FUJ00119633 - Fujitsu, Executive Steering Committee, HNGX update

Evidence on official site

FUJ00119633
FUJ00119633

Executive Steering Committee
HNGX Update

31° March 10

Copyright 2009 Fujitsu Services Limited
ie)

FUJITSU

FU.

Agreed Baselines FUSITSU

 =Schedule
® V100.A00 draft
* (The plan that will be reported against from now onwards)
% V80.A00 check-pointed with the client

Requirements
®@ version 1.42

@ Testing Baselines
= SVI- 01.08.03
= LST — 01.08.03 + hot fixes

Copyright 2009 Fujitsu Services Limited

1

FUJ00119633
1J00119633
FUJ00119633
FUJ00119633

Red

0)

Major issue impacting timescales, cost or risk a
Major issue but with actions agreed to resolveFUJITSU

aoproved Budget
Reptcement Deployment Manager required

Resourcing Rezowrengot cepoymen and sericeteams, REPWCEMEN.Depiayment Menagert0e I ¥> ay 49
under review. Additional PCO being recruited. ”
Ndiom Volume Pit re-start reoate, ign I DagrOse vesigaons cntnaing, Oracle Pach

sched Notre stated 210/10, bt suspended

cule inplemertatontolve o address rel BranchI 05 Apr 10
2503/0. stebsaloncfivesewensine I Balemeniatniro veto adcess ral Br
highest prion. made in live 28/03/10.

Reqarenetie

achiece

apps Development I amber I amber [seven Oaty provtaatonaf new eeves trom” [Ou eviews of rtcalPeakstines soAgr 10
livetest. High volume of Hot fixes. lelivereditestec
volte cyl 2 competed 5109/10, Cycle 3. I maven lantor sa of Cycle 3 tbe onfmed
Tequrng Vong. Testereqeto prove [/Reguveieseedback or Acceptance Gateway [06 Apr 10
resins for ltt promod ean sched
Red for HNG Migrations due to High Volume

Maran Prot beng stopenied Branch Rou Revised sche fr High Volume Pot & Rott I 2 pr 49

nastructire amber IScheltle” Says fo Vedstne Backes dese Resove Vodafone netnarkiosuesandeompiete Ir. npr 49
Abe nt on cea pa 9

von y going ontorng in place ore sue. Acton [conere to eview we sandce ebay + PPO lop ag

[Service Transition Armbet plan required to priortise incidents from live sites. I through HVP. }08 Apr 10

coareat

ers

Copyright 2009 Fujitsu Services Limited

2
FUJ00119633

FUJ00119633
Exec Summary FUfitsu
@ Medium Volume pilot re-started 18/03/10 after 2 weeks of improved stability
of solution. 400 branches trading on HNG-X by 23/03/10.
® Approval given to proceed to High Volume Pilot 24/03/10
@ High Volume Pilot Started 25/03/10 (212 additional branches migrated)
@ 622 Branches (1,754 counters) on HNG-X, including 8 Model offices
@ Live service issues last week:-
® 25/03/10 following application of Oracle patches resulted in all 400 branches not
trading for 4 hours.
® Branch database hanging incidents occurred 26/03/10, 27/03/10 & 29/03/10
# Intensive monitoring in place
* Oracle Patch Set being progressed through testing, targeted for implementation
into Live 02/04/10
® Investigations into other potential causes ongoing
@ High Volume Pilot migrations suspended until live service issue resolved
@ Full rollout start on 12/04/10 delayed — revised date tbc
@ 9,519 Branch Router installations completed (83% of estate).
®@ Milestones — 32 completed on schedule, 10 completed ahead of schedule,
64 completed behind schedule

Copyright 2009 Fujitsu Services Limited
3
FUJ00119633

FUJ00119633

Risks & Issues Summary

@ Key Risks

® Significant live issues (Horizon or
HNGX) may result in the rollout
being delayed again

® Beat rate during full rollout cannot
be sustained, leading to delays

= Slip to programme puts exit from
Wigan/Bootle Datacentres by
31/07/10 at risk

f@ Key Issues

FUfitsu

Live issues affecting all HNG-X
branches seriously impacting
customer confidence & attracting
Press Coverage. High volume pilot
postponed 26/03/10.

