ICL Pathway
FUJ00119673
FUJ00119673
Training and User Awareness Ref: BP/TRN/001
: Version: 79
Baseline Document Date: 1 )99
Document Title:
Document Type:
Training and User Awareness Baseline Document
Reference Document
Abstract: This document provides a description of the ICL Pathway
Training and User Awareness programme to be delivered to an
agreed number of POCL staff and agents. This document forms
the strategy for an agreed approach between ICL Pathway and
POCL.
Status: AWAITING APPROVAL
Distribution: Ann Cocker POCL
Trevor Rollason POCL
Douglas Craik POCL
Bruce McNiven POCL General Mgr of Horizon
Implementation Team
Mike Coombs ICL Pathway
Steve Reed ICL Pathway
Terry Austin ICL Pathway
Liam Foley ICL Pathway
Barrie Davies ICL Pathway
Dean Felix ICL Pathway
John Dicks ICL Pathway
Andy Barkham ICL Pathway
Steve Muchow ICL Pathway
Bob McDermott ICL Pathway
Mark Fisk ICL Pathway
Allen Prescott ICL Pathway
Paul Underwood ICL Pathway
David Howells ICL Pathway
Barry Hancill ICL Pathway
Bill Herd ICL Pathway
Eamonn Long ICL Pathway
Claire Roberts ICL Pathway
Paul Butler ICL Peritas
Stuart Keams ICL Peritas
Authors: Lorraine Holt ICL Pathway
Richard Kelly ICL Peritas
COMMERCIAL IN CONFIDENCE Page I of S1
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref: BP/TRN/O1
Version: 7.9
Baseline Document Dale: 19
0 Document control
0.1 Document history
Version Date Reason
Issue 1.0 5.11.95 Training and User Awareness Baseline document in response to
Requirement 915 submitted as part of the contract and original bid
proposal, Ref. BP/TRN/001
Issue 1.1 10.11.95 Draft Baseline for discussion.
Issue 1.2 09.09.96 Draft Baseline.
Issue 1.3. 15/5/97 Revised Baseline with ICL Peritas comments
Issue 1.4 20/5/97 Revised baseline with ICL Pathway comments
Issue 1.5 20/10/97 _ Revised as part of POCL/ICL Pathway Training review meetings.
All inclusions have been discussed with POCL/ICL Pathway
Programme Teams and have been minuted.
Issue 2.0 10/11/97 __ Final draft sent for review by POCL and comments prior to sign off
(comments returned 17/12/97)
Issue 2.1 5/1/98 Further review by POCL and comments from sponsor reviews.
Issue 2.2 26/3/98 Review by POCL as a result of issues meeting
Issue 3.0 12/6/98 Final submission by ICL Pathway prior to commencement of NRO.
Distributed for approval.
Issue 4.0 7/8/98 Revised final submission by ICL Pathway following internal review.
Submitted to POCL as an attachment to CCN286.
Issue 5.0 21/8/98 Revised final submission by ICL Pathway following internal review
following rejection by POCL of CCN286. Submitted to POCL as an
attachment to CCN286a.
Issue 6.0 ‘11/12/98 _ Revised baseline following POCL comments and revised CCN.
Issue 7.0 8/1/99 Revised baseline following comments from Alan Fowler and to
ensure consistency with the TNA document
0.2 Approval authorities
Name Position Signature Date
SL Kearns ICL Peritas Training Project
Manager
COMMERCIAL IN CONFIDENCE Page 2 of 51
© 1998 ICL Pathway
ICL Pathway
Training and User Awareness Ref: BP/TRN(OOL
Version: 79
Baseline Document Date: 1 )99
FUJ00119673
FUJ00119673
Steve Lovegrove
B Davies
Bruce McNiven
S. Reed
Liam Foley
Andy Barkham
ICL Pathway User
Implementation Manager
ICL Pathway Implementation
Manager
POCL General Manager of
Horizon Implementation
Team
ICL Pathway Commercial
Manager
ICL Pathway Business
Development Director
ICL Pathway Training and
Awareness Manager
© 1998 ICL Pathway
COMMERCIAL IN CONFIDENCE Page 3 of SI
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref; BP/TRN/O01
Baseline Document vee ” 09
0.3 Associated documents
CP105 and Peritas 1.0 30/1/97 Agreed CP between ICL Pathway and POCL plus
document PATH-30- sub-contractor’s impact statement and changes to
007 contract wording.
TM/STR/0017 1.0 17/4/97 In Office Migration Release le
SU/TRN/0001 1.0 18/4/97 Training Needs Analysis
SU/TRN/006 1.0 26/11/97 Remedial Training
SU/TRN/OOS 1.0 29/10/97 Training Evaluation paper
TM/DOC/004 14 31/10/97 Implementation Programme Proposal
PATH/PUBS/001 4.0 09/06/98 Training and User Awareness Style Guide
BP/PRD/006 1.0 13/8/98 POCL Policy on competency testing (CAR
531.000.03)
BP/PRD/007 1.0 13/8/98 POCL Policy for Releasing staff (CAR 532.000.03)
IM/STR/0019 1.0 24/10/97 Training for Horizon Releases 1a to 1¢
SY/REP/021 1.0 29/10/97 Standard Reports and Formats
IM/PRO/147 1.0 OS/11/97 Procedure for ordering consumables for training
events
IMP/REQ/014 1.0 27/05/98 Training Scheduling and Minimum Training,
Compliance
PATH/PROC/0004 2.0 03/06/98 Training Venue Administration
0.4 Abbreviations
TPAS Training Project Administration System
POCL Post Office Counters Limited
RNM Retail Network Manager
HIM Horizon Implementation Manager
TNA Training needs Analysis
Scenario G Training provided on software releases 1a to Ic up to “Live trial”
NRO National Roll Out of training after live trial.
UA User Awareness
MS Microsoft
CAR Contracting Authorities Responsibility
RLM Regional Liaison Manager
SLA Service Level Agreement
COMMERCIAL IN CONFIDENCE Page 4 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref: BP/TRN(OOL
Version: 7.9
Baseline Document Date:
8/1/99
MOR Model Office Rehearsal
MOT Model Office Testing
MTC Minimum Training Compliance
New Release Live Trial and National Rollout functionality as part of the original
2
bid/contract baseline
New Release Update to the New Release 2 National Rollout platform to finalise
2+
functionality covered in the original bid/contract baseline.
New Release New functionality and New products included on the Horizon platform as
3 part of a separate costing and implementation proposal to POCL from ICL
Pathway.
HSHD Horizon System Help Desk
NGW Nancy Groff Witton
HW Horizon Hardware
SW Horizon New Release 2 (and New Release 2+) Software
UK United Kingdom
UAE User Awareness Event
E-mail Electronic Mail
Horizon ICL Pathway’s automated platform and New Release 2 (New Release 2+)
system
0.5 Changes in this version
Amended so that commercially this document more closely resembles the
arrangements agreed as part of CCN105. Issued for final sign off by POCL and ICL
Pathway.
The following changes have also been included to assist with the review of this
revised baseline:
e Cross references to ICL Pathway document PATH-030-007, dated 30/1/97,
Version 1.0 have been included in brackets at the end of each relevant section and
highlighted in bold and underline ie. (Bullet point 1) or (Para 1). This will
indicate that the “exact” wording used as previously described in the above
document. — If a section or para has been reworded then this will be displayed ie.
(Bullet point 1 reworded) or (Para 1 reworded) as appropriate.
¢ Where there is a bracket with the word “new” included ie. (New) then this has been
added, as a new section, within that particular cross reference.
COMMERCIAL IN CONFIDENCE Page 5 of S1
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref, BP/TRN/OOL
Version: 7.9
Baseline Document Dale: 19
e Paragraphs were there are no cross references or brackets with bold and underline,
then these are new sections included as part of this baseline and do not appear
anywhere, in the ICL Pathway PATH-030-007 document.
COMMERCIAL IN CONFIDENCE Page 6 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref: BP/TRN/001
Version: 70
Baseline Document Date: 1 )99
0.6 Table of content
1 MANAGEMENT SUMMARY.
2 SCOPE...
3 PROGRAMME MANAGEMENT
3.1 MANAGEMENT TEAM....
3.1.1 Implementation of the Training Project Administration System (TPAS)
3.1.2 Key Roles... sesseesuseeeeee .
ICL PATHWAY’S SUB-CONTRACTOR BOOKING SYSTEM (TPAS)
TRAINING ADMINISTRATION CENTRE
3.3.1 Description .....
3.3.2 Key Deliverables.
3.3.3 Acceptance.
3.3.4 Dependencies
4 TRAINING PRE NATIONAL ROLL OUT...
4.1 HORIZON RELEASES 1A TO IC........
5 USER AWARENESS & TRAINING DEVELOPMENT ..
5.1 DESCRIPTION .
5.2 USER AWARE Key DELIVERABL
5.3. DEVELOPMENT ACCEPTANCE (CROSS REFERENCE 2.3.3 “ACCEPTANCE”)
5.4 DEVELOPMENT LOGISTICS (CROSS REFERENCE 2.3.4 “LOGISTICS”)
5.5. DEVELOPMENT ASSUMPTIONS (CROSS REFERENCE TO 2.2.5 “ASSUMPTIO?
5.6 DEVELOPMENT DEPENDENCIES.
5.7 BENEFITS AGENCY.
5.8 TRAINING DOCUMENTATION (CROSS
REI
ERENCE 2.5 “DESCRIPTION”...
6 EVALUATION (CROSS REFERENCE 2.10 “DESCRIPTION”)...
6.1 DESCRIPTION...
6.6 DEPENDENCIES (CROSS REFERENCE 2.10 “DEPENDENCIES” ....
7 USER AWARENESS DELIVERY
7.1 USER AWARENESS DESCRIPTION (CROSS REFERENCE TO 2.2.4 “LOGISTICS”) .
7.1.1 User Awareness Key Deliverables (Cross reference to. Deliverables
7.1.2 User Awareness Acceptance (Cross reference to 2.3.3 “Acceptance”)
7.1.3 User Awareness Logistics (Cross reference to 2.2.4 “Logistic:
7.1.4 Assumptions (Cross reference to 2.2.5 “Assumptions
7.1.5. Dependencies (Cross reference to 2.2.6 “Dependencies
8 TRAINING DELIVERY ....
8.1 DESCRIPTION (CROSS REFERENCE 2.3.1 “DESCRIPTION”)
8.2 ALL SUBPOSTMASTERS, OUTLET AND IDENT
2.3.1 “MANAGERS” ..
8.3. COUNTER
COMMERCIAL IN CONFIDENCE Page 7 of 51
© 1998 ICL Pathway
FU.
