing the
goodwill of the Network

e Number of calls to, and Level of support from HSD. The rate
of calls from Horizon Online branches has been running at

HNG Post Office Highlight Report 100303.doc Page 1 of 5

HNG — Post Office Highlight Report (for Joint Release Board) €&

FUJ00094305
FUJ00094305

has been poor in some cases.

peripheral configurations have been encountered causing
new examples of this since last report)

arising from Pilot to enable HVP to progress further.
« HNG Volume Testing. Phase 1 of Volume testing has

Pilot commences.

around 10 times that from Horizon, and level of support received

* Counter configurations. A number of unexpected counter /

implementation issues and failures to migrate branches. These
need to be resolved to support higher rollout volumes (nb — no

e Live System Test (LST): Work is now focused on testing issues
completed. A number of key areas need resolution before the

system can be confirmed as supportable at higher volumes,
although this is expected to be achieved before High Volume

Key ¢ Over 50% of the network now has Branch Router installed

Achievements I ¢ POL-FS is on track to migrate this coming weekend (6/7 March) following

very positive progress through pre live proving and DR testing

2.1 Issues and risks / Items for Discussion

NEW ITEMS FOR DISCUSSION :

« Management of live issues; responsiveness and reporting.

e Provision of management information to assess pilot issues and progress.

boots
e Progress against other areas of “action plan” to re-start pilot
« Assessment of BRDB issue arising on 3 March
e Confirm position on Volume Testing ahead of High Volume Pilot
e SECURITY - position against Acceptance Incidents
e SECURITY - progress of PCI audit
e Progress on erroneous “zeros” in client files

« POL-FS - final confirmation of position before migration weekend

EXISTING ITEMS FOR DISCUSSION:

« Progress on assessment of high incidence of Screen Freezes, Recoveries and Re-

HNG Post Office Highlight Report 100303.doc Page 2 of 5
FUJ00094305
FUJ00094305

HNG — Post Office Highlight Report (for Joint Release Board) €&

¢ Contention for SV+I rig between HNG release 1 and release 2 : update on position
¢ Validation of performance during pilot : update on position
e Pre-migration counter packages — Update on overall position.

¢ Release approach and configuration management going forward. This needs greater
emphasis and visibility.

Other key items are covered within the “Joint Risk Log”.

3 Milestone Tracking Summary

The baselined dates below are the latest contractually agreed set at plan v60 a40 (as
referred to from CCN1246).

The pre-Christmas changes to accommodate the EDS testing and additional code
releases (V80.a20) are indicated in green., with current forecast below this — if different.

Unique ID Milestone: Owner I Baseline Forecast! ‘Comments
Delivery Actual
Date: Delivery
Date:
HNGX-D-069_II POL Sample Use Case POL 25/08/2006 I 25/08/2006 I Complete
Available for U!
HINGX-D-073 II Receipt of POL general POL 25/08/2006 I 25/08/2006 I Complete
requirements for the UI
HNGX-D-030__I] Service Barrels/Use Cases for__I POL 30/08/2006 I 02/08/2006 I Complete
App 4 available
HINGX-D-067 II POL Joint Test Resourcing JOINT 0344/2006 _I 25/01/2007 _I Complete.
Profile Agreed 31/01/2007
HNGX-D-071 II Receipt of POL Business Rules I POL 75/09/2006 I 16/09/2006 _I Complete
for Postal Services
HNGX-D-07éa II Confirm all clients plan tomove I POL 29/09/2006 I 29/09/2006 I Complete
to EDG, EDG GO/NO GO.
HINGX-D-038 II Service Barrels Gateway 4 POL 29/09/2006 I 29/09/2006 I Complete
Completed
FINGX-D-004b II Service Barrels Gateway 6 POL 30/10/2006 I 30/10/2006 _I Complete
Completed.
HINGX-D-057 I Order Router (Initial Order) POL 07/42/2006 I 20/04/2007 I Complete
01/03/2007 Confirmation provided to
Fujitsu on 20/04/07
HNGX-D-063 II POL Provide Reference Data to I POL 29/04/2007 07101708 I Complete (final drop provided
support INT4 System Test 02/04/2007 and agreed)
HNGX-D-056_ II Purchase Point 1: Purchase of I POL 09/03/2007 I 20/04/2007 I Complete
the branch router.
HNGX-D-003_II Wire frame & details ofthe UI__I POL 29/03/2007 I 29/03/2007 _I Complete
including house style, look & ‘Sample Screen shots have
feel been supplied
HNGX-D-064 II POL Provide Reference Data to I POL 7e/0e/2007 I 05/05/2008 I Complete
support SV&HINTS INT7 System
Test in IRE
HNGX-D-047 II System Test Report Issued POL 28/10/2007 I 12/09/2008 I Complete. Initial Reports
NF) (INT7) produced, but INT7 now
merged with INT8, INT9 and
INT10 with formal report
covered under HNGX-D-074
HNGX-D-076 II Router & Gateway solution Fujitsu 29/08/2008 I 29/08/2008 I Complete
developed (NB This excludes
development for the 2

