POL00337637 - Change Control & RAID or RIDAC RE: ServiceNow extending to traditional RAID log and others change controls

Evidence on official site

POL00337637
POL00337637

~ CHANGE
REQUEST

DECISION

Change Control & RAID or RIDAC

ServiceNow extends the traditional RAID log to include Change Control
through the use of a set of records that cover
Risk, Issues, Decisions, Actions and Change Requests (RIDAC).

The aim of the RIDAC function is to easily associate and manage Risks as they
become Issues which in turn generate Actions, Decisions and project Change
Requests.

Each type of record may be generated independently of each other or can be
spun off from an existing one (see below)

i CHANGE CONTROL & RAID

INNOVATE PROVE DELIVER

Risk Risk
Workshop Workshop

I I

Vv Manage Manage ,
© new RAID G RAID
& Ss =e now
‘ mt Capture s” Capture in s-
Identity Capture in = p =2 pr
Risk ———™ Prove Plan ® {RIDAC =] BTL. —— 8 pupac P— in snov
Control Control

Change Change
POL00337637

POL00337637
RIDAC FLOW 3
REQUEST
DECISION I a
CHANGE

} issue I I scncn I cE
CHANGE
REQUE:
Traditionally projects managed a RAID log (RISKS,
ACTION ASSUMPTIONS, ISSUES & DEPENDENCIES). In the SNow
environment ASSUMPTIONS are held in a separate table

CHANGE and DEPENDENCIES are mapped between Tasks within the
REQUEST planning console. With RIDAC - A represents ACTION and [

represents DECISION

Risk Standards

Milestone Change Control.pptx

Change Risk & Assurance

2 eo ®

Change Harm Table

Change risk universe

kia

Training

Q Name v Description Format v N
I Milestone Change Control.pptx

POL Project Risk Management Sta...

@) _ RIDAC Fundamentals.pptx

[>I RISKS ISSUES Statements Overvie...

Templates

(S Description Name v

Overview of change
control for milestones

Updated advice on
RIDAC and Risk
Management

Overview of RIDAC on
SNow

Video overview of Risk
Statements in SNow.
Based on Kelly Punter's
Changing Change
presentation.

Powerpoint

Powerpoint

Powerpoint

Video

Mandated v

POL00337637
POL00337637
A template that can be
tailored to the specific
needs of a project or
programme when
providing
SteerCo/Senior
Stakeholders with
updates and for
decision making’

Summary of the projects
achievements as against
the baseline plan with
any subsequent change
requests

From July 2019 all RAID
logs for projects are
entered and maintained
in ServiceNow against
the project.

This template outlines
the problem or
opportunity and the
mini-project plan
required to prove the
business outcome are
viable and the
assumption correct. It is
submitted to seek
Approval to Prove and
request seed funding

If project is outside of
tolerance for time, cost
or quality - it must
submit this form to PRB.
This form is also used to
request funding
drawdown for waterfall
projects

HoTPs have devolved
Governance authority
under certain
conditions. This
paperwork has to be
completed and
approved by th HoTP
before SPO will process
the project.

Contains the
information required to
instruct the project
team on the delivery
method

PPMO document to
support the Project
Healthcheck orocess

SteerCo Status Report template.p...

REQUEST TO CLOSE REPORT PR3n...

RAID Log in SNow.url

PROVE PLAN.docx ®@

PROJECT CHANGE REQUEST PRJn...

Project Brief (HoTP Devolved).docx

PID PRJIname PRJcode.docx

Health Check 1st Tier Assurance.xl...

Yes

Yes

Yes

Yes

Yes

No

Yes

No

POL00337637
POL00337637

1
Fi

n
Fi
Outline the expected BUSINESS CASE WATERFALL PRJn...

benefits to be achieved
and costs incurred
through the delivery of
the project. To guide the
project execution and to
support portfolio