ICL Pathway Training and User Awareness Ref: BP/TRN/001
Version: 70
Baseline Document Date: 1 )99
10
11
12
8.4 OTHER IDENTIFIED POCL STAFF: (CROSS REFERENCE TO 2.3.1.”BACK OFFICE AUDIT” AND “POCL TRAIN
THE TRAINER”)
8.5 KEY DELIVERABLES
8.6 ACCEPTANCE (CROSS REFERENCE TO 2.3.3 “ACCEPTANCE”)..
8.7 LoGisTICs (CROSS REFERENCE TO 2.
8.8 ASSUMPTIONS (CROS z
8.9 DEPENDENCIES (CROSS REFERENCE TO 2.3.6 “DEPENDENCIES”)
8.10 WORKBOOK PRACTICE AND TRAINING MODE .
8.10.1 Description (Cross reference to 2.4.1 “Description”’).
8.10.2 Key Deliverables (Cross reference to 2.4.2 “Key Deliverable:
8.10.3 Acceptance.
8.10.4 Logistics (Cross reference to 2.44 “Logistics”) .
8.10.5 Assumptions.
8.11 HORIZON FIELD SUPPORT AND MIGRATION VISIT (INFORMATION ONLY)
8.11.1 Overview Description (Cross reference to 2.7 “Description”) ..
8.11.2 Overview Key Deliverables.
8.11.3 Dependencies
REMEDIAL TRAINING...
9.1.1 Description (Cross reference to 2.8 “Description”...
Key Deliverables.
Acceptance
Logistics.
Assumptions.
Dependencies.
ACCOMMODATION
10.1.1 Description
10.1.2 Key Deliverable.
10.1.3 Acceptance.
10.1.4 Logistics.
10.1.5 Assumption
10.1.6 Dependencies
NEW PRODUCT AND UPDATE TRAINING (RELEASE 3 ONWARDS).
11.1.1 Description
11.1.2 Key Deliverables for New Product Training if agreed (subject to separate co
control process)... se
11.1.3 Acceptance.
11.1.4 Logisti
11.1.5. Assumptions .
11.1.6 Dependencies
MANAGEMENT REPORTING & PERFORMANCE MEASURES..
12.1 DESCRIPTION...
and change
COMMERCIAL IN CONFIDENCE Page 8 of 51
© 1998 ICL Pathway
FUJ00119673
}J00119673
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref, BP/TRN/OOL
Version: 7.9
Baseline Document Dale: 19
1 Management Summary
The purpose of this document is to identify ICL Pathway’s approach to the Training
and User Awareness Programme, as part of the implementation of the Horizon system
at post offices.
ICL Pathway Limited is a wholly owned subsidiary of ICL (International Computers
Limited) and has been formed in response to the needs of Post Office Counters
Limited (POCL) and the Benefits Agency (BA) to automate the nation’s post offices
key service functions, in particular benefit payments.
ICL Pathway has engaged a number of sub-contractors to deliver this programme and
ICL Peritas has been selected to design, develop, deliver and manage the Training and
User Awareness Programme. ICL Peritas is the UK’s leading provider of Information
Technology related training.
This document is being updated to reflect the changes that have been made to the
Training and User Awareness Programme since the last ICL Pathway baseline
document submitted in November 1995 as part of ICL Pathway’s contractual solution.
The reasons for the changes are covered in some detail by the associated documents
referenced. The following points summarise the key changes which have been
implemented :-
e The User Awareness event is no longer mandatory as proposed, but will be strongly
recommended by POCL for all staff to attend, especially managers and
subpostmasters.
e The user training has been changed from a four hour evening event followed by
supported workbook based consolidation and learning to either a one day or one
and a half day classroom training event (dependent upon job role).
e The competence test now takes place at the end of the extended classroom training
event as stated above.
e There will be no workbook based learning in the baseline training solution for
National Roll Out. Workbook based exercises will however be provided and are
recommended for use back at the outlet. Workbook based learning will be
considered for training on new software releases.
e The proposed After Care Visit (Training Review Visit) will not be undertaken by
ICL Pathway.
¢ There will no longer be a specialist training help desk to support distance learning.
The renamed Training Administration Centre will support user bookings and
rescheduling activities and will also accept queries regarding workbook exercises
via the Horizon System Help Desk.
COMMERCIAL IN CONFIDENCE Page 9 of SI
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref: BP/TRN/OO1
Version: 79
Baseline Document Date: 1 )99
This is by no means an exhaustive list of changes but identifies the key areas that have
been altered in response to the various discussions which have taken place.
The new training solution is represented in Figure 1 (and supersedes the diagram
shown in PATH-30-007, Section 2, page 4):
POCL shall use all reasonable endeavours to ensure that its Agents co-operate with
ICL Pathway to the extent reasonably necessary to permit ICL Pathway to perform the
training services described in this document.
COMMERCIAL IN CONFIDENCE Page 10 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref: BP/TRN/OO1
Version: 79
Baseline Document Date:
8/1/99
2 Scope
This document describes all the activities associated with the Training and User
Awareness Programme, which continues up to the end of National Rollout. After
National Rollout, training and user awareness will be carried out by POCL.
The activities can be summarised as follows:-
Programme Management and course booking system
Pre National Roll Out training
User Awareness and Training Development
User Awareness Delivery
Evaluation
UA Delivery
Training Delivery, Documentation and Competency Testing
Remedial Training
Training and User Awareness venues and catering
HFSO Training Review Visit (After care visit)
Management Reporting
The document also describes Update and New Product Training, which might be
undertaken by ICL Pathway at POCL’s request, subject to change control.
The scope of the training programme is also defined by the following:-
¢ Definition of users and their associated job roles provided by POCL and
documented as part of ICL Pathway Training Needs Analysis document reference
SU/TRN/0001.
e ICL Pathway Migration Plan (Source: In Office Migration Release le, Version 1.0,
reference IM/STR/0017. This document is soon to be updated to version 2.0
relating to Release 2 migration)
e Agreed course content (Source: ICL Pathway Training Needs Analysis, reference
SU/TRN/0001).
e ICL Pathway Remedial Training document reference SU/TRN/006, Version 1.0.
© ICL Pathway Training Evaluation Paper reference SU/TRN/005, Version 1.0.
COMMERCIAL IN CONFIDENCE Page 11 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref: BP/TRN/O1
Version: 7.9
Baseline Document Dale: 19
3 Programme Management
3.1. Management Team
The training programme management function is responsible for managing all
services provided by ICL Peritas (on behalf of ICL Pathway), liaising with ICL
Pathway Programmes Managers, ensuring that the training deliverables are fully
integrated with the delivery schedules of ICL Pathway and other suppliers to ICL
Pathway’s Implementation Team.
The management function will also ensure that training resource availability
incorporates sufficient contingency provision to ensure that no events are cancelled or
increased due to a lack of training resource.
3.1.1. Implementation of the Training Project Administration System (TPAS)
The training project administration system provides facilities used to administer the
delivery of training programmes and control of the supporting logistics management
system. The work package will include the development of the import and export
modules and customisation of the management reporting functions required to meet
ICL Pathway and programme requirements.
ICL Pathway’s sub-contractor (ICL Peritas) will locate a dedicated ICL Pathway
Training Office in North West England, i.e. Stockport and will accommodate all
office based staff. This accommodation will also provide adequate storage space to
manage the documentation and equipment delivered as part of the training
programme.
3.1.2 Key Roles
3.1.2.1 Training Project Manager
This role provides a single point of contact with responsibility for all aspects of the
training programme, co-ordination of the activities within it, with those of the wider
ICL Pathway programmes and those of the other sub-contractors to ICL Pathway.
3.1.2.2 Project Control Officer
This role is responsible for the administration of the project library, monitoring the
progress against project plans and the administration of the commercial processes
required to support the programme.
COMMERCIAL IN CONFIDENCE Page 12 of SI
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref: BP/TRN/001
Version: 7.9
Baseline Document Date: 1 )99
3.1.2.3 Training Team Leader
3.1.2.4
3.1.2.5
3.1.2.6
3.2
This role manages the selection of training staff and ensures that all training deliveries
conform to the quality standards agreed with Pathway for the programme.
Logistics Manager
Responsible for the provision of logistical support to the training implementation.
They will also manage the integration of ICL Pathway’s sub-contractor and Pathway
MIS interfaces.
Evaluation Officer
Responsible for building training evaluation criteria and operating the various
measurement exercise required by POCL for the training activity e.g. course
assessments, after course questionnaires etc. They will provide all management
information to the Training Programme Manager.
Development Manager
Responsible for the overall management of all training and User Awareness event
development.
ICL Pathway’s Sub-contractor Booking System (TPAS)
ICL Pathway’s sub-contractor training booking system has been tailored to meet
contractual obligations regarding scheduling and invitations notice period. It has also
been developed alongside ICL Pathway’s Rollout Database system to ensure accurate
and contractually compliant information is available and transferred electronically
using approved file and report structures. This work has involved the following
activities:
Applications development
System trials
+ Integration trials with Pathway control system
The composition and specification of functional modules will be formally defined
within an updated functional specification published after detailed consultation with
ICL Pathway programmes office at Feltham.
In addition this system will provide additional ICL Pathway User reports regarding
competency, attendance levels and scheduling details to ICL Pathway Programme
Managers and POCL nominated representatives (for more details on reports and
layout please refer to ICL Pathway Standard Reports and Formats document ref.
COMMERCIAL IN CONFIDENCE Page 13 of SI
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref, BP/TRN/OOL
Version: 7.9
Baseline Document Dale: 19
SY/REP/021). All reports will be transmitted via e-mail with some reports requiring
POCL actions within 24 hours (or next working day).
3.3. Training Administration Centre
3.3.1 Description
A dedicated administration function manned with staff able to provide immediate
assistance with:
¢ Logistics and content of the training programme
¢ Bookings and attendance on courses.
¢ General questions concerning training and user awareness programmes.
¢ Scheduling enquiries from nominated representatives.
The Training Administration Centre will undertake the following tasks:
¢ Import of installation schedules from ICL Pathway
e Generation of training and user awareness schedules to ICL Pathway
¢ Dealing with enquiries made from the HSHD to ICL Pathway’s sub-
contractor relating to Workbook Exercises
e Survey of post office training and UA requirements, e.g. completion of
training booking forms
e Assignment of course places to training and UA schedules and re-
scheduling bookings
e Issue of training and user awareness invitations from ICL Pathway’s sub-
contractor to users.
¢ Follow up confirmations to invitations and course joining instructions.
¢ Distribution of user implementation briefing packs if non-attendance at UA
events.
¢ Ordering and despatch of supporting logistics
© Generation of attendance lists via reports to ICL Pathway and POCL
Regional Representatives.
e Export of training and user awareness completion records to ICL Pathway’s
Rollout Database and via ICL Pathway’s standard reports (as defined in ICL
Pathway Standard Reports and Formats document reference SY/REP/021).
e Export of training competence test reports to ICL Pathway’s Rollout
Database and via ICL Pathway Standard Reports (as detailed in the above
document).
COMMERCIAL IN CONFIDENCE Page 14 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref: BP/TRN/O1
Version: 7.9
Baseline Document Dale: 19
3.3.2
3.3.3
3.3.4
41
e Export of training and user awareness statistics to POCL regional staff and
ICL Pathway management.
Key Deliverables
e “Lo-call” telephone number for inbound queries from post office outlets.
¢ Operates 8.30am to 10.30pm Monday - Friday and 9.00am to 5.00pm on Saturday
at the start of live trial training events up to the end of National Rollout in all
POCL regions.
e Transaction logging will be maintained on all data changes to TPAS and
automatically notified to the ICL Pathway Roll Out database.