High Volume of Hot fixes in addition
to maintenance fixes leading to
testing bottleneck & delays in
implementation.

4 High Severity Acceptance
Incidents that need to be reduced
to Medium Severity to enable
rollout to proceed (AG4)

+ Live issues

+ Risk Management

« Patch/Vulnerability Management
+ 2 Factor Authentication

Actions in place to reduce this to 2
Medium Severity Incidents by AG4

Copyright 2009 Fujitsu Services Limited

4
FUJ00119633
FUJ00119633

Cy

Client Ref

THNG-3R0008

2HNG-»R0006

3 HNG-»R0008

4HNGxRO018

SHNG-aR0020

6B HNG-aRO028

THNG-aR0040

BHNG-aR0042

SHNG-aR0050

AO HING 90051

41 HNG 20058

12 HNG-xR0067

13HNG-»RO071

14 HNG-2R0073

Key Risks

‘Owner

‘Jobson Pete

Butts Geott

Richareson

Debbie 08

Butts Geott

Butts Geott

Butts Geott

Butts Geott

Butts Geott

Butts Geott

Butts Geott

Cochrane Vince

Butts Geott

‘Allen Graham
«BRAO1)
Dosington Chris

Unites System Architecture Requirements celay Acceptance or roll out (for non - CCD Arch Does) (POL
‘owner IT)
We may not be compliant from a Security perspective before we go into pilot (POL owner TGilan Trundel}

During Post Live VOL testing, the solution ces not operate in accordance with the required performance
targets (Le. Transactions per second BALIOSR) (POL owner IT)
HNG-X Rollout fas in Pit leading to PiltRoliout stop (POL owner WR}

‘Customer will be unable to meet rliout rate (.e, POL overwhelmes by rate of rollout) (POL. owner WR)

CConiractuel acceptance documentation is not formalise leaving to late changes and failure to pass the
acceptance citeria (POL owner Phil Norton)

POL. may halt root cue to unforeseen financial difference in pre- ane post- migration reports. (POL. owner
wR)

“The volume of suppor calls cannot be handled by the support teams anc infrastructure - Horizon Day! +
‘ongoing support requited during migration (POL owner WR)

Live Usage wil icenity volume relates performance issues that were not encountered during VOL. testing (POL
‘owner WR)

‘SYSMAN cistribution cannot sustain the currently proposed beat rate of 275 branches per right (POL owner
wR)

Following migration of Data Centre critical elements of Horizon fall. (POL Owner WR)

RDB Hycra Vol Issues are not resolved sufcienl to support the Max rollout beat rate of 275 per right (POL,
‘ower ITWR)
Recuited fxes cannot be delivers in time fr fst Maintenance Release (ehead of large volume pat)

Further unexpected ciflerences in counter configurations will cause rollout to be extended. POL owner B Evans

Probability

10%

20%

15%

10%

30%

10%

4 On
2 006
4 02
8 028
4 one
4 one
4 one
2 048
4 one
4 one
4 one
4 one
4 02
4 one

FUSITSU

Copyright 2009 Fujitsu Services Limited

5
FUJ00119633

Delay to start of HNG-X Rollout

® Branch Router implementation on target to complete to 99.6% of estate by
original baseline date (13/04/10), excluding Satellite branches

FUJ00119633
1 Fo)

Progress Against Plan FUJITSU
® Original Plan (Baselined June 2009) Key Milestones:-

® Branch Router Rollout complete - 13/04/10

® HNG-X Branch Migration Rollout complete - 22/04/10
@ Delays caused by:-

* Data Centre Migration Slip - 3 weeks

# Branch Router solution delays - 1 week

® Delay to start of Medium Volume Pilot - 1 week

® Delay to start of High Volume Pilot - 2 weeks

i

2 weeks (estimated)

Copyright 2009 Fujitsu Services Limited

6
Copyright 2009 Fujitsu Services Limited

7

FUJ00119633
FUJ00119633

Milestone

Key Milestones

Team

Planned!

