FUJ00174034 - Annex - Post Office Ltd ‘Costs’ and Loss of Benefits from Re-Baseline HNG-X Plan to V80 (from V60A40).
Evidence on official site
Annex
POL ‘Costs’ and Loss of benefits from Re-Baseline HNG-X
Plan to V80 (from V60A40)
The following items form the basis of the additional costs and loss
of benefits as identified to date — inclusive of VAT where applicable
~incurred by Post Office as a result of potential change in dates
from the V60A40 plan (baselined as part of CCN1246) to a new
proposed plan titled V80.
1.
POL staff being covered by contractors (on the basis these
resources should have been released):
£2.62m — based on 31 persons covered by contractors at an
average day rate of £565.
External contractors employed on HNG-X extended to
support the revised timescales.
£2.46m — based on 27 persons at an average day rate of
£609.
Retention of trainers to support rollout. £2m based on
retaining an average of 166 people for an additional 6
months. This is an example, as mentioned in our letter, where
Post Office would seek to absorb some of this cost by utilising
these resources elsewhere when possible.
Additional client and supplier costs — current estimate £300k.
NB Fujitsu are requested to note that this is a minimum
estimate as Post Office does not wish to push for exact costs
as past experience has shown that additional costs are
increased where a push approach is used. Should Fujitsu
wish Post Office to push for exact costs at the current time,
the total may increase.
£115k - Extension of lease for laptops and storage due to
delayed rollout.
£200k - Other costs including maintenance of Online Help
alongside existing manuals, support at Post Office Helpdesk
(NBSC) and other incidentals.
FUJ00174034
FUJ00174034
FUJ00174034
FUJ00174034
7. Additional network costs incurred owing to delayed router
rollout - £105k.
8. Loss of benefits from delays to other POL activities - we
currently assess this to be a minimum of £500k. However we
are undertaking further analysis of the impact of the delay on
projects.