© Call logging will be maintained on the HSHD on all enquiries passed to ICL
Pathway’s sub-contractor from the Horizon System Help Desk. Monthly reports
will be issued to ICL Pathway.
Acceptance
There are performance measures covering:
¢ Reporting (Requirement 915)
¢ Course availability (Requirement 915)
© Course cancellations (Requirement 915)
Dependencies
e Specific call quality and performance measures will be agreed with ICL Pathway as
part of the functional specification of the Training Administration Centre.
e POCL will receive updates via Training Review meetings scheduled during
National Rollout.
e Agreed formats to ICL Pathway, POCL and POCL Reports as outlined in ICL ICL
Pathway Standard Reports and Formats document, reference SY/REP/021.
¢ Compliance to ICL Pathway internal SLA’s in accordance with ICL Pathway’s sub-
contractor’s contract and performance measures. This is required in Excel format
as provided by ICL Pathway.
Training pre National Roll Out
Horizon Releases 1a to 1c
The replanning of the implementation programme for Horizon into controlled phases
has meant that the awareness and training events received by the users has had to be
redefined. In line with best practice and contractual requirements, users will need to
receive training associated with the functionality of the system or upgrade. Training
COMMERCIAL IN CONFIDENCE Page 15 of SI
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref, BP/TRN/OOL
Version: 7.9
Baseline Document Dale: 19
5.1
should use (where appropriate) existing processes and procedures which have been
defined for Live Trial and National Rollout though no formal Service Level
Agreement (SLA) measurement will apply for Release 1a to Ic training
The phasing of the implementation of Horizon functionality also means that some
outlets will require upgrade training as the facilities and services available to them are
expanded.
The ICL Pathway Horizon Training for Release 1a to 1c document (dated 24/10/97,
reference IM/STR/0019) describes the training programme for the different releases of
Horizon and how it will be implemented. This has been agreed and signed off by
POCL.
User Awareness & Training Development
The User Awareness programme is being developed to encompass the split in
implementation between the new infrastructure programme and the main
implementation programme (this is described in detail in ICL Pathway
Implementation Programme Proposal document, reference IM/DOC/004).
The User Awareness event is aimed at ALL users working within, or providing
support to, post offices. The purpose of the event is to provide a understanding of the
impact the impending installation and automation programme will have on them as
individuals and their outlet as a whole. The overall aim is to elevate concern users
may have of the Horizon system and encourage participation during training and
installation.
Description
The Horizon training portfolio will comprise:
e User Awareness event (2.5 hours)
¢ Subpostmaster/POCL Managers course (1.5 days)
e Counter Assistants Course (1 day)
e POCL Train the Trainer course (5 days)
© Other POCL staff specialist course (up to 2 days) based upon the postmaster or
outlet manager course for non users of the platform and other POCL staff as
defined in ICL Pathway TNA document. This will also cover any staff who will be
changing role to a management function. It is expected that these will be
identified by POCL as part of an agreed booking process and procedure between
ICL Pathway and POCL.
COMMERCIAL IN CONFIDENCE Page 16 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref. BP/TRN(OOL
Version: 7,
Baseline Document Date: ve
8/1/99
5.2 User Awareness Key Deliverables
A formal Training Needs Analysis which defines the training requirements, assesses
the expected volumes of users to be trained and contains specifications for all training
events as part of New Release 2 (and New Release 2+). ICL Pathway Training Needs
Analysis document SU/TRN/0001, constitutes this deliverable.
User Awareness Description (Cross reference: 2.2.1 “Description”)
A seminar style face to face presentation delivered in a lecture environment, which
provides all staff who work within a post office, with an overview of the ICL Pathway
project and a detailed understanding of both the user functions and the training
support functions provided by the project. (Para 1)
There will be an ICL Pathway team to deliver each event consisting of (Para 3
e Change Management Consultant
e Trainer
e Administrator
In addition, a POCL Manager will be present at each event. (Para 4)
Development deliverables for the User Awareness event (Cross reference 2.2.2
“Key Deliverables”
This will comprise a formal course kit containing:
e Event specification (Bullet point 1)
e Event invitation (Bullet point 2)
e Event questionnaire (Bullet point 3)
¢ User Implementation Guide (issued to users at the event) (Bullet point 5)
@ Implementation process overview
@ Training programme guide
e Event Design and Development (Bullet point 4)
@ Preview video (New)
@ Agree Video storyboard and scripts (Cross ref. 2.2.3 “Acceptance”
bullet point 2)
™@ Agree presentation scripts (New)
e Dry run to sample users (Cross ref. 2.2.3 “Acceptance” bullet point 6)
¢ Scripted demonstration (for presenters only) (Bullet point 7)
e Prepared questions and answers to be provided by POCL (for presenters
only) (Bullet point 8)
COMMERCIAL IN CONFIDENCE Page 17 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref. BP/TRN/O01
: Version: 79
Baseline Document Date: 1 )99
Training Description (Cross reference 2.3.1 “Description”)
The objective of the training is to ensure that all staff who work in post offices are
competent in the use of the automated platform, are aware of the impact on
operational procedures of that platform and that specialist staff are provided with the
appropriate additional information to perform their job role within an automated post
office. (Para 1)
The proposed solution offers three main training streams, namely:- (Para 2)
Managers (Cross reference 2.3.1 “Managers”)
e A 1.5 day contiguous training event delivered over two days to include venue set
up and clear down. (Bullet point 1)
e This course would be targeted at staff who are required to understand the full
functionality of the automated platform. (Bullet point 4)
e It is understood that all management grades will need this training. It is also
understood that other staff may perform these tasks, in some cases as back up, and
they will also need the Managers training event. (Bullet point 5)
Counter staff (Cross reference 2.3.1 “Counter staff”)
e A one day contiguous training event. (Bullet point 1)
© It is recognised that some of these staff, who perform some management functions,
will attend the above 1.5 day event instead of this one as more fully defined in
paragraph 8.3 of this document. (Bullet point 5)
Specialist staff and HQ roles: (Cross reference 2.3.1 “Back office audit” and
“POCL Train the Trainer”)
Back Office Audit
This is a two day course based on the content delivered to the systems
managers but tailored to meet the needs of the central audit office of the Post
Office. The same course will be taken by computer auditors and regional
auditors. (Para 1)
POCL Train the Trainer
This 5 day course is aimed at existing POCL trainers, who will be training
both existing staff and new staff on the automated counter transaction system.
(Para 1)
Development deliverables for each training event
This will comprise a formal course kit containing:
e Loose leaf workbook (issued to users at the event)
© Quick reference guide (issued to users at the event)
COMMERCIAL IN CONFIDENCE Page 18 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref: BP/TRN/O1
Version: 7.9
Baseline Document Dale: 19
5.3
5.4
e Ring Binder for workbook (issued to users at the event)
¢ Formal script and session plans (for presenters/trainers only)
¢ Course kit binder (POCL and ICL Pathway’s Train the Trainer event only)
© Slides
e Review forms and questionnaires (to be completed by users as part of the
event)
¢ Competence test (completed as part of the event)
Development Acceptance (Cross reference 2.3.3
“Acceptance”)
e ICL Pathway Training Needs Analysis document reference SU/TRN/0001, Version
1.0 (approved and signed off by ICL Pathway 19/3/97 and by POCL on the
22/4/97). (Bullet point 1)
e Structure and format of training materials to be approved by ICL Pathway and
POCL as part of formal acceptance. (New)
e Sign off as part of the training course dry run process. (Bullet point 2 reworded)
e Video sessions will be agreed by POCL and ICL Pathway prior to ICL Pathway’s
internal dry run as part of a separate Training Review meeting. (New)
¢ Training materials i.e. training workbooks and quick reference guides will be
signed off as part of a “Fagin” review and inspection carried out by ICL Pathway
and POCL. (New)
e Formal written notification of acceptance is required from POCL before
commencement of National Rollout Training. (New)
Development Logistics (Cross reference 2.3.4 “Logistics”)
e All Training and Awareness documentation will be produced and distributed by
ICL Pathway’s sub-contractor on behalf of ICL Pathway. This excludes the
distribution of POCL material. (New)
e ICL Pathway will provide training systems for demonstration purposes. (New)
e Version control of ICL Pathway documents and training materials will be operated
on all training documentation. Once baselined, all documentation will be subject
to a formal change control process. (New)
e ICL Pathway’s sub-contractor will offer a service that secures the delivery
accommodation, issues the invitations to the events and manages the delivery
schedule and management information. This will be co-ordinated via the Training
Administration Centre complemented by the logistics management function.
New
COMMERCIAL IN CONFIDENCE Page 19 of SI
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref: BP/TRN/O1
Version: 7.9
Baseline Document Dale: 19
5.5
5.6
e Trainer gear up will be accomplished via a 3 week training programme. (Bullet
point 1)
Development Assumptions (Cross reference to 2.2.5
“Assumptions”)
e There will be 60 days notice of product updates from ICL Pathway and POCL to
ICL Pathway’s sub-contractor. This will form part of a formal specification of
requirements to ICL Pathway who will cost and assess within a 2 week period from
notification, with a further 60 days required for development purposes and
acceptance. (New)
¢ Formal notification of the volumes of materials and distribution schedules will be
available from ICL Pathway’s sub-contractor for ICL Pathway’s approval prior to
notification of New Release 2 (New Release 2+). (New)
¢ Training attendance is mandatory for all users who work in post offices. (New)
e User Awareness event content is identical for all staff. (Bullet point 1)
Development Dependencies
e Availability of suitably qualified users to attend dry runs. These should be
representative of the target audience for each event.
e Assistance with development material from POCL specialist staff e.g. POCL
Security and Audit.
¢ Software availability dates as required by ICL Pathway’s sub-contractor will be
met by ICL Pathway prior to MOR and MOT.
© 60 days’ prior notice of any new product updates after New Release 2 from POCL
to ICL Pathway.
e POCL and ICL Pathway will be reviewed against SHARED project “handshake”
milestones/project plans. This will be co-ordinated by POCL and ICL Pathway
project teams and reviewed within agreed timescales.
e Formal project plans are received from ICL Pathway’s sub-contractor to ICL
Pathway in a timely manner within agreed timescales. This is an ICL Pathway
management activity only.
e Updates on training progress and development activities are delivered within
project timescales.
e Formal ordering and invoice processes to be documented between ICL Pathway
and ICL Pathway’s sub-contractor prior to submission to ICL internal account
teams.
e ICL Pathway’s sub-contractor to notify ICL Pathway of any cost saving regarding
the use of POCL venues used within the ICL Pathway training programme. This
COMMERCIAL IN CONFIDENCE Page 20 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref: BP/TRN/O1
Version: 7.9
Baseline Document Dale: 19
5.7
5.8
process will be agreed between ICL Pathway and POCL and documented
accordingly.
e All invoices and requests for orders are accompanied with ‘back up’ or supporting
material as proof of delivery. This is an ICL Pathway management activity only.
e POCL will advise staff that managers are expected to attend a Managers event. In
the case of sub post offices, if the Postmaster cannot attend then he will appoint a
deputy.
e ICL Pathway Programme function will be responsible for advising the offices
planned for implementation in the appropriate time scale.
e ICL Pathway will provide training systems for awareness and training events.