HNG Post Office Highlight Report 100303.doc Page 3 of 5
FUJ00094305

FUJ00094305
HNG — Post Office Highlight Report (for Joint Release Board) €&
Unique ID Milestone: Owner Baseline Forecast! Comments
Delivery Actual
Date: Delivery
Date:
WWAN provider)
HNGX-D-077 Network Rebuild Fujitsu 29/08/2008 29/08/2008 Complete
HNGX-D-074 Formal System Test Report for POL 12/09/2008 12/09/2008 Complete
Cycles 10-12 issued
HNGX-D-078 Application development Fujitsu 27/10/2008 27/10/2008 Complete
completed
HNGX-D-079 II System test completed Fujitsu 27/10/2008 72/12/2008 I Complete
HNGX-D-080 SV4&I testing commenced on Fujitsu 03/1 1/2008 26/11/2008 Complete
HNG
HNGX-D-075, Final Formal System Test POL 14/11/2008 07/01/2009 Complete — Document out for
Report issued review
HNGX-D-072b II Provide list of Pilot branches for I POL 31/10/2008 31/10/2008 Complete
Router rollout
HNGX-D-016b I} Confirm all clients have POL 04/02/2008 16/10/2008 Complete
successfully moved to EDG 28/07/2008
16/01/2009
HNG-X-D-089 II V&I Testing Commenced Fujitsu 34/42/2007 16/03/2009" “Complete
18/12/2008 However it should be noted
that this is now only Integrity
Testing.
HNGX-D-046 Train the Trainers Commences POL 01/02/2008 31/01/2010 'V80 a20 forecast
26/01/2009 18/11/2009 Current forecast
Complete
HNGX-D-065, POL Provide Reference Datato I POL 15/02/2008 01/10/2009 V80 date in Bold
‘support Pilot 02/02/2009 22/10/2009 80 a20 forecast
Complete. Data is ready for
LRODP after DC migration
HNGX-D-081 Data centre migration prep Fujitsu 09/02/2009 05/10/2009 Allows us to proceed with the
complete 26/40/2009 migration of the Data Centres
30/10/2009 V80 date in Bold
80 a20 forecast
COMPLETE
HNGX-D-052 Provide access to all Pilot POL 34401/2008 46/02/2009" Notification that Access
Branches for Router installation 16/02/2009 26/05/2009* has been granted to FS has

been given. Propose
closure of this milestone.
HINGX-D-082 II Weekends B&C complete Fujitsu 23/02/2008 I 11/10/2009 _I Critical applications moved to

01/11/2009 I Belfast and new Data
Centres operational

80 date in Bold
V80 a20 forecast
COMPLETE
HNGX-D-083 II Router pilot commenced JOINT 16/02/2009 02/11/2009. V80 a20 forecast
20/11/2009 _I Complete
HNGX-D-058 II HNGX Pilot in Model Office JOINT te is 23/11/2009 V80 a20 forecast
commences 16/03/2009 47/42/2009 I Complete
24/12/2009
HNGX-D-090 II HNGX Pilot in Live Office JOINT 14:04/2008 07/12/2009 V80 a20 forecast
‘Commences 30/03/2009 13/01/2010 Complete
HNGX-D-084 II POL FS migrated to new Data Fujitsu 15/05/2009 12/12/2009 V80 a20 forecast
Centres 47101/2010

28/02/2040 I Current forecast — * moved to
07/03/2010" avoid financial period end
FINGX-D-085 II Full roll out commences JOINT 22/06/2008 I 15/02/2010 I V80 220 forecast
25/02/2010 Current published forecast
29/03/2010 I Working plan date (not

released)
HNGX-D-054 II HNG-X Application Rolloutis I JOINT (0170472008 _I~ 21/04/2010 _I V80 a20 forecast
completed 18/09/2009 I 30/04/2010 I Current published forecast
07/06/2010 I Working plan date (not
released)
HNGX-D-053 _II Enable FS to access Back POL (0770472008 _I~ 27/07/2009 I CCN1245 revised contract
Olfice Printers for Network TBA states XP rollout no longer
Conneetivity included
HNGX-D-059__I[ X5—Counter-XP-Rollout FS ‘O770/2008_I~ 05/04/2030 _I CCN1245 — revised contract
completes TBA states XP rollout no longer
included

HNG Post Office Highlight Report 100303.doc Page 4 of 5
HNG - Post Office Highlight Report (for Joint Release Board)

HNG Post Office Highlight Report 100303.doc

Page 5 of 5