Forecast

FUSITSU

Comment

Counter Roll Out Commence

Fig

09/11/09)

1204/10

[Subject to Satisfactory Completion of High Volume Pilot and Volume
[Testing (Vol Test Cycles 1 & 2 are complete, some key tacts need te be

ied in Cycle 3}, Will be delayed due to live issues. Start date sill
be reviewed with POL on 06/04/10 after remedial steps completed

Branch Router Rol Out Complete

nig

1511708)

EET)

[iain Branch router rollout currently forecast to complete by 1370410 as
planned. £3 remote branches requiring satellite comms enabled router
will not receive Branch Router until May 2010 due te delays in
Idavalopmont caused by resource contantion. A revised plan has now
been agrsed and work is progressing cn schadule to make the solution
available from early May 2010

IR,

AG

Counter Rail Gut Complete

30GIAD

TOTO

Exchides 4% tail Start of rollout on 12/04/10 will slip due to delays in
completion of High Volume Pilot. Programme Team looking at
increasing beat rate of branch migrations. Revised completion date to be
[confirmed

Hilestones Closed since fast report

FUJ00119633
FUJ00119633

Development

Copyright 2009 Fujitsu Services Limited
8

Copyright 2009 Fujitsu Services Limited

9

FUJ00119633
FUJ00119633

Slip Chart

FUJ00119633
FUJ00119633

alysis FUSITSU

Preity

Rasingre  Vitigh (A) Heeb) Medic) tow (2)
SveE

Rv

vel

ave

ot

oe

ar
cTricar
nb

iY ive
vou
POLES

plolwlos]_lg)elgly]o
Bw] fim Ir frofof talc Lig foo] [is

SGbset OF total with POL
‘SUbSRE OF total net PEAKS

Copyright 2009 Fujitsu Services Limited
10
FUJ00119633
FUJ00119633

Defect Trend FUJITSU

osoVerall defect trend

kas ep haaat]

—feiting st
2620 / al
1500

&

a

7
B 8 8 82 8 8 2828 ¢€8 822 28
§ 3 s BS 8 8 & @ € & S$ BB

Copyright 2009 Fujitsu Services Limited
11
FUJ00119633
FUJ00119633

FUSITSU

I Commen

Customer Status
eX eee

Time

Cost Amber

Quality

The Horizon Online application is running in 608
branches.

Medium Volume Pilot halted for 2 weeks following Branch
database issues in live 03/03/10 — 05/03/10. Restarted
on 18/03/10, and High Volume Pilot started 25/03/10 but
migrations suspended for 26/03/10 after live outages.
The final rollout profile continues to be assessed by the
Programme and Service teams and remains subject to
approval by the Internal and Joint Release Authorisation
Boards.

Reverted to Amber (from Green) due to likely over-run of
programme and additional costs incurred.

National Federation of Subpostmasters complaining over
outages on 26/03/10. Loss of confidence after last 2
weeks had shown improvement in live stability.