Benefits Agency
There will be no formal course development associated with Benefits Agency staff
training. ICL Pathway’s sub-contractor will provide a training review cycle on
documentation generated by the Benefit Agency and in return a QA process will be
carried out by the DSS training teams on ICL Pathway’s sub-contractor training
materials. This will be on an on-going basis until the end of the National Rollout
programme.
Training Documentation (Cross reference 2.5 “Description”)
Users on all courses will receive a training workbook comprising the following:
(Para 1 reworded)
© Quick reference guides (Bullet point 1)
e A workbook (Bullet point 2)
™ This contains classroom exercises (carried out as part of the training
event) and activity review sheets (carried out as part of “after training”
consolidation). Some questions may be used during the training event so
the trainer can gauge students’ reaction to a particular training session.
This will assist with trainers’ understanding on where individual user
support is needed. There is also the opportunity to use training mode to
practice all transactions carried out at the counter using counter
procedures manuals). These will be completed at users’ discretion, on or
after their training event but will be an optional activity. (New)
© Course notes (New)
e Training ring binder (New)
e Sample bar-codes, training APS & BPS cards (1 pack per outlet) (New)
COMMERCIAL IN CONFIDENCE Page 21 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref: BP/TRN/001
Version: 70
Baseline Document Date: 1 )99
The training workbook is a loose leaf document contained within a training binder. It
contains the following module related structure (as stated in ICL Pathway document
reference PATH-30-007, dated 30/1/98, section 2.5): (Para 2 reworded)
Workbook Structure
(fopeS’]I BPS” II (ABs) [Poss] I I System
The workbook will be double sided, in monochrome, provided in a ring binder.
Should system functionality change or expand, and additional pages be required, a
change control request will be needed (Cross reference to Schedule A15 for approved
process). (Para 3)
The Quick Reference Guide is a one or more, A4 tri-fold colour sheets covering:
(Cross reference to 2.5 “Quick reference guide”)
e Getting Started (Bullet point 1)
e Basic System Process (Bullet point 2)
e Benefit Payments BPS/OBCS (Bullet point 3)
EPOSS/APS (New)
(Cross reference 2.4 “Description”)
An electronic training mode on the automated platform which can be used in
conjunction with a workbook of exercises for self study periods in order to: (Para 1)
e Refresh use of system after training. (Bullet point 1)
© Provide drill and practice to increase speed and accuracy. (Bullet point 2)
COMMERCIAL IN CONFIDENCE Page 22 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref; BP/TRN/0OL
Version: 79
Baseline Document Date: 1 )99
6.1
6.2
e Provides an opportunity to practice on linked (end to end) transactions using
counter procedure manuals (plus training scenarios) thus consolidating knowledge.
(Bullet point 3 reworded)
Assumptions (Cross reference 2.4.5 “Assumptions”)
e Training workbooks will be kept updated as system versions change (up to
new Release 2+) for new outlets to Horizon as part of National Rollout.
Once training for an outlet has been completed no further training materials
will be sent to that outlet, whether for new staff, product or system updates,
unless ordered by POCL. (Bullet point 1 reworded)
e All training documentation will be produced and distributed by ICL
Pathway’s sub-contractor to users as part of their training event. (New)
¢ Version control will be required on all training materials during National
Rollout. (New)
Dependencies
¢ POCL will carry out a formal review on training workbooks prior to MOT.
¢ Sign off by POCL and ICL Pathway by the end of MOT.
Evaluation (Cross reference 2.10 “Description”)
Description
ICL Pathway will provide Kirkpatrick conformant level 1 and level 2 evaluation
comprising: (Para 1 reworded)
e A training questionnaire i.e. course appraisal form administered at the end of each
training event (Level 1) (Bullet 1 reworded)
e¢ A competency test. One hour allowed for completion (Level 2) (Bullet 2)
Key Deliverables (Cross reference 2.10 “Key Deliverables”)
© Overall competency test will not exceed a duration of I hour. (2.10 - Para 1,
Bullet 2
e ICL Pathway’s sub-contractor certificate for successful candidates. This will be
sent to delegates after the course. (Bullet point 1)
e Reporting on level 1 questionnaire results. (Bullet point 2)
e Reporting on competency level results. (Bullet point 3)
¢ Reporting on competency level failure analysis. (Bullet point 4)
COMMERCIAL IN CONFIDENCE Page 23 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref: BP/TRN/O1
Version: 7.9
Baseline Document Dale: 19
6.3
e Venue appraisal form completed by users as part of their training event (this is
handed to the trainer at the end of the course for review). (New)
e Training or Awareness course appraisal forms will be completed by users at the
end of their event and handed back to the trainer for review before leaving the
training or awareness venue. (New)
e ICL Pathway’s sub-contractor will forward a certificate for users who pass the
competency test. This will be known as the Horizon Achievement Certificate and
will be sent to delegates after the course. This certificate will identify the level of
attainment in terms of job category as: (New
e Trainer
¢ Auditor
¢ Subpostmaster or Outlet/POCL Manager
¢ Counter Assistant
e Regular reporting on level 1 of the Kirkpatrick model will report course appraisal
results. These are e-mailed to ICL Pathway and POCL by ICL Pathway’s sub-
contractor for review weekly or monthly. (This will be dependent upon POCL’s
written confirmation of preferred option i.e. weekly or monthly). (New)
e Regular reporting on level 2 of the Kirkpatrick model will report competency level
results. This is e-mailed to ICL Pathway and POCL by ICL Pathway’s sub-
contractor within 24 hours or next working day. This will require the same
turnaround from both sides for actioning as part of POCL CAR 531.000.03
document reference BP/PRD/006. (New)
e In addition reporting and analysis of competency tests will be e-mailed by ICL
Pathway’s sub-contractor to ICL Pathway and POCL Regions as part of joint
monthly review meetings between ICL Pathway and POCL (in accordance with
ICL Pathway Standard Reports and Layouts document reference SY/REP/021).
New
Acceptance (Cross reference 2.10 “Acceptance”)
ICL Pathway and POCL signed and agreed content of ICL Pathway Training
Evaluation paper reference SU/TRN/005 covering: (Para 1 reworded)
e Level 1 Questionnaire. (Bullet point 1)
e Level 2 Competency test. (Bullet point 2)
Reports on Level I satisfaction and Level 2 competency test results are outlined
within the ICL Pathway Standard Reports and Formats document reference
SY/REP/021 agreed with POCL. (Para 3 reworded)
COMMERCIAL IN CONFIDENCE Page 24 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref. BP/TRN(OOL
Version: 7.9
Baseline Document Date:
8/1/99
6.4 Logistics (Cross reference 2.10 “Assumptions”)
6.5
6.6
ICL Pathway
e The course appraisal is completed prior to competency test. (Para 1)
e The competency test will be administered by trainers immediately after each
training event to users under supervision. (New)
e If and when delegates have twice failed the competency test, ICL Pathway will be
notified immediately by exception reports to POCL Regions and ICL Pathway via
e-mail. This will be the responsibility of ICL Pathway’s sub-contractor to distribute
and manage. (New)
POCL
e The RLM and POCL will be notified by e-mail within 24 hours (or the next
working day) of each and every test failure or subsequent pass. A turnaround of
24 hours (or next working day) is expected by POCL Regions to ICL Pathway’s
sub-contractor on action taken. (New)
e It is POCL’s responsibility to ensure all users of Horizon platform attend remedial
training, as arranged by ICL Pathway and understand the importance of a
competency test. (New)
Assumptions
¢ All outlet users of the Horizon platform will be advised via POCL communications
of POCL’s requirements for a competency test and that it is their responsibility to
ensure the process is understood regarding its impact and management. All results
will be stored electronically via the ICL Pathway’s sub-contractor’s system (TPAS)
with notification to users, as required by the Data Protection Act. This will be
stored by ICL Pathway’s sub-contractor during National Rollout, up to individual
post office outlet acceptance and go live.
© Course appraisal forms are completed by users prior to the competency test.
Dependencies (Cross reference 2.10 “Dependencies”)
e Agreed approach (set of words from POCL) for telling users they have failed a
competency level. (Para 1)
e Formal agreement to words and criteria used for level 1 course appraisal and venue
acceptability forms (for more information please refer to ICL Pathway Training
Evaluation Paper reference SU/TRN/005). (New
e Formal definition and agreed criteria between POCL, ICL Pathway and ICL
Pathway’s sub-contractor for level 2 competency test as part of POCL’s CAR
531.000.03 reference BP/PRD/006, Version 1.0 (which has been agreed by POCL).
(New)
COMMERCIAL IN CONFIDENCE Page 25 of SI
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref, BP/TRN/OOL
Version: 7.9
Baseline Document Dale: 19
e¢ POCL commitment from delegates in undertaking a competency test and any
remedial training required (as outlined in section 1 “Management Summary”, fig.1
of this document). This is outlined in POCL’s CAR 531.000.03, reference
BP/PRD/006, and cascaded by both POCL Regions through internal
communications. This will also be reiterated by ICL Pathway on the User
Awareness events. (New)
e Agree how questions are selected from a pool of possible questions submitted by
ICL Pathway’s sub-contractor. (Para 2
e Auto - what happens if questions does not relate to job role. National standard v
non answer (counts as pass). (Bullet point 2)
e The following 5 evaluation forms will be contractually adhered to by ICL Pathway
and ICL Pathway’s sub-contractor as part of National Rollout (for more
information please refer to ICL Pathway Training Evaluation paper reference
SU/TRN/005). This complies to Requirement 915. (New)
e User awareness appraisal (1 form)
e Training course appraisal (1 form)
© Venue Satisfaction (1 form)
¢ Competency test (1 form)
e Trainer assessment of each individual delegate (1 form)
As detailed in Requirement 915 “the training Services provided shall ensure that 95%
of trainees on completion of the training shall be able to demonstrate achievement of
the agreed level of competence, which shall reflect a score of 90% for knowledge
related areas for transactions and the operating platform”. To facilitate this ICL
Pathway, via ICL Pathway’s sub-contractor, will provide exception reports on failures
within 24 hours (or next working day) to POCL representatives via e-mail. This will
be documented in ICL Pathway Training Scheduling and Minimum Training
Compliance document reference IMP/REQ/014. Both documents identify what action
will be taken by the ICL Pathway and POCL Regions within 24 hours or next working
day. After the third attempt by a user to pass the test, action will be taken by POCL.
As part of this process POCL will require POCL Regional teams to communicate this
to users as part of POCL’s Horizon communications programme. (New)
Any further evaluation by ICL Pathway and ICL Pathway’s sub-contractor on training
will be subject to separate and additional agreement. (New)
¢ POCL will ensure that competency assessments are maintained for all users of the
Horizon platform after site acceptance. This will be documented and agreed with
POCL Regions in advance of completion of ICL Pathway’s development activities.
Any training events or training materials which are required by POCL from ICL
Pathway to achieve this must be subject to separate and additional agreement
between POCL and ICL Pathway. (New)
¢ Copyright for all training materials are the property of ICL Pathway’s sub-
contractor. Neither POCL nor users may make copies of any training material
COMMERCIAL IN CONFIDENCE Page 26 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref; BP/TRN/0OL
Version: 70
Baseline Document Date: 1 )99
7.1
(either in part or in full) without ICL Pathway’s consent. ICL Pathway will be
pleased to quote POCL for the supply of additional or replacement copies. Subject
to commercial agreement, an agreed ordering process between ICL Pathway and
POCL should be put in place before the commencement of future training events
during Live Trial and National Rollout. (New)
e Turnover training is currently the responsibility of POCL staff and agency trainers.
All strategies and policy decisions regarding POCL’s delivery will be documented
and agreed between POCL and ICL Pathway. A\ll processes and procedures will
be logged in both POCL and ICL Pathway libraries for reference purposes. (New)
User Awareness Delivery
This is a key deliverable of the training programme and helps familiarise users with
the Horizon system prior to their training event and installation.
User Awareness Description (Cross reference to 2.2.4
“Logistics”)
Attendance on the user awareness programme will be strongly recommended for all
staff and will be delivered locally to reduce travel. (Para 2)
ICL Pathway’s sub-contractor propose to run a series of evening events in locations
throughout the UK which will consist of a formal presentation and demonstration.
ICL Pathway’s sub-contractor will control the mailing of invitations to users. It is
anticipated that each event should target 90 attendees in the urban areas, 50 in rural
and 30 in the Highlands and Islands, (Para 2)
”
1 “Desc
Cross reference to 2.. ion’
This consists of a seminar style face to face presentation delivered in a lecture
environment. This will provide all users and POCL staff with an overview of the ICL
Pathway programme as a whole helping to identify key roles and responsibilities both
within ICL Pathway and the POCL Regions. It will assist with users’ understanding
of the Horizon system, the training and support programmes which are in place, along
with key user messages regarding business change and the future of POCL. (Para 1
reworded)
The objectives of the User Awareness event are to: (Para 2)
e Gain user commitment to the training, installation and support programmes.
(Bullet point 1 reworded)
© Increase user awareness of the Horizon system, its training programme, its
installation and migration activities. (Bullet point 2 reworded
¢ Increase level of user ownership of the Horizon system and its use. (Bullet point
2»
COMMERCIAL IN CONFIDENCE Page 27 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref; BP/TRN/0OL
Version: 79
Baseline Document Date: 1 )99
7.14
e Provide a suitable forum to identify and respond to user concerns and issues
regarding training, migration, on-going support and documentation. (Bullet point
4 reworded)
User Awareness Key Deliverables (Cross reference to 2.2.2 “Key
Deliverables”)
e Event Specification (Bullet point 1)
e Event invitation (Bullet point 2)
e Event questionnaire. (Bullet point 3)
e Event presentation slides and script (for presenters only) (New)
e Implementation guide (distributed as part of the event) (Bullet point 5)
This includes:
@ User Implementation Process overview (Bullet point 5 - first sub bullet)
@ Installation process overview (New)
@ Training programme guide and booking procedure (Bullet_point 5 2"! sub
bullet)
@ Migration and after care support overview (New)
e Video sessions are used to support presentations (for presenters only) (Bullet
point 6 reworded)
¢ Scripted demonstration (for presenters only) (Bullet point 7)
e Prepared questions and answers (to be provided by POCL for presenters only)
(Bullet point 8)
(Cross reference to 2.2.1 “Description”)
There will be an ICL Pathway’s sub-contractor team to deliver each event consisting
of a lead trainer and presenter, a trainer for demonstrations (who can also act as lead
trainer and presenter) and an administrator (who is a Horizon trainer). This allows
eases delivery, as well as contingency at the event itself, in case of sickness. (Para 3
reworded)
In addition, a POCL Manager may be present at each event (this is not mandatory, but
is seen as a positive partnership approach). (Para 4 reworded)
User Awareness Acceptance (Cross reference to 2.3.3 “Acceptance”)
Contractual performance measures cover: (Bullet point 3)
© Course availability (Requirement 915)
e Venue quality (Requirement 915)
COMMERCIAL IN CONFIDENCE Page 28 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref, BP/TRN/OOL
Version: 7.9
Baseline Document Dale: 19
e Training course quality (Requirement 915)
© Cancellations of courses (Requirement 915)
e Training course feedback by trainers (Requirement 915)
e Delivery (as described in the ICL Pathway Training Scheduling and
Minimum Training Compliance document reference IMP/REQ/014)
7.1.3. User Awareness Logistics (Cross reference to 2.2.4 “Logistics”
ICL Pathway’s sub-contractor will offer a service that secures the delivery
accommodation, issues the invitations to the events and manages the delivery
schedule and management information. This will be co-ordinated via the Training
Administration Centre complemented by the logistics management function. (Para 1)
Events will be delivered within a 30 mile radius to reduce travel due to availability of
suitable venues. This is largely due to the maximum size of venue required to
accommodate 120 people and Health and Safety Regulations. ICL Pathway’s sub-
contractor will deliver a series of evening events in locations throughout the UK
which will consist of a formal presentation and demonstration. ICL Pathway’s sub-
contractor will control the mailing of invitations to users. Each event should have a
maximum of 90 to 120 attendees within the implementation requirements defined by
the ICL Pathway Roll Out database. (Para 2 reworded)
The timing of the events should be in line with the overall implementation plan and
are planned approximately seven weeks prior to the installation date. More
information relating to timescales and approach is contained in ICL Pathway
Implementation Programme Proposal document reference IM/DOC/004. (Para 3
reworded)
All events will start at 7.00pm with a demonstration, the main event will start at
7.30pm, unless specifically agreed beforehand between ICL Pathway and POCL.
(Para 4 reworded)
Horizon systems will be available at each event and demonstrations will be given
before and after the main seminar. The presentation will be driven directly to a large
display and developed using MS-PowerPoint. (New)
Non attendees will be sent the user implementation guide (as provided to attendees at
the User Awareness event) along with a covering letter plus a copy of the UAE video.
User implementation guides will only be sent to outlets for which no user awareness
attendees have been logged. Only one guide per outlet will be sent. (New)
Administration of the event will be undertaken by ICL Pathway’s sub-contractor.
(Para 7 reworded)
Management of venues will be undertaken by ICL Pathway’s sub-contractor.
(Para 7 reworded)
COMMERCIAL IN CONFIDENCE Page 29 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref; BP/TRN/0OL
Version: 70
Baseline Document Date: 1 )99
7.1.4 Assumptions (Cross reference to 2.2.5 “Assumptions”,
e User Awareness event content is identical for all users. (Bullet point 1
© User Awareness attendance is strongly recommended for all staff who work in post
offices. (Bullet point 2)
e POCL staff, particularly RLM’s, HIM’s and RNM’s will proactively encourage
attendance. (New)
7.1.5 Dependencies (Cross reference to 2.2.6 “Dependencies”
8.1
¢ POCL will advise POCL staff and potential Horizon users and outlet managers that
attendance is expected at this event. In the case of Outlets, if the subpostmaster
cannot attend then he or she will appoint a deputy. All subpostmaster assistants
and POCL staff will also be strongly encouraged to attend to ease transition to the
Horizon platform. (Bullet point 1 reworded)
e ICL Pathway Implementation Programme function and Rollout team will be
responsible for advising ICL Pathway’s sub-contractor of the offices planned for
implementation in the appropriate timescales. (Bullet point 2)
e ICL Pathway will provide training systems for demonstration purposes. (Bullet
point 4)
e Large venues are required to accommodate attendance levels and meet with fire,
health and safety regulations. The use of POCL venues is excluded from this
section. (New)
¢ POCL will provide one manager at each event. This will normally be the RLM or
his/her nominated deputy. (Bullet point 3)
Training Delivery
Description (Cross reference 2.3.1 “Description”)
The overall training approach during for Live Trial and National Roll Out will be to
deliver classroom based events. A full competence test will be introduced for the
National Roll Out phase and integrated into the timing for the event. A workbook will
be issued to enable staff to practice during their training event. (New)
The objective of the training is to ensure that all staff who work in post offices are
competent in the use of the automated platform, are aware of the impact on
operational procedures of that platform and that specialist staff are provided with the
appropriate additional information to perform their job role within an automated post
office. It is also compulsory that all users of the Horizon platform complete a training
event (within the contractual training window reference Requirement 915) and a
competency test. (Para 1 reworded)
COMMERCIAL IN CONFIDENCE Page 30 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref; BP/TRN/0OL
Version: 70
Baseline Document Date: 1 )99
8.2
8.3
The proposed solution offers five main training streams, namely: (Para 2 reworded)
e Managers 1.5 day event is aimed at subpostmasters, branch managers,
RNMs, Regional Support staff, franchise managers, outlet managers,
nominated deputies for an outlet/Relief managers, Heads of Retail Network,
POCL User Acceptance team, POCL staff who perform stock balancing and
POCL nominated staff.
e Counter Assistant 1.0 day event is aimed at branch and subpostmasters’
assistants/staff, POCL retail assistants and Franchise staff).
¢ Auditors 2.0 day event is aimed at National and Regional Auditors, POCL
Security and Investigators.
e Train the Trainer 5 day event is aimed at POCL and agency trainers.
¢ POCL Helpline event is aimed at POCL Helpline staff and managers.
These are detailed below.
Managers 1.5 day event (Cross reference to 2.3.1 “Managers”)
e A 1.5 day contiguous training event delivered over two days (to include venue set
up and clear down procedures (within the working day). (Bullet point 1)
e A competency test would be undertaken at the end of the course. (Bullet point 2)
e The course will be completed not more than five working days prior to the date an
individual outlet is planned to undertake live operation. (Bullet point 3
e This course would be targeted at staff who are required to understand the full
functionality of the automated platform including balancing activities. (Bullet
point 4)
e It is understood that all management grades will need this training. It is also
understood that other staff may perform these tasks, in some cases as back up, and
they too will attend this training (this was originally stated in PATH-30-007, dated
30/1/97, Section 2.3.1, “Managers” bullet point 5). (Bullet point 5)
Counter Assistants 1 day event (Cross reference to 2.3.1
“Counter staff”)
e A one day contiguous training event (i.e. not two separate half days). (Bullet point
Db
e The course will take place within the working day and be completed not more than
five working days prior to that individual outlet being planned to undertake live
operation. (Bullet point 2)
e A competency test will be completed at the end of the course. (Bullet point 3)
COMMERCIAL IN CONFIDENCE Page 31 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref. BP/TRN/O01
: Version: 79
Baseline Document Date: 1 )99
e It is understood that subpostmasters assistants, counter assistants and retail
assistants would be the principal audience. A single course for all these job roles
teflects POCL policy for counter operations and ensures a national standard of
competence. (this was originally stated in PATH-30-007, dated 30/1/97, Section
2.3.1, “Counter staff”, bullet point 4). (Bullet point 4)
e It is recognised that some of these staff, who perform some management functions,
will attend the above 1.5 day event instead of this one. (this was originally stated in
PATH-30-007, dated 30/1/97, Section 2.3.1, “Counter staff’, bullet point 5).
(Bullet point 5)
8.4 Other identified POCL staff (Auditors, Trainers, and newly
promoted staff)
(Cross reference to 2.3.1.”Back office audit” and “POCL Train the
Trainer”)
e Auditors 2 day event (includes national and regional auditors, POCL security
and investigators)
This is a two day course based on the content delivered to outlet managers but
tailored to meet the needs of the central audit office of the post office. The
same course will be taken by computer auditors and regional auditors. (Para
D
. POCL Train the Trainer 5 day event (includes POCL and Agency
trainers)
This 5 day course is aimed at existing POCL trainers, who will be training
both existing staff and new staff on the automated counter transactions system.