Copyright 2009 Fujitsu Services Limited

12
FUJ00119633
FUJ00119633

Risk Profile FUSITSU

e000

ea,000 +
:

£7,000 +

£6,000

e000

£k

£4,000 Test & MorasonI

3,000

£2,000

£1,000

‘Sep-09 Ape-10
fomea a7 ae
jane waw [ever [ei [ee I os I cor [ean [ooo [ew [ee ew fen fen
[ertesta mezaton [=n 20 Iea.00 [enor [anos [ez.a0 [eneza] ever [eas [exes [exea [ere I coo I axe

Copyright 2009 Fujitsu Services Limited
13
FUJ00119633
FUJ00119633

FUSITSU

PMO)

Test 17.0 174 (0.0)
Rigs & Networks 44 44 (0.0)
IDC Migration & Rollout 35 3.3 0.2
Contingency 05 0.5 0.0
[Sub-Total 74.2 741 0.1

Others (BOM, Expenses,

Depreciation) 18.0 18.1 (0.1)
TOTAL 92.2 92.2 0.0

Copyright 2009 Fujitsu Services Limited
14

Finance example from HNGX.
FUJ00119633
FUJ00119633

Finance - Cost Curve FUSITSU

=o Gureni forecast

~ Baseline (03,

92,000

87,000

£k

82,000

77,000

72,000

‘Apr-09 May-09 Jun-09 JuhOO Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Ner-10 Apr-10 May-10 Jun-10 Ju-10 Aug-10 Sep-10

Summary

+Project commenced July 2006 trend above commences in April 2009

Increased costs in July relate to Hardware spend which was phased across July and August in the
Baseline

Total Project costs remain on target

Copyright 2009 Fujitsu Services Limited
15

For Fujitsu Eyes Only

Copyright 2009 Fujitsu Services Limited
15

Finance details. Can be a graph (EV for example) or a table, but actual vs baseline must be shown.
FUJ00119633
FUJ00119633

Resource Profile

FUSITSU

arto Aerio Way-10 iano wrt
Deveoprent 45 00 00 00 00
rirastucture 30 oo 00 20 00
craton 27 162 733 39 38
Gr) 25 25 00 00 oo
Progranme 00 30 00 00 00
Test 92 35 00 00 00
Period

[a Development
lm htrastructixeI
Jangraton

la pmo

I Programme:
latest

Copyright 2009 Fujitsu Services Limited

16
FUJ00119633
FUJ00119633

Commercial Milestones

FUSITSU

Acceptance gateway

AG1 : Readiness
for Router Roll-
Out

01/10/09

22/10/09

Acceptance

B6.3

AG2 :Readiness
for Data Centre
Migration

18/09/09

22/10/09

Acceptance

B6.3

AG3 : Readiness
for Live Pilot

22/10/09

14/12/09

Acceptance

B6.3

AG4 : Readiness
for Branch
Migratio

Acceptance

B6.3

Gateway 5 was
cancelled

Acceptance

B6.3

AG6 : End of Live
Monitoring

05/02/10

28/04/10

08/04/10

02/07/10

™ AG 5 formerly covered update of the Operating Systems

Copyright 2009 Fujitsu Services Limited
17

Milestone RAG status. Should include value.
FUJ00119633
FUJ00119633

. [3]
Commercial & Governance FUJITSU
® Client:
® Joint Steering Board - held fortnightly with Client Programme Manager and Team
Interim Steering Board - held fortnightly with Client Programme Manager and Team
Test Governance Board — held weekly with Client Test Manager & Programme Manager

Release Approval Board — held prior to major release deployment with Client Programme
Manager, Client Service Manager, Head of IS&S

% Acceptance Gateway — held prior to major phase completion Client Programme Manager,
Client Service Manager, Head of IS&S

@ Internal:
= ‘Morning Prayers'- held daily with Programme Management Team
# Amber Alert call - held weekly with Alert Team

% Monthly Programme Board - held with Account Director, Core Resource Units, Delivery
Assurance, HOP & PSD Ops Director

® Executive Review - held quarterly with CEO, HOP, Account Director, Finance Director and
Corp 1st Senior VP & President Global Business Group, Fujitsu Ltd

Copyright 2009 Fujitsu Services Limited
18

Narrative of Governance in place - meetings and reports. Not for Japan pack.
FUJ00119633
FUJ00119633

(oe)
FUJITSU

Copyright 2009 Fujitsu Services Limited
19