Regional staff will attend a similar event. Trained staff will be certificated
upon successful completion of this event. (Para 1)
As part of the Train the Trainer programme, ICL Pathway’s sub-contractor
staff will support the first live training delivery of each newly trained trainer
(on a standard 1.5 day Managers event or 1 day Counter event being delivered
as identified in this document). POCL or agency training staff will be
accredited to deliver ICL Pathway Managers course to Horizon users upon
successful completion of their first event. POCL trainers will also be invited
to attend a standard Managers training event in their Region to observe an ICL
Pathway trainer delivery. (New)
Trainer upgrade briefings will be available to existing POCL Horizon trainers
for New Release 2+ Horizon software. Further upgrade programmes will be
subject to a separate agreement and process between ICL Pathway and POCL
and as outlined in Schedule A06 section 11.1 of the Authorities Agreement.
Further accreditation will be required for new trainers during Rollout for New
Release 2 and New Release 2+ onwards. (Costs associated for additional
COMMERCIAL IN CONFIDENCE Page 32 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref: BP/TRN/O1
Version: 7.9
Baseline Document Dale: 19
training events are covered in schedule A06, Section 11.1 as mentioned
above). (New)
e At POCL’s discretion newly promoted POCL staff can attend a similar event to
outlet manager or counter assistant as appropriate to their role. Any newly
promoted staff member who attends such an event will be scheduled within the
specified course limits and places as outlined in section 8.8 of this document. This
will meet ICL Pathway’s contractual responsibility (Requirement 534) as outlined
in the POCL Schedule A15. Each event delivered will be part of the National
Rollout allocation and training schedule. Booking staff on these events will be
part of an agreed process between ICL Pathway and POCL and will be defined as
part of POCL’s internal procedures (for more information please refer to POCL
CAR 532.000.03 document reference BP/PRD/007). (New)
8.5 Key Deliverables (Cross reference to 2.3.2 “Key
Deliverables”)
¢ Suitability of training venue will be measured by ICL Pathway (for more
details on measurement criteria please refer to ICL Pathway Training Venue
Administration document reference PATH/PROC/0004 and to Requirement
915). (Bullet point 1 reworded)
© Quick reference guide and workbook will be distributed on each event. Each
workbook and quick reference guide will be produced by ICL Pathway’s sub-
contractor in accordance with the ICL Pathway Training and User Awareness
Style Guide reference PATH/PUBS/001). (Bullet point 2 reworded)
e Trainer performance will be measured (for more detailed information please
refer to ICL Pathway Training Evaluation paper reference SU/TRN/005).
(Bullet point 3)
¢ Course will be to agreed specification (as described in the ICL Pathway
Training Needs Analysis document reference SU/TRN/O001 for cross
referencing to course specifications and workbook structures). This will be
measured by ICL Pathway. (Bullet point 4)
e Competency Test, administered at the end of each course. This will involve a
“Horizon Achievement Certificate’ awarded to attendees who successfully
complete the course by passing the competency test. Please note that
competency tests during National Rollout will be known to users as the
“Horizon Achievement Certificate’. (Bullet point 5 reworded)
e Reporting and feedback to ICL Pathway (and POCL) will be in accordance
with ICL Pathway Standard Reports and Formats document reference
SY/REP/021. (Bullet point 6 reworded)
e Accreditation for POCL trainers up to New Release 2 (and New Release 2+)
will be subject to an agreed process between ICL Pathway and POCL. (Bullet
point 7 reworded)
COMMERCIAL IN CONFIDENCE Page 33 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref; BP/TRN/0OL
Version: 70
Baseline Document Date: 1 )99
e Trainers’ course kit to be presented to ICL Pathway and POCL trainers as part
of Train the Trainer events. (New)
¢ Copyright for all trainers’ course kits (and updates) is the property of ICL
Pathway’s sub-contractor. Neither POCL, agency trainers, users, managers
may make copies of any training material without ICL Pathway’s consent.
This also applies to style and layout. ICL Pathway will be pleased to quote
POCL for the supply of additional or replacement copies and sees this as a
positive approach towards a managed service during National Rollout. Subject
to commercial agreement, an agreed ordering process between ICL Pathway
and POCL should be put in place before the commencement of future training
events during Live Trial and National Rollout. (New)
e ICL Pathway trainer gear up will be accomplished via a three week training
programme. (Cross reference to 2.3.4 “Logistics” Bullet point 1)
e Training venues (rooms) will be provided by ICL Pathway’s sub-contractor.
All venues will be subject to venue inspection and approval prior to use. ICL
Pathway’s sub-contractor will consider using POCL provided venues subject to
inspection. Such venues would be paid for at budgeted rates. The current plan
is to provide catering for all training events. This will comprise coffee two
times daily and lunch. All venues will provide access for the disabled. (Cross
reference to 2.3.4 “Logistics” Bullet point 2)
e Trainers will be provided by ICL Pathway’s sub-contractor. ICL Pathway’s
sub-contractor will consider using POCL staff provided that they meet the
appropriate quality criteria and are available for suitably long periods of time
(at least 3 months). (Cross reference to 2.3.4 “Logistics” Bullet point 3)
8.6 Acceptance (Cross reference to 2.3.3 “Acceptance”)
Contractual performance measures cover: (Bullet point 3)
© Course availability to users. (Requirement 915)
e Venue quality as rated by users. (Requirement 915)
¢ Training course quality (Requirement 915)
¢ Cancellations of courses (Requirement 915)
¢ Achieved competence levels (Requirement 915)
e Training course feedback by trainer on each delegate (Requirement 915)
¢ Delivery within appropriate time scale. (Requirement 915)
8.7 Logistics (Cross reference to 2.3.4 “Logistics”)
e ICL Pathway to provide contingency for spares and equipment on ICL
Pathway’s trainers’ vans. (New)
COMMERCIAL IN CONFIDENCE Page 34 of 51
© 1998 ICL Pathway
ICL Pathway
FUJ00119673
FUJ00119673
Training and User Awareness Ref. BP/TRN@OL
, Version: 7
Baseline Document Date: 1 )99
ICL Pathway’s trainer gear up will be accomplished via a three week
training programme. This covers one weeks training to be a Sub-
Postmaster, one weeks training to be an accomplished Pathway trainer, i.e.
training techniques associated with the Horizon programme and one week
to deliver and understand the Horizon system. (Bullet point 1 reworded)
POCL to define their approach to training after site acceptance and outlet
go live. This will be subject to ICL Pathway and POCL agreement.
POCL’s training policy will need to be communicated to POCL and agent
outlets (as a separate activity by POCL), so that messages are consistent,
and that ICL Pathway and POCL are complementary on way forward.
(New)
All Training materials i.e. course kits and Train the Trainer events will
accredit POCL trainers and agency trainers to deliver an ICL Pathway event
rather than a POCL variant which may be adopted for steady state training.
There are no turnover training events offered as part of this baseline
however additional events and course materials can be provided using the
approved change control process (Cross reference POCL Schedule A15 and
costings Schedule A06). (New)
Training venues (rooms) will be provided by ICL Pathway’s sub-contractor
or POCL during Live Trial and National Rollout. All venues will be
subject to venue inspection and approval prior to use by ICL Pathway (for
more information please refer to ICL Pathway Training Venue
Administration document reference PATH/PROC/0004). ICL Pathway will
consider using POCL venues subject to inspection. Such venues would be
paid for at budgeted rates. The current plan is to provide catering for all
events. This will comprise coffee and tea twice daily. It is currently
planned that a fixed price lunch will be provided on the first day only (as
requested by POCL). All venues will provide access for disabled users and
comply to Health and Safety Regulations (this is a contractual requirement).
(Bullet point 2 reworded)
8.8 Assumptions (Cross reference 2.3.5 “Assumptions”)
e Training days are Monday to Friday. (Bullet point 1)
e Vo
lumes of users requiring training are as per Fig 8.1 (of this document).
(Bullet point 2)
e All
courses will start at or before 10.00 am. (Bullet point 3 reworded)
¢ There will be a maximum of 6 staff on each event. (Bullet point 4)
e Timing of events for outlets will be determined by ICL Pathway’s
Implementation Rollout database. (Bullet point 5)
¢ Timing of courses for specialist roles will be via ICL Pathway’s order under
written request from POCL. (Bullet point 6)
© 1998 ICL Pathway
COMMERCIAL IN CONFIDENCE Page 35 of 51
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref, BP/TRN/OOL
Version: 7.9
Baseline Document Dale: 19
e The training audience will be a maximum of 72,000 post office staff,
subpostmasters and assistants as defined in figure 8.1 overleaf. Timing of
courses for specialist roles will be via ICL Pathway’s order under written
request from POCL. (New)
COMMERCIAL IN CONFIDENCE Page 36 of 51
© 1998 ICL Pathway
ICL Pathway Training and User Awareness Ref: BP/TRN/O1
Version: 7.9
Baseline Document Dale: 19
FUJ00119673
FUJ00119673
e A maximum number of 12,600 courses will be run for the target audience of
72,000 users and whichever of these limits is achieved first will complete ICL
Pathway’s contractual commitment for delivery of training. The 12,600
courses anticipates 95% course occupancy. Within this number of courses a
maximum of 5,504 one day Counter Assistants Courses will be run and a
maximum of 7,004 one and a half day Managers Courses will be run. The
balance of the 12,600 will be made up of a number of specialist courses such
A full breakdown of all courses including
as Train the trainer events etc.
managers, assistants and specialist are detailed below:
PREVIOUS OFFER CURRENT OFFER
TYPE DURATION TOTAL
TYPE DURATION TOTAL
*Managers 1.5 days 6,596 *Managers 1.5 days 7,004
* Assistants 1.0 days 5,185 * Assistants 1.0 days 5,504
*Train the I 5.0 days 25 *Train the I 5.0 days 25
Trainer Trainer
*Auditors 2.0 days 34 *Auditors 2.0 days 34
POCL 1.5 days 33 POCL 1.5 days 33
Helpline Helpline
Total 12,600
Key to audience types per course:
*Managers course = Branch managers, Assistant Branch manager (ABM), Postal
Officer Assistant Branch manager (POA), subpostmasters, franchise managers,
nominee managers, Head of Retail Networks (HORNs), regional support staff, relief
or deputy managers, Retail Network Managers, Outlet managers, POCL User
acceptance team, POCL staff who perform stock unit balancing, and nominated POCL
staff and officers.
*Counter Assistants course = Postal officers, Counter Clerks, POCL retail assistants,
subpostmaster’s assistants and franchise staff
*Train the Trainer = POCL and agency trainers
*Auditors course = National and Regional auditors, POCL Security and Investigators
COMMERCIAL IN CONFIDENCE Page 37 of 51
© 1998 ICL Pathway
ICL Pathway
Training and User Awareness
Baseline Document
FUJ00119673
FUJ00119673
Ref: BP/TRN/O1
Version: 79
Date: 8/1/99
POCL Helpline = POCL Helpline staff and managers
Fig 8.1 POST OFFICE USER ROLE BREAKDOWN
(Previously shown in PATH-30-007, dated 30/1/97, Section 2.1):
Course No Staff No User No Staffl_ No Staff © NoMGT No
Duration Aware Day 1Sday = MGT
Events Courses PS courses Places
Postal Officers 1 6,500 I 7,200 1084 6,500
Postal Officers 2 700 117 700
Branch Managers/ABM/POA I 2 1,300 I 1,300 217 1,300
Retail Assistants 1 750 750 125 750
Sub Postmasters 2 17,750 I 17,750 2959 17,750
Sub Postmasters Assistants 1 22,250 I 40,000 3709 22,250
Sub Postmasters Assistants 2 17,750 2959 17,750
Franchise Managers 2 400 400 67 400
Franchise Staff 1 1,600 1,600 267 1,600
Nominees & Staff 2 1,000 I 1,000 167 1,000
Retail Network Managers 2 350 350 59 350
Auditors Specialist 200 I 0
Post Office Security 2 100 I 0 17 100
POCL Helpline Specialist 160 I 0 27 160
POCL Trainers Specialist 130 I 0
Regional Support Staff 5 150 I 0
Heads of Retail Network 2 16 I 0 3 16
PDA User Acceptance Team I 2 20 I 0 4 20
Total Staff 71,126 I 70,350
Total Courses 704 5,185 31,100 6,596 39,546
Note: The regional support staff are also known as “buddies” or tutors in some
documentation.
8.9 Dependencies (Cross reference to 2.3.6 “Dependencies”)
e Agreed release rates of staff. (Bullet point 1)
© 1998 ICL Pathway
COMMERCIAL IN CONFIDENCE
Page 38 of 51
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref, BP/TRN/OOL
Version: 7.9
Baseline Document Dale: 19
e Determination of % staff that must be declared competent prior to an outlet
migrating to Horizon and going live. (Bullet point 2)
e Managers must be available for training any of Monday to Friday including
Wednesdays. Scheduling will be Monday/Tuesday, Tuesday/Wednesday and
Thursday/Friday. It will be necessary to schedule some managers courses on
Tuesday/Wednesday in order to offer choice of training dates. (New)
© Staff must be declared competent prior to an outlet migrating to Horizon and going
live. This will be defined by POCL as a matrix for use within ICL Pathway
Implementation Roll Out Database for scheduling subpostmasters, outlet managers
or relief managers onto training (Cross reference to POCL CAR 532.000.01
document reference BP/PRD/007). (New)
e Specialist training events ie. Auditors, Investigators, RNMs, POCL trainers and
other NON COUNTER personnel must be booked with ICL Pathway 6 weeks prior
to the desired training event (using POCL’s approved forms - Cross reference to
POCL’s document BP/PRD/007). POCL to ensure 6 people are booked and
confirmed prior to raising a request with ICL Pathway and submitting relevant
paperwork. Each event for such staff will have a maximum occupancy of 6 per
event. (New)
¢ Invitations for each event will be generated by ICL Pathway’s sub-contractor. All
POCL specialist training requests and booking forms are to be sent electronically
via a nominated POCL Course booker(s) to a nominated ICL Pathway
representative. (New)
It is the responsibility of POCL to ensure that all users of the Horizon system at the
counter, during National Rollout, attend training and remedial training (where
necessary to meet Minimum Training Compliance) within the training window as
defined in Requirement 915. This has been contractually set by POCL (ref.
Requirement 915) as not more than 5 days from installation and go live of the
Horizon platform. Any changes to this process will need to be agreed jointly and
follow normal POCL and ICL Pathway change control procedures (cross reference
to Schedule A15 for more information regarding change control process). (New)
¢ POCL will release all identified specialist staff in accordance with National Rollout
plan and course limits (6 per course) a minimum of 6 weeks before the first user
goes live during Live Trial and National Rollout (and within that POCL Region).
This will be based upon POCL’s formal written instruction before delivery and
invitations of any upgrade, Live Trial or National Rollout training programmes.
(New)
8.10 Workbook practice and training mode
8.10.1 Description (Cross reference to 2.4.1 “Description”)
Training mode on the automated platform, which can be used in conjunction with a
workbook of exercises for self study in order to: (Para 1)
COMMERCIAL IN CONFIDENCE Page 39 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref: BP/TRN/O1
Version: 7.9
Baseline Document Dale: 19
e Refresh their use of the Horizon system after training. (Bullet point 1
e Gain an opportunity during Live Trial and National Rollout (for New Release
2 and New Release 2+ functionality as appropriate). (Bullet_point 2
reworded)
e Provide practice on linked (end to end) transactions to help consolidate
knowledge of the Horizon platform. (Bullet point 3 reworded)
Any subsequent releases will be subject to a separate agreement and training
solution as part of ICL Pathway and Authorities Agreement Schedule A06.
(New)
8.10.2 Key Deliverables (Cross reference to 2.4.2 “Key Deliverables”’
e Training mode will be available from day one of installation at an outlet. This
will cover transactions carried out as part of their training event. (Bullet point
1 reworded)
e Training workbooks covering training scenarios will be issued by ICL
Pathway’s sub-contractor to users on their training events and explained during
all training courses. (Bullet point 2 reworded)
e Activity sheets ie. question sheets will be available for users to complete
during and after the course as part of their consolidation. This would be an
option and not mandated. Each sheet will be designed by ICL Pathway trainers
to help assist users in reinforcing their training covered as part of their training
event. (New)
8.10.3 Acceptance
e Development of training mode is being undertaken by ICL Pathway with
testing by ICL Pathway and POCL Model Office testing teams.
e The training workbook is a deliverable as part of MOT and is subject to a
separate ICL Pathway, DSS, BA and POCL review as part of training
development prior to and during MOT.
8.10.4 Logistics (Cross reference to 2.4.4 “Logistics”)
e ICL Pathway will provide training mode on all counter systems at the time of
installation in post offices of New Release 2 (and New Release 2+). This
would be subject to a separate agreement for subsequent releases i.e. new
functionality or Release 3 onwards. (Bullet point 1 reworded)
e ICL Pathway’s sub-contractor will prepare and distribute training workbooks
for all new users who do not have Horizon, on training courses for New
Release 2 (and New Release 2+ as appropriate). (Bullet point 2 reworded)
¢ POCL will distribute all POCL Counter procedures i.e. Horizon User Guide(s)
in line with the Live Trial and National Rollout schedules (as provided by
POCL project teams). All Horizon User Guide(s) will need to be made
available by POCL to users at the counter at the start of go live during Live
COMMERCIAL IN CONFIDENCE Page 40 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref, BP/TRN/OOL
Version: 7.9
Baseline Document Dale: 19
Trial and National Rollout (for new Release 2 and New Release 2+). All
updates to the Horizon User Guide will be the responsibility of POCL. (New)
8.10.5 Assumptions
8.11
¢ Copyright for all ICL Pathway training materials for all courses (regardless of type)
are the property of ICL Pathway’s sub-contractor. Neither POCL nor users may
produce copies of any training material (in part or in style) without ICL Pathway’s
consent. ICL Pathway will be happy to quote costs to POCL for the supply of
additional or replacement copies (as appropriate). This is seen as a positive
approach in offering a managed service to POCL during Live Trial and National
Rollout. Subject to commercial agreement, an agreed ordering process between
ICL Pathway and POCL should be put in place before the commencement of future
training events during Live Trial and National Rollout.
e ICL Pathway and POCL are to agree a process for ordering workbooks for use on
POCL training events as part of an ICL Pathway Procedure for Ordering
Consumables for Training Events document reference IM/PRO/147. POCL are to
ensure that this procedure or similar POCL procedure is adhered to within the
POCL Regions or by POCL National Training Teams as appropriate.
e ICL Pathway’s Training workbooks will be quality reviewed if required under ICL
Pathway’s change control process. Any future Release 3 (and onwards) upgrade
programmes or new product training will be subject to separate workbook and
costing agreements as outlined in ICL Pathway and POCL Authorities Agreement
Schedule A06.
e All counter staff will have access to an up-to-date workbook during National
Rollout.
¢ Staff contact training helpdesk (TPAS) if they need additional support.
Horizon Field Support and Migration Visit (information only)
ICL Pathway are not currently contracted to provide this service as described in
section 8.11 however ICL Pathway recommends POCL to undertake this service. ICL
Pathway will be pleased to deliver this service, subject to change control.
8.11.1 Overview Description (Cross reference to 2.7 “Description”
A specific visit to each post office following completion of the training programme.
In the case of automated offices (all types) the visit will be planned to occur on
installation or go live day. Also known as the Horizon Field Support visit. (Para 1
reworded)
The purpose of the visit is to ensure a smooth hand over to live running and ensure
that all staff are operating without difficulty. Individual managers will be asked for
specific guidance as to how the visit is to be used but in every case all staff will be
observed for assistance regarding reinforcements of training. This will be managed as
COMMERCIAL IN CONFIDENCE Page 41 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref: BP/TRN/O1
Version: 7.9
Baseline Document Dale: 19
part of a separate activity and does not involve ICL Pathway trainers. _(Para 2
reworded)
It is ICL Pathway’s experience that users require further support after training to help
remember topics covered by their training event and build confidence in daily use.
Therefore the Horizon Field Support visit is part of this document for
recommendation purposes only. (New)
8.11.2 Overview Key Deliverables
This function will be carried out by POCL and, subject to change control, ICL
Pathway as part of the Horizon Field Support Officer and migration role. This is not a
deliverable under the Horizon training and user awareness programme. (For more
detailed information please refer to ICL Pathway Release 2 In office Migration
Strategy reference IM/STR/0017).
8.11.3 Dependencies
9.1.2
Not relevant as part of this document.
Remedial training
Description (Cross reference to 2.8 “Description”)
Remedial training function becomes operable when any member of staff fails the
competency test on completion of their assigned training programme. (For more detail
please refer to ICL Pathway Remedial training document reference SU/TRN/006).
Below is a summary of activities involved. (Para 1)
Remedial training will comprise any or all of the following: (Para 2)
e Attendance on another scheduled training event (Bullet point 1)
e A specially scheduled remedial training event scheduled immediately after each
training event or the following day. (Bullet point 2)
Staff will be given a choice wherever possible but the exact remedial training offered
will be at ICL Pathway’s sub-contractor’s discretion and based upon logistical criteria.
Marginal failures candidates will be offered additional support on a 1:1 basis. (Para
32
Any contingency places factored into the training schedule caters for remedial training
and choice of dates offered to users during Rollout. (New)
Key Deliverables
e All staff failing a competency test are immediately offered remedial training and
support.
¢ It is recommended that all staff failing to reach the standard are immediately
offered remedial training and support which may occur on the same day as their
original training event or on a specific day. (This is required due to Minimum
COMMERCIAL IN CONFIDENCE Page 42 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref, BP/TRN/OOL
Version: 7.9
Baseline Document Dale: 19
9.1.3
Training Compliance and go live during Rollout). The provision of such remedial
training is consistent with the implementation timetable, this implies that such
provision is focused on evening delivery and may occur on the evening of the same
day as the original training event.
e An ICL Pathway certificate will be awarded for passing the competency test and
teaching the required standard i.e. 90% accuracy. This will be known as the
Horizon Achievement Certificate. Separate certificates will be available for job
roles as defined in the ICL Pathway Training Needs Analysis document reference
SU/TRN/0001.
e All remedial training will be completed within the 5 day contractual training
window (Cross reference to Requirement 915 and ICL Pathway Remedial Training
document reference SU/TRN/006).
Acceptance
The standard of competence required and competency test format will be agreed by
ICL Pathway and POCL for each training event type i.e. Train the Trainer, Managers
and Counter Assistants events.
Logistics
Remedial training and coaching sessions will be undertaken by ICL Pathway trainers
and carried out at a training location with immediate notice to individuals for
attendance.
Delegates failing the competency test will be offered:
e The opportunity to stay after the event for additional coaching and a competency
test re-try.
e The opportunity to attend an additional training course the next day.
e The opportunity to attend an evening remedial session within the same working
week as their initial training event.
In every case delegates will be offered the option of staying behind at the end of the
course or being rescheduled on the next available event.
Managers will get the option of evening sessions on Tuesdays and Fridays, plus an
additional session on Saturday am. This needs to be strongly encouraged by POCL
Regions and POCL Project Teams.
Counter staff will get the option of evening sessions on Monday, Wednesday and
Thursdays which will be in or outside their training area.
It is important to note that the trainer is always best placed to observe and recommend
the most appropriate course of action in respect of achieving competency as they will
have first hand experience of user difficulties. Where failure to reach competency is
not Horizon system based, but due to lack of POCL transactional knowledge,
recommendations via the ICL Pathway trainer’s (e-mailed) report will instigate POCL
COMMERCIAL IN CONFIDENCE Page 43 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref, BP/TRN/OOL
Version: 7.9
Baseline Document Dale: 19
9.1.5
9.1.6
referral. This is documented by POCL as part of their contractual response to CAR
531.000.03, reference BP/PRD/006.
Assumptions
Remedial training is only completed when the staff member successfully completes a
competency test. Staff failing to achieve the standard on a third attempt will be
referred to the Regional POCL representative or POCL manager for review. This
referral will be the next working day after failing the third attempt.
There will be no remedial training for POCL trainers, Auditors or non counter staff
personnel.
Installation is under threat if users do not attend remedial training and meet Minimum
Training Compliance within the contractual window of 5 days from installation.
Pass rate for competency tests is 90%.
Dependencies
POCL to mandate training and remedial training as part of POCL’s communication
cascade. POCL Regional teams will target known outlets where attendance on
previous programmes has been poor to encourage and stress attendance during
Rollout.
POCL to advise and document informing ICL Pathway on how to manage relief
managers and their training during Rollout. This should be a documented process
agreed by all parties i.e. POCL Regions prior to commencement of Live Trial and
National Rollout invitations.
Availability of POCL staff and users in outlets. (Cross reference to 2.8
“Dependencies” - Bullet point 1 reworded)
Attitude of POCL staff and users to achieving the required competency standard and
retaking a test. It is assumed that POCL staff and users will accept the requirement to
achieve the required standard as mandated by POCL. In the event of this not being the
case the ICL Pathway trainer will refer the case to ICL Pathway Programme Managers
via the Rollout database and to POCL nominated representatives via ICL Pathway’s
sub-contractor exception reports.
All users who are to be tested must have been briefed by POCL such that the
requirements of the Data Protection Act have been met.
Process for mandating training and remedial training is managed by POCL (for more
information please refer to POCL CAR 532.000.03 document reference
BP/PRD/007).
COMMERCIAL IN CONFIDENCE Page 44 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref: BP/TRN/O1
Version: 7.9
Baseline Document Dale: 19
10 Accommodation
10.1.1 Description
The provision of training venues and catering as agreed between ICL Pathway and
ICL Pathway’s sub-contractor are in accordance with Training Venue Administration
document reference PATH/PROC/0004.
10.1.2 Key Deliverables
e The building will be in a state of good repair and be clean and tidy.
e Tea and coffee will be provided for all delegates during each event.
e In urban centres the venue should be accessible by public transport.
e The venue will have provision for disabled access where demand requires it.
e There will be separate toilet and cloakroom facilities for both sexes and at least one
facility with disabled access.
e The room will be adequately lit, heated and ventilated.
e All rooms will be in compliance with Fire, Health and Safety regulations and carry
public liability insurance.
e The training room should accommodate ICL Pathway’s sub-contractor preferred
room and furniture layout as described in ICL Pathway’s sub-contractor’s Training
Venue Administration document reference PATH/PROC/0004.
10.1.3 Acceptance
e Acceptability of training venues is governed by ICL Pathway and POCL
performance measure (as described in Requirement 915.
10.1.4 Logistics
e Sourcing and reservation of possible venues is the responsibility of ICL Pathway’s
sub-contractor Training Administration Centre. This is required 3 months in
advance of booking.
e Inspection service by ICL Pathway and ICL Pathway’s sub-contractor
representatives only during Live Trial and National Rollout.
10.1.5 Assumptions
¢ POCL training venues will be used where suitable and available.
10.1.6 Dependencies
e Forward schedules of offices and possible POCL personnel are made available to
ICL Pathway’s sub-contractor by ICL Pathway not less than 16 and 8 weeks
respectively prior to each event.
COMMERCIAL IN CONFIDENCE Page 45 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref; BP/TRN/0OL
Version: 70
Baseline Document Date: 1 )99
11
e Venue bookings will vary in terms and conditions offered by ICL Pathway and ICL.
Pathway’s sub-contractor and cancellation charges will apply for late cancellations
to POCL respectively.
New Product and Update training (Release 3 onwards)
ICL Pathway are not currently contracted to provide this service however ICL
Pathway will be pleased to deliver this service, subject to change control.
11.1.1 Description
ICL Pathway has the competence and resources to deliver update and upgrade
programmes to POCL approval and acceptance but will be only be required to do so if
and when a subsequent CCN is agreed. All these options will be at an incremental
cost to POCL as outlined in Schedule A06 of the Contract. ICL Pathway will ensure
that trainers have access to any New Release 2 or New Release 2+ updates and are
properly trained so that they can provide training (where appropriate) to new users of
the Horizon platform. This is also an option for future Update and Upgrade
programmes at an incremental cost to POCL.
There are 3 categories of update defined for which there is a corresponding training
strategy/policy: (Cross reference to 2.9 “Description” - Para 1)
Category 1: A new product which uses existing counter processes and equivalent
procedures to those already being used. Policy: An updated workbook
would be made available for staff to practise using training mode.
(Category 1)
Category 2: A new transaction and/or new process within existing subsystems. An
outlet update or series of seminar type briefings provide during the
working day or evening respectively. (Category 2
Category 3: A new subsystem, or major revision to user interface for existing
transactions. Policy: Classroom training provided in half day, i.e. up
to 3 hours, the timing of which is determined by trainee. Options being
p.m. or evening. (Category 3)
The above options are available only at an incremental cost to POCL as
described in paragraph 11 of this document (Cross reference to the Authorities
schedule A06 for ICL Pathway Standard Costs) more information regarding
options available are detailed below:
Options
e Development and distribution via 1“ class post of an updated workbook plus the
upgrade of the counter training mode facility and POCL/ICL Pathway training
systems
e Classroom training provided as determined by POCL and ICL Pathway. Options
being morning, afternoon or evening.
COMMERCIAL IN CONFIDENCE Page 46 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref: BP/TRN/O1
Version: 7.9
Baseline Document Dale: 19
e An outlet update or series of seminar/briefings provided during the working day or
evening respectively.
e Interactive video via the Horizon platform in modular format with a tailored
workbook.
e Self-teach and modular redeveloped Training mode
11.1.2 Key Deliverables for New Product Training if agreed (subject to
separate cost and change control process)
e A revised workbook to be distributed to users as part of a Release 3 event. ICL
Pathway’s sub-contractor will update training materials during New Release 2
(and New Release 2+) only for new outlets to Horizon as part of National Rollout.
e An additional POCL trainer event by ICL Pathway’s sub-contractor to maintain
ICL Pathway’s accreditation on new releases plus revised trainer’s course kit.
¢ Development of training mode for the revised platform.
© Development and delivery of briefing events.
¢ Training systems up-graded and supported during implementation.
11.1.3 Acceptance
Acceptance will be by POCL sign off of the agreed training strategy for each discrete
update by ICL Pathway.
11.1.4 Logistics
This will vary for each and every update programme depending upon the training
strategy employed and agreed by ICL Pathway and POCL.
11.1.5 Assumptions
The choice and design of update programme will depend upon an impact assessment
of the change. Programmes will always be subject to verification and sign off by ICL
Pathway and POCL.
11.1.6 Dependencies
Workbook based training strategy will depend upon the availability of training mode
and training development systems in the updated software version prior to the agreed
update implementation programme.
COMMERCIAL IN CONFIDENCE Page 47 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref: BP/TRN/O1
Version: 7.9
Baseline Document Dale: 19
12 Management Reporting & Performance Measures
12.1 Description
As part of Requirement 915 progress and exception reports are required from ICL
Pathway’s sub-contractor to ICL Pathway, POCL and POCL Representatives via e-
mail. All reports are documented and have been agreed by ICL Pathway, ICL
Pathway’s sub-contractor and POCL programme teams as part of ICL Pathway
Standard Reports and Formats document, reference SY/REP/021.
Training scheduling and compliance to POCL Minimum Training Compliance which
is documented in POCL’s CAR 532.000.03 reference BP/PRD/007.
Below shows a summary diagram of ICL Pathway’s training schedule however for
more information on end to end scheduling processes can be found in ICL Pathway
Training Scheduling and Minimum Training Compliance document reference
IMP/REQ/014.
Fig 12.1 POST OFFICE TRAINING TIMETABLE
Installation
&
Go Live
I I
HSFO Visit
Day=
12.2 Key Deliverables
Reports for the User Awareness event covering:
¢ List of venue details
COMMERCIAL IN CONFIDENCE Page 48 of 51
© 1998 ICL Pathway
FUJ00119673
FUJ00119673
ICL Pathway Training and User Awareness Ref, BP/TRN/OOL
Version: 7.9
Baseline Document Dale: 19
e Forecast versus actual attendance
© Qualitative response
¢ Comments report
Standard formats and formats have been agreed between ICL Pathway, ICL Pathway’s
sub-contractor, POCL and POCL Regions and are documented in ICL Pathway
Standard Reports and Formats document reference SY/REP/021.
Reports for user training as part of Contractual performance measures cover:
¢ Course bookings and attendance.
e Venue quality of 85% satisfaction level.
e Training course quality of 95% user satisfaction level.
© Cancellations of courses. No more than 2% of course bookings may be cancelled at
instigation of ICL Pathway’s sub-contractor.
e Achieved competence levels. 95% of users to all courses must score at least 90%
on their competence tests.
¢ Training course feedback by trainer on each user.
¢ Delivery within appropriate time scale. Training must be completed no more than 5
days before outlet installation date for the contractually agreed minimum number
of staff and no more than 2 days after intended first operation for the remainder.
e List of training venues (non-contractual).
e Total numbers attending training by POCL Region (non-contractual).
COMMERCIAL IN CONFIDENCE Page 49